Redacted_Soo Lock - NLC - Pre-Proposal Conference Presentation - 13 Jul 21_003.pdf
PDF 16 MB Posted
- Attached to
- New Lock at the Soo, New Third Lock
- Solicitation number
- W911XK21R0001
About this file
This document provides details regarding a solicitation for the construction of the New Soo Locks, New Third Lock project. The US Army Corps of Engineers, Detroit District intends to solicit offers for the construction of a new lock at the Soo including a base bid and seven optional contract line items. Major components of the base bid include mobilization, cofferdam construction, relocations, care and diversion of water, construction of a new power plant bridge and shaft, demolition, excavation, construction of monoliths and installation of gates, valves and arrestors. The options include additional monolith construction, pump well completion, piping and equipment installation, approach wall construction, mooring system installation and arrestor fabrication. The total value of construction is estimated to exceed $500 million. The solicitation documents will be provided to certified offerors via a secure site. A pre-proposal conference will be held on July 13, 2021 and a site visit is scheduled for July 14, 2021, with registration required by July 8 for both.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
.59
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
INFORMATION CONTAINED IN THIS DOCUMENT IS PRE-DECISIONAL
AND NOT TO BE RELEASED OUTSIDE THE DEPARTMENT OF THE ARMY
Kevin McDaniels Mick Awbrey Mollie Mahoney Travis Specht Darin H. White, P.E.
John Behrens, P.E.
Clint Dougherty, P.E.
13 Jul 21
NEW LOCK AT THE SOO
NEW THIRD LOCK
PRE-PROPOSAL CONFERENCE
W911XK21R0001
NEW LOCK AT THE SOO
CONSTRUCTION CONTRACT PHASING
UCD
UAW
UAW
UAW
NLC
NLC
NLC
FY21
FY22
FY23
FY24
UCD Upstream Channel Deepening
UAW Upstream Approach Walls
NLC New Lock Chamber
SOLICITATION REQUIREMENTS –
TRAVIS SPECHT– CHIEF OF THE CONTRACTING OFFICE
DETROIT DISTRICT
OFFICE PHONE: 313-226-2283
EMAIL: TRAVIS.J.SPECHT@USACE.ARMY.MIL
mailto:Travis.J.Specht@usace.army.mil
SOLICITATION DETAILS
BEST VALUE TRADE OFF
REQUEST FOR PROPOSAL
• Full and open procurement.
• The NAICS code is 237990, with a Small Business Size of $39.5 million in average annual receipts
• Magnitude of the proposed construction contract is over $500,000,000
• Based Bid and 7 Optional Line Items
• Period of Performance is 1642 calendar days for the Base Bid and Options 2, 4, 5, 6 and/or 7. An additional 365 calendar days if Option 1 is exercised and an additional 365 calendar days if Option 3 is exercised.
• Price will be evaluated inclusive of options.
Note: Evaluation of options does not guarantee that the options will be exercised.
SOLICITATION DETAILS
(CONTINUE)
• Funds are presently not available
• All information will be posted on www.SAM.gov
• Offeror’s Questions and Comments
– Bidder Inquiry in ProjNet at www.ProjNet.org/ProjNet
– Bidder Inquiry Key: E9EZI9-WW7UCU
• Documents contain Controlled Unclassified Information (CUI).
To received the documents, firm must be vetted thru DLA, Joint Certified Program (JCP) and have an approved DD 2345.
https://www.dla.mil/HQ/LogisticsOperations/Services/JCP/ http://www.sam.gov/ http://www.projnet.org/ProjNet
SECURITY & INSURANCE REQUIREMENTS
• The Soo Locks is a secure Department of Defense (DoD) facility, and personnel working at the project site are subject to security rules and regulations that apply to work at an international port and within a DoD facility.
• Must be pre-screen by the E-Verify Program
• All contractor and Sub-contractor employees are required to have a National Crime Information Center (NCIC) check
• Access to areas containing systems or components of
Supervisory Control And Data Acquisition (SCADA) will require at least Tier 1 Personnel Security Investigation with Fingerprints.
• Insurance is required on Government Facility. Minimum amount is listed in the Solicitation
BEST VALUE TRADE-OFF PROCEDURE
• Factor I: Technical Management: Each Offeror’s technical management will be reviewed to determine the risk
• Factor II: Technical Approach: Each Offeror’s technical approach will be reviewed to determine a clear understanding of key technical complexities and constraints of the requirement, including schedule, site plan, concrete work, and water diversion, and how that Offeror intends on managing those during contract performance.
• Factor III: Past Performance: Each Offeror’s past performance will be evaluated to determine the level of confidence the Government has in the Offeror completing the solicited work.
• Factor IV: Small Business Participation Plan: Each Offeror’s proposal will be evaluated to ensure proper utilization of small business concerns during the course of contract performance
• Factor V: Price: The resulting award will be a FFP contract. Price reasonableness will be utilized in the evaluation of the FFP effort.
BIFURCATED REQUEST FOR PROPOSAL
PROCUREMENT PROCESS
STAGGERED PROCESS
STAGGER ONE
• Section 00 21 16 – Instruction to Proposers
• Stagger One is based on 90% design documents.
