PreBidSlides_W911YN19B5000.pdf

PDF 294 KB Posted

Attached to
Repair Building 1005 Roof & Drying Tower Water Leaks
Solicitation number
W911YN19B5000
Issued by

About this file

Pre Bid Slides

View the file

Other files

File Type Posted
Abstract_(W911YN18B5000)a.pdf PDF
Bid_Opening_Sign_in.pdf PDF
imagejpeg_3003.jpg JPG image
imagejpeg_3005.jpg JPG image
imagejpeg_2001.jpg JPG image
imagejpeg_0003.jpg JPG image
imagejpeg_4.jpg JPG image
imagejpeg_2002.jpg JPG image
imagejpeg_0001.jpg JPG image
imagejpeg_1001.jpg JPG image
imagejpeg_3001.jpg JPG image
imagejpeg_3002.jpg JPG image
imagejpeg_1002.jpg JPG image
imagejpeg_0002.jpg JPG image
imagejpeg_1003.jpg JPG image
imagejpeg_2003.jpg JPG image
PIC.pdf PDF
amendment_0003.pdf PDF
W911YN19B5000-0002.pdf PDF
Q&A.pdf PDF
Q&A.pdf PDF
W911YN19B5000-0001.pdf PDF
BLDG_1005_TOWER_PICs.pdf PDF
Site_Visit_Sign_in_Roster.pdf PDF
W911YN19B5000_Roof_Repair_Bldg_1005.pdf PDF
SOW_Building_1005_Drying_Tower_and_Roof_Water_Leak.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911YN19B5000

LSGA182601 Repair Building 1005

Roof & Drying Tower Water Jacksonville Air National Guard Base

Jacksonville International Airport

PRE-BID CONFERENCE DATE:

Oct 18, 2018

INTRODUCTION

• Mr. Remi J. Eggers - Contracting Officer

• Maj Brandon Pruitt- Base Civil Engineer, 125TH FW, Contracting Officer’s Representative (COR)

INTRODUCTION

• Ensure you sign in on the attendance roster

• Your Name

• Company

• Your Position in Company

• Are you a Prime or a Subcontractor/supplier

SYNOPSIS

• Project: Project is to roof and flashing on building 1005 Jacksonville Air National Guard Base Magnitude-Between $100,000 and $250,000.

• A firm-fixed price contract will be awarded.

• Award will be to a Service Disabled Veteran Owned Small Businesses

(SDVOSB).

SOLICITATION

• On the web: www.fbo.gov

• Solicitation

– Attachments

– Questions & Answers Document (if any)

– Amendments (SF 30) (if any)

– check regularly & refresh web page

– Wage Determination FL180246 current (checked & updated within 10 days of bid opening if a new WD applies) http://www.fbo.gov/ https://www.fbo.gov/index?mode=form&id=0eac588309caa46eb26474697ed5ba84&tab=ntype

IMPORTANT ITEMS

• Please curtail questions to the solicitation document.

• A site visit will follow this presentation.

• Please stay together as a group for security and accountability

• Any questions you have during the site visit should be followed up in writing for an official response in accordance with the solicitation.

• A secondary organized site visit is not scheduled but might be if necessary

INVITATION FOR BID (IFB)

BASICS

• In the invitation for bid (IFB), FAR Part 14, process, a public bid opening occurs when the bids are due and the prices are read to the public

– There will be no discussion

– No correction of mistakes in most cases

– Award is always to the low, responsive, responsible bidder

BASIS FOR AWARD

• FAR 14.101(e) After bids are publicly opened, an award will be made with reasonable promptness to that responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price and the price-related factors included in the invitation.

• Must bid all items

• A bidder is determined to be responsible in accordance with FAR 9.104

WHAT IS THE CONTRACT

PERIOD?

Construction period is 30 calendar days after receiving the Notice to

Proceed.

This does not mean you have to take the entire period if the work can be accomplished in a shorter schedule.

