Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_W91236-13-B-0001.pdf | ||
| W91236-13-B-0001-0001.pdf | ||
| Bldg24_DLA_Site_Visit_Attendance_Sign_In_(29Jan2013).pdf | ||
| Background_Check_Form_2012_(2).xls | XLS spreadsheet | |
| W91236-13-B-0001.pdf | ||
| DLA_Building_24.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
REPAIR BUILDING 24
DEFENSE GENERAL SUPPLY CENTER, VIRGINIA
PROJECT NO. P.2012.00356
WTS PROJECT NO. 0906-XX
RTA SUBMITTAL
26 OCTOBER 2012
WALLER, TODD & SADLER ARCHITECTS, INC.
1909 CYPRESS AVENUE
VIRGINIA BEACH, VIRGINIA 23451
(757) 417-0140; FAX (757) 417-0144
email: wts@wtsarch.com
REPAIR BUILDING 24, DEFENSE GENERAL SUPPLY CENTER P.2012.00356
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 30 00.10 50 PROJECT WORK REQUIREMENTS AND RESTRICTIONS
01 30 00.20 50 ADMINISTRATIVE REQUIREMENTS
01 31 19.00 50 PROJECT MEETINGS
01 32 01.00 50 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00.00 50 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01.10 USACE QUALITY CONTROL SYSTEM (QCS)
01 45 01 USACE QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 50 61 DUST CONTROL
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 58 00 PROJECT IDENTIFICATION
01 60 00.00 50 PRODUCT REQUIREMENTS
01 62 35.00 50 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23.00 50 OPERATION AND MAINTENANCE DATA
01 80 00 COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 83 13.00 20 LEAD IN CONSTRUCTION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 40 00 COLD-FORMED METAL FRAMING
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 41 16.00 10 LAMINATE CLAD ARCHITECTURAL CASEWORK
06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 21 40 FOAMED-IN-PLACE MASONRY WALL INSULATION
07 22 00 ROOF AND DECK INSULATION
07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
07 57 13 SPRAYED POLYURETHANE FOAM (SPF) INSULATION
07 60 00 FLASHING AND SHEET METAL
PROJECT TABLE OF CONTENTS Page 1
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 60 45 TRANSLUCENT PANELS
08 71 00 DOOR HARDWARE
08 78 00 SPECIAL FUNCTION HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 29 00 GYPSUM BOARD
09 30 00 CERAMIC TILE AND MARBLE
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 68 00 CARPET
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 21 13 TOILET COMPARTMENTS
10 22 13 WIRE MESH PARTITIONS
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 21 - FIRE SUPPRESSION
21 13 17.00 10 DRY PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 93.00 10 TESTING, ADJUSTING, AND BALANCING OF HVAC SYSTEMS
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS
23 09 23 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 11 23.00 10 GAS PIPING SYSTEMS
23 23 00 REFRIGERANT PIPING
23 52 00.00 10 WATER AND STEAM HEATING; OIL, GAS OR BOTH; UP TO 20 MBTUH
23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
PROJECT TABLE OF CONTENTS Page 2
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 11 23 NATURAL GAS PIPING
33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND
33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
SECTION 01 30 00.10 50
PROJECT WORK REQUIREMENTS AND RESTRICTIONS
07/07
PART 1 GENERAL
1.1 DEFINITIONS
a. Facility: The facility is:
Building 24 Defense General Supply Center, Virginia
CO: Contracting Officer or his authorized representative.
DPW: Defense General Supply Center Directorate of Public Works:
Raymond Hall; (804) 279-4855 POC: Utilities Chief, Glenn Cooper; (804) 279-3996
1.2 SPECIAL CONTRACTOR REQUIREMENTS
1.2.1 Project Phasing and Performance period
The Contractor shall complete the work within the duration specified in Section 00800 "Contract Requirements". The Contractor shall be required to phase the work as required to assure that all schedule durations are met.
1.2.2 STRUCTURAL DRAWING DIMENSIONS
The building layout, including both horizontal and vertical dimensions, is shown on the Architectural sheets contained in the contract drawings.
