Breakwater Reconstruction Grand Marais Harbor, MI GRANMA12
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 10 REAL ESTATE
01 22 00.00 10 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 35 13.10 SPECIAL PROJECT PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 02.00 10 QUALITY CONTROL SYSTEM (QCS)
01 45 04.00 10 CONTRACTOR QUALITY CONTROL
01 57 20.00 20 ENVIRONMENTAL PROTECTION
01 99 90 LISTING OF ENCLOSED DOCUMENTS, EXHIBITS AND OTHER
ATTACHEMENT
DIVISION 31 - EARTHWORK
31 00 00 SITE PREPARATION
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 31 19.45 03 STONE MATERIALS
35 31 19 STONE PLACEMENT AND CONSTRUCTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 10
REAL ESTATE
PART 1 GENERAL
1.1 SUBMITTALS
1.2 REGULATORY REQUIREMENTS
1.2.1 Real Estate Rights
1.2.2 Additional Real Estate Rights
1.3 PROJECT/SITE CONDITIONS
1.3.1 Location and Verification
1.3.2 Survey Markers
1.3.2.1 Semipermanent Markers
-- End of Section Table of Contents --
SECTION 01 10 10 Page 1
SECTION 01 10 10
REAL ESTATE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Additional Property Agreements; G-RED.
Copies of any agreements for Contractor-acquired real estate rights for this project shall be furnished before entering thereon.
1.2 REGULATORY REQUIREMENTS
1.2.1 Real Estate Rights
Rights for the use of the work and storage areas have been obtained and the general limits of the areas are shown on the drawings. Copies of instruments conveying rights for use of the work and storage areas shown on the drawings and specified herein are available for inspection in the Engineering & Construction Division Design Branch, U.S. Army Corps of Engineers, Detroit District, 477 Michigan Avenue, McNamara Building, Detroit, Michigan. Conformance to all applicable requirements of the instruments conveying rights is required.
1.2.2 Additional Real Estate Rights
Any additional property agreements and/or real estate rights desired by the Contractor shall be obtained by the Contractor at its own expense. Such agreements shall clearly relieve the Government of any responsibility for damages or liability resulting from the Contractor's use of such grounds.
1.3 PROJECT/SITE CONDITIONS
1.3.1 Location and Verification
It shall be the Contractor's responsibility to accurately locate the limits of all lands utilized under the contract. The corner and angle points of each area for which rights have been obtained shall be marked with semipermanent markers except where there is an approved existing property marker. Temporary markers shall be placed at points on alignment. The points on alignment shall be marked at stations so that intervals between points do not exceed 200 feet.
1.3.2 Survey Markers
All markers shall be installed in an area prior to its use and they shall
SECTION 01 10 10 Page 2 be available for reference during and upon completion of use of the area.
Where approved existing property markers are found, a witness stake, as specified in Subparagraph, "Semipermanent Markers" below, shall be provided. If the types of markers specified hereinafter cannot be used, other types, as approved by the Contracting Officer, shall be provided.
1.3.2.1 Semipermanent Markers
The markers shall be a steel rod one-half inch in diameter and four (4) feet long. The steel rod shall be driven vertically into the ground so that the top is flush with the finished ground surface. Each marker shall be witnessed by a 2" x 2" yellow stake extending two (2) feet above the ground surface and driven into the ground until stable, with not less than one (1) foot penetration.
-- End of Section --
SECTION 01 10 10 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 LUMP SUM PAYMENT ITEMS
1.2.1 Mobilization and Demobilization (Payment Item No. 0001)
1.2.2 Site Preparation/Restoration (Payment Item No. 0002)
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 Amor Stone (Payment Item No. 0003, 0006, 0009, and 0012 )
1.3.2 Filter Stone (Payment Item No. 0004, 0007, 0010 and 0013)
1.3.3 Core Stone (Payment Item No. 0005, 0008, 00011, and 0014)
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 10 Page 1
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Weight Certificates
Submit certified weight certificates for R 200 core, bedding, underlayer and armor stone.
