FY19 Muskegon South Breakwater Connector Repair

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 10 REAL ESTATE

Real Estate

01 22 00.00 10 PRICE AND PAYMENT PROCEDURES

lump sum schedule payment items and unit price schedule payment items

01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

the preparation and use of construction schedules for small projects

01 33 00 SUBMITTAL PROCEDURES

general procedures regarding submittals, data normally submitted for review to establish conformance with the design concept and contract documents

01 35 13 SPECIAL PROJECT PROCEDURES

SPECIAL PROJECT PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

safety and occupational health requirements for the protection of Contractor and Government personnel, property, and resources

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

listing of organizations whose publications are referenced in other sections of the specifications.

01 45 00.00 10 QUALITY CONTROL

Contractor Quality Control for construction projects or design-build construction projects

01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)

use of the Quality Control System (QCS) for contract monitoring and administration.

01 57 20.00 20 ENVIRONMENTAL PROTECTION

Environmental Requirements for Project

01 58 00 PROJECT IDENTIFICATION

temporary signs for project identification

01 78 00 CLOSEOUT SUBMITTALS

closeout submittals including: revised project documents, warranty management, testing, adjusting and balancing, O & M manuals, and cleanup

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

demolition, deconstructon, dismantling, reconditioning and disposal of existing building materials, equipment and utilities as a part of new construction or renovation work

PROJECT TABLE OF CONTENTS Page 1 Certified Final - Ready to Advertise

DIVISION 03 - CONCRETE

03 15 00.00 10 CONCRETE ACCESSORIES

expansion joints, contraction joints and waterstops used in concrete construction.

03 20 00.00 10 CONCRETE REINFORCING

concrete reinforcement, including welded wire reinforcemetn and fibrous reinforcing

03 31 01.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS

furnishing, hauling, and placing the cast-in-place structural concrete complete, as specified herein and shown on the contract drawings

DIVISION 05 - METALS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

miscellaneous metalwork

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 31 19 STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR

STRUCTURES

stone protection, including foundation preparation, bedding layers and filters, for the slopes and bottom of channels, ditches, structures, lock approaches, etc.;

constructing trenchfill revetment, bank paving, and outlet drains; stone revetment, stonefill dikes, stoneroots, and junctions; constructing stone capouts and revetment reinforcing along the river; revetment repairs;

shoreline/coastal protection

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 2

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 10

REAL ESTATE

03/01

Real Estate

PART 1 GENERAL

1.1 SUBMITTALS

1.2 REGULATORY REQUIREMENTS

1.2.1 Real Estate Rights

1.2.2 Additional Real Estate Rights

1.3 PROJECT/SITE CONDITIONS

1.3.1 Location and Verification

1.3.2 Survey Markers

1.3.2.1 Semipermanent Markers

1.3.2.2 Temporary Markers

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section Table of Contents --

SECTION 01 10 10 Page 1

SECTION 01 10 10

REAL ESTATE

03/01

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Additional Property Agreements; G-RED.

Copies of any agreements for Contractor-acquired real estate rights for this project shall be furnished before entering thereon.

Certified Survey Results

Furnish a copy of certified results of surveys which verify areas and limits of Contractor-acquired real estate rights.

1.2 REGULATORY REQUIREMENTS

1.2.1 Real Estate Rights

Rights for the use of the work and storage areas have been obtained and the general limits of the areas are shown on the drawings. Copies of instruments conveying rights for use of the work and storage areas shown on the drawings and specified herein are available for inspection in the Engineering, Design, & Construction Office, U.S. Army Corps of Engineers, Detroit District, 477 Michigan Avenue, McNamara Building, Detroit, Michigan. Conformance to all applicable requirements of the instruments conveying rights is required. Two (2) copies of each instrument will be furnished to the Contractor. No other real estate rights have been obtained by the Government for this project.

1.2.2 Additional Real Estate Rights

Any additional property agreements and/or real estate rights desired by the Contractor shall be obtained by the Contractor at its own expense. Such agreements shall clearly relieve the Government of any responsibility for damages or liability resulting from the Contractor's use of such grounds.