• Submit Documents thru DoD SAFE
• Submit:
Volume I – Factor I – Technical Management Volume I – Factor II – Technical Approach Volume I – Factor III – Past Performance Volume II – Tab A – Standard Form 1442 Volume II – Tab B – Joint Venture Agreement Volume II – Tab D – Pre-Award Information
BIFURCATED REQUEST FOR PROPOSAL
PROCUREMENT PROCESS
STAGGERED PROCESS
STAGGER TWO
• Amendment will be issued with 100% design document, final bid schedule, and due date for submission. Will be issued only to firms that submitted a stagger one proposal.
• Submit
– Volume I - Factor IV – Small Business Participation Plan
– Volume II – Tab A – Standard Form 1442 and Price
Breakout Schedule
• Bid Bond
– Volume II – Tab C- Evidence of Ability to Obtain Bonding and Proof of Financial Capability
– Volume II – Tab E – Small Business Subcontracting Plan
Intend to award without discussions. Submit your best proposal the 1st time.
FACTOR IV – SMALL BUSINESS PARTICIPATION PLAN
TAB E – SMALL BUSINESS SUBCONTRACTING PLAN
• Each offeror is to submit a Small Business Participation Plan
– This will be evaluated as acceptable or unacceptable (Reference Section 00 21 16 in the RFP).
– Must be submitted by both Large AND Small business offerors.
• Large Business offerors MUST also submit a Small Business Subcontracting Plan.
– Although this is not a rated element as a part of the Source Selection process, it is a condition of award.
PROPOSAL PREPARATION
Carefully review sections
- 00 21 00 Instructions to Offerors
SAM registration Questions
- 00 21 16 Instruction to Proposers Proposal format Method to submit Proposal Content Proposal Evaluation Basis of Award
PROPOSAL PREPARATION
RFP includes in section 00 73 00, Davis-Bacon Wage Determination IL 18 and MI 33
A bid guarantee is required, 20% of bid price or $3 million, whichever is less.
Performance and Payment Bonds in 100% of the contract value must be provided within 10 days after award (52.228- 15 (Dev))
IMPORTANT REMINDERS
• All documents and amendments will be posted (or listed) on SAM.gov
• Check regularly for updates
• Read the solicitation requirements carefully
• Small Business is evaluated on a Acceptable/Unacceptable basis while Technical Management, Technical Approach and Past Performance are each approximately equal to each other. All Evaluation Factors other than price, when combined, are considered approximately equal to cost or price. Offerors will be reminded to include their best proposals in their initial offers (Stagger One and Stagger Two Offers)
• The Government intends to award without discussions – do not anticipate a chance to make corrections or changes.
• The number and identities of Offerors are not revealed to anyone who is not involved in the evaluation and award process or to other Offerors. Proposals will be evaluated based on the factors described herein, and the basis of award is the Best Value Tradeoff Process.
SOLICITATION – WHAT DID WE GIVE YOU?
Plans:
• 01 Series – Base and Options, Site Plans, Geotech, Geology, General
• 02 Series – Widewall Monoliths
• 03 Series – Chamber Monoliths
• 04 Series – Lock Floor and Sills
• 05 Series – Miter Gates
• 06 Series – Culvert Valves, Bulkheads, Intake Screens, Fillers
• 07 Series – Miscellaneous Metals
(Wall armor, mooring bollards, covers, stairs, etc.)
• 08 Series – Mechanical
• 09 Series – Electrical
• 10 Series – Security, Telecommunications, Fire Protection
• 11 Series – Control House
• 12 Series - Control House
• 13 Series – Control House
• 14 Series – Control House
• 15 Series – Shaft 6
• 16 Series – New Pump Well
• 17 Series – Davis Pump Well (Rehab)
• 18 Series – Poe Pump Well (Rehab)
• 19 Series – Not Used
• 20 Series – Downstream Approach Wall
• 21 Series – East Center Pier
• 22 Series – Hands Free Mooring
• 23 Series – NPP Bridge
*Some drawings should be printed in color
Specifications:
Division 01 – GENERAL REQUIREMENTS
• 01 22 00.00 10 – Price and Payment Procedures
-Describes measurement and payment for bid items
• 01 35 13 – Special Project Procedures
- Information on constraints, sequencing, working with others
• 01 35 26 – Government Safety Requirements
-Accident prevention, EM385-1-1
• 01 50 00 – Temporary Construction Facilities
-Information on temporary buildings and other facilities
• 01 57 19 Temporary Environmental Controls
-Information regarding environmental considerations/constraints
• 01 78 00 – Closeout Submittals
-In conjunction with other specifications describes developing as-builts including the 3-D model
Specifications:
Division 01 – GENERAL REQUIREMENTS
• 01 99 90 – Listing of Enclosed Documents, Exhibits and Other
Attachments
Appendix A – Information (photos, existing facility drawings) Appendix B – Geotechnical Information Appendix C – Environmental Information Appendix D – HTRW Other Information – Misc. Signs, Safety info., Dig permit
• Division 02-43 Technical Specifications
BACKGROUND - SITE PLAN – OVERVIEW – NEW LOCK
Drawing No. 01-VA100
SITE CONDITIONS – ACCESS/WEATHER
REFERENCE: Contract Clause 52-236-4 Specification Sections 01 35 13 and 01 50 00
• No land access to the “Island”
• During winter months (15 Jan – 25 Mar) navigation ceases
• Limited access will be provided through the facility (up to
25 Management personnel)
• Check the weather – adverse weather days are shown in
Section 01 35 13
SITE CONDITIONS - SECURITY
REFEERENCE: “Security Requirements” in Front End Specifications, Section 01 50 00 and Section 01 35 13
• Soo Locks is a secure DoD facility.
