Abstract (Final) Tar Lake Superfund.pdf

PDF 101 KB Posted

Attached to
Tar Lake Superfund
Solicitation number
W911XK26BA030
Issued by

About this file

This is an Abstract of Offers for solicitation W911XK26BA030 issued by the US Army Corps of Engineers, Detroit District on 20 August 2026 with offers opened on 21 September 2026. The solicitation concerns the Tar Lake Superfund remediation project and was certified by Contracting Officer Kari L. Tauriainen. Five offerors submitted bids: North Wind Remediation, LLC; Arrowhead Contracting, LLC; Taplin Enterprises, LLC; Engineering Remediation Resources Group, Inc.; and Cape Environmental Management, Inc. All offerors provided bid bonds at 20 percent or NTE $3 million and are registered in SAM with NAICS code 562910. Three amendments were issued prior to the opening.

The base bid includes 15 line items covering environmental remediation services with estimated quantities including 2,000 tons of demolition, 172,500 cubic yards of excavation, 130,200 tons of transportation and disposal, 130,200 tons of backfill import material, 85,700 cubic yards of backfill reuse material, 14 monitoring well abandonments, 40 monitoring well installations, biosparge system work, site restoration, utility services, and operational/functional services. Base bid totals ranged from $19,618,508.82 to $27,337,074.00. Option 1 includes six additional line items for Area G work with option bid totals ranging from $37,095.80 to $235,209.00. Total prices including the option ranged from $19,716,399.99 to $27,572,283.00. The abstract notes a typographical error in unit price only on one line item.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF OFFERS

1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES

W911 XK26BA030 20 August 2026 21 September 2026 1 1

4. ISSUING OFFICE I CERTIFY that I have opened, read, and recorded NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE) on this abstract al offers received in response to Kari L. Tauriainen, Contracting Officer

US Army Corps of Engineers this solicitation.

SIGNATURE

Detroit District �� Date: 2026.09.22 10:43:22 -04'00'

5. PROJECT TITLE I. GOVERNMENT ESTIMATE I.OFFERS

(Check A, B, Of' C and complete D, E, and F) N0.1 N0.2 N0.3 N0.4 N0.5

A. OFFEROR: A. OFFEROR: A. OFFEROR: A. OFFEROR: A.OFFEROR:

Tar Lake Superfund

A. HIRED LABOR

North Wind Remediation, LLC Arrowhead Contracting, LLC Taplin Enterprises, LLC Engineering Remediation Resources Cape Environmental Management, Group, Inc. Inc.

X B. REASONABLE CONTRACT (Without Proftt) B. BIO SECURITY (Type and Amount) B. BIO SECURITY (Type and Amount) B. BID SECURITY (Type and Amount) B. BIO SECURITY (Type and Amount) B. BIO SECURITY (Type and Amount)

Bid Bond 20%/NTE $3M Bid Bond 20%/NTE $3M Bid Bond $3M Bid Bond 20%/NTE $3M Bid Bond 20°/4/NTE $3M

6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C . .AM:NCM:NTS ACKNOWLEDGED C . .AM:NCM:NTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

C. REASONABLE CONTRACT (Including Proftt) 3 3 3 3 3

NAICS Code 562910 registered in SAM yes yes yes yes yes 7A. 7C.EST. D. F. ESTIMATED E. ESTIMATED E. ESTIMATED E. ESTIMATED E. ESTIMATED E. ESTIMATED ITEM 7B. DESCRIPTION OF OFFERED ITEM QUANTIT UNIT E. UNIT PRICE AMOUNT D. UNIT PRICE AMOUNT D. UNIT PRICE AMOUNT D. UNIT PRICE AMOUNT D. UNIT PRICE AMOUNT D. UNIT PRICE AMOUNT NO y

0001 TEMPORARY FACILITIES 1 JA $ 1,590,237.00 $ 1,590,237.00 $ 1,975,462.45 $ 1,975,462.45 $ 3,484,728.98 $ 3,484,728.98 $ 1,526,392.70 $ 1,526,392.70 $ 2,646,590.00 $ 2,646,590.00 $ 1,070,855.52 $ 1,070,855.52

0002 SITE PREPARATION 1 JA $ 574,552.00 $ 574,552.00 $ 7,989,247.82 $ 7,989,247.82 $ 2,066,281.12 $ 2,066,281.12 $ 3,511,744.39 $ 3,511,744.39 $ 4,581,990.00 $ 4,581,990.00 $ 3,725,743.50 $ 3,725,743.50

0003 DEMOLITION 2,000 TON $ 89.69 $ 179,380.00 $ 166.23 $ 332,460.00 $ 77.59 $ 155,180.00 $ 204.39 $ 408,780.00 $ 171.00 $ 342,000.00 $ 84.60 $ 169,200.00

0004 EXCAVATION -AREAS AJB/C/0 172,500 CY $ 17.43 $ 3,006,675.00 $ 20.38 $ 3,515,550.00 $ 20.44 $ 3,525,900.00 $ 14.60 $ 2,518,500.00 $ 19.50 $ 3,363,750.00 $ 14.65 $ 2,527,125.00

0005 TRANSPORTATION & DISPOSAL OF 130,200 TON $ 63.18 $ 8,226,036.00 $ 42.07 $ 5,477,514.00 $ 35.54 $ 4,627,308.00 $ 43.02 $ 5,601,204.00 $ 45.24 $ 5,890,248.00 $ 38.28 $ 4,984,056.00 EXCAVATED MATERIAL-AREAS AlB/C/D