1.3 PROJECT/SITE CONDITIONS

1.3.1 Location and Verification

It shall be the Contractor's responsibility to accurately locate the limits

SECTION 01 10 10 Page 2 of all lands utilized under the contract. The corner and angle points of each area for which rights have been obtained shall be marked with semipermanent markers except where there is an approved existing property marker. Temporary markers shall be placed at points on alignment. The points on alignment shall be marked at stations so that intervals between points do not exceed 200 feet.

1.3.2 Survey Markers

All markers shall be installed in an area prior to its use and they shall be available for reference during and upon completion of use of the area.

Where approved existing property markers are found, a witness stake, as specified in Subparagraph, "Semipermanent Markers" below, shall be provided. If the types of markers specified hereinafter cannot be used, other types, as approved by the Contracting Officer, shall be provided.

1.3.2.1 Semipermanent Markers

The markers shall be a steel rod one-half inch in diameter and four (4) feet long. The steel rod shall be driven vertically into the ground so that the top is flush with the finished ground surface. Each marker shall be witnessed by a 2" x 2" yellow stake extending two (2) feet above the ground surface and driven into the ground until stable, with not less than one (1) foot penetration.

1.3.2.2 Temporary Markers

Markers shall be 2" x 2", red-colored, wood hub stakes driven into the ground until stable (not less than one (1) foot penetration) with two (2) feet projecting above the ground surface. If the period in which temporary markers are to be in place exceeds one (1) construction season, a more permanent type of marker, as approved, shall be provided.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 10 10 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

PRICE AND PAYMENT PROCEDURES

08/15 lump sum schedule payment items and unit price schedule payment items

PART 1 GENERAL

1.1 SINGLE JOB PAYMENT ITEMS

1.2 UNIT PRICE PAYMENT ITEMS

1.3 BIDDING SCHEDULE

1.3.1 0001: Mobilization and Demobilization

1.3.1.1 Payment

1.3.1.2 Unit of Measure

1.3.2 0002, 0007, 0011: Existing Structure Demolition

1.3.2.1 Payment

1.3.2.2 Unit of Measure

1.3.3 0003, 0008, 0012: Required Concrete Slab Cap

1.3.3.1 Payment

1.3.3.2 Unit of Measure

1.3.4 0004, 0004aa, 0004ab: Required 8 - 13 ton Armor Stone for

Sections F-1 and F

1.3.4.1 Payment

1.3.4.2 Unit of Measure

1.3.5 0005, 0005aa, 0005ab , 0009, 0009aa, 0009ab: Required 2 - 4 ton Armor Stone For Section G

1.3.5.1 Payment

1.3.5.2 Unit of Measure

1.3.6 0006, 0006aa, 0006ab, 0010, 0010aa, 0010ab: Required Stone

Fill 1"x 3" stone Sections F-1, F, G, and Existing Voids

1.3.6.1 Payment

1.3.6.2 Unit of Measure

1.4 Additional Stone Requirements

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 22 00.00 10 Page 1

SECTION 01 22 00.00 10

PRICE AND PAYMENT PROCEDURES

08/15

PART 1 GENERAL

1.1 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.3 BIDDING SCHEDULE

1.3.1 0001: Mobilization and Demobilization

1.3.1.1 Payment

Payment will be made for costs associated with mobilization, demobilization and preparation work associated with Muskegon Connector Rehabilitation Project as shown in the plans and specifications.

1.3.1.2 Unit of Measure

Unit of measure: Job (JA)

1.3.2 0002, 0007, 0011: Existing Structure Demolition

1.3.2.1 Payment

Payment will be made for costs associated with demolition work associated with Muskegon Connector Rehabilitation Project as shown in the plans and specifications.

1.3.2.2 Unit of Measure

Unit of measure: JOB (JA)

SECTION 01 22 00.00 10 Page 2

1.3.3 0003, 0008, 0012: Required Concrete Slab Cap

1.3.3.1 Payment

Payment will be made for costs associated with demolition work associated with Muskegon Connector Rehabilitation Project as shown in the plans and specifications.