DISCLAIMER

The following is a brief overview of the bid requirements

BIDDERS ARE STRONGLY

CAUTIONED TO CAREFULLY

READ THE REQUIREMENTS OF

THE SOLICITATION AND

COMPLY ACCORDINGLY

WHAT YOU MUST SUBMIT

(see section 00010)

• SF 1442, (Blocks 14-20c)

– Do not enter less than 60 days in Block

• Bid Bonds

• Section 00010, Bid Schedule

• Section 00600, Reps and Certs

• Acknowledge all Amendments (SF 30)

BID SCHEDULE

ITEM NO SUPPLIES/SERVICES QTY UNIT UNIT PRICE AMOUNT

0001 Repair Building 1005 1 Job Firm Fixed Price

PROJECT #: LSGA182601 repair building 1005 roof & drying tower water leaks at 125th Fighter Wing, Jacksonville, FL. The contractor shall provide all parts, tools, materials, labor, travel, expertise, and supervision necessary to complete the work as described in the attached statement

NET AMT $

BID SCHEDULE

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 Contractor Manpower 1 Job

Reporting

CONTRACTOR MUST INCLUDE A PRICE OR

MARK "NOT SEPARATELY PRICED"

Firm Fixed Price The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Air Force via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address:

http://www.ecmra.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government Fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2014. Contractors may direct questions to the help desk at: http://www.ecmra.mil.

FOB: Destination

NET AMT $

http://www.ecmra.mil/

ADDITIONAL REQUIREMENTS

Complete Page 2 of the SF 1442

- Enter Cage Code and DUNS Number in Block 14

THE SOLICITATION

• Section 00600 - Complete and insert representations and certifications (return those in Section 00600)

– Complete Electronic Representations and

Certifications in SAM– website provided in Section 00600

BID SUBMISSION

-Send to address in Block 7 of SF 1442 -Hand Carried Bids

- Deliver to address in Block 7, SF 1442 prior to bid due date

- Deliver to place of bid opening if hand carrying and attending the bid opening (125th FW, Bldg. 1006, LRS Class Room)

Mark the front of the envelope with, “Bid No. W911YN-18- B-5002”, Name and Address of Bidder -Due Date/Time: November 7, 2018, 10:00 AM Eastern (subject to change through Amendment)

WHAT TO EXPECT AT

OPENING

• Official Time based on www.time.gov, bid opening officer (BOO) will announce exact time bids are due and that no more bids will be accepted

• Bids are opened and read out loud with no comment on responsiveness (FAR 14.301) of bids, and recorded

• BOO opens Government estimate, records

• Abstract will be certified and posted to www.fbo.gov as soon as practical. Low bidder determined in accordance with DFARS 252.236-7007 http://www.time.gov/ http://www.fbo.gov/

IMPORTANT REMINDERS,

NOTICES, CONDITIONS

• Prospective bidders must bid on all items to be considered for award.

TECHNICAL INFORMATION

• Working hours on the Base (section 01000)

• Availability of Utilities

• Water and Electric (section 01000)

HOW QUESTIONS WILL BE

HANDLED

• ALL QUESTIONS AND ANSWERS SHALL BE

IN WRITING AND SHALL BE AN

ATTACHMENT TO THE SOLICITATION

• See solicitation section 00100. Questions must be submitted in writing only via email

• Submit questions NLT 5th business day prior to bid opening (currently 7 Nov).

• Questions and Answers will be posted on a non-attribution basis with solicitation information at www.fbo.gov

• May result in revisions to solicitation if warranted

QUESTIONS ???

Email your questions (if it’s not in writing, it didn’t happen)

Site Visit Follows This Briefing

Slide Number 1
Slide Number 2
INTRODUCTION
Slide Number 4
SOLICITATION
IMPORTANT ITEMS
INVITATION FOR BID (IFB) BASICS
BASIS FOR AWARD
WHAT IS THE CONTRACT PERIOD?
DISCLAIMER �The following is a brief overview of the bid requirements
WHAT YOU MUST SUBMIT�(see section 00010)
BID SCHEDULE
BID SCHEDULE
ADDITIONAL REQUIREMENTS
THE SOLICITATION
BID SUBMISSION
Slide Number 17
IMPORTANT REMINDERS, NOTICES, CONDITIONS
TECHNICAL INFORMATION
HOW QUESTIONS WILL BE HANDLED
QUESTIONS ???�Email your questions (if it’s not in writing, it didn’t happen)