JOHN W FLANNAGAN RESERVOIR
HAROLD E. MILLER
192 WHITE WATER ROAD
HAYSI VA 24256
TEL: 276-835-9544 FAX:
W81F8E82188547
REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
W9123718Q0027 23-Aug-2018 5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NOTE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
USACE, CONTRACTING BRANCH
JOSH WESTGATE, 502 8TH STREET
HUNTINGTON WV 25701
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
06-Sep-2018(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
304-399-5050JOSH WESTGATE
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
W9123718Q0027
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job JWF - Tainter Gate Painting
FFP
Contractor shall provide all materials, labor, and supervision necessary for the blasting and cleaning of the tainter gate at John W. Flannagan Dam, Haysi, VA, in accordance with the attached statement of work. This CLIN is for funding purposes only.
FOB: Destination
PURCHASE REQUEST NUMBER: W81F8E82188547
NET AMT
PRICE BREAKOUT SCHEDULE
Line Item No. Description of Requirement QTY./Unit of Measure Extended Price
0001 Reimbursement of actual cost 1/Job $ ___________ of payment protection if total price exceed $35,000.00.
0002 Labor for the Blast Cleaning and 1/Job $ ____________ Painting of a Tainter Gate at John W. Flannagan Dam, Haysi, VA
In accordance with the attached Scope of Work
0003 Materials for the Blast Cleaning and 1/Job $ ____________ Painting of a Tainter Gate at John W. Flannagan Dam, Haysi, VA
In accordance with the attached Scope of Work
TOTAL: $ ____________
ADDITIONAL INFORMATION
*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE.
SEE CLAUSE 52.236-27 FOR ADDITIONAL INFORMATION.
*PLEASE DIRECT ALL QUESTIONS TO JOSHUA WESTGATE AT (304) 399-5050 or VIA EMAIL AT Joshua.K.Westgate@usace.army.mil. ANY INFORMATION RECEIVED AT THE SITE VISIT WHICH
CONFLICTS WITH THIS SOLICITATION SHOULD BE BROUGHT TO THE ATTENTION OF MR.
WESTGATE. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE GOVERNING
DOCUMENT IN ALL CASES.
**QUOTES CAN PREFERABLY BE E-MAILED TO JOSH WESTGATE AT
Joshua.K.Westgate@usace.army.mil or faxed to (304) 399-5281 by September 6th, 2018 at 5p.m. Eastern.
Per FAR 36.204 the estimated price range for this project is between $25,000.00 and $100,000.00.
NOTE: In accordance with FAR Part 28.102-1(b)(1), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.
(i) Payment bond
OR
(ii) Irrevocable letter of credit
A Payment Bond or Irrecovable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 calendar days after receipt of award.
The payment made under this provision shall not exceed the amount included for Line Item 0001 of the Price Breakout Schedule, which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. FURTHERMORE, THE GOVERNMENT SHALL ONLY REIMBURSE THE CONTRACTOR THE
ACTUAL AMOUNT PAID TO THE SURETY COMPANY FOR PAYMENT BONDS, LESS ANY DISCOUNTS
OR REBATES. AN INVOICE FROM THE SURETY SHALL BE PROVIDED BEFORE PAYMENT IS MADE.
CONTRACTORS ARE ADVISED THAT LINE ITEM 0001 IS ONLY FOR THE COST OF BONDS. OTHER
COSTS SHOULD BE ALLOCATED TO THE REMAINING PRICE BREAKOUT SCHEDULE ITEM(S).
QUOTATION INSTRUCTIONS (Provide the following with your quote):
Company Name and Address: _________________________________
Phone Number: ______________________________
Fax Number: ____________________________
Email Address: ______________________________________________
Business Size (select all that apply)
Large Business _____ Small Business_____ HUBZone Business_____ 8A _____
Woman-Owned ____ Service-Disabled Veteran-Owned ____
If subcontractor will be used for this work, please provide company name and credentials/qualifications: ___________________________________.
Contractors must be registered in the System for Awards Management (SAM) database (www.sam.gov ) to receive an award (See FAR 52.204-7). (Formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA).) Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website.
Contractor is registered with SAM: _____ YES _____ NO (See FAR 52.204-7)
**Please note, as of April 2018, GSA's System for Award Management (SAM) system is requiring new registrations and renewals of existing registrations to submit an original signed notarized letter identifying the authorized Entity Administrator. Vendors are encouraged to check their entity's status in SAM.gov and plan accordingly. If the prospective contractor is not registered in the SAM database, the Contracting Officer will following the procedures at FAR 4.1103. Contact the supporting Federal Service Desk at www.fsd.gov, or by telephone at 866- 606-8220 (toll free) or 334-206-7828 (internationally) Monday through Friday from 8 a.m. to 8 p.m. (EDT), for FREE assistance.**
Provide business Unique Entity Identifier (Previously referred to as DUNS) number:
___________________________(phone 800-333-0505 for more information).
Provide business CAGE code: _______________________________
Provide Tax Identification Number: _________________________________
Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference.