1.3.3.2 Unit of Measure

Unit of measure: JOB (JA)

1.3.4 0004, 0004aa, 0004ab: Required 8 - 13 ton Armor Stone for Sections F-1 and F

1.3.4.1 Payment

Payment will be made for costs associated with operations necessary for construction of the Concrete as specified in the plans and specification sections 03 11 13.00 10 STRUCTURAL CONCRETE FORMWORK, 03 15 00.00 10 CONCRETE ACCESSORIES, 03 20 00.00 10 CONCRETE REINFORCING and 03 31 01.00

10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS.

1.3.4.2 Unit of Measure

Unit of measure: JOB (JA)

1.3.5 0005, 0005aa, 0005ab , 0009, 0009aa, 0009ab: Required 2 - 4 ton Armor Stone For Section G

1.3.5.1 Payment

Payment will be made for costs associated with operations necessary for construction of the Concrete as specified in the plans and specification sections 03 11 13.00 10 STRUCTURAL CONCRETE FORMWORK, 03 15 00.00 10 CONCRETE ACCESSORIES, 03 20 00.00 10 CONCRETE REINFORCING and 03 31 01.00

10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS.

1.3.5.2 Unit of Measure

Unit of measure: JOB (JA)

1.3.6 0006, 0006aa, 0006ab, 0010, 0010aa, 0010ab: Required Stone Fill 1"x 3" stone Sections F-1, F, G, and Existing Voids

1.3.6.1 Payment

Payment will be made for costs associated with operations necessary for construction of the Concrete as specified in the plans and specification sections 03 11 13.00 10 STRUCTURAL CONCRETE FORMWORK, 03 15 00.00 10 CONCRETE ACCESSORIES, 03 20 00.00 10 CONCRETE REINFORCING and 03 31 01.00

10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS.

1.3.6.2 Unit of Measure

Unit of measure: Ton (TON)

SECTION 01 22 00.00 10 Page 3

1.4 Additional Stone Requirements

The following requirements apply to bid items 0003, 0004, 0005, 0006, and 0007.

All Stone will be measured for payment by the ton as determined by barge/vessel displacement, certified railroad weights, where direct placement into structure(s) is practicable, or by weighing by the truckload on approved scales meeting the requirements of paragraph TRUCKLOAD.

a. Truckload. Each truck load will be weighed to the nearest 0.1 ton and the final quantity rounded to the nearest whole ton. Stone will be measured for payment by weighing on approved scales before being placed in the work. Scales shall be of sufficient length to permit simultaneous weighing of all axle loads and shall have an accuracy within 0.2 percent throughout the range of the scales. The scale's accuracy shall conform to the applicable requirements of NIST HB 44 and shall be certified by an acceptable scales company representative prior to weighing any stone. The scales shall be capable of printing a weight ticket including time, date, truck number, and weight. If commercial scales are readily available in close proximity (within 10 miles) of site of work, documentation shall be submitted certifying that the scales meet the requirements of the specification. Furnish the scales and weigh the stone in the presence of the Contracting Officer,. The Contracting Officer may elect to accept certified railroad weights or weight certificates furnished by a public weighmaster in lieu of scale weights at the jobsite. Scales will be checked and certified before hauling stone and after each 50,000 tons increment of stone weighed under this contract.

b. Barge or vessel Load

(1) If delivered by barge or vessel, stone will be measured for payment by the Contracting Officer by weight determined by barge/vessel displacement. Furnish the Contracting Officer a barge/vessel displacement table not less than 10 work days prior to unloading the stone from any barge/vessel. Each table submitted shall show the name and/or number of the barge/vessel owner, the name of the fabricator, and the certification and date of certification of the person or firm preparing the table.