• Personnel are subject to rules/regulations to work at an international port and within a DoD facility.
• All Contractor personnel will be subject to a National
Crime Information Center (NCIC) check and FBI fingerprint check.
• Contractor personnel needing access to SCADA and other sensitive areas (Buildings, Operating Shelters, Galleries, Deep Service Tunnel) will require a more extensive background check.
• Contractor personnel must carry picture ID.
• Contractor shall keep a Security Access List.
• Contractor personnel will be issued access cards which will be programmed appropriately.
SITE CONDITIONS – CWL/LWL
Drawing No. 01-GC016 Drawing No. 01-GC017
See 01 Series Drawings -Note constraints and restrictions
SITE CONDITIONS – CWL/LWL
Drawing No. 01-GC018
See 01 Series Drawings -Note constraints and restrictions
SITE CONDITIONS – WORKING WITH OTHERS
Drawing No. 01-GC015 Specification Section 01 35 13 Specification Section 01 50 00
SITE CONDITIONS - GEOLOGY
Drawing No. 01-BS303
MAJOR FEATURES – COFFERDAM SURFACE
Drawing No. 01-CF101 (annotated)
Hybrid Wall
Struts
SCB Wall
Rock Anchors
Struts
Grout Curtain
Rock Anchors
U/S Cofferdam Cells
D/S Cofferdam Cells
Grout Curtain
Upper Pool
601.6 Lower Pool
580.1
Crossover Tunnel Plug
MAJOR FEATURES – COFFERDAM CELLS
U/S Cofferdam Cells Drawing No. 01-CF107
D/S Cofferdam Cells Drawing No. 01-CF110
MAJOR FEATURES – SCB WALL
Drawing No. 01-CF206
Drawing No. 01-CF307 Drawing No. 01-CF503
MAJOR FEATURES – GROUT CURTAIN
Drawing No. 01-CF203
Drawing No. 01-CF307
MAJOR FEATURES – ANCHORS/COFFERBOX
Drawing No. 01-CH103
Drawing No. 01-SF001
Drawing No. 01-CH501
MAJOR FEATURES – HYBRID
WALL/STRUTS/CROSSOVER TUNNEL PLUG
Drawing No. 01-CF502
Drawing No. 01-CH503
Drawing No. 01-SF590
Redacted Image
MAJOR FEATURES - DEMOLITION
Drawing No. 01-CD401
Demolition:
• Buildings
• Equipment
• Gates
• Ship Arrestors
• Lights
• Concrete
• Handrail
• Footbridge
MAJOR FEATURES – DEMOLITION/HTRW
Drawing No. 01-CD403See 01 Series Drawings Section 01 99 90 Appendix A, D Section 02 81 00, 02 81 02, 02 81 03, 02 84 33
MAJOR FEATURES – DEMOLITION/EXCAVATION
Drawing No. 01-BD300
MAJOR FEATURES – ROCK EXCAVATION
Drawing No. 01-BD108 Spec Section 31 23 05 Spec Section 31 23 06
MAJOR FEATURES – BLASTING (IF CHOSEN METHOD)
Drawing No. 01-BD100 Spec Section 31 23 06 Spec Section 01 57 19
MAJOR FEATURES - CONCRETE LOCK WALLS 35
• WidewallMonoliths: Monoliths on the U/S and D/S end of the chamber that house the Bulkhead Recesses, Ship Arrestors, Miter Gates and Culvert Valves. Also, these monoliths have the intake and discharge for the filling and emptying system.
• Chamber Monoliths: Monoliths toward the middle of the chamber that primarily have a culvert and gallery.