0006 BACKFILL -IMPORT MATERIAL -AREAS AJB/C/0 130,200 TON $ 39.22 $ 5,106,444.00 $ 26.16 $ 3,406,032.00 $ 19.87 $ 2,587,074.00 $ 14.27 $ 1,857,954.00 $ 35.00 $ 4,557,000.00 $ 22.16 $ 2,885,232.00

0007 BACKFILL -REUSE MATERIAL-AREAS A/B/C/0 85,700 CY $ 21.76 $ 1,864,832.00 $ 7.36 $ 630,752.00 $ 5.61 $ 480,777.00 $ 11.32 $ 970,124.00 $ 20.00 $ 1,714,000.00 $ 10.93 $ 936,701.00

0008 MONITORING WELL ABANDONMENT 14 EA $ 3,987.00 $ 55,818.00 $ 1,601.89 $ 22,426.46 $ 1,788.60 $ 25,040.40 $ 11,857.33 $ 166,002.62 $ 9,538.00 $ 133,532.00 $ 1,238.99 $ 17,345.86

0009 MONITORING WELL INSTALLATION 40 EA $ 29,175.00 $ 1,167,000.00 $ 2,375.43 $ 95,017.20 $ 13,445.03 $ 537,801.20 $ 10,478.30 $ 419,132.00 $ 13,212.00 $ 528,480.00 $ 11,151.30 $ 446,052.00

0010 EXISTING BIOSPARGE SYSTEM ABANDONMENT 1 JA $ 70,794.00 $ 70,794.00 $ 496,886.65 $ 496,886.65 $ 373,086.18 $ 373,086.18 $ 513,713.66 $ 513,713.66 $ 50,719.00 $ 50,719.00 $ 23,792.45 $ 23,792.45 AND REINSTALLATION

0011 BIOSPARGE SYSTEM BUILDING INSTALLATION 1 JA $ 344,279.00 $ 344,279.00 $ 802,830.60 $ 802,830.60 $ 639,376.84 $ 639,376.84 $ 639,504.50 $ 639,504.50 $ 764,729.00 $ 764,729.00 $ 1,097,662.56 $ 1,097,662.56

0012 BIOSPARGE SYSTEM PIPING ANO WELL 1 JA $ 1,587,243.00 $ 1,587,243.00 $ 871,006.10 $ 871,006.10 $ 813,483.46 $ 813,483.46 $ 824,939.95 $ 824,939.95 $ 905,603.00 $ 905,603.00 $ 812,193.54 $ 812,193.54 EXPANSION

0013 SITE RESTORATION 1 JA $ 199,283.00 $ 199,283.00 $ 660,108.58 $ 660,108.58 $ 605,730.52 $ 605,730.52 $ 679,217.59 $ 679,217.59 $ 1,554,477.00 $ 1,554,477.00 $ 789,571.00 $ 789,571.42

0014 SITE UTILITY SERVICES 1 JA $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00

0015 OPERATIONAL & FUNCTIONAL PERIOD 1 JA $ 222,227.00 $ 222,227.00 $ 44,942.63 $ 44,942.63 $ 157,821.78 $ 157,821.78 $ 83,160.00 $ 83,160.00 $ 253,956.00 $ 253,956.00 $ 82,977.97 $ 82,977.97

TOTAL AMOUNT OF BASE BID $ 24,244,800.00 $ 26,370,236.49 $ 20,129,589.48 $ 19,770,369.41 $ 27,337,074.00 $ 19,618,508.82

OPTION 1

0016 SITE PREPARATION -AREA G 1 JA $ 8,687.00 $ 8,687.00 $ 25,277.26 $ 25,277.26 $ 14,371.45 $ 14,371.45 $ 8,237.24 $ 8,237.24 $ 54,635.00 $ 54,635.00 $ 10,960.98 $ 10,960.98

0017 EXCAVATION-AREA G 180 CY $ 31.50 $ 5,670.00 $ 12.91 $ 2,323.80 $ 113.66 $ 20,458.80 $ 29.98 $ 5,396.40 $ 178.00 $ 32,040.00 $ 197.96 $ 35,632.80

0018 TRANSPORTATION & DISPOSAL OF 130 TON $ 69.23 $ 8,999.90 $ 42.07 $ 5,469.10 $ 90.74 $ 11,796.20 $ 40.95 $ 5,323.50 $ 248.00 $ 32,240.00 $ 52.19 $ 6,784.70 EXCAVATED MATERIAL-AREA G

0019 BACKFILL -IMPORT MATERIAL -AREA G 130 TON $ 39.09 $ 5,081.70 $ 23.87 $ 3,103.10 $ 55.48 $ 7,212.40 $ 41.70 $ 5,421.00 $ 253.00 $ 32,890.00 $ 215.09 $ 27,961.70

0020 BACKFILL -REUSE MATERIAL -AREA G 90 CY $ 26.48 $ 2,383.20 $ 7.16 $ 644.40 $ 54.69 $ 4,922.10 $ 25.97 $ 2,337.30 $ 347.00 $ 31,230.00 $ 113.41 $ 10,206.90

0021 SITE RESTORATION -AREA G 1 JA $ 6,292.00 $ 6,292.00 $ 22,768.27 $ 22,768.27 $ 15,363.52 $ 15,363.52 $ 10,380.36 $ 10,380.36 $ 52,174.00 $ 52,174.00 $ 6,344.09 $ 6,344.09

TOTAL AMOUNT OF OPTION 1 BID $ 37,113.80 $ 59,585.93 $ 74,124.47 $ 37,095.80 $ 235,209.00 $ 97,891.17

Total Price $ 24 281 913.80 $ 26 429 822.42 $ 20 203 713.95 $ 19 807465.21 $ 27 572 283.00 $ 19 716 399.99

•Typographical error in unit price onty.