Furnish with the barge vessel displacement tables a drawing or sketch of each barge/vessel, dimensioned in sufficient detail to permit checking of the tables. The drawings shall show, as a minimum, the length, width, depth of the barge/vessel, and dimensions of the rake or rakes. Each such table shall have its accuracy certified by a person or firm, other than the Contractor, customarily performing this service. Each table submitted shall contain, in parallel columns, the freeboard of the barge/vessel in feet and tenths from zero to the full depth of the barge/vessel and the corresponding gross displacement to the nearest ton. Each barge/vessel shall be suitably marked with two displacement gaging locations on each side near each end of the barge/vessel and two amidships on opposite sides. Each gaging location shall be marked by a line perpendicular to the edge of the barge/vessel, 4 inches wide and 1 foot long, on both the deck and side of the barge/vesseland two amid ship on opposite sides. BargesVessels with rakes shall have the displacement gaging lines placed at each corner of the box section between the rakes. If a barge/vessel has a box end or ends, the gaging locations shall be placed

SECTION 01 22 00.00 10 Page 4 approximately 4 feet from the box end(s). The freeboard will be measured at the four gaging locations and the displacement determined by the use of "STANDARD BARGE/VESSEL TABLES" from the average of these measurements. The displacement will be determined before and after being unloaded and the difference between these values shall be the quantity delivered. Submit the Gaging Table Data, stone hauling vessel, gaging tables and a copy of the data and calculations used for the preparation of the tables. BargesVessels shall be loaded so that the readings taken at the gaging locations do not vary more than 1.5 feet port to starboard fore and aft and do not vary more than 0.5 feet port to starboard. If such is not the case, trim the carrier by shifting the stone until this limit is reached, before the measurement will be accepted. The draft shall be determined from the average of all six readings weighting the readings of the middle gage at double those of the end gages. (G1 + G2 + 2xG3 + 2xG4 + G5 + G6) divided by 8 = average draft. All carriers used in transporting stone shall be free of leaks such as would render accurate gauging difficult. Facilities for inspecting the hold of each carrier to determine whether leakage is occurring shall be provided. Each carrier shall also be provided with adequate pumping facilities, and if water is found to be accumulating in the hold, the carrier shall be pumped dry before each gaging, both before and after unloading. Lightening by pumping or by transfer of crew or supplies will not be permitted while stone is being transferred.

Rejected stone and unacceptable material shall be left aboard the barge/vessel until after the final readings have been taken.

(2) If barge/vessel tables are furnished for fresh water and if it is believed that barge/vessel displacement measurements made within the contract limits of the work are being taken in water that has salinity, the Contractor has the option of obtaining water samples and determining densities or unit weights of these samples. These water samples shall be taken in accordance with ASTM D3370 (Practice A - Grab Samples) at depths of 4 and 8 feet in the area where measurements are made. Water sampling shall be performed when the bargesvessels are measured for quantities, both when fully loaded and when empty. Take water samples, as witnessed by the Contracting Officer, with the use of "Polypro" 2000 ml water sampler, or equal. Densities shall be determined as specified in ASTM D1429 (Method D-Hydrometer Method). Testing shall be done for the Contractor by a certified testing laboratory, and test results certified by the laboratory. After review and approval of the test results by the Contracting Officer, the average of the densities obtained at 4 and 8 feet will be used as the suitable salt water conversion factor. In all calculations, the unit weight of 62.4 pounds per cubic foot will be used for fresh water.

c. Stockpiled Stone . If the Contractor elects to stockpile stone on the worksite or offsite, the stone shall be weighed immediately before placement by either method described above. Stone placed in temporary storage on the worksite as specified section 35 31 19 STONE MATERIALS AND PLACEMENT paragraph WORKSITE STOCKPILE will not be required to be re-weighed prior to placement. If the barge/vessel displacement method is elected, a minimum of one-third the total maximum displacement of the barge/vessel tons of stone is required on each bargevessel.

d. Determination of Excess Stone. All stone outside the limits and tolerances of the cross sections of the structure, except variations so