MAJOR FEATURES – WIDEWALL MONOLITHS
Drawing No. 02-S-409
MAJOR FEATURES – CHAMBER MONOLITHS
Drawing No. 03-S-402
MAJOR FEATURES – MISC. METALS
07 Series Drawings
MAJOR FEATURES – LOCK FLOOR
Drawing No. 04-S-101
See 04 Series Drawings
• Sills
• Floor
• Laterals
MAJOR FEATURES – LOCK FLOOR - SILLS
Drawing No. 04-S-401A
Drawing No. 04-S-402A Drawing No. 04-S-410A
Drawing No. 04-S-411F
MAJOR FEATURES – LOCK FLOOR
Drawing No. 04-S-402J
See 04 Series Drawings:
• Weep holes
• Anchors
• Underdrain System
• Delayed Pours
MAJOR FEATURES – LOCK FLOOR - LATERALS
Drawing No. 04-S-404E
Drawing No. 04-S-404F
Drawing No. 04-S-404J
MAJOR FEATURES - CIVIL
• Demolition of North/South Sabin Wall
• Demolition of Existing F&E System (mostly)
• Rock Excavation
• Soil Excavation – South Sabin/North Davis
• Fill Davis Chamber
• Disposal: On-site
N
Drawing No. 01-CG3XX
MAJOR FEATURES - D/S MITER GATES 44
Upstream Miter Gate Leaf
34.8 ft c/c top/bottom girders
8 horizontal girders
Drawing No. 05 S-008
MAJOR FEATURE - U/S MITER GATES 45
Drawing No. 05 S-009
MAJOR FEATURES - MITER GATE MACHINERY
Drawing No. 08-MG901
Drawing No. 08-MG301
MAJOR FEATURES - CULVERT VALVES
Drawing No. 06-SV301
MAJOR FEATURES - CULVERT VALVE MACHINERY
Drawing No. 08-MT301
Drawing No. 08-MT901
MAJOR FEATURES – CULVERT BULKHEADS 49
Drawing No. 06-SB511
MAJOR FEATURES - SHIP ARRESTORS
• Intended to protect miter gates from collision with a vessel.
Ship Arrestor
MAJOR FEATURES - SHIP ARRESTORS
Drawing No. 01-MA301
Drawing No. 01-MA912
MAJOR FEATURES – SHIP ARRESTOR BOOM 52
Drawing No. 06-SA302
MAJOR FEATURES – FILLERS 53
Drawing No. 06-BF001
Drawing No. 06-SB509
Drawing No. 22-SB511
MAJOR FEATURES – SHAFT 6
See 15 Series Drawings
54Drawing No. 15-S-302
MAJOR FEATURES - MECHANICAL – SYSTEMS
See 08-MY Series Drawings (Hydraulics)
• 4-corner setup…HPU in each Control
House
• Lines run in the gallery
Drawing No. 08-MY901
See 08-MH Series Drawings
• Ventilation
• Sump Pump Piping
See 08-MP Series Drawings
• Air Piping
• Steam Piping
• Condensate Piping
MAJOR FEATURES - ELECTRICAL RELOCATION
Drawing No. 09-E0-101
Drawing No. 09-E1-401Drawing No. 09-E1P503
Image Redacted
Drawing No. 09-ED-402
For Official Use Only
MAJOR FEATURES – ELECTRICAL - POWER
Drawing No. 09-E0P601 Drawing No. 09-E0P602
MAJOR FEATURES - ELECTRICAL – LOCK CONTROL
Drawing No. 09-E3I-601
MAJOR FEATURES - ELECTRICAL - CCTV
• Various camera locations throughout for lock operations/control
• Viewing from the control consoles
• Independent EtherNet/IP network for CCTV
Drawing No. 09-E3T-501 Drawing No. 09-E3T-609
MAJOR FEATURES - ELECTRICAL – LIGHTING
• High Mast Lighting
• 80 ft. poles for lock chamber
• 50 ft. poles for approach walls
Drawing No. 09-E3L-501
MAJOR FEATURES - HANDS FREE MOORING
• 22 Series Drawings – Cover sheet notes that “B” in the drawing title means Base, “O” means Option.
Drawing No. 22-MO101
Drawing No. 22-MO102
MAJOR FEATURES - DOWNSTREAM APPROACH
WALL
Drawing No. 20-SS100
Drawing No. 20-SS302Drawing No. 20-SS301 Drawing No. 20-ST508
MAJOR FEATURES - EAST CENTER PIER
Drawing No. 21-SS100
Drawing No. 21-SS301Drawing No. 21-SS300
MAJOR FEATURES – CONTROL HOUSES
See 11-14 Series Drawings
• Control Houses 1N, 2N, 1S, 2S
• Control Houses on the North Wall have restrooms
• General Details for Control Houses in Series 11.
Drawing No. 11-A -101
Drawing No. 11-A -201
Upstream Approach
Walls
New Lock Chamber
MAJOR FEATURES – NEW PUMP WELL
See 16 Series Drawings
From 3-D model
Upstream Approach
Walls
New Lock Chamber
MAJOR FEATURES - NPP BRIDGE
See 23 Series Drawings
BREAK
**********TAKE A 15 MINUTE BREAK***********
BASE - DEWATERED
Drawing No. 01-GC002 Drawing No. 01-GC003
BASE - DEMOLITION
Drawing No. 01-GC005
BASE - EXCAVATION
Drawing No. 01-GC006
BASE – WIDEWALL MONOLITHS
Drawing No. 01-GC007
OPTION 1- CHAMBER MONOLITHS
Drawing No. 01-GC008
OPTION 2 – NEW PUMP WELL (CONTINUED)
Drawing No. 01-GC009
OPTION 3- WRAP UP – LOCK OPERATIONAL
Drawing No. 01-GC010
OPTION 4 – D/S APPROACH WALL AND ECP
Drawing No. 01-GC011
OPTION 5/6 – HFM AND D/S SHIP ARRESTORS
Drawing No. 01-GC012
OPTION 7 – ALLIGATOR’S MOUTH EXPANSION
Drawing No. 01-GC013
BID SCHEDULE
Intentionally set up that way for a number of reasons
• Accounting perspective (different funding)
• Make it easier to distinguish bid items (Base and Options)
• 1XXX Bid Items are Option 1, 2XXX Bid items are Option 2 etc.