The Contractor shall use the dimensions from the Architectural sheets to obtain dimensions for foundation layout and structural members as necessary to prepare all shop drawings and fabricate structural members. There may be some instances where the Contractor shall have to adjust actual dimensions to the submitted items that he will use, to finalize the location of a structural member. Any such adjustments shall be clearly identified on the submitted shop drawings for Government review.
1.3 COOPERATION WITH USING AGENCY AND OTHER CONTRACTORS
During the period of this contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of work being accomplished under this contract. It shall be the responsibility of the Contractor on this contract to be fully informed of the extent of the limits of work to be performed by other Contractors. Should there be any conflict between these limits, it shall be brought to the attention of the Contracting Officer(CO)and the CO's decision shall be final. Also, prior to completion of work under this contract, members of the Using Agency may be performing work or occupying facilities on or adjacent to the area. The Contractor shall arrange his plant and shall schedule and perform this work so as to effectively cooperate with all other Contractors and Government agencies.
1.4 PERSONNEL RESTRICTIONS
Personnel are limited to the immediate site areas and shall not enter buildings or facilities not involved in the work. All employees of the
SECTION 01 30 00.10 50 Page 1
Contractor will be subject to all rules and regulations of the Facility which pertain to personnel. The Contractor shall erect fences and signs as specified and be responsible for the restrictions of all personnel. The Contractor's plans for restricting personnel access to the project site shall be submitted for approval as a part of the Safety Plan (Accident Prevention Plan). Facility access shall be restricted. Contractor shall comply with current security requirements. All vehicles shall be registered with the military police.
1.5 TRANSPORTATION FACILITIES
The Facility is served by an all weather surfaced road network. Road(s) within the Facility proposed to be used by the Contractor shall be subject to prior approval of the Facility authorities and such roads, if used, shall be maintained throughout construction and shall be restored to as good condition as existed prior to their use. The Contractor shall also construct, subject to approval, such temporary haul roads and bridges as may be necessary for conducting his work. Any such temporary construction shall be removed and the affected area restored to its original condition.
All costs for the use of existing transportation facilities, for the construction of temporary facilities, and for maintenance, repair, removal and restoration shall be borne by the Contractor.
1.5.1 Use of Roads
Hard-surfaced roads from major and primary municipal roads serve the Facility. The movement of all vehicles within the Facility shall be confined to the roads designated and shall comply with traffic regulations within the Facility. The Contractor shall keep all roads clear of all obstructions and free of mud and other foreign materials resulting from operations. The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull off the road and come to a complete stop when meeting emergency vehicles, or vehicles with flashing lights. Facility speed limits and traffic controls shall be observed.
1.5.2 Road Restrictions
The movement of all vehicles within the Facility shall be confined to the roads designated and shall comply with traffic regulations within the Facility. Other roads may be used only with the approval of the CO.
1.5.3 Cleated Vehicles
Cleated vehicles shall not be moved over surfaced roads except at the immediate site of the area where they are to be used.
1.6 COORDINATION IN WORK AREAS
1.6.1 Unoccupied Work Area
The area where the Contractor is scheduled to perform the work will not be occupied during the work, however, the Contractors work activities may affect other area(s) that are occupied. All work shall be in accordance with the Contractor's work plan.
1.6.2 Maintenance of Utilities
Any active utilities, including but not limited to electricity, gas, water, sewer, heating, air conditioning, or any like service, that will require
SECTION 01 30 00.10 50 Page 2 interruption or replacement in any occupied area affected as a result of the Contractors scheduled work activities, shall be temporarily provided by the Contractor at his own expense until the affected service is fully and permanently restored. All temporary method(s) of service replacement the Contractor proposes for use on this contract shall be approved by the CO prior to commencing the work.
1.6.3 Hours of Work
The normal work hours for construction shall be from 7:00 a.m. to 4:30 p.m.
Monday through Friday of each week. Any request to change these hours shall be made in writing to the Contracting Officer at least two calendar days prior to the desired day on which the change is to go into effect.