The contractor that receives this award will have 10 calendar days to provide an Accident Prevention Plan (APP). If this deadline is not met, the contractor will be given a cure notice stating that they will have 10 calendar days to provide an acceptable APP, otherwise the contract may be terminated for default.
The Government intends to award to the contractor provided the lowest priced quote. The intent is to award without discussions.
The specifications identifies some items as brand name or equal. Are your providing the brand name items as specified in the statement of work (please mark one): ____________ YES ___________ NO
If in your quote you are providing an "equal" product for any or all of these items, identify the item(s) in the space below by providing the brand name, make, and model number:
If you identify an "equal" product above, you must provide descriptive literature (See FAR Clause 52.211-6(b)(3)) with your quote demonstrating the "equal" product being provided meets the minimum requirements in the specifications.
Section C - Descriptions and Specifications
STATEMENT OF WORK
JW FLANNAGAN TAINTER GATE REHABILITATION
BLAST CLEANING AND PAINTING OF TAINTER GATE REPAIR AREAS
DESCRIPTION/SPECIFICATIONS/WORK STATEMENTS
1. PERFORMANCE WORK STATEMENT.
a. Contractor shall provide all labor, material and equipment necessary to properly clean, prepare and paint the new field repairs that were previously completed according to the following specifications.
There is approximately 500 ft2 of area to be blasted and painted. See typical picture in the A.01.13 Photos.pdf attachment. (Areas to be blasted and painted are the areas showing no paint)
2. DETAILED REQUIREMENTS.
a. Prepare all surfaces of all components for painting by “Commercial Blast Cleaning” to SSPC –SP6 or greater with an anchor profile of 1.0 to 3.0 mile. The frames and components before painting shall be free of all visible oil, grease, dirt, dust mill scale, oxides, corrosion products, and other foreign matter.
Before blast cleaning, visible deposits of oil or grease shall be removed by any of the methods specified in SSPC-SP1 or other agreed upon methods.
b. Paint the entire frame with one coat of Carbozinc 85 (or equal) two coats of Carboguard 235 HAR with LT (or equal) cure multi-purpose marine epoxy coating system. Apply two coats of Carboguard 235 HAR with LT (or equal) Cure at 4 to 8 mils per coat, plus two stripe coats over edges, cutouts and welds. The final coating shall be Carbothane 134 HG (or equal) according to the manufacturer’s recommendations. The final coating color shall match that of the existing tainter gates. All coatings shall be applied in accordance with Manufacturer’s product Data Sheets.
3. BLAST CLEANING AND PAINTING.
This paragraph covers surface preparation and painting standards applicable to the items of work specified in paragraph 1.
a. Surface Preparation. Surface preparation of bare metal as well as tightly adhering coating shall conform to manufacturer’s recommendations, unless specified differently in this document. Areas that might require blast cleaning in preparation for application of the paint system, for example but not limited to damaged coating, corroded metal, and bare metal, shall be performed in accordance with Steel Structures Painting Council Specification SSPC-SP6 for “Commercial Blast Cleaning”. Surfaces shall be dry at the time of blasting. Within eight (8) hours after cleaning, but in any event prior to the deposition or formation of any detectable moisture or corrosion, all blast cleaned surfaces shall be cleaned of dust and abrasive particles by brushing, vacuum cleaning, and/or blow-down with clean, dry compressed air, and given the first coat of paint. Cleaning and painting shall be programmed so that dust or other contaminants from the cleaning process do not fall on wet, newly painted surfaces, and surfaces not intended to be painted shall be suitably protected from the effects of cleaning and painting operations. Prior to painting, abrasive particles, dust, water, and all other matter on the frames which might, in the opinion of the Contracting Officer or Government Representative, adversely affect the painting application, shall be removed to the satisfaction of the Contracting Officer or Government Representative.
b. Paint Requirements. Paint shall be delivered in sealed containers with labels to indicate manufacturer, contents, and any special instructions. Paints and painting materials shall be stored under cover and protected from extreme temperatures. Paints shall not be used if they have exceeded the closed shelf life or pot life recommended by the manufacturer. Additionally, paints shall not be applied in weather or humidity conditions not recommended by the manufacturer.
