Copy of RFIs - Duluth Drydocking Services 24 Feb 2022.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
FY22 Duluth Drydocking
Solicitation number
W911XK22R0006
Issued by

About this file

This document includes a request for proposal from the U.S. Army Corps of Engineers Detroit District for drydocking and repair services of a tug and derrick barge in Duluth, Minnesota. The services include transporting the vessels to the contractor's site, drydocking them simultaneously for inspection and repairs by 19 May 2022, and providing required certification and documentation by 26 August 2022. The requirement is anticipated as a hybrid contract consisting of firm fixed price and time and materials CLINs. The solicitation is set aside 100% for small businesses, with award planned for 21 March 2022 to allow time for the contractor to receive the government vessels on 25 April 2022. Interested parties may submit questions to the Contract Specialist by the specified date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Solicitation IssuedFeb 14 2022Solicitation # W91XK-22-R-0006Questions CloseFeb 21 2022
FY22 Duluth Drydocking Services
NumberDate/Time

Received in Outlook (Govt Exchange Server) Question Answer Initials of Respondant Date/Time Answered

12/17/22 3:44PM-Schwartz CLIN 0002 Item 0035 & Billmaier CLIN 0001 Item 0015
oApproximately how much fuel is expected to be in each tank on arrival?
oDo we need to keep all the fuel separate during storage or can identical fuels be stored together?Current Levels Schwartz: Day Crane Tank 700 Gallons & Barge Tank 12,500 Current Levels: Tug Billmaier: #1 Port 1780 /4387 #1 STB 1780/4387 #2 Port 0/5276 #2 STB 0/5222 #2 CL 0/2940 Daytank 700/812, It is anticipated the tug will have 1500-2000 Gallons of Fuel on board. Fuel can be stored togetherDKC2-18-2022/ 3:40PM
22/21/22 4:19PMPeriod of Performance appears tight, and also conflicts itself. Is it 31 or 22 days?On 25 April 2022 the vessels will be delivered to the Contractors destination by the Government. All inspections and repairs will be conducted while in Drydock at the Contractors dock. The Government anticipates accepting the vessels at the contractors location on 19 May 2022 and receiving final ABS certification no later than 26 August 2022. Any contract extension requests must be approved by the Contracting Officer.DKC2-22-2022/ 3:00PM
32/21/22 4:19PMIf it is determined that the schedule cannot be met would you still like a submittal with a realistic plan based on the current lead times? Or should we no bid at this point?Yes, Still provide a proposal based on lead times and how it affects the contract completion deadlineDKC2-22-2022/ 3:00PM
42/21/22 4:19PMTug Billmaier - CLIN 0001 Item 0017 Gunnel repairs: is this 110' continuous or is it in numerous locations?If so, can you give approximate sizes per run?Not 110' Continuous, PER PWS, The contractor shall inspect and provide a condition found report of the entire gunnel. The contractor shall remove and replace 110 ft of gunnel & Stanchions with new. The 110 ft shall be approved by the Contracting Officer. It is antipated Upward of 4 runs, minimum run will be vertical stanchion to vertical stanchion.DKC2-22-2022/ 3:00PM
52/21/22 4:19PMTug Billmaier - CLIN 0001 Item 0018 Vertical D-Ring Fendering: Do you have a part number or better description of the existing fenders? Closest I could find to the description and pictures is a D shape D bore extrusion that is approximately 8" wide 8" high.(Timco F9-0000)The Top Rubber D Fendering is 10" x 10. The new Fendering shall meet the dimensions of the Top Rubber Fendering & Bottom Steel Half Pipe Fendering.DKC2-22-2022/ 3:00PM
62/21/22 4:19PMTug Billmaier - CLIN 0001 Item 0019 Stern Fendering: A better description is required if possible. I can approximate for estimating however for leadtime knowing the exact item would be beneficial.Shall match existing dimensions of the Top Rubber Fending of 10" x 10" D Rubber.DKC2-22-2022/ 3:00PM
72/21/22 4:19PMTechnical Capability, Volume 2: Is this an actual requirement, as we only have one drydock and would need to lift each vessel independently we cannot lift them simultaneously.Each Vessel is required to by drydocked together at the same facility simultaneously.DKC2-22-2022/ 3:00PM
82/22/22 1:00PMTug Billmaier - CLIN 0010 Item 0026 Option 6: ABS Load Line Certification and Plimsoil Line: we can price out administering the paperwork and interacting with ABS but this item is difficult if not impossible to bid complete outside of covering the submittal, performing the stability test and answering engineering questions posed by ABS.Can this question be rephrased? Tug Billmaier is required per SubChapter M to have Load Lines on the vessel. The contractor shall cordinate with ABS to achieve this.DKC2-22-2022/ 3:00PM
92/23/2022 8:51AMTug Billmaier - CLIN 0006 Item 0022 Option 2: Can the COE specify a type, brand, or model of dripless packing they are looking for? The more specific the betterContractor shall propose a dripless packing system for the Tug Billmaier that meets existing Shaft Size and Opening.DKC2-23-2022/12:00PM
102/23/22 8:51AMTug Billmaier - CLIN 0001 Item 0011: Please verify that this is a Load Line conversion only, the Billmaier is not being classedTug Billmiaer is required to have load lines installed in compliance with Sub Chapter M and ABS Certified and inspected vessel.DKC2-23-2022/12:00PM
112/23/22 8:51AMTug Billmaier - CLIN 0001 Item 0011: Can the COE post a comprehensive list of existing drawings for the Billmaier?Contact Daniel Carlson and will provide all known drawings of the Tug Billmaier including the original operating manual. List of drawings are attachedDKC2-23-2022/12:00PM
122/23/22 8:51AMTug Billmaier - CLIN 0001 Item 0007/0008: In the actual work descriptions, page 27 of PWS, the descriptions are identical, is that correct?0007 Balast Tank Inpspection - There are 3 ballast tanks 0008 Cooling Tank Inspection - There are 2 tanks which are interconnectedDKC2-23-2022/12:00PM
132/23/2022 3:30PMTug Billmaier - CLIN 0001 Item 0012aa/bb: What is meant by "Sandblast and Paint Exterior Haul FIRST and OVER?Currently we do not know the condition of the paint under the water surface. Once all vessels are drydocked, the Contracting Officer Representative and Contractor will go through the exterior hulls on the Billmaier and Schwartz & Internal Voids on the Schwartz and highlight all areas that need to be painted. After all areas are highlighted an agreed upon square footage by the COR and Contractor. It is anticipated that the all the first will be used. If there is more than the first quantity then it will be paid on the over contract line item. If there are less or more Square Footage required, the contract Square Footage will be adjusted by a Variation and Estimating Quantities ModificationDKC2-24-2022/ 8:55AM
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54

Sheet2

Drawing V-100 indicates that approximately 280 cyd of excess material is to be removed from the work area per note 1. Specification 31 00 00 paragraph 3.6 states to remove surplus material from Government property and deliver it to a licensed/permitted facility, indicating a landfill. Some of the excavated material may be substantial in size, such as rock, and may not be acceptable to a landfill. It appears that slopes adjacent to the excavated area may be suitable for placement of excess material. Could excess material remain on site and be placed on adjacent slopes?
Detail A2, Restricted Sign Profile on drawing CN200 shows the dimensions for the concrete foundation to be 4’-0” deep and 11’-0” wide. Detail D7 on drawing CN501 and F1 on drawing CN502 show the dimensions to be 3’6” deep and 10’-0” wide. Please verify the correct dimensions.
Will the Contractor be allowed access to the Warning Sign work site through the NW Pier where there is currently other work taking place by others?