The changed hours shall not go into effect until written permission has been received from the Contracting Officer.
1.6.4 Existing Utility Location
Existing utilities must be located before doing any digging work on Facility. The Contractor shall be responsible to contact Miss Utility, obtain all necessary existing utility locations, which may be necessary to accomplish his work, and mark any utility lines in the immediate vicinity of his work. It shall be the responsibility of the Contractor to contact Miss Utilities at 1-800-552-7110 for locating commercial utilities 48 hours prior to digging operations.
1.6.5 Digging Permits
Contractor is responsible for obtaining all digging permits, including associated locating and marking services, in accordance with installation and local requirements, at no additional cost to the Government.
"Clearance Permits for Digging', must be obtained before doing any work on Facility. The Contractor shall be responsible to obtain all necessary digging permits and pay costs associated with the permit,which may be necessary to accomplish his work.
1.6.6 Personnel Escort
An authorized Contractor representative must escort all personnel attempting to obtain a badge to Security. The representative shall sign documentation that the employee meets Security criteria and is suitable for a badge to be issued.
1.7 NOTIFICATION OF WORK
It shall be the responsibility of the Contractor to submit a "Notification of Work" form prior to performance of work that may come into contact with electrical distribution system components within DVP's zone of responsibility. Submission shall be required a minimum of 48 hours in advance of the scheduled work. DVP's zone of responsibility is defined as all primary lines (600 volts and above) and down to the first point of positive disconnection past the distribution transformer reducing the supply voltage below 600 volts. Provide copies of this notification to the POC, DSCR's Utilities Chief, Glenn Cooper, (804) 279-3996(phone), and DSCR's Directorate of Public Works (DPW) Raymond Hall (804) 279-4857(fax).
SECTION 01 30 00.10 50 Page 3
1.8 INTERRUPTIONS OF UTILITIES
1.8.1 Approval
Utility services shall not be interrupted by the Contractor to relocate, make connections, or interrupt for any purpose, without written approval of the CO.
1.8.2 Request
Request for permission to shut down services shall be submitted in writing to the CO not less than 10 calendar days prior to date of proposed interruption.The request shall give the following information:
a. Nature of Utility (Gas, L.P. or H.P., Water, Elec.)
b. Size of line and location of shutoff.
c. Buildings and services affected.
d. Hours and date of shutoff.
e. Estimated length of time service will be interrupted.
1.8.3 Service Interruptions
Services shall not be shut off until receipt of approval of the proposed hours and date from the Contracting Officer.
1.8.4 Timely Disconnections
Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or non-work days of the Using Agency without any additional cost to the Government.
1.8.5 Utilities Operation
Operation of valves on water mains will be by Government personnel. Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Facility Fire Department shall be notified by the Contractor in writing 72 hours prior to the proposed interruption. The Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay and shall restore service without delay in event of emergency.
1.8.6 Gas
Flow in gas mains which have been shut off shall not be restored until the Government inspector has determined that all items serviced by the gas line have been shut off.
1.8.7 Electrical: Dominion Virginia Power (DVP)
An "Outage Request" form shall be submitted a minimum of 14 days in advance of any required electrical power outage.
SECTION 01 30 00.10 50 Page 4
1.8.7 Cost of Government Responsibility
Cost for which the Government is responsible for:
a. Notify the COR of the planned outage.
b. Complete the "Request for Outage at Defense General Supply Center" form and provide copies to the COR and DPW (Raymond Hall) 804-279-4857(fax)
1.8.8 Cost of Contractor Responsibility
Cost for which the Contractor is responsible for:
a. Notify the COR of the planned outage.
b. Complete the "Request for Outage at Defense General Supply Center" form and provide copies as follows:
(1) COR
(2) FAX to Defense General Supply Center DPW (Raymond Hall)
(3) FAX to POC (Utilities Chief, Glenn Cooper) so that billing arrangements can be established
1.8.9 Outage Request Processing
a. DPW will forward the request to the Facility Computer Room.
b. The Computer Room will notify DSCR's Utilities Chief (POC) (Glenn Cooper) at least 10 days in advance of the requested outage date.
c. DSCR's Utilities Chief (POC) (Glenn Cooper) will arrange to meet requestor and DPW (Chuck Hudson) at the site to determine method of disconnection and the customers to be interrupted.
d. DPW (Raymond Hall) will notify affected customers and confirm outage schedule.
e. DPW (Raymond Hall) will notify DSCR's Utilities Chief (POC) (Glenn Cooper) that the schedule is confirmed.
f. DSCR's Utilities Chief (POC) (Glenn Cooper) will execute the outage as agreed.