SECTION 01 22 00.00 10 Page 5 minor as not to be measurable, will be deducted from the quantity of new stone for which payment is to be made. Weight of excess stone will be determined from the cross sections obtained by the method provided for in paragraph FINAL SURVEYS, on the basis that the cubic feet of volume (including voids) for each type of stone, as listed in the Table in section 35 31 19 STONE MATERIALS AND PLACEMENT paragraph FACTORS USED FOR CONVERTING IN PLACE VOLUME TO WEIGHT, is equal to one ton or 2,000 pounds for the bulk specific gravity and percentage of voids shown. If the bulk specific gravity of the stone furnished or the percentage of voids is other than as listed below, the cubic feet of volume equaling 2,000 pounds shall be recomputed. Should any excess stone be disclosed above the tolerance line as defined in paragraph TOLERANCES, its volume will be computed by the average end area method, based upon the cross section in the following manner. The average end area of excess stone above the tolerance line for two (2) successive cross sections, multiplied by the distance between the cross sections will be accepted as the volume. In addition to the above, stone, which has been delivered to the site and has been lost or wasted or otherwise not properly incorporated into the final required work, shall be deducted from the quantity for which payment is to be made.

e. Final Surveys. Survey work and measurements required for determination of excess volume computations for stone materials shall be performed in the presence of the Contracting Officer. Notify the Contracting Officer not less than 3 days in advance of each survey. In the event of unavailability of the Contracting Officer, perform the survey and certify to the Contracting Officer that it complies with the specifications. Cross section surveys shall be taken perpendicular to the axis of the structures. Elevations and soundings shall be taken on lines 25 feet apart measuring along the structure reference line, with the readings at 5-foot intervals and at breaks in the grade along the line. Other survey intervals and readings may be used if deemed appropriate or advisable by the Government's on-site representative.

Additional cross sections, elevations, and soundings may be taken if determined necessary by the Government's on-site representative.

Determination of quantities will be made by the Government's on-site representative and having once been made, will not reopen, except on evidence of collusion, fraud or obvious error. Prior to performing any work under this Section, coordinate all operations with the Government's on-site representative so that excess volume surveys will be made at the appropriate time. The surveys made under section 35 31 19 STONE MATERIALS AND PLACEMENT paragraph CHECK SURVEYS may be used when deemed appropriate by the Government's on-site representative, as part of the surveys required herein. Stone quantity computations shall be based entirely upon weights of new stone as determined from carrier displacement or certified scale weight tickets. Existing stone placed in lieu of new stone from off-site sources is excluded from measurement and payment.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 22 00.00 10 Page 6

SECTION 01 22 00.00 10 Page 7

DIVISION 01 - GENERAL REQUIREMENTS

SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

02/15 the preparation and use of construction schedules for small projects

PART 1 GENERAL

1.1 SUBMITTALS

1.2 ACCEPTANCE

1.3 SCHEDULE FORMAT

1.3.1 Network Analysis Schedule (NAS)

1.3.1.1 Primavera P6 Settings and Parameters

1.3.1.2 Microsoft Project 2010 Settings and Parameters

1.3.1.3 Cost Loading Microsoft Project 2010 Schedules

1.3.2 Schedule Submittals and Procedures

1.4 SCHEDULE MONTHLY UPDATES

1.5 CONTRACT MODIFICATION

1.6 4-WEEK LOOK AHEAD SCHEDULE

1.7 CORRESPONDENCE AND TEST REPORTS:

1.8 ADDITIONAL SCHEDULING REQUIREMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 32 16.00 20 Page 1

SECTION 01 32 16.00 20

SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

02/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Schedule; G, AOF

SD-07 Certificates

Monthly Updates

1.2 ACCEPTANCE

Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a construction schedule in the form of a Bar Chart Schedule in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract.

The acceptance of a Baseline Construction Schedule is a condition precedent to:

a. The Contractor starting work on the demolition or construction stage(s) of the contract.

b. Processing Contractor's invoice(s) for construction activities/items of work.

c. Review of any schedule updates.

Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).

1.3 SCHEDULE FORMAT

1.3.1 Network Analysis Schedule (NAS)

Use the critical path method (CPM) to schedule and control project activities. Prepare and maintain project schedules using Primavera P6 or Microsoft Project 2010. Importing data into the scheduling program using data conversion techniques or third party software is cause for rejection of the submitted schedule. Build the schedule as follows:

SECTION 01 32 16.00 20 Page 2

a. The Project Schedule must show submittals, Government review periods, material/equipment delivery, utility outages, all on-site construction, inspection, testing, and closeout activities. Government and Contractor on-site work activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.