1.2 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Mobilization and Demobilization (Payment Item No. 0001)
Payment: Payment will be made for costs associated with mobilization and demobilization, as defined in Special Clause PAYMENT FOR MOBILIZATION AND
DEMOBILIZATION.
Unit of Measure: Lump sum.
1.2.2 Site Preparation/Restoration (Payment Item No. 0002)
Payment: Payment will be made for costs associated with Site Preparation required under SECTION 31 00 00 "SITE PREPARATION" , SECTION 01 35 13.10 "SPECIAL PROJECT PROCEDURES", and SECTION 01 57 20.00 20 "ENVIROMENTAL
PROTECTION".
Unit of Measure: Lump sum.
SECTION 01 22 00.00 10 Page 2
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.3.1 Amor Stone (Payment Item No. 0003, 0006, 0009, and 0012 )
Payment: Payment will be made for costs associated with furnishing, transporting, stockpiling (if applicable), placing, and constructing the stone protection as specified and shown.
Measurement: Measurement for payment for bedding stone will be made as specified in SECTION 35 31 19.45 03 "STONE MATERIALS" and SECTION 35 31 19 "STONE PLACEMENT AND CONSTRUCTION". The payement will be made at the applicable contract unit price per ton for the payment items, Bid Item 0003 "Armor Stone", Bid Item 0003AA "First 3,600 Tons"; and Bid Item 0003AB "Over 3,600 Tons". OPTION-1, Bid Item 0006 "Armor Stone", Bid Item 0006AA "First 850 Tons"; and Bid Item 0006AB "Over 850 Tons". OPTION-2, Bid Item 0009 "Armor Stone", Bid Item 0009AA "First 850 Tons"; and Bid Item 0009AB "Over 850 Tons". OPTION-3, Bid Item 0012 "Armor Stone", Bid Item 0012AA "First 850 Tons"; and Bid Item 0012AB "Over 850 Tons".
Unit of measure: Ton (2,000 pounds).
1.3.2 Filter Stone (Payment Item No. 0004, 0007, 0010 and 0013)
Payment: Payment will be made for costs associated with furnishing, transporting, stockpiling (if applicable),and placing, the fillstone as specified and shown.
Measurement: Measurement for payment for fill stone will be made as specified in SECTION 35 31 19.45 03 "STONE MATERIALS" and SECTION 35 31 19 "STONE PLACEMENT AND CONSTRUCTION". The payement will be made at the applicable contract unit price per ton for the payment items, Bid Item 0004 "Filter Stone", Bid Item 0004AA "First 610 Tons"; and Bid Item 0004AB "Over 610 Tons". OPTION - 1 Bid Item 0007 "Filter Stone", Bid Item 0007AA "First 180 Tons"; and Bid Item 0007AB "Over 180 Tons". OPTION - 2, Bid Item 0010 "Filter Stone", Bid Item 0010AA "First 180 Tons"; and Bid Item 0010AB "Over 180 Tons" and OPTION - 3, Bid Item 0013 "Filter Stone", Bid Item 0013AA "First 180 Tons"; and Bid Item 0013AB "Over 180 Tons".
Unit of measure: Ton (2,000 pounds).
1.3.3 Core Stone (Payment Item No. 0005, 0008, 00011, and 0014)
Payment: Payment will be made for costs associated with furnishing, transporting, stockpiling (if applicable), placing, and constructing the stone protection as specified and shown.
