This document summarizes a solicitation for construction services to blast and coat a miter gate at the Poe Lock located in Sault Sainte Marie, Michigan. The general scope of work involves surface preparation and application of a marine-grade vinyl coating to two approximately 63-foot by 35-foot miter gate leaves. Some disassembly, repair, and reassembly of gate components will be required. The contractor must furnish new gate seals, timber fenders, and structural diagonals. The estimated cost range for the construction is between $1 million to $5 million. The solicitation will use full and open competition and a 10% HUBZone price evaluation preference. The NAICS code is 237990 and size standard is $39.5 million in average annual receipts. One firm-fixed price contract will be awarded using best value tradeoff. The solicitation package is available electronically on beta.sam.gov and the period for questions ended on April 30, 2021 with the bid due date of May 18, 2021 remaining unchanged.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Visit Roster.pdf | ||
| W911XK20R0021.pdf | ||
| Poe Lock Gate 1 Blasting and Coating Certified Final RTA SPECS.pdf | ||
| Poe Lock Gate 1 Blasting and Coating Certified Final RTA PLANS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Poe Lock Gate 1 Blasting and Coating Amendment 0001 This amendment is issued to:
1. Revise the specif ications as described in Section SF30 Block 14 Continuation Page.
2. Provide answ ers to questions received during the Request for Information period as described in SF 30 Block 14 Continuation Page.
3. All other terms, conditions, requirements, and clauses remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 07-May-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911XK20R0021
X 9B. DATED (SEE ITEM 11)
15-Apr-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-May-2021
CODE
U.S.ARMY ENGINEER DISTRICT, DETROIT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
W911XK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911XK20R0021
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
CERTIFIED FINAL DOCUMENTS – W911XK20R0021 TECHNICAL SPECIFICATIONS
The following sections have been revised:
1. SECTION 02 41 00.01 APPURTENANCES REMOVAL AND REINSTALLATION
Delete Paragraph 3.4 Miter Gate Stressing Add revised paragraph 3.4 Miter Gate Position “Upon removal of the existing gate tensioning diagonals, the gate shall not be further moved until new gate diagonals have been installed and fully tensioned per SECTION 35 20 16.33 MITER GATE - DIAGONALS, APPURTENANCES AND APPURTENANT ITEMS.”
2. SECTION 35 20 16.23 MITER GATE – DIAGONALS, APPURTENANCES AND APPURTENANT ITEMS Delete paragraph 3.5 PAINTING Add revised paragraph 3.5 PAINTING “All exposed parts of the gate and appurtenances except corrosion-resistant surfaces, shall be painted as specified in Section <SRF>09 97 02</SRF> PAINTING: HYDRAULIC STRUCTURES. Machined surfaces and other specified surfaces shall not be painted.”
Solicitation Issued April 15, 2021
Solicitation # W911XK20R0021 Questions as of April 30, 2021 Poe Lock Gate 1 Blasting & Coating
Number Question Answer
Is there a prequalification form that we need to send out to you for the Poe Lock Gate 1 Blasting & Coating or one that we would use if we have to use any subcontractors?
No. All applicable documents to be submitted can be found in the "Submission Requirements" section of the solicitation.
Can a mobilization/demobilization pay item be added? The Government does not intend to add mobilization/demobilization as a separate line item for this contract.
3 Are only the bottom gate seals to be replaced, or are any other seal (i.e. corner) to be replaced?
Only the bottom seals are to be replaced per sheet CD200
4 Are the sill angles to be blasted/painted? Yes, sill angles shall be blasted and coated as well, unless specifically addressed in Spec Section 02 41 00.01. See Paragraph 1.2.2 for general requirements.
5 Can the Certified Coatings Inspector be employed by the painting subcontractor?
Yes, the Certified Coatings Inspector may be employed by the Prime or Subcontractor.
6 What are the extents of the previously-blasted areas of the gates where blasting will not be allowed for paint removal as described in Paragraph 3.1.3 of Specification 09 97 02?
Blasting is the form of paint removal, blasting shall not further put the existing profile out of the requirements of specification 09 97 02. The entire gate has an existing profile under current coating system, which shall be addressed by means described in paragraph 3.1.3, in either case blasting will be the way of paint removal for this project.
W911XK20R0021
7 Please confirm that any specifications and plans showing “Required Strain Gauge Configuration” are for reference only, as per Paragraph 3.4 of Specification 02 41 00.01 the Government is providing strain gauge instrumentation and personnel.
Contractor to provide strain guage. This was intended to be removed. See Sheet SC 500 and Spec Section 35 20 16.33 section 3.4 for installation process. Amendment to revise paragraph 3.4.
8 Can photos of the reaction bars and wrench be provided per Paragraph 3.4 of Specification 02 41 00.01?
See above comment.
9 Are there restrictions on how the gate leaves can be positioned when the different phases of work are being performed (i.e. open, partially open, closed)?
Only restriction is that the gate shall not be moved once the Diagonals have been removed.
See updated paragraph 3.4 in spec section 02 41 00.01.
10 Please clarify the statement made in Paragraph 3.5 of Specification 35 20 16.23 that, “All exposed parts of the gate and appurtenances except, including corrosion-resistant surfaces, shall be painted as specified….”
Should corrosion-resistant surfaces be painted?
No, do not paint corrosion resistant surfaces, intended to paint all gate appurtenances except corrosion surfaces. Amendment to revise paragraph 3.5.
11 For the new timber fender bolts, is the roll-threading process acceptable? This is a process where the manufacturer starts with a slightly undersized rod. When they ‘roll’ the threads, the steel is displaced making 1 1/8” threads but no material is removed. This does result in a diameter less than 1-1/8” on the unthreaded portion of the rod.
Roll threading of the new timber fender bolts is acceptable.
12 Are digital signatures acceptable for the bid submission? Yes, digital signatures are acceptable. The bid submission must be signed by authorized individual of the firm.
13 Was it the Government’s intent to require varying material specifications and grades between parts, such as the positive/negative diagonal bars (A709 Gr. 50 and A709 Gr. 70W, respectively) or positive/negative insert plates (A709 Gr. 50 and A572 Gr. 42, respectively)?
Yes, Designer intends to have different materials.
14 Can the question period for W911XK20R0021- Poe Gate 1 Blasting and Coating be extended till Friday May 14, 2021?
No, the question period of April 30, 2021 remains unchanged.
15 Can the bid date be extended to Tuesday May 25, 2021 or a later date? Another large USACE Detroit district project proposal bid date was extended to 5-18-21, same day this project is currently due.
No, the bid due date of May 18, 2021 remains unchanged.
(End of Summary of Changes)