b. With the exception of the Contract Award and End Contract milestone activities, no activities shall be open-ended; each activity must have predecessor and successor ties. No activity must have open start or open finish (dangling) logic. Minimize redundant logic ties. Once an activity exists on the schedule it must not be deleted or renamed to change the scope of the activity and must not be removed from the schedule logic without approval from the Contracting Officer. While an activity cannot be deleted, where said activity is no longer applicable to the schedule but must remain within the logic stream for historical record, it can be changed to a milestone. Document any such change in the milestone's "Notebook", including a date and explanation for the change. The ID number for a deleted activity must not be re-used for another activity.

c. Each activity must be assigned its appropriate Responsibility Code indicating responsibility to accomplish the work indicated by the activity, Phase Code and Work Location Code.

d. Date/time constraint(s) and/or lags, other than those required by the contract, are not allowed unless accepted by the Contracting Officer.

Include as the last activity in the contract schedule, a milestone activity named "Contract Completion Date".

1.3.1.1 Primavera P6 Settings and Parameters

Use the following Primavera P6 settings and parameters in preparing the Baseline Schedule. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.

a. General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.

b. Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:

(1) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week, 172.0 Hours/Month and 2000.0 Hours/Year.

(2) Use assigned calendar to specify the number of work hours for each time period: Must be checked.

c. Project Level, Dates Tab:

(1) Set "Must Finish By" date to "Contract Completion Date".

d. Project Level, Defaults Tab:

(1) Duration Type: Set to "Fixed Duration & Units".

(2) Percent Complete Type: Set to "Physical".

(3) Activity Type: Set to "Task Dependent".

SECTION 01 32 16.00 20 Page 3

(4) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days.

Alternative calendars may be used with Contracting Officer approval.

e. Project Level, Calculations Tab:

(1) Activity percent complete based on activity steps: Must be Checked.

(2) Reset Remaining Duration and Units to Original: Must be Checked.

(3) Subtract Actual from At Completion: Must be Checked.

(4) Recalculate Actual units and Cost when duration percent(%) complete changes: Must be Checked.

(5) Link Actual to Date and Actual This Period Units and Cost: Must be Checked.

f. Project Level, Settings Tab:

(1) Define Critical Activities: Check "Total Float is less than or equal to" and add "0d".

g. No on-site construction activity may have durations in excess of 20 working days.

1.3.1.2 Microsoft Project 2010 Settings and Parameters

The Network must have a minimum of 30 construction activities. No on-site construction activity may have durations in excess of 20 working days.

1.3.1.3 Cost Loading Microsoft Project 2010 Schedules

Assign material, labor and equipment costs to their respective Construction Activities. Material and equipment costs for which payment will be requested in advance of installation must be assigned to their respective procurement activity (i.e. the material/equipment on-site activity).

Evenly disperse overhead and profit to each activity over the duration of the project. Cost loading must total to 100 percent of the value of the contract.

a. Submit an Earned Value Report with each schedule update showing activity budget, cost percent complete, earned amount and cost to complete as directed by the Contracting Officer.

b. With each schedule submission, provide a Schedule Variance control (SVC) diagram showing:

(1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates.

(2) Earned Value to-date. Revise Cash Flow S-Curves when the contract is modified, or as directed by the Contracting Officer.

1.3.2 Schedule Submittals and Procedures

Submit Network Analysis Schedules (NAS) and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an

SECTION 01 32 16.00 20 Page 4 electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.

1.4 SCHEDULE MONTHLY UPDATES

Update the Construction Schedule at monthly intervals or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.

a. Narrative Report: Provide with schedule updates. Identify and justify;

(1) Progress made in each area of the project

(2) Critical Path

(3) Date/time constraint(s), other than those required by the contract

(4) Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones, planned sequence of operations, and critical path

(5) Status of Contract Completion Date and interim milestones;

(6) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);

(7) Description of current and future schedule problem areas.

Each entry in the narrative report must cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change.