Measurement: Measurement for payment for bedding stone will be made as specified in SECTION 35 31 19.45 03 "STONE MATERIALS" and SECTION 35 31 19 "STONE PLACEMENT AND CONSTRUCTION". The payement will be made at the applicable contract unit price per ton for the payment items, Bid Item 0005
SECTION 01 22 00.00 10 Page 3
"Core Stone", Bid Item 0005AA "First 3,900 Tons"; and Bid Item 0005AB "Over 3,900 Tons". OPTION - 1, Bid Item 0008 "Core Stone", Bid Item 0008AA "First 800 Tons"; and Bid Item 0008AB "Over 800 Tons". OPTION - 2, Bid Item 0011 "Core Stone", Bid Item 0011AA "First 800 Tons"; and Bid Item 0011AB "Over 800 Tons". OPTION - 3, Bid Item 0014 "Core Stone", Bid Item 0014AA "First 800 Tons"; and Bid Item 0014AB "Over 800 Tons".
Unit of measure: Ton (2,000 pounds).
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 10 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved [G]
1.4.2 Information Only
1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.5.1 Submittals Required from the Contractor
1.5.1.1 O&M Data
1.6 PREPARATION
1.6.1 Transmittal Form
1.7 QUANTITY OF SUBMITTALS
1.7.1 Number of Copies of SD-02 Shop Drawings
1.7.2 Number of Copies of SD-03 Product Data and SD-08
Manufacturer's Instructions
1.7.3 Number of Samples SD-04 Samples
1.7.4 Number of Copies SD-05 Design Data and SD-07 Certificates
1.7.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's
Field Reports
1.7.6 Number of Copies of SD-10 Operation and Maintenance Data
1.7.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11
Closeout Submittals
1.8 INFORMATION ONLY SUBMITTALS
1.9 VARIATIONS
1.9.1 Considering Variations
1.9.2 Proposing Variations
1.9.3 Warranting That Variations Are Compatible
1.9.4 Review Schedule Is Modified
1.10 SUBMITTAL REGISTER
1.10.1 Use of Submittal Register
1.10.2 Contractor Use of Submittal Register
1.10.3 Approving Authority Use of Submittal Register
1.10.4 Copies Delivered to the Government
1.11 SCHEDULING
1.12 GOVERNMENT APPROVING AUTHORITY
1.12.1 Review Notations
1.13 DISAPPROVED[ OR REJECTED] SUBMITTALS
1.14 APPROVED[/ACCEPTED] SUBMITTALS
1.15 APPROVED SAMPLES
1.16 WITHHOLDING OF PAYMENT
1.17 PROGRESS SCHEDULE
SECTION 01 33 00 Page 1
1.17.1 Bar Chart
1.18 STATUS REPORT ON MATERIALS ORDERS
1.19 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance
Surety bonds
List of proposed Subcontractors
SECTION 01 33 00 Page 3
List of proposed products
Construction Progress Schedule
Network Analysis Schedule (NAS)
Submittal register
Schedule of prices
Health and safety plan
Work plan
Quality Control(QC) plan
Environmental protection plan
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, SECTION 01 33 00 Page 4 installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
Area Office Field (AOF) Real Estate Office (REO) Engineering, Design and Construction Office (EDC)
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor QC approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G, AOF
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved [G]
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled, "Specifications and
SECTION 01 33 00 Page 5
Drawings for Construction," they are considered to be "shop drawings."
1.4.2 Information Only
Submittals not requiring Government approval will be for information only.
They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.5.1 Submittals Required from the Contractor
As soon as practicable after award of contract, and before procurement of fabrication, forward to the submittals required in the technical sections of this specification, including shop drawings, product data and samples.
One copy of the transmittal form for all submittals shall be forwarded to the Resident Officer in Charge of Construction.
[The Architect-Engineer for this project] [NAVFAC Atlantic] will review and approve for the Contracting Officer those submittals reserved for Contracting Officer approval to verify submittals comply with the contract requirements.
1.5.1.1 O&M Data
[The Architect-Engineer for this project] [NAVFAC Atlantic] will review and approve for the Contracting Officer O&M Data to verify the submittals comply with the contract requirements; submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.
In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.