• Note: 3 bid items in the Base for “…Bond”.
Excerpts from Bid Schedule
NEW PUMP WELL
• Applicable Specification Divisions
• Division 01 – General Requirements
• Division 02 – Existing Conditions
• Division 03 – Concrete
• Division 05 – Metals
• Division 06 – Wood, Plastics, and Composites
• Division 07 – Therma and Moisture Protection
• Division 08 – Openings
• Division 09 – Finishes
• Division 10 – Specialties
• Division 22 – Plumbing
• Division 23 – Heating, Ventilating, And Air Conditioning (HVAC)
• Division 25 – Integrated Automation
• Division 26 – Electrical
• Division 27 – Communications
• Division 28 – Electronic Safety and Security
• Division 31 – Earthwork
• Division 32 – Exterior Improvements
• Division 33 – Utilities
• Division 35 – Waterway and Marine Construction
• Division 40 – Process Interconnections
• Division 41 – Material Processing and Handling Equipment
• Division 43 – Process Gas and Liquid Handling, Purification, and
Storage Equipment
• Plans – Volume 7, Divisions #16, 17, 18
• Division #16 – New Pump Well
• Division #17 – Davis Well
• Division #18 – Poe Well
• Spec Sections – 01 22 00.00 10 - Price and Payment Procedures
• Base Bid Items with applicability to New Pump Well
• 0036 Diversion and Care of Water – Subsequent Maintenance
• 0037 Crossover Tunnel Plug
• 0053 Pump Well Discharge Lines
• 0102 Thru 0117 Hydraulic Modeling of New Pump Well Through Furnish and Install Sluice Gates – New Pump Well
• Option 2 Bid Items with applicability to New Pump Well
• 2002 Thru 2043 Site Work – Pump Wells Through Security System – New Pump Well
• Plans – Volume 7, Divisions #16, 17, 18
• Division #16 – New Pump Well
• Division #17 – Davis Well (Rehab)
• Division #18 – Poe Well (Rehab)
NEW PUMP WELL
Drawing 16-CS101
• Located in the existing Davis Lock chamber just north of the Davis Well
• Discharge east through DS cofferbox
• New Pump Well Design Functionality
• Replace Davis Well and Poe Well for dewatering capacity
• Ability to muck in the New Pump Well and the Davis Well
• Maintain as a dry well when not in use
NEW PUMP WELL
Discharge lines
DS Cofferbox
For Official Use Only
EXISTING PUMPING SYSTEM & NEW PUMP WELL
New Lock
Existing Sabin Lock To New Lock Tunnel
Existing Poe Pump Well Existing Poe Discharge Pipe
Existing Cross Over Tunnel Existing Davis Pump Well
Existing Davis Lock Tunnel Existing Davis Discharge Pipe
Existing Poe Lock Tunnel
Existing South Sabin Tunnel
New Pump Well
Existing North Sabin Tunnel
Existing Mac Lock Tunnel
SPECIAL REQUIREMENTS
SECTION 01 35 13 PARA. 1.5.7
GENERAL COMMISSIONING
SECTION 01 91 00.15 10
DIVERSION AND CARE
OF WATER
SECTION 31 45 00
DEMOLITION AND
DECONSTRUCTION
SECTION 02 41 00
PIPE ABANDONMENT
SECTION 02 36 00
WET WELL PHYSICAL
MODEL STUDY
SECTION 35 45 02
For Official Use Only
DEWATERED CONDITION BASE BID ACTIVITIES
NEW PUMP WELL
• Install Crossover Tunnel Plug – Section 01 35 13
• Complete Wet Well Physical Model Study – Spec 35 45 02
• Install Temporary Pumping Electrical for Government Use
• See Drawings 18-EP101 & 18-EP502
Drawing 01-GC002
For Official Use Only
DEMOLITION BASE BID ACTIVITIES
NEW PUMP WELL
• Rock Excavation for New Pump Well See Drawing 01-CD112,
• Placement Fill material for New Pump Well Discharge Pipes
Drawing 01-GC005
For Official Use Only
BASE BID ACTIVITIES
NEW PUMP WELL
