BASE
| BASE CONTRACT YEAR (Exhibit A) | |||||||
| CLIN | Description | ||||||
| Note: Fill in blue Section Only | |||||||
| 1001 | Preventive Maintenance- All labor, plant, parts, supplies and consumables to provide for the preventive maintenance of the facilities listed herein as specified in the Requirements (summation of 1001A through 1001K below) | $0.00 | |||||
| 1001A | FORT STEWART DSO | 1 | LS | $ | |||
| 1001B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 1001C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 1001D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 1001E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 1001F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 1001G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 1001H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 1001I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 1001J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| 1002 | Demand Maintenance- All labor, plant, parts, supplies and consumables to provide for tasks as conceived by the offeror in the demand maintenance plan within Limit of Liability for the facilities listed herein as specified in the Requirements (summation of 2002A through 2002K below) | $0.00 | |||||
| 1002A | FORT STEWART DSO | 1 | LS | $ | |||
| 1002B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 1002C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 1002D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 1002E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 1002F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 1002G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 1002H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 1002I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 1002J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| 1003 | Restorative Maintenance- All labor, plant, parts, supplies and consumables to provide for the restorative maintenance tasks as conceived by the offeror in the demand maintenance plan within Limit of Liability for the facilities listed herein as specified in the Requirements (summation of 1003A through 1003K below) | $0.00 | |||||
| 1003A | FORT STEWART DSO | 1 | LS | $ | |||
| 1003B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 1003C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 1003D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 1003E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 1003F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 1003G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 1003H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 1003I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 1003J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| 1004 | Mobilization/Demobilization | $0.00 | |||||
| 1004 | Mobilization/Demobilization | 1 | LS | $ | |||
| TOTAL BASE CONTRACT YEAR (sum of 1001 and 1002) | $0.00 |
&"Times New Roman,Bold"SECTION B
SUPPLIES OR SERVICES AND PRICES/COSTS
&"Times New Roman,Bold"Section B - Page &P of 5
OPT1
| OPTION YEAR 1 (Exhibit B) | |||||||
| CLIN | Description | ||||||
| Note: Fill in blue Section Only | |||||||
| 2001 | Preventive Maintenance- All labor, plant, parts, supplies and consumables to provide for the preventive maintenance of the facilities listed herein as specified in the Requirements (summation of 2001A through 2001K below) | $0.00 | |||||
| 2001A | FORT STEWART DSO | 1 | LS | $ | |||
| 2001B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 2001C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 2001D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 2001E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 2001F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 2001G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 2001H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 2001I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 2001J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| 2002 | Demand Maintenance- All labor, plant, parts, supplies and consumables to provide for tasks as conceived by the offeror in the demand maintenance plan within Limit of Liability for the facilities listed herein as specified in the Requirements (summation of 2002A through 2002K below) | $0.00 | |||||
| 2002A | FORT STEWART DSO | 1 | LS | $ | |||
| 2002B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 2002C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 2002D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 2002E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 2002F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 2002G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 2002H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 2002I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 2002J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| TOTAL OPTION YEAR 1 (sum of 2001 and 2002) | $0.00 |
SUPPLIES OR SERVICES AND PRICES/COSTS
&"Times New Roman,Bold"Section B - Page &P of 5
OPT2
| OPTION YEAR 2 (Exhibit C) | |||||||
| CLIN | Description | ||||||
| Note: Fill in blue Section Only | |||||||
| 3001 | Preventive Maintenance- All labor, plant, parts, supplies and consumables to provide for the preventive maintenance of the facilities listed herein as specified in the Requirements (summation of 3001A through 3001K below) | $0.00 | |||||
| 3001A | FORT STEWART DSO | 1 | LS | $ | |||