]1.6 PREPARATION
1.6.1 Transmittal Form
Use the attached sample transmittal form (ENG Form 4025) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms are included in the QCS software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.7 QUANTITY OF SUBMITTALS
1.7.1 Number of Copies of SD-02 Shop Drawings
Submit six copies of submittals of shop drawings requiring review and approval only by QC organization and seven copies of shop drawings requiring review and approval by Contracting Officer.
SECTION 01 33 00 Page 6
1.7.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions
Submit in compliance with quantity requirements specified for shop drawings.
1.7.3 Number of Samples SD-04 Samples
a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.7.4 Number of Copies SD-05 Design Data and SD-07 Certificates
Submit in compliance with quantity requirements specified for shop drawings.
1.7.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.
1.7.6 Number of Copies of SD-10 Operation and Maintenance Data
Submit [Five][three][_____] copies of O&M Data to the Contracting Officer for review and approval.
1.7.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
Unless otherwise specified, submit [two][three] sets of administrative submittals.
1.8 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.9 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will
SECTION 01 33 00 Page 7 be considered where advantageous to Government.
1.9.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.9.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.
The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.9.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.9.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
1.10 SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and
(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS). [The Government will provide the initial submittal register ][in electronic format][ with the following fields completed, to the extent that will be required by the Government during subsequent usage.]
Column (c): Lists specification section in which submittal is
SECTION 01 33 00 Page 8 required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
[ Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.10.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
[ Column (a) Activity Number: Activity number from the project schedule.
][ Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
][ Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
][ Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
]1.10.2 Contractor Use of Submittal Register
Update the following fields[ in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor] with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.10.3 Approving Authority Use of Submittal Register
Update the following fields[ in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor].
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
SECTION 01 33 00 Page 9
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.10.4 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.11 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals. An additional 10 calendar days will be allowed and shown on the register for review and approval of submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.12 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph entitled, "Review Notations," of this section and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. 3 copies of the approved submittal will be retained by the Contracting Officer and 3 copies of the submittal will be returned to the Contractor.
SECTION 01 33 00 Page 10
1.12.1 Review Notations
Contracting Officer review will be completed within 14 calendar days after date of submission. Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" "or approved except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.13 DISAPPROVED[ OR REJECTED] SUBMITTALS
Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.
Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.14 APPROVED[/ACCEPTED] SUBMITTALS
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is
SECTION 01 33 00 Page 11 necessary.
1.15 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested.
Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.
Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.
Contractor to replace such materials or equipment to meet contract requirements.
Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.
1.16 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
1.17 PROGRESS SCHEDULE
1.17.1 Bar Chart
[ a. Submit the progress chart, for approval by the Contracting Officer, at the Preconstruction Conference in one reproducible and 4 copies.
b. Prepare the progress chart in the form of a bar chart utilizing form "Construction Progress Chart" or comparable format acceptable to the Contracting Officer.
c. Include no less than the following information on the progress chart:
(1) Break out by major headings for primary work activity.
(2) A line item break out under each major heading sufficient to track the progress of the work.
(3) A line item showing contract finalization task which includes punch list, clean-up and demolition, and final construction drawings.
SECTION 01 33 00 Page 12
(4) A materials bar and a separate labor bar for each line item.
Both bars will show the scheduled percentage complete for any given date within the contract performance period. Labor bar will also show the number of men (man-load) expected to be working on any given date within the contract performance period.
(5) The estimated cost and percentage weight of total contract cost for each materials and labor bar on the chart.
(6) Separate line items for mobilization and drawing submittal and approval. (These items are to show no associated costs.)
d. Update the progress schedule in one reproduction and 4 copies every 30 calendar days throughout the contract performance period.
]1.18 STATUS REPORT ON MATERIALS ORDERS
Within 10 calendar days after notice to proceed, submit, for approval by the Contracting Officer, an initial material status report on all materials orders. This report will be updated and re-submitted every 10 calendar days as the status on material orders changes.