c. Application of Coatings. Surface preparation and paint application shall be in strict compliance with the coating manufacturer’s recommendations. The Contractor shall take particular care to insure that coating system requirements are met in all areas, especially those difficult to coat, such as flange undersides. All requirements outlined in this specification are additional to the manufacturer’s recommendations and does not relieve the Contractor from meeting both the manufacturer’s recommendations along with the additional requirements outlined in this specification.
d. Coating System. Paint the entire frame with one coat of Carbozinc 85 (or equal); two coats of
Carboguard 235 HAR with LT (or equal) Cure multi-purpose marine epoxy coating system. Apply two coats of Carboguard 235 HAR with LT (or equal) Cure at 4 to 8 mils per coat, plus two stripe coats over edges, cutouts and welds. The final coating shall be Carbothane 134 HG (or equal) according to the manufacturer’s recommendations. The final coating color shall match that of the existing tainter gates.
e. Inspection. Surface preparation and paint application may be inspected by the Contracting Officer or Government Representative for compliance with the provisions of this section. Blast cleaned surfaces and each applied coat of paint may be examined for imperfections by the Contracting Officer or Government Representative.
f. Warranty. The contractor shall warranty all labor, parts and materials relative to the work described above for a minimum of one (1) year. This warranty shall be in writing and specify that mechanical failure to the above described Tainter Gate Brace Frames directly associated with the workmanship performed under the scope of this contract shall be repaired within a reasonable period of time (not longer than four weeks) upon failure without cost to the Government resulting from labor, travel or shipping.
4. INSURANCE VERIFICATION.
Contractor shall provide Contracting Officer with written proof that all insurance required by State and Local Governments have been acquired for the time period covered under this contract. No further insurance requirements will be imposed by the Corps of Engineers for this contract.
5. WAGE RATES
In accordance with contract clause FAR 52.222-6, Davis-Bacon wage rates are applicable to this procurement and can be located at http://www.dol.gov.
6. DAMAGE REPORTS
All instances where Government materials, supplies, property, and/or equipment are damaged shall be reported immediately to the Project Supervisor at John W. Flannagan Dam. When the damage is caused by contract employees, a written report of the incident and extent of such damage shall be submitted to the Project Supervisor, Within 2 work days (less weekends and holidays) of occurrence. For property damage Accidents of $2,000 or more, the Contractor will complete and submit to the Resource Manager a copy of ENG 3394.
7. CONTRACT EMPLOYEES' CONDUCT AND COMPETENCY
Employees shall conduct themselves in a proper manner at all times. Since the majority of work shall be performed in the presence of the general public, the conduct of all Employees are critical and will be closely monitored. Use of controlled substances or Consumption of beer or alcoholic beverages by contract employees is strictly prohibited.
The contractor may be required to immediately remove from the work site any employee Of the Contractor who is incompetent or who endangers persons or property or who’s Physical or mental condition is such that it would impair the employee's ability to satisfactorily perform the work.
8. WORKING HOURS
Normal working hours are Monday through Friday, 7:30 a.m. to 4:00 p.m. Eastern excluding government holidays. Work inside Government buildings or other secured areas shall be performed during the above referenced work hours.
Ten Federal holidays observed are as follows:
New Year's Day (January 1st) Martin Luther King Day (3rd Monday in January) President's Day (3rd Monday in February) Memorial Day (Last Monday in May) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veteran's Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)
When one of the above designated holidays falls on a Sunday, the following Monday is Observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.
Work that interferes with other ongoing functions at the project shall be scheduled around Normal working hours.
Work shall be scheduled around the above listed Federal holidays unless approved in advance.
Work shall be performed during daylight hours and days to be worked will be at the Discretion of the Project Supervisor.
9. REQUIRED START AND COMPLETION DAYS
Once the successful contractor is given the Notice-To-Proceed (NTP), the contractor will start the work within five
(5) calendar days. The contractor will have twenty-five (25) calendar days to finish the work from receipt of the notice to proceed.
10. DEFICIENCIES
The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises. If the Contractor does not promptly replace or correct rejected work, the Government may –
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor
OR
(2) Terminate for default the Contractor’s right to proceed.
11. PRE-CONSTRUCTION CONFERENCE
The Contractor shall attend a pre-construction conference, prior to the initiation of work under this contract. The Contractor's Accident Prevention Plan and all contractor submittals must be accepted prior to this meeting.
12. SITE VISIT
Contractors are encouraged to make a site visit by contacting:
Chip Miller
(276) 835-9544 X 8970 192 White Water Rd
Haysi, VA 24256
13. CONTRACTOR INVOICE
Contractor shall submit their invoice to:
U.S. Army Corps of Engineers
ATTN: Steve Hann OR-TM 502 8th Street Huntington, WV 25701
(304) 399-6972
14. CONTRACTOR AND GOVERNMENT EQUIPMENT AND SUPPLIES
The contractor shall furnish all personnel, equipment, transportation, disposal, supplies, materials, and supervision to perform the work. No government equipment or supplies shall be used for this project. The Contractor shall provide Personal Protection Equipment (PPE) to include steel-toed safety boots, hard hat, safety glasses or goggles, hearing protection, sleeved shirts, long pants, gloves, sunscreen and other applicable PPE specified in EM 385-1-1 and Appendix A.
15. EQUIPMENT, MATERIAL, AND SUPPLY INSPECTIONS:
All materials shall be inspected upon delivery and/or prior to use by government personnel. Materials shall be of high quality, commercial grade and meet or exceed industry standards or otherwise specified by this contract.
16. CONTRACTOR SUBMITTALS
The successful offeror shall provide as a minimum the following documentation. All contractor submittals must be reviewed and accepted by the contracting officer or government designated authority prior to commencement of any work.
A. Accident Prevention Plan B. Activity Hazard Analysis C. Invoice as stated on the contract award.
D. Man hour report to project office at completion of work.
17. SAFETY-CONTRACTOR SAFETY REQUIREMENTS
a. General. Contractor must prepare an accident safety plan. If the Contractor fails or refuses to promptly comply with safety and security requirements as specified herein, any project employee may stop all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such work stoppage shall be made subject to any claims for extension of time or for excess costs or damages sustained by the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.
i. The contractor is responsible to ensure safe access to all areas needing blasted and painted.
b. Contractor Accident Prevention Plan (APP) Contractor Accident Prevention Plan (APP). The
Contractor shall prepare an Abbreviated Accident Prevention Plan following the outline provided in EM 385-1-1, Appendix A.11 as a minimum. The contractor shall address each element and sub-element in the outline in the order they appear in Appendix A. If other areas of the EM 385-1- 1 are pertinent to the contract the contractor must assure these areas are addressed as well. Any item from the outline that does not apply must be listed and a brief explanation of the reason it is not required. The plan must be accepted by the Contracting Officer prior to commencement of any work. Appendix A is included as attachment 1 to this document.
i. The Web Address for EM-385-1-1 is (may have to copy and paste link):
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_ 385-1-1.pdf
ii. Contractor crews of two or more must have at least two people holding current certification in First Aid and CPR as approved by the American Red Cross. Individuals working alone must hold current certification in First Air as approved by the American Red Cross.
c. Activity Hazard Analysis (AHA). Before beginning each work activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity shall prepare an AHA. All on-site employees shall review the approved AHA prior to performing work and during weekly and “Tool Box” safety meetings as appropriate. All employees performing work under this contract shall wear personal protective equipment as specified in EM 385-1-1 including as a minimum safety-toed boots, hard hat, safety glasses, hearing protection, sleeved shirts, long pants, and gloves and other equipment common to trade as specified in EM 385-1-1.
a. AHAs shall define the activities being performed and identify the work sequences, the specific anticipated hazards, site conditions, equipment, materials, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level of risk.
b. Work shall not begin until the AHA for the work activity has been accepted by the Government
Designated Authority (GDA) and discussed with all engaged in the activity, including the Contractor, subcontractor(s), and Government on-site representatives at preparatory and initial control phase meetings.
c. The names of the Competent/Qualified Person(s) required for a particular activity (for example, electrical, excavations, scaffolding, fall protection, other activities as specified by OSHA and this manual) shall be identified and included in the AHA. Proof of their competency/qualification shall be submitted to the GDA for acceptance prior to the start of that work activity.
d. The AHA shall be reviewed and modified as necessary to address changing site conditions, operations, or change of competent/qualified person(s).
18. SECURITY REQUIREMENTS
All Contractors and subcontractor employee(s) working on this contract who require access in and/or around any Huntington District facilities shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD 12). The Huntington District Security Management Office shall submit contractor(s) personal information in order to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results provided by the Huntington District Security Management Office of the background investigation. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Huntington District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.
Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Huntington District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted unescorted access in or on District facilities. The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working, (2) Project Name, (3) Contract Number and (4) Task Order Number when applicable.
The documents listed below are required:
SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual must take prints, ORI block on the FD 258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management office).
Contractor shall report any changes in personnel or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.
Following submission of paperwork, the Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, Security Management Office will make recommendations to the PCO or their Designated Representative. The Security Management Office cannot give approval due to unfavorable report(s). The Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise Contractor of the decision.
