W56MES90425202

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT: Superior Entry North Pier, Duluth-Superior Harbor, St. Louis County, MN

PURPOSE: The purpose of this amendment is to:

1. Revise the Specifications in accordance w ith the Summary of Changes.

2. Provide 1959 Soil Borings as a reference for information only.

3. The bid due date is extended to August 27, 2019.

4. Update DFARS 252.236-7001, Contract Draw ings and Specifications.

5. FAR 52.252-3, Alterations in Solicitation is updated.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911XK19B0017

X 9B. DATED (SEE ITEM 11)

12-Jul-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Aug-2019

CODE

CONTRACTING BRANCH

USACE DETROIT DISTRICT

477 MICHIGAN AVENUE, 7TH FLOOR

DETROIT MI 48226-4523

965416 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911XK19B0017

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

TECH SPEC CHANGES--AMEND 0002

1. Provide 1959 Soil Borings as a reference for information only. This file is located on www.fbo.gov as a separate file.

Amendment 0002 Changes to W911XK19B0017 – Final RTA Specifications

CHANGES TO SPECIFICATIONS

1. Specification Section 31 4117 STEEL SHEET PILING:

• Add text "clearing the drive line" to Paragraph 1.1 DESCRIPTION OF WORK

• Delete Paragraph 1.3 SUBMITTALS QC Inspector for Steel Sheet Pile Coating; G, ECD

Add paragraph 1.3 SUBMITTALS QC Inspector for Steel Sheet Pile Coating; G, ECD with the below language:

"Contractor shall employ third party inspectors, at a minimum, level 2 certified in the SSPC Protective Coatings Inspector Program (PCI) or level 2 certified National Association of Corrosion Engineers (NACE) International Coating Inspector Program. The third party inspector shall not be an employee of the coating facility or the sheet pile manufacturer. Submit applicable certifications for the Qualified Paint Inspector. Submit all certificate renewals if they occur within the contract performance period."

• Delete Paragraph 3.3.3 QC for Sheet Pile Coating

Add Paragraph 3.3.3 QC for Sheet Pile Coating with the below language:

"Contractor shall employ third party inspectors, at a minimum, level 2 certified in the SSPC Protective Coatings Inspector Program (PCI) or level 2 certified National Association of Corrosion Engineers (NACE) International Coating Inspector Program. The third party inspector shall not be an employee of the coating facility or the sheet pile manufacturer. A PCI or NACE level 2 inspector shall be performing field inspections at any time abrasive blasting or paint application is being performed and as necessary following work activities to inspect results. An inspector shall be present during all required quality control phases as defined in section 0145 00.00 10 QUALITY CONTROL. The certified inspector shall not perform any abrasive blasting or paint application activities. Submit applicable certifications for the Qualified Paint Inspector. The inspectors shall be certified prior to award of this contract and remain actively certified for the contract duration.

Submit all certificate renewals if they occur within the contract performance period. Renewals shall be achieved prior to expiration occurring. Inspectors with expired certificates shall not be allowed to perform inspection activities."

• Paragraph 2.1.1Hot Rolled Sheet Piles

Delete nominal section modulus "40.14" in Properties of Hot-Rolled SSP Table Add nominal section modulus "39.5" in Properties of Hot-Rolled SSP Table

2. Specification 013513 SPECIAL PROJECT PROCECURES

• Add subparagraph 1.4.2 "Work Period Restrictions" under paragraph 1.4 SEQUENCING AND

SCHEDULING

1.4.2 Work Period Restrictions

No construction activities, to include but not limited to demolition of the concrete, are allowed to commence at the project site until 16 April 2020.

• Add subparagraph 1.3.16 Structure under Paragraph 1.3 PROJECT/SITE CONDITIONS

1.3.16 Structure

Maximum surcharge load to the existing structure is 250 psf. The Contractor shall be responsible for the temporary support of structure during construction.

Whenever the work is discontinued for periods exceeding two (2) calendar days, the Contractor, before closing down operations, shall protect all the exposed partially completed work against damage.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 20-Aug-2019 02:00 PM to 27-Aug-2019 02:00 PM.

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001:

PROJECT: Superior Entry North Pier, Duluth-Superior Harbor, St. Louis County, MN

PURPOSE: The purpose of this amendment is to:

1. Provide the Pre-Bid and Site Visit Minutes.

2. The closing date for questions/Request for Information remains August 7, 2019. The bid due date is extended to August 20, 2019.

3. Revise the Specifications in accordance with the Summary of Changes.

4. Update DFARS 252.236-7001, Contract Drawings and Specifications.

5. Update Wage Determination MN20190040.

Amendment 0002:

PROJECT: Superior Entry North Pier, Duluth-Superior Harbor, St. Louis County, MN

PURPOSE: The purpose of this amendment is to:

1. Revise the Specifications in accordance with the Summary of Changes.

2. Provide 1959 Soil Borings as a reference for information only.

3. The bid due date is extended to August 27, 2019.

4. Update DFARS 252.236-7001, Contract Drawings and Specifications.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been modified:

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

W911XK19B0017 – Final RTA Specifications W911XK19B0017 – Final RTA Plans

W911XK19B0017 - Final RTA Plans Signed Cover Sheet

*Amendment 0001 Changes to W911XK19B0017 – Final RTA Specifications *Amendment 0002 Changes to W911XK19B0017 – Final RTA Specifications

(End of clause)

(End of Summary of Changes)