Report to include list, in chronological order by need date, materials orders necessary for completion of the contract. The following information will be required for each material order listed:
a. Material name, supplier, and invoice number.
b. Bar chart line item or CPM activity number affected by the order.
c. Delivery date needed to allow directly and indirectly related work to be completed within the contract performance period.
d. Current delivery date agreed on by supplier.
e. When item d exceeds item c, the effect that delayed delivery date will have on contract completion date.
f. When item d exceeds item c, a summary of efforts made by the Contractor to expedite the delayed delivery date to bring it in line with the needed delivery date, including efforts made to place the order (or subcontract) with other suppliers.
1.19 STAMPS
Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements is to be similar to the following:
SECTION 01 33 00 Page 13
| CONTRACTOR |
| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s) |
| SIGNATURE: __________________________________________________________ |
| TITLE: ______________________________________________________________ |
| DATE: _______________________________________________________________ |
For design-build construction, both the Contractor Quality Control System Manager and the Designer of Record are to stamp and sign to certify that the submittal meets contract requirements.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 33 00 Page 14
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 3 PAGES
Breakwater Reconstruction Grand Marais Harbor, MI
01 10 10 SD-01 Preconstruction Submittals
1.2.2 G REDAdditional Property Agreements
01 22 00.00 10 SD-03 Product Data Weight Certificates
01 33 00 SD-01 Preconstruction Submittals
1.10 G AOFSubmittal Register
01 35 13.10 SD-01 Preconstruction Submittals 1.7.2Payrolls and Basic Records
1.7.3 G AOFProgress Chart
1.4.2NOTICE TO MARINERS
2.1.1 G ECDNon-listed, Non-Commercially
Active Stone or Material Source
1.4.4 G AOFUtility Location Findings
SD-07 Certificates 2.2As-Built Technician's
Qualifications
2.2 G AOFAs-built Drawings
01 35 26 SD-01 Preconstruction Submittals
1.6 G AOFAccident Prevention Plan (APP)
1.7 G AOFActivity Hazard Analysis (AHA)
1.6.1 G AOFCrane Critical Lift Plan
1.5.1.3 G AOFCrane Operators
SD-06 Test Reports 1.11Reports 1.11.1Accident Reports 1.11.3Crane Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 3 PAGES
01 35 26 Gas Protection SD-07 Certificates
1.8Confined Space Entry Permit 1.8Hot work permit
License Certificates G AOFContractor Safety Self-Evaluation
Checklist Third Party Certification of Barge-Mounted Mobile Cranes
1.11.4Certificate of Compliance Machinery & Mechanized Equipment Certification Form
01 57 20.00 20 SD-01 Preconstruction Submittals
1.7 G AOFEnvironmental Protection Plan
31 00 00 SD-03 Product Data Work Plan
SD-09 Manufacturer’s Field Reports Utilization of Excavated Materials
35 31 19.45 03 SD-03 Product Data G EDCStone Source G EDCStone Materials Control (SMC)
Plan G EDCRevision of SMC Plan or
Inspection Staffing
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 3 PAGES
35 31 19.45 03 G EDCSMC Field Supervisor Qualifications
SD-06 Test Reports G AOFStone Test Results G EDCSMC Reports G EDCDisplacement Gauge Installation
Data Gauging Table Equipment Data
G EDCRedesign Data Weigh Scale Certification Certified Weight Scale Tickets
G EDCBulk Specific Gravity of Stone Stone Placement Records
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
DIVISION 01 - GENERAL REQUIREMENTS
SECTION [01 35 13.10]
SPECIAL PROJECT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 REGULATORY REQUIREMENTS
1.3.1 Additional Work Proposed and Not Authorized
1.3.1.1 Work Subject to 33 CFR 320-330
1.3.1.2 Work Subject to 40 CFR 233
1.4 PROJECT/SITE CONDITIONS