• Install Pump Well Discharge Pipes – See Drawings 16-M-105, 16-M-205
• Construct New Pump Well Division 16 Drawings
Drawing 01-GC006
Pump Well Isometric from 3D Model
For Official Use Only
OPTION 2 ACTIVITIES
NEW PUMP WELL, DAVIS WELL, POE WELL
• New Pump Well Construction – Division 16 Drawings
• Davis Well Rehabilitation – Division 17 Drawings
• Temporary Government Facilities – Drawing 17-C-101
• Poe Well Rehabilitation – Division 18 Drawings, Section 01 35 13
• Crossover Tunnel Plug Removal - Division 18 Drawings
Drawing 01-GC009
NEW PUMP WELL PHYSICAL HYDRAULIC MODEL
• BASE BID - Physical Model of New Pump Well Sump
• Specification Section – Wet Well Physical Model Study 35 45 02
Drawing 16-G-501
Drawing 16-G-501
Drawing 16-S-104
NEW PUMP WELL EXCAVATION (DAVIS FLOOR)
Reinforced concrete floor, culverts and rock will be demolished and excavated to construct new pump well. 93
• Concrete and Rock Demolition/Excavation
• Tunnel Sealing and Modification
• Historic photos See Spec Section 01 99 90 Appendix A
** Historic Construction Photos do not represent As-Built Conditions
Drawing 16-SD101
• Sabin and Davis Tunnel Modifications
• Historic photos See Spec Section 01 99 90 Appendix A
• See Drawing 16-SD301
• See Drawings 16-S-550 and 16-S-551
** Historic Tunnel Photos do not represent As-Built Conditions
TUNNEL EXCAVATIONS
Drawing 16-S-550
Drawing 16-S-551
95MECHANICAL AND ELECTRICAL
See Specification Divisions
• Openings – Division 08
• Finishes – Division 09
• Plumbing – Division 22
• Heating, Ventilating, and Air Conditioning – Division 23
• Integrated Automation – Division 25
• Electrical – Division 26
• Communications – Division 27
• Electronic Safety and Security – Division 28
• Utilities – Division 33
• Waterway and Marine Construction – Division 35
• Process Interconnections – Division 40
• Material Processing and Handling Equipment – Division 41
• Process Gas and Liquid Handling…– Division 43
Drawing 16-M-202
ACCUMULATOR ROOM – UTILITY TUNNEL
• See Drawings
• 16-SD102
• 16-SD103
• 16-S-560
• 16-S-561
• 16-MD101
• 16-MD501
• 16-M106
• 16-M-207
• 16-ED400
• 16-EP409
• 16-EL405
Drawing 16-MD501 Drawing 16-MD501
Drawing 16-MD101
Drawing 16-M-207
• Demolition
• Discharge Line Sealing/Plugging
• Davis Tunnel Modification
• Davis Well Rehabilitation
• New Mechanical/Electrical
DAVIS PUMP WELL
Crossover Tunnel Rehabilitation Dwg 17-S-530 South Sabin
Tunnel Modification
Dwg 16-S-550
Floor Modification Dwg 17-S-102
Platform and Structural Steel Dwg 17-S-102
Discharge Line Dwg 17-C-102
Hatch Opening Dwg 17-S-101
Stairs Dwg 17-S-402
Well Ventilation System
Dwg 17-M-101
Monorail and hoist Dwg 17-S-510
Davis Tunnel Modification Dwg 17-S-520, Dwg 17-C-102
Im ag e R ed ac te d
CROSSOVER TUNNEL
• Crossover Tunnel Temporary Plug See Dwg. 01-SF590
• Crossover Tunnel Mucking. See Section 02 41 00
• Crossover Tunnel Rehabilitation. See Dwg. 17-SD530
Drawing 01-SF590
Drawing 17-SD530
Drawing 17-SD530
Image Redacted Image
Redacted
Image Redacted
POE PUMP WELL
• Demolition
• Dewatering Tunnel Connections
• New Knife Gate Valves/Piping
• New Bulkhead
• New Mechanical/Electrical
• Floor & Wall Rehabilitation
Poe Dewatering Tunnel
MacArthur Dewatering Tunnel
Bonneted Knife Gate Valves Section 40 33 33
Crossover Tunnel Dwg. 17-SD530 & Dwg. 01-SF590
Bulkhead Dwg. 18-S-520
Bulkhead Slot
Ladder
Jib Crane Dwg.
