This document contains questions and answers related to a solicitation for sediment remediation work in the Azcon/Duluth Seaway Port Authority slip. The solicitation seeks a contractor to install a silt curtain, dredge the slip with a mechanical plant and treat sediment in scows with 5% Portland cement for offloading and disposal. The contractor will then place two layers of cap material, with Layer A consisting of dredged material and an armor stone layer placed above. Ongoing government surveys will be conducted after installation of construction features. The work must be completed by October 30, 2020 assuming a notice to proceed by August 14, 2020. The document provides responses to questions on right of entry areas, sign-in sheets, design files, volume calculations, monitoring requirements and debris clearing.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
10-Jun-20
W911XK20B0014
Number Date/Time
Received in Outlook (Govt Exchange Server)
Answer Initials of Respondant
Date/Time Answered
1 6/19/2020 @ 0935
USACE has a Right of Entry for the access areas shown on Sheet RR101, but the landowners still have property rights. The intent of the 20 foot ROE is to allow the Contractor to tie off work barges since spudding isn't allowed. The access areas are not intended for storage of equipment. Contractor shall reference the Coordination with Others paragraph 1.6.11 in the Section 01 35 13, and contact Steve Schoff, MPCA Project Manager, (651) 757-2701.
VBP 6/26/2020 @ 1545
2 6/19/2020 @ 0935 Site Visit Sign-In Sheet is available at beta.sam.gov DCB 6/25/2020 @ 1545
3 6/19/2020 @ 0935
The Existing Surface dtm file and the Design Model dgm file (the Outlines and hatching for the required areas) are attached. The xyz files for the existing bathymetry and the design model files are being provided for reference only and are not considered contractually binding.
VBP 6/26/2020 @ 1545
4 6/19/2020 @ 0935 Contractor shall compute volumes from the areas, required dredge depths, and required cap thicknesses presented in the Plans. VBP 6/26/2020 @ 1545
5 6/19/2020 @ 0935 Contractor shall compute volumes from the areas, required dredge depths, and required cap thicknesses presented in the Plans. VBP 6/26/2020 @ 1545
6 6/25/2020 @ 0944 The project performance period shall be completed by October 30, 2020 assuming NTP by August 14, 2020. The Solicitation form 1442 will be revised to reflect this performance period.
VBP 6/26/2020 @ 1545
7 6/25/2020 @ 0944 Turbidity curtain monitoring is required only during working hours in the slip. VBP 6/26/2020 @ 1545
Solicitation form 1442 says complete within 84 days of NTP, however 52.211-10Alt1 states October 30 as completion date assuming NTP by Aug 14. Which is the correct performance period?
Section 35 20 23 paragraph 1.13.2 Turbidity Curtain Monitoring requires monitoring at “minimum” intervals of 4 hours. Assuming 4 hours is intended as the maximum interval, is monitoring required during non-working hours such as nights, weekends, and holidays?
Sheet RR101 please confirm that the access areas will be cleared of debris/material before project use.
Please provide sign in list
Please provide the Autocad files and XYZ files for the top of sediment and design of the dredging and capping surfaces.
Please provide the dredge volumes by area to be removed.
Please provide the anticipated cap volumes by material type and area.
Solicitation Issued
Question
Questions Close 25 JUNE 2020 @ 10:00AM