1.5 CONTRACT MODIFICATION

Submit a Time Impact Analysis (TIA) with each cost and time proposal for a proposed change. TIA must illustrate the influence of each change or delay on the Contract Completion Date or milestones. No time extensions will be granted nor delay damages paid unless a delay occurs which consumes all available Project Float, and extends the Projected Finish beyond the Contract Completion Date.

a. Each TIA must be in both narrative and schedule form. The narrative must define the scope and conditions of the change; provide start and finish dates of impact, successor and predecessor activity to impact period, responsible party, describe how it originated, and how it impacts the schedule. The schedule submission must consist of three native files:

(1) Fragnet used to define the scope of the changed condition

(2) Most recent accepted schedule update as of the time of the proposal or claim submission that has been updated to show all activity progress as of the time of the impact start date.

(3) The impacted schedule that has the fragnet inserted in the updated schedule and the schedule "run" so that the new completion date is

SECTION 01 32 16.00 20 Page 5 determined.

b. For claimed as-built project delay, the inserted fragnet TIA method must be modified to account for as-built events known to occur after the data date of schedule update used.

c. All TIAs must include any mitigation, and must determine the apportionment of the overall delay assignable to each individual delay. The associated narrative must clearly describe the findings in a chronological listing beginning with the earliest delay event.

(1) Identify types of delays as follows:

(a) Excusable Delay: Force-Majeure (e.g. weather) - Contractor may receive time extension, but time will not be compensable.

(b) Inexcusable Delay: Contractor Responsibility - Contractor will not receive time extension.

(c) Compensable Delay: Government Responsibility - Contractor may receive compensable time extension.

(2) If a combination of any of the delay types outlined above occurs, it is considered a Concurrent Delay, which will require an analysis of the facts to determine compensability and entitlement to any time extension under the applicable contract clauses.

d. Submit Data disks containing the narrative and native schedule files.

e. Unless the Contracting Officer requests otherwise, only add conformed contract modifications into the Project NAS.

1.6 4-WEEK LOOK AHEAD SCHEDULE

Prepare and issue a 4-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.

Key the work plans to activity numbers when a NAS is required and update each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Construction Schedule on an electronic spreadsheet program and printed on 8-1/2 by 11 inch sheets as directed by the Contracting Officer. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Deliver three hard copies and one electronic file of the 4-Week Look Ahead Schedule to the Contracting Officer for review during the weekly CQC Coordination or Production Meeting.

1.7 CORRESPONDENCE AND TEST REPORTS:

All correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) must reference Schedule Activities that are being addressed. All test reports (e.g., concrete, soil compaction, weld, pressure) must reference Schedule Activities that are being addressed.

SECTION 01 32 16.00 20 Page 6

1.8 ADDITIONAL SCHEDULING REQUIREMENTS

Any references to additional scheduling requirements, including systems to be inspected, tested and commissioned, that are located throughout the remainder of the Contract Documents, are subject to all requirements of this section.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 32 16.00 20 Page 7

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11 general procedures regarding submittals, data normally submitted for review to establish conformance with the design concept and contract documents

PART 1 GENERAL

1.1 SUMMARY

1.2 SUBMITTAL PROCEDURES

1.2.1 Electronic File Format

1.3 DEFINITIONS

1.3.1 Submittal Descriptions (SD)

1.3.2 Approving Authority

1.3.3 Work

1.4 SUBMITTALS

1.5 SUBMITTAL CLASSIFICATION

1.5.1 Government Approved (G)

1.5.2 Information Only

1.6 PREPARATION

1.6.1 Transmittal Form

1.7 QUANTITY OF SUBMITTALS

1.7.1 Number of Copies of SD-02 Shop Drawings

1.7.2 Number of Copies of SD-03 Product Data and SD-08

Manufacturer's Instructions

1.7.3 Number of Samples SD-04 Samples

1.7.4 Number of Copies SD-05 Design Data and SD-07 Certificates

1.7.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's

Field Reports

1.7.6 Number of Copies of SD-10 Operation and Maintenance Data

1.7.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11

Closeout Submittals

1.8 INFORMATION ONLY SUBMITTALS

1.9 VARIATIONS

1.9.1 Considering Variations

1.9.2 Proposing Variations

1.9.3 Warranting That Variations Are Compatible

1.9.4 Review Schedule Is Modified

1.10 SUBMITTAL REGISTER

1.10.1 Use of Submittal Register

1.10.2 Contractor Use of Submittal Register

1.10.3 Approving Authority Use of Submittal Register

1.10.4 Copies Delivered to the Government

1.11 SCHEDULING

1.12 GOVERNMENT APPROVING AUTHORITY

1.12.1 Review Notations

1.13 DISAPPROVED OR REJECTED SUBMITTALS

1.14 APPROVED/ACCEPTED SUBMITTALS

SECTION 01 33 00 Page 1

1.15 APPROVED SAMPLES

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders;