1.9 PHYSICAL DATA
The physical conditions indicated on the drawings and in the specifications are the result of site visits, surveys, and borings. Geotechnical report is appended to these specifications.
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
SECTION 01 30 00.10 50 Page 5
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
1.10.1 Schedule
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS
BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Defense 10 9 8 6 7 7 9 6 5 5 6 9 General Supply Center
1.10.2 Records
Upon acknowledgement of the Notice to Proceed and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
1.10.3 Impacted Days
The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day in each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the schedule of monthly anticipated adverse weather delays, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clauses entitled "Default (Fixed Price Construction)".
1.11 SITE CONTAMINATION
This site is designated a Category I site and is defined as a site that is located in a traditional non-hazardous location, such as in an administrative, recreation, or housing area and that the Government has no reason to suspect contamination.
1.11.1 Contamination Removal
In the event that contamination beyond that shown or specified is encountered, the Contracting Officer shall be advised immediately. The contamination shall be removed as directed and replaced with satisfactory
SECTION 01 30 00.10 50 Page 6 material. Payment therefore will be made in conformance with the CHANGES clause of the CONTRACT CLAUSES.
1.11.2 Compliance Requirements
The Contractor shall comply with applicable Federal, state and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with any hazardous material, substance or waste.
1.11.3 Requirements
The requirements of this clause and any act or failure to act by the Government shall not relieve the Contractor of any responsibility or liability for the safety of Government, Contractor or subcontractor personnel or property.
1.12 WORK IN QUARANTINED AREA
The work called for by this contract involves activities in counties quarantined by the Department of Agriculture to prevent the spread of certain plant pests which may be present in the soil. The Contractor agrees that all construction equipment and tools to be moved from such counties shall be thoroughly cleaned of all soil residues at the construction site with water under pressure and that hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, if this contract involves the identification, shipping, storage, testing, or disposal of soils from such a quarantined area, the Contractor agrees to comply with the provisions of ER 1110-1-5 and attachments, a copy of which will be made available by the Contracting Officer upon request.
The Contractor agrees to assure compliance with this obligation by all subcontractors.
1.13 HISTORICAL AND ARCHAEOLOGICAL FINDS
Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historical, and archaeological data, including relics and specimens which might otherwise be lost due to alteration of the terrain or building features as a result of any Federal construction project. Should the Contractor, or any of the Contractor's employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historical, or archaeological data, the Contractor shall immediately cease work at that location, avoid further disturbance, and notify the Contracting Officer, giving the location and nature of the findings. The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contractor shall exercise care so as not to disturb or damage artifacts or fossils uncovered during excavation operations, and shall provide such cooperation and assistance as may be necessary to preserve the findings for removal or other disposition. Any person who, without permission, injures, destroys, excavates, appropriates, or removes any historical or prehistoric artifact, object of antiquity, or archaeological resource on the public lands of the United States is subject to arrest and penalty of law. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in the contract in accordance with the applicable clauses of the contract.
SECTION 01 30 00.10 50 Page 7
1.14 EQUIPMENT-IN-PLACE LIST:
The Contractor shall maintain a list of equipment installed under the terms of the contract. In the event that the contract includes more than one building or facility, a list must be maintained for each and delivered to the Contracting Officer upon acceptance of each building or facility.