| 3001B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 3001C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 3001D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 3001E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 3001F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 3001G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 3001H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 3001I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 3001J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| 3002 | Demand Maintenance- All labor, plant, parts, supplies and consumables to provide for tasks as conceived by the offeror in the demand maintenance plan within Limit of Liability for the facilities listed herein as specified in the Requirements (summation of 3002A through 3002K below) | $0.00 | |||||
| 3002A | FORT STEWART DSO | 1 | LS | $ | |||
| 3002B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 3002C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 3002D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 3002E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 3002F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 3002G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 3002H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 3002I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 3002J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| TOTAL OPTION YEAR 2 (sum of 3001 and 3002) | $0.00 |
SUPPLIES OR SERVICES AND PRICES/COSTS
&"Times New Roman,Bold"Section B - Page &P of 5
OPT3
| OPTION YEAR 3 (Exhibit D) | |||||||
| CLIN | Description | ||||||
| Note: Fill in blue Section Only | |||||||
| 4001 | Preventive Maintenance- All labor, plant, parts, supplies and consumables to provide for the preventive maintenance of the facilities listed herein as specified in the Requirements (summation of 4001A through 4001K below) | $0.00 | |||||
| 4001A | FORT STEWART DSO | 1 | LS | $ | |||
| 4001B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 4001C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 4001D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 4001E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 4001F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 4001G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 4001H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 4001I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 4001J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| 4002 | Demand Maintenance- All labor, plant, parts, supplies and consumables to provide for tasks as conceived by the offeror in the demand maintenance plan within Limit of Liability for the facilities listed herein as specified in the Requirements (summation of 4002A through 4002K below) | $0.00 | |||||
| 4002A | FORT STEWART DSO | 1 | LS | $ | |||
| 4002B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 4002C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 4002D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 4002E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 4002F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 4002G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 4002H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 4002I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 4002J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| TOTAL OPTION YEAR 3 (sum of 4001 and 4002) | $0.00 |
SUPPLIES OR SERVICES AND PRICES/COSTS
&"Times New Roman,Bold"Section B - Page &P of 5
OPT4
| OPTION YEAR 4 (Exhibit E) | |||||||
| CLIN | Description | ||||||
| Note: Fill in blue Section Only | |||||||
| 5001 | Preventive Maintenance- All labor, plant, parts, supplies and consumables to provide for the preventive maintenance of the facilities listed herein as specified in the Requirements (summation of 5001A through 5001K below) | $0.00 | |||||
| 5001A | FORT STEWART DSO | 1 | LS | $ | |||
| 5001B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 5001C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 5001D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 5001E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 5001F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 5001G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 5001H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 5001I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 5001J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| 5002 | Demand Maintenance- All labor, plant, parts, supplies and consumables to provide for tasks as conceived by the offeror in the demand maintenance plan within Limit of Liability for the facilities listed herein as specified in the Requirements (summation of 5002A through 5002K below) | $0.00 | |||||
| 5002A | FORT STEWART DSO | 1 | LS | $ | |||
| 5002B | BRITTIN ES- FT. STEWART | 1 | LS | $ | |||
| 5002C | DIAMOND ES- FT. STEWART | 1 | LS | $ | |||
| 5002D | KESSLER ES- FT. STEWART | 1 | LS | $ | |||
| 5002E | PINCKNEY ES- FT. JACKSON | 1 | LS | $ | |||
| 5002F | PIERCE TERRACE ES- FT JACKSON | 1 | LS | $ | |||
| 5002G | LAUREL BAY CSO- LAUREL BAY | 1 | LS | $ | |||
| 5002H | BOLDEN ES- LAUREL BAY | 1 | LS | $ | |||
| 5002I | GALER ES- LAUREL BAY | 1 | LS | $ | |||
| 5002J | ELLIOT ES- LAUREL BAY | 1 | LS | $ | |||
| TOTAL OPTION YEAR 4 (sum of 5001 and 5002) | $0.00 |
SUPPLIES OR SERVICES AND PRICES/COSTS
&"Times New Roman,Bold"Section B - Page &P of 5
Other files
| File | Type | Posted |
|---|---|---|
| W91236-10-R-0021-0002.pdf | ||
| W91236-10-R-0021-0001 | — | |
| Attachments | — | |
| W91236-10-R-0021.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .