Q&A.pdf

PDF 52 KB Posted

Attached to
Repair Building 1005 Roof & Drying Tower Water Leaks
Solicitation number
W911YN19B5000
Issued by

View the file

Other files

File Type Posted
Abstract_(W911YN18B5000)a.pdf PDF
Bid_Opening_Sign_in.pdf PDF
imagejpeg_3003.jpg JPG image
imagejpeg_3005.jpg JPG image
imagejpeg_2001.jpg JPG image
imagejpeg_0003.jpg JPG image
imagejpeg_4.jpg JPG image
imagejpeg_2002.jpg JPG image
imagejpeg_0001.jpg JPG image
imagejpeg_1001.jpg JPG image
imagejpeg_3001.jpg JPG image
imagejpeg_3002.jpg JPG image
imagejpeg_1002.jpg JPG image
imagejpeg_0002.jpg JPG image
imagejpeg_1003.jpg JPG image
imagejpeg_2003.jpg JPG image
PIC.pdf PDF
amendment_0003.pdf PDF
W911YN19B5000-0002.pdf PDF
Q&A.pdf PDF
W911YN19B5000-0001.pdf PDF
BLDG_1005_TOWER_PICs.pdf PDF
PreBidSlides_W911YN19B5000.pdf PDF
Site_Visit_Sign_in_Roster.pdf PDF
W911YN19B5000_Roof_Repair_Bldg_1005.pdf PDF
SOW_Building_1005_Drying_Tower_and_Roof_Water_Leak.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q.1 What is the time line for the site phots submission?

A.1 Photos are loaded in FBO

Q.2 Clarify “temporary repairs”?

A.2 The term “Temporary repairs” is a naming convention to distinguish this project from potential future projects on the same building.

Q.3 What is the time line of the base removal of the equipment; and how long after the award and before NTP will the work occur?

A.3 The contract awardee will be required to submit Payment and Performance Bonds within 10 days of Award. NTP will be issued when pre-construction submittals (i.e Bonds) are correct and legally binding.

See FAR Clause 52.211-10 Commencement and Prosecution and Completion of Work.

Q.4 Is there any specialized access for approval for the flight line access work?

A.4 Access to the flight line requires escort by NGB personnel.

Q.5 Can the requirement for no Monday and weekend work be amended, the 30 day POP is challenging since the leak location is undetermined?

A.5. The POP is 30 days.

Q.6 What is the Bid Bond requirement – percentage and/or amount?

A.6 The amount of the bonds should comply with FAR 28.101-2 (b)-- Solicitation Provision or Contract Clause. The bid guarantee amount shall be at least 20 percent of the bid price but shall not exceed $3 million.

Q.7 What is the Power of Attorney for?

A.7 The Power of Attorney gives the Bonding companies signatory the legal ability to act on behalf of the surety.

Q.8 Describe “and/or replace” drip edge and seals?

A.8 – Drip edge may be repaired if not distressed beyond said state and sealed to prevent water intrusion.

Q.9 Clarify “temporary/replace’ drip edge and seals?

A.9 – Refer to Q.8

Q.10 What are the crane access requirements?

A.10 – Define crane verse a high lift. Equipment extending above BLDG 1005 Tower would require contractor to coordinate permit through JIA.

Q.11 Clarify “temporarily/replace equipment infrastructure”?

A.11 – Any equipment attached to the tower that needs to be temporarily removed to complete work will need to be replaced in original location and condition.

Q.12 Will the shop drawings and as builts require engineer stamp?

A.12 – No

Q.13 Clarify the preparation requirements for the wall panel installation?

A.13 – This requirement will not apply to this contract.

Q.14 Clarify the Shop Drawing requirement

A.14 – All drawings to be submitted in PDF and AutoCAD DWG format.

Q.15 What is the duration for Construction permit approval?

A.15 – 180 Days, No exception

File details come from the government source that posted it.