FOREIGN NATIONALS
The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters Staff to accomplish. All Foreign Nationals must comply with the following paragraph:
In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.
In order to assure forms are properly completed, and to minimize time delays, Contractor is encouraged to work closely with the Security Management Office. Per AR 380-10, Foreign Disclosure, All Foreign National Visits must be submitted to the Security Office within 30 days prior to the visit. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.
The Contractor shall contact the Security Management Office by phone, letter, or email at the following numbers/addresses:
CELRH-SM
502 Eighth Street Huntington, WV 25701
Stephen R. Curry, phone (304) 399-5695; email stephen.r.curry@usace.army.mil Matthew D. Green, phone (304) 399-5294; email matthew.d.green@usace.army.mil Sandra L. Hardwick, phone (304) 399-5612; email sandra.l.hardwick@usace.army.mil
AT/OPSEC Requirements
1. AT Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.
2. Access and General Protection/Security Policy and Procedures. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
3. For contractors who do not require CAC, but require access to a DoD facility or installation.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
4. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something). The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
5. For Contracts that Require OPSEC Training. All new contractor employees will complete Level I
OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites: https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.
6. Pre-screen candidates using E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
*When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
5152.222-9000 Contractor Supply and Use of Electronic Software for Processing Wage Rate Requirements Statute Certified Labor Payrolls (APR 2011)
(a) The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.
(b) If the contractor elects to use an electronic payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with the Wage Rate Requirements statute. When the contractor uses an electronic payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.
(c) The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the Federal Acquisition Regulation (FAR);
(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract
(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export in an Excel spreadsheet to be imported into the contractor's Quality Control System (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government's RMS;
USACE Acquisition Instruction (UAI) Version 4 dated 25 JAN 2017
(5) demonstrated security of data and data entry rights;
(6) ability to produce contractor-certified electronic versions of weekly payroll data;
(7) ability to identify erroneous entries and track the date/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;
(8) capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.
(d) All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services shall not be a separately priced or reimbursed item under this contract.
(End of clause)
5152.231-9000 Equipment Ownership and Operating Expense Schedule (MAR 1995)
(a) This clause does not apply to terminations. See UAI 5152.249-9000, Basis for Settlement of Proposals, and Federal Acquisition Regulation (FAR) part 49.
(b) Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region II. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-
36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the simplified acquisition threshold (SAT), the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
5152.236-9009 Partnering (FEB 2000)
In order to most effectively accomplish this contract, the Government proposes to form a partnership with the Contractor to develop a cohesive building team. It is anticipated that this partnership would involve the Contractor, primary subcontractors and designers, and the Corps of Engineers. This partnership would strive to develop a cooperative management team drawing on the strengths of each team member in an effort to achieve a quality project within budget and on schedule. This partnership would be bilateral in membership and participation will be completely voluntary. Any cost associated with effectuating this partnership, excluding travel and lodging cost of Government personnel, will be borne by each party. The partnering meetings, if needed, shall be held informally during the period of performance at John W.
Flannagan Dam, Haysi, VA; at the request of either the Contractor or the Government. Participation attendance via phone conference/web meeting would be allowed for those personnel not already working on site.
Section H - Special Contract Requirements
DAVIS BACON WAGE DETERMINATION
General Decision Number: VA180025 01/05/2018 VA25
Superseded General Decision Number: VA20170025
State: Virginia
Construction Types: Heavy (Heavy and Sewer and Water Line)
Counties: Bland, Carroll, Dickenson, Floyd, Galax*, Grayson, Henry, Lee, Martinsville*, Norton*, Russell, Wise and Wythe Counties in Virginia.
*INDEPENDENT CITIES
HEAVY CONSTRUCTION PROJECTS (Including Sewer and Water Lines)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.
Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/05/2018
SUVA2010-026 09/01/2010
Rates Fringes
CARPENTER........................$ 9.00 0.84
CEMENT MASON/CONCRETE FINISHER...$ 11.00 1.02
ELECTRICIAN......................$ 15.55 2.37
LABORERS
Common or General...........$ 7.64 0.51 Flagger.....................$ 7.25 Pipelayer...................$ 7.89
POWER EQUIPMENT OPERATOR:
Backhoe.....................$ 10.97 0.72 Bulldozer...................$ 18.00 Crane.......................$ 20.63 7.28 Excavator...................$ 11.36 1.09 Loader......................$ 12.79 1.17
TRUCK DRIVER
Dump Truck..................$ 10.61 1.03 Off the Road Truck..........$ 16.50
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate
(weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.204-22 Alternative Line Item Proposal JAN 2017 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.222-3 Convict Labor JUN 2003 52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005…