18-S-510
Modified Discharge Pipe Dwg. 18-C-101 Dwg. 18-M-102
Sump Pump Dwg. 18-M-502
Structural Framing & Platform Dwg. 18-S-430 Dwg. 18-S-102
Floor Modification Dwg. 18-S-502
Concrete Infill Dwg. 18-S-102 & Dwg. 18-S-301
Sump Pump Dwg. 18-M-502
Bonneted Knife Gate Valves Section 40 33 33
Piping Dwg. 18-S-440 Dwg. 18-M-101
Im ag e R ed ac te d
NPP BRIDGE
NPP BRIDGE (SERIES 23 DRAWINGS)
UTILITY
RACEWAY
BRIDGE TO
NPP (0020)
VEHICULAR
BRIDGE &
PLATFORM
(0202)
RAMP FROM
UTILITY
RACEWAY TO
CENTER DIKE
(0203)
Drawing No. 23-S-102
UTILITY RACEWAY BRIDGE TO NEW POWER PLANT
(0020)
Drawing No. 23-S-101
New Man-doorNorth Vault
Pier #3Bridge Superstructure with Utility Support Framing
West Portion of Pier #1
Riprap
South Vault
S. Abutment & Walls
Payment Line Pier #1
UTILITY RACEWAY BRIDGE DECK & GIRDERS
Drawing No. 23-S-311
TYPICAL PIER
Drawing No. 23-S-302
Drawing No. 23-S-504
Pier Cap
3’ Dia. Pier Columns
Pay Line
Pier Cap
Bearings
BT63
Prestressed Precast Girders
Barriers Deck
Diaphragms
TYPICAL DRILLED SHAFTS & PIER COLUMNS
Drawing No. 23-SS501 8’ Rock Socket
Drilled Shaft Reinforcement Differs from Column
UTILITY RACEWAY BRIDGE
DEMO ITEMS
Drawing No. 23-SD900
Existing Footbridge Demo See 01 & 15 Series Sheets
Crib Dam Fence
Wall Penetrations New Man door Opening
Exterior Platform
Waterway Signs
VEHICULAR BRIDGE & PLATFORM (0202)
Drawing No. 23-S-201
Exterior Barriers Reinforced Concrete Composite Deck
BT63 Girders
VEHICULAR BRIDGE
Drawing No. 23-S-312 Drawing No. 23-S-313
PLATFORM
Platform
Vehicular Bridge
RAMP FROM UTILITY BRIDGE TO CENTER DIKE (0203)
Drawing No. 23-S-203
Pier 4
Pier 5 Pier 6
Exterior Barriers
36” Box Beams BT63
Girders
Ramp Landing
Civil Grading
RAMP & LANDING
Drawing No. 23-S-306
Drawing No. 23-S-315 Drawing No. 23-S-314
Precast Prestressed 36” Box Beams
Box Beam Bearings
Existing Crib Dam
Pier 6 Pier 5
Exterior Barriers
LANDING RAMP
BT63
GIRDERSRC Deck
RC Deck
SPECIFICATION 03 41 00: PRECAST PRESTRESSED
CONCRETE BRIDGE GIRDERS
PRIMARY SPECIFICATION FOR BRIDGE RELATED
ITEMS
- AASHTO LRFD BRIDGE CONSTRUCTION
SPECIFICATIONS, 4TH ED. 2017
- AASHTO LRFD BRIDGE DESIGN SPECIFICATIONS, 9TH
ED. 2020
- SOME REFERENCES TO MDOT STANDARD
SPECIFICATIONS FOR CONSTRUCTION, 2012.
- PCI BULB TEE 63 GIRDERS
- BOX BEAM 36 GIRDERS
ELECTRIC ITEMS
- INFRASTRUCTURE FOR SUPPORTING UTILITIES:
DUCTBANK AND RACEWAY SUPPORT STRUCTURE
FRAMING, CONDUITS, ETC.
- BRIDGE, RACEWAY, AND VAULT LIGHTING
- S. VAULT – TRANSFORMER & PANEL BOARD
(LIGHTING & RECEPTACLES)
- SEE DIVISION 26 SPECIFICATIONS
ELECTRIC ITEMS
Drawing No. 23-E-101
Disconnect Switch
Transformer
New S. Vault Equipment
Drawing No. 23-E-503 Demo of Existing Equipment in NPP
New Bridge & Vault Lighting
Drawing No. 23-EL100 to EL 102
Bridge Conduits & Raceway Supports
Drawing No. 23-E-501
Redacted Image
CONTRACTOR DESIGN ITEMS:
1. SOUTH ABUTMENT VAULT (23-ST501&502)
2. NORTH VAULT WITH PRECAST ARCH. CONCRETE
TO MATCH THE EXISTING NPP. (23-ST503)
3. FLOATING MOORING FRAMES (23-SS502)
4. UTILITY RACEWAY BRIDGE UTILITY SUPPORT
FRAMING (23-S-311)
5. LINTEL FOR NEW MANDOOR (23-A-600)
1. SOUTH VAULT
2. NORTH VAULT
NORTH VAULT
SOUTH VAULT
Precast Arch.
Concrete to Match Historic NPP Building, Spec 03 45 00
Precast or CIP Concrete.
Design shall consider wheel loadings and anchorage to roof for approach guardrail
Approach Guardrail & Posts
Drawing No. 23-S-508
Drawing No. 23-ST502
Drawing No. 23-ST503
Drawing No. 23-ST502
Redacted Image
3. FLOATING MOORING FRAMES
Pier 1 Floating Mooring Frame
Pier 2 Floating Mooring Frame Drawing No. 23-SS502
4. UTILITY RACEWAY SUPPORT FRAMING
Drawing No. 23-S-311
New Utility and Future Utility Support Frame and Anchorage to Girders. See Spec 03 41 00.
5. LINTEL FOR NEW MANDOOR INTO NPP
Drawing No. 23-SD300
New Lintel with Head and Jamb details for New Man-door. See Spec 02 41 00 and Drawing No. 23-A-600
QUESTIONS
• Only questions related to information already provided by the government may be addressed today
• All questions related to information not previously provided must be submitted through Projnet
• Even questions written and submitted today must be submitted through Projnet to receive a formal response
| New LOCK at the SOO�New THIRD Lock �PRE-Proposal Conference�W911XK21R0001� |
| New Lock at the Soo�Construction Contract phasing |
| Solicitation Requirements – W911XK21R0001�Travis Specht– Chief of the Contracting Office�Detroit District�Office Phone: 313-226-2283�Email: Travis.J.Specht@usace.army.mil |
| Solicitation Details�W911XK21R0001�Best Value Trade Off �Request for Proposal��� |
| Solicitation Details�W911XK21R0001�(Continue) |
| Security & Insurance Requirements |
| Best Value Trade-off Procedure�� � |
| Best Value Trade-off Procedure�Bifurcated Request for Proposal Procurement Process�Staggered Process�Stagger One�� |
| Best Value Trade-off Procedure�Bifurcated Request for Proposal Procurement Process�Staggered Process�Stagger Two� |
| Factor IV – Small Business Participation Plan�Tab E – Small Business Subcontracting Plan��� |
| Proposal Preparation |
| Proposal Preparation |
| Important Reminders |
| Solicitation – what did we give you? |
| Solicitation – what did we give you? |
| Solicitation – what did we give you? |
| Background - Site Plan – overview – NEW LOCK |
| Site conditions – access/Weather |
| Site conditions - Security |
| Site conditions – CWL/LWL |
| Site conditions – CWL/LWL |
| Site conditions – working with others |
| Site conditions - Geology |
| Major features – Cofferdam surface |
| Major features – Cofferdam cells |
| Major features – SCB Wall |
| Major features – Grout curtain |
| Major features – anchors/cofferbox |
| Major features – hybrid wall/struts/crossover tunnel plug |
| Major features - Demolition |
| Major features – Demolition/htrw |
| Major features – Demolition/Excavation |
| Major features – Rock excavation |
| Major features – blasting (if chosen Method) |
| Major features - Concrete lock walls |
| Major features – widewall monoliths |
| Major features – Chamber monoliths |
| Major features – misc. metals |
| Major features – lock floor |
| Major features – lock floor - Sills |
| Major features – lock floor |
| Major features – lock floor - laterals |
| Major Features - Civil |
| Major features - D/S Miter gates |
| Major feature - U/s Miter gates |
| Major Features - Miter gate machinery |
| Major Features - Culvert valves |
| Major Features - Culvert valve Machinery |
| Major features – Culvert bulkheads |
| Major Features - Ship Arrestors |
| Major features - SHIP ARRESTORS |
| Major Features – Ship arrestor boom |
| Major features – fillers |
| Major features – Shaft 6 |
| Major features - Mechanical – Systems |
| Major features - Electrical relocation |
| Major Features - Electrical relocation |
| Major Features - Electrical relocation |
| Major Features – Electrical - Power |
| Major features - Electrical – LOCK control |
| Major features - Electrical - CCTV |
| Major features - Electrical – lighting |
| Major Features - Hands Free Mooring |
| Major features - Downstream approach wall |
| Major features - East center Pier |
| Major Features – control houses |
| Slide Number 67 |
| Slide Number 68 |
| Break |
| Base - Dewatered |
| Base - Demolition |
| Base - Excavation |
| Base – Widewall monoliths |
| Option 1- Chamber Monoliths |
| Option 2 – New Pump well (continued) |
| Option 3- Wrap up – Lock Operational |
| Option 4 – D/S approach Wall and ECP |
| Option 5/6 – HFM and D/S Ship Arrestors |
| Option 7 – alligator’s Mouth expansion |
| Bid schedule |
| New Pump Well |
| NEW PUMP WELL |
| New Pump Well |
| New Pump Well |
| New Pump Well |
| New Pump Well |
| EXISTING PUMPING SYSTEM & new pump well |
| Dewatered Condition Base BID Activities�new pump well |
| Demolition Base BID Activities�new pump well |
| Base Bid Activities �new pump well |
| Option 2 Activities�new pump well, Davis Well, Poe Well |
| New Pump Well Physical Hydraulic Model |
| New Pump Well Excavation (Davis Floor) |
| Tunnel Excavations |
| Mechanical and Electrical�New Pump Well |
| Accumulator Room – Utility Tunnel |
| Davis Pump Well |
| Crossover Tunnel |
| Poe Pump Well |
| NPP Bridge |
| Npp bridge (Series 23 drawings) |
| UTILITY RACEWAY BRIDGE TO NEW POWER PLANT (0020) |
| Utility raceway bridge deck & girders |
| typical PIER |
| Typical DRILLED SHAFTS & PIER COLUMNS |
| Utility raceway bridge |
| Vehicular Bridge & Platform (0202) |
| RAMP FROM UTILITY BRIDGE TO CENTER DIKE (0203) |
| Ramp & Landing |
| SPECIFICATION 03 41 00: PRECAST PRESTRESSED CONCRETE BRIDGE GIRDERS |
| Electric items |
| Electric items |
| CONTRACTOR DESIGN ITEMS: |
| 1. South vault �2. north VAULT |
| 3. FLOATING MOORING FRAMES |
| 4. UTILITY RACEWAY SUPPORT FRAMING |
| 5. LINTEL FOR NEW MANDOOR INTO NPP |
| Questions |