Forms to be used for this purpose shall be obtained from the Area Engineer's Office. The list shall include the following:
a. Contract number
b. Description of item
c. Model number
d. Serial number
e. Capacity
f. Name of manufacturer
g. Address of manufacturer
h. Condition of item
i. Replacement cost
j. Name of person who checked item
1.15 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.15.1 Allowable Costs
Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data when the Government can determine both ownership and operating costs for each piece of equipment or equipment groups of similar serial and series from the Contractor's accounting records. When both ownership and operating costs cannot be determined from the Contractor's accounting records, equipment costs shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule," Region II.
Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.
1.15.2 Rental Costs
Equipment rental costs are allowable, subject to the applicable provisions of the Federal Acquisition Regulations, and shall be substantiated by certified copies of paid invoices. Rates for equipment rented from an organization under common control, lease-purchase or sale-leaseback arrangements will be determined using the schedule except that rental costs leased form an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees are allowable. Costs for major repairs and overhaul are unallowable.
1.15.3 Equipment Costs
When actual equipment costs are proposed and the total amount of the pricing action is over $25,000, cost or pricing data shall be submitted on the Standard Form 1411, "Contract Pricing Proposal Cover Sheet". By submitting cost or pricing data, the Contractor grants to the Contracting Officer or an authorizing representative the right to examine those books, SECTION 01 30 00.10 50 Page 8 records, documents and other supporting data that will permit evaluation of the proposed equipment costs. After price agreement the Contractor shall certify that the equipment costs or pricing data submitted are accurate, complete and current.
1.16 SUBCONTRACTS AND WORK COORDINATION
Contract Clauses "SUBCONTRACTS", "PERMITS AND RESPONSIBILITIES", and "MATERIAL AND WORKMANSHIP" are supplemented as follows:
a. Divisions or sections of specifications are not intended to control the Contractor in dividing the work among subcontractor, or to limit work performed by any trade.
b. Contractor shall be responsible for coordination of the work of the trades, subcontractors, and materials.
c. The Government or its representative will not undertake to settle any difference between the Contractor and Contractor's subcontractors, or between subcontractors.
d. The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Corps of Engineers projects, or for any other reason is considered by the Contracting Officer to be incompetent or otherwise objectionable.
1.17 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT
The Contractor shall submit executed CENAO Form 987, Construction Manpower and Equipment Report daily. The report shall include manpower and equipment for the general and subcontractors. Forms are available from the Contracting Officer.
1.18 PURCHASE ORDERS
To ensure proper expediting of orders the Contractor and his subcontractors shall furnish to the Contracting Officer, one copy of each purchase order covering supplies or services required for performance of the work. Each purchase order shall clearly indicate the date of placement, the date delivery is required in order to avoid delay in the scheduled progress of the work, and the date delivery is promised by the supplier or producer.
Copies of purchase orders shall be forwarded on the date issued.
1.19 PROFIT
1.19.1 Weighted Guidelines
Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors shall be as follows:
Factor Rate Weight Value
Degree of Risk 20 Relative difficulty of work 15 Size of Job 15 Period of performance 15
SECTION 01 30 00.10 50 Page 9
Factor Rate Weight Value Contractor's investment 05 Assistance by Government 05 Subcontracting 25
1.19.2 Value
Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.
1.19.2.1 Degree of Risk
Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.
1.19.2.2 Relative Difficulty of Work
If the work is most difficult and complex, the weighting should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some things to consider: the nature of the work, by whom it is to be done, where, and what is the time schedule.
1.19.2.3 Size of Job
All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.
1.19.2.4 Periods of Performance
Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionately weighted to a minimum of .03 for jobs not to exceed 30 days. No weight where additional time not required.
1.19.2.5 Contractor's Investment
To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.
1.19.2.6 Assistance by Government
To be weighted from .12 to .03 on the basis of average to above average.
Things to consider: use of Government owned property, equipment and facilities, and expediting assistance.
SECTION 01 30 00.10 50 Page 10
1.19.2.7 Subcontracting
To be weighted inversely proportional to the amount of subcontracting.
Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionately increased to .12 where all the work is performed by the Contractor's own forces.
1.20 BLASTING
Blasting will not be permitted.
PART 2 PRODUCTS (THIS PART NOT USED)
PART 3 EXECUTION (THIS PART NOT USED)
-- End of Section --
SECTION 01 30 00.10 50 Page 11
SECTION 01 30 00.20 50
ADMINISTRATIVE REQUIREMENTS
10/06
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-04 Samples
COLOR/FINISH BOARDS; G
Physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
1.2 COLOR/FINISH BOARDS
Submit five sets of color boards within 63 calendar days after notice to proceed. The samples shall be presented on 8-1/2 by 11 inch boards (modules) with a maximum spread of 24 by 31 1/2 inches for foldouts.
Modules shall be designed to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, samples not less than 12 inches square shall be submitted with the board. If more space is needed, more than one board per set may be submitted. The Contractor shall certify that he has reviewed the color samples in detail and that the color samples are in accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples shall not relieve the Contractor of the responsibility to submit samples required elsewhere herein. Submittals shall be complete; Sheets containing samples shall consist of heavy, medium gray illustration board (not white or colored) capable of supporting a four inch by eight inch quarry tile without distorting the binder release or causing sheet tear-out due to hole failure. The sample board backing material shall be of sufficient strength to maintain its original configuration after samples have been attached to it for the duration of the construction.
1.2.1 Interior color/finish boards
Interior color/finish boards shall have attached samples of all interior appearance related construction items the Contractor proposes to furnish, including, but not limited to such items as interior paints; wood finishes;
ceramic tile; floor coverings; wall coverings; ceiling tiles; plastic laminates; solid surface materials; signage, etc.
SECTION 01 30 00.20 50 Page 1
1.2.2 Exterior color/finish boards
Exterior color/finish boards shall have attached samples of all exterior appearance related construction items the Contractor proposes to furnish, including but not limited to such items as brick, mortar, paints, window and door frames, roof, soffits, pre-cast units, gutters, and downspouts, etc.
1.2.3 Content
Color board shall consist of all samples, a finish schedule, floor plan, and interior elevations with each clearly indicating the location of each finish/color. Items other than material sample boards may be folded to 8-1/2" by 11" (i.e., floor plans, finish schedules etc.).
1.2.4 Identification
Identify each sample by use, location, and manufacturer's name. Group according to the location where each used.
1.2.5 Approval
Upon final approval, the Contractor shall prepare and submit to the Contracting Officer one set of the approved and corrected color/finish sample boards.
1.3 SUPERVISION
Contractor shall have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.4 PARTNERING
LEVEL A PARTNERING: To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership with the contractor and its subcontractors. In addition, other key personnel, including the client who will occupy the facility, the designer-of-record, principal individuals from the Government, the project sponsor, and the representative(s) of the facility owner will also be invited to participate in the partnering process. The partnering relationship is based upon trust, dedication to common goals, an understanding of each other's expectations and values, and a commitment to success. The goals of the partnering process are improved communication, efficiency and cost effectiveness, increased opportunity for innovation, and the continuous improvement of product quality. The partnership will strive to draw on the strength of each organization in an effort to achieve a quality project done right the first time, within budget, on schedule, and without any safety mishaps, thereby providing the opportunity for the contractor to make a reasonable profit.
Anticipate that the initial session will be one-day minimum and the follow-on sessions, held at a minimum of once every three months or as agreed to by the partners, will be half-day minimum. The initial partnering session shall be held away from the project site at a location acceptable to the contractor and to the Government; the follow-on sessions can be held at locations agreed to by the partners. Key members of the
SECTION 01 30 00.20 50 Page 2 prime and subcontractors teams, including senior management, must participate. For a Level A partnering session, the contractor is responsible for providing an experienced professional facilitator to conduct the meeting. The contractor shall pay all costs associated with the partnering effort, including facilitator, meeting room, audio-visual equipment, refreshments, and working meals. All participants are responsible for the costs of their own meals, lodging, and transportation required in order to attend the partnering session.
1.5 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions.
Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.
The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
1.6 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, SECTION 01 30 00.20 50 Page 3 such as hurricanes, terrorist threats, etc. Multiple email address will not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 30 00.20 50 Page 4
SECTION 01 31 19.00 50
PROJECT MEETINGS
04/06
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
A Project Submittal Schedule shall be submitted in accordance with paragraph entitled, "Project Meetings," of this section.