samples; O&M manuals (including parts list); certifications; warranties;

and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

1.2 SUBMITTAL PROCEDURES

*Note - also see section 01 45 02.00 10 for submittal procedures using QCS.

1.2.1 Electronic File Format

Provide submittals other than material samples in both hard copy (paper) and electronic formats. The electronic submittal file must be compiled as a single, complete document, to include the Transmittal Form described in this section. The electronic submittal file must be named specifically according to its contents (e.g. 01 45 00.00-1.2_Quality Control Plan.pdf).

Electronic files must be of sufficient quality that all information is legible. Electronic format shall be in Adobe.PDF format, unless otherwise specified or directed by the Contracting Officer's Representative (COR).

Whenever possible, PDF files shall be generated from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Files exceeding 30 pages shall be indexed and bookmarked to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.

SECTION 01 33 00 Page 3

Email electronic submittal documents fewer than 10MB to an email address as directed by the COR. Electronic documents over 10MB shall be provided on a CD/DVD, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:

https://safe.amrdec.army.mil/safe/

Provide hard copies of submittals as specified in this or other specification sections.

1.3 DEFINITIONS

1.3.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates of insurance

Surety bonds

List of proposed Subcontractors

List of proposed products

Construction progress schedule

Network Analysis Schedule (NAS)

Submittal register

Schedule of prices

Health and safety plan

Work plan

Quality Control(QC) plan

Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

SECTION 01 33 00 Page 4

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by

SECTION 01 33 00 Page 5 responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

SD-10 Operation and Maintenance Data

Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

This data is intended to be incorporated in an operations and maintenance manual or control system.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

Interim "DD Form 1354" with cost breakout for all assets 30 days prior to facility turnover.

1.3.2 Approving Authority

Office or designated person authorized to approve submittal.

AOF

Grand Haven Area Office ATTN: Chris Schropp 307 S Harbor Dr, Grand Haven, MI 49417 Phone: 616-842-5510

ECG

Detroit District USACE ATTN: Blake Gerken 477 Michigan Ave Detroit, MI 48226 Phone: 313-226-3189

SECTION 01 33 00 Page 6

1.3.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G, AOF

1.5 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.5.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract Clause 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings.

1.5.2 Information Only

Submittals not requiring Government approval will be for information only.

They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.6 PREPARATION

1.6.1 Transmittal Form

Use the attached sample transmittal form (ENG Form 4025) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms are included in the QCS software that the Contractor is required to use for this contract.

Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.7 QUANTITY OF SUBMITTALS

1.7.1 Number of Copies of SD-02 Shop Drawings

Submit 6 copies of submittals of shop drawings requiring review and approval only by QC organization and 7 copies of shop drawings requiring review and approval by Contracting Officer.

SECTION 01 33 00 Page 7

1.7.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions

Submit in compliance with quantity requirements specified for shop drawings.

1.7.3 Number of Samples SD-04 Samples

a. Submit 2 samples, or 2 sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.

b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.

c. Submit one sample installation, where directed.

d. Submit one sample of non-solid materials.

1.7.4 Number of Copies SD-05 Design Data and SD-07 Certificates

Submit in compliance with quantity requirements specified for shop drawings.

1.7.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports

Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.

1.7.6 Number of Copies of SD-10 Operation and Maintenance Data

Submit 3 copies of O&M Data to the Contracting Officer for review and approval.

1.7.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals

Unless otherwise specified, submit 2 sets of administrative submittals.

1.8 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.9 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

SECTION 01 33 00 Page 8

1.9.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.9.2 Proposing Variations