The Contractor shall submit a Monthly Progress Report at the first meeting of each month.
1.2 PRECONSTRUCTION CONFERENCE
1.2.1 Scheduling
After award of the construction contract and prior to the start of any construction work, the Contracting Officer (CO) will schedule and conduct a preconstruction conference. The Contractor's Project Manager, Superintendent and Quality Control System Manager shall attend this meeting. The Contractor is encouraged to have an officer of his company (Project Manager could be this person) and representation from each of his sub-contractors at the conference. This conference will be held at a location and time as specified by the CO.
1.2.2 Purpose
The purpose of this preconstruction conference is to enable the CO to outline the procedures that will be followed by the Government in its administration of this construction contract and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's supervision and inspection of contract work, about security requirements, regulations, etc. The CO may invite Using Service personnel and any other Government personnel to attend this conference.
1.2.3 Discussion Items
The following is a list of items for discussion during the preconstruction conference. However, the Contracting Officer may include additional items for discussion as conditions and the work require.
a. Authority of the Area/Resident Engineer and organization of the Area/Resident office.
b. Contractor's Progress Schedule.
c. Correspondence Procedures.
SECTION 01 31 19.00 50 Page 1
d. Contractor Labor Standards Provisions.
e. Contract Modifications and Administrative Procedures.
f. Contractor's Administrative, Laydown and Storage Areas.
g. Procedures for Processing Submittals.
h. Payment Estimate Data and Procedures.
i. Contractor Utilities.
j. Security Requirements and Other Regulations, if applicable.
k. Government Furnished Equipment, if applicable.
l. Disposition of Salvage Property.
m. Contractor Insurance Requirements.
n. Value Engineering Program.
o. Contractor Performance Evaluation.
p. As-Built Drawings.
q. Single Point of Contact for Warranty of Construction.
r. Turnover of Completed Facilities.
1.3 PROJECT MEETINGS
The Contractor shall attend monthly project meetings scheduled by the Government. The Contractor's Superintendent shall attend scheduled project meetings. Subcontractor representatives shall also attend.
A Monthly Progress Report shall be submitted with the progress schedule, and shall address potential factors of delay, deficiencies, material delivery schedules, submittals, and safety issues.
A Project Submittal Schedule shall be submitted showing full coordination with the project schedule. All products and tests under each submittal number shall be prioritized and linked to the progress schedule.
1.4 OTHER MEETINGS
Other meetings are or may be scheduled to be held after the Preconstruction Conference, and such meetings may include the following:
a. Accident Prevention Safety Plan
b. Quality Control Plan.
c. Environmental Protection Plan.
d. Warranty Management Plan (Post Construction Warranty Conference)
SECTION 01 31 19.00 50 Page 2
1.5 FACILITY MEETINGS
The Facility may also schedule meetings with the Contractor through the CO during the progress of construction work.
1.6 MINUTES OF MEETINGS
The Government will prepare minutes of the meeting and will provide the Contractor with a signed original for review and concurrence. The minutes shall include all items discussed at the meeting and the Government will make all corrections provided by the Contractor and resubmit the corrected minutes to the Contractor within seven days.
1.7 Warranty Management Plan
The Contractor shall provide a Warranty Management Plan, not less than 30 days prior to the Post-Construction Warranty Conference. As a minimum, include a table, showing the requirements, and attach certificates:
a. List of warranties provided.
b. List of equipment, names of manufacturers and suppliers and phone numbers.
c. Period of warranties and Start Date.
d. List of Extended Warranties.
e. Warranty Certificates.
f. Single Point of Contact for Warranty of Construction.
PART 2 PRODUCTS (This Part Not Used)
PART 3 EXECUTION (This Part Not Used)
SECTION 01 31 19.00 50 Page 3
SECTION 01 32 01.00 50
PROJECT SCHEDULE
10/06
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Progress, Schedules, and Network Analysis Systems
1.2 QUALIFICATIONS
The Contractor shall designate an authorized representative who shall be responsible for the preparation of all required project schedule reports.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Qualifications; G
Standard Activity Coding Dictionary;
SD-02 Shop Drawings
Preliminary NAS Project Schedule; G
Initial NAS Project Schedule; G
Baseline Network Analysis Schedule; G
Monthly Network Analysis Updates; G
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS, a Project Schedule as described below shall be prepared. The NAS Project Schedule shall be a composite schedule. The scheduling of construction shall be the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing
SECTION 01 32 01.00 50 Page 1 and maintaining an accurate Project Schedule. The approved Project Schedule shall be used to measure the progress of the work, to aid in evaluating time extensions, and to provide the basis of all progress payments. The Government will use the NAS Project Schedule to evaluate the contractor's progress for timely completion, plan for Quality Assurance verification of the work and evaluate the effects of a proposed modification on the contract duration (critical path activities).
3.2 QUALIFICATIONS- CONTRACTOR SCHEDULING REPRESENTATIVE
The Contractor shall designate, a scheduling representative, full-time on the job site, no other duties who shall be responsible for the preparation and submittal of the entire NAS project schedule including all items specified below and revisions to the schedule or supplemental completion schedules, as applicable or directed by the Contracting Officer. The scheduling representative shall be approved by the Contracting Officer based on a resume indicating as a minimum, formal training from software vendor or 5 years experience in working with NAS schedules.
3.3 BASIS FOR PAYMENT
The schedule shall be the basis for measuring Contractor progress. Lack of an approved schedule or scheduling personnel will result in an inability of the Contracting Officer to evaluate Contractor's progress for the purposes of payment. Failure of the Contractor to provide all information, as specified below, shall result in the disapproval of the entire Project Schedule submission and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes. In the case where Project Schedule revisions have been directed by the Contracting Officer and those revisions have not been included in the Project Schedule, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until revisions to the Project Schedule have been made.
3.4 PROJECT SCHEDULE
The contractor shall prepare the NAS schedule using a computer software system. The system utilized by the Contractor shall be capable of satisfying all requirements of this specification and ER 1-1-11. Manual methods used to produce any required information shall require prior approval by the Contracting Officer. The Contracting Officer intends to use PRIMAVERA P3. Should the contractor utilize software that is different than that utilized by the Contracting Officer, based on the software utilized by the contractor for the preparation of the NAS schedule, the contractor shall provide a copy of the software and a license to the Administrative Contracting Officer at the Government field office. The Contractor shall submit a copy of the user's manual outlining the selected CPM computer program's mathematical analysis capabilities, details, functions and operation. The Contractor shall provide to the Government a complete input listing for the selected software.
3.4.1 Use of the Critical Path Method
The Critical Path Method (CPM) of network calculation shall be used to generate the Project Schedule. The Contractor shall provide the Project Schedule in the Precedence Diagram Method (PDM).
SECTION 01 32 01.00 50 Page 2
3.4.2 Level of Detail Required
The Project Schedule shall include an appropriate level of detail. Failure to develop or update the Project Schedule or provide data to the Contracting Officer at the appropriate level of detail, as specified by the Contracting Officer, shall result in the disapproval of the schedule. The Contracting Officer will use, but is not limited to, the following conditions to determine the appropriate level of detail to be used in the Project Schedule:
3.4.2.1 Cost and Resource Loading
a. Cost Loading Activities: Equipment costs will be assigned to their respective Procurement Activities (i.e., the delivery milestone activity). Costs for installation of the material/equipment (labor, construction equipment, and temporary materials) will be assigned to their respective Construction Activities. The value of inspection/testing activities will not be less than 10 percent of the total costs for Procurement and Construction Activities. Evenly disperse overhead and profit to each activity over the duration of the project. The total of all cost loaded activities; including costs for material and equipment delivered for installation on the project, and labor and construction equipment loaded construction activities, shall total to 100 percent of the value of the contract.
b. Quantities and Units of Measure: Each cost loaded activity will have a detailed breakdown of the contract price, giving…