1.4.1 Condition and Use of Project Site
1.4.1.1 Physical Conditions
1.4.1.2 Work and Storage Areas
1.4.1.2.1 Site Restoration of Work and Storage Area
1.4.2 Waterways Navigation and Traffic
1.4.2.1 Navigation
1.4.2.2 Traffic
1.4.3 Prevailing Lake Levels
1.4.4 Existing Vegetation, Structures, Equipment, Utilities &
Improvements
1.4.5 Vehicular Access
1.4.6 Utility Services
1.4.6.1 Contractor-Furnished Utility Services
1.4.7 Protection and Maintenance of Traffic
1.4.7.1 Haul Roads
1.4.7.2 Barricades
1.4.8 Identification of Employees
1.4.9 Security Requirements and Clearance of Personnel
1.4.9.1 Loitering
1.4.10 Contract Supervision and Representation
1.4.11 Quantity Surveys
1.4.12 Coordination with Others
1.4.13 Traffic Control Plan
1.4.14 Temporary Lights, Signals and Buoys Required by Coast Guard
1.4.15 Navigation Buoys
1.4.15.1 Relocation of Existing Buoys
1.4.15.2 Temporary Dredging and Construction Buoys
1.4.15.3 Buoy Markings
1.4.16 Layout of Work and Surveys
1.4.16.1 Layout of Work
1.4.16.2 Surveyor Requirements
1.4.16.3 Suspension
1.4.16.4 Verification
1.5 SEQUENCING AND SCHEDULING
1.5.1 Exclusion of Period in Computing Completion Schedules
1.5.2 Sunday, Holiday And Night and Extended Hours of Operations
1.5.3 Work Period Restrictions
1.5.4 Start Work
1.6 ACCOMMODATIONS FOR INSPECTORS
SECTION 01 35 13.10 Page 1
1.6.1 Field Office
1.6.1.1 Door Locks
1.6.1.2 Security Window Guards
1.6.1.3 Lighting
1.6.1.4 Storage Closet
1.6.1.5 Cleaning
1.7 REPORT REQUIREMENTS
1.7.1 Accident Prevention Plan
1.7.2 Payrolls and Basic Records
1.7.3 Progress Chart
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Use of Materials from Non-Listed, Non-Commercially Active
Sources
2.2 AS-BUILT DRAWINGS
PART 3 EXECUTION (NOT APPLICABLE)
SECTION 01 35 13.10 Page 2
SECTION [01 35 13.10]
SPECIAL PROJECT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. GOVERNMENT CODE OF FEDERAL REGULATIONS (CFR)
33 CFR 320-330 General Regulatory Policies, Permits, Enforcement and Definitions
40 CFR 233 State Program Regulations
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Payrolls and Basic Records
Contractor shall submit payrolls and basic records in accordance with the CLAUSE entitled "PAYROLLS AND BASIC RECORDS (FEB 1988)".
Progress Chart; G-AOF
Contractor shall submit progress chart in accordance with the Contract clause entitled "SCHEDULE FOR CONSTRUCTION CONTRACTS (APR 1984)".
NOTICE TO MARINERS
Contractor shall submit coordination details with the U.S. Coast Guard prior to its activities at the work site
Non-listed, Non-Commercially Active Stone or Material Source; G-ECD
If after award of a contract, the Contractor proposes to furnish stone, [soil], [granular] [or aggregate] materials from non-listed, or non-commercially active sources, the following information and data for each non-listed or non-commercially active source of stone, [soil], [granular] [or aggregate] material shall be furnished forty-five (45) or more calendar days prior to the date the Contractor is scheduled to obtain
SECTION 01 35 13.10 Page 3 materials from such source(s).
a. Name and address (Property Owner).
b. Location, site map, and legal description (or appropriate substitute) of the area.
c. Previous land use information.
d. A topographic map of the area.
e. Photographs showing the area proposed for use.
f. Written permission of the owners of the proposed non-listed or non-commercially active sources(s).
g. Written permission of the owners of the access properties involved.
h. All data required to assess potential environmental impacts. This information is required in order to determine the necessity for environmental documentation for any non-commercially active, non-listed source(s).
i. Documentation of coordination of the use of proposed non-commercially active, non-listed source(s) with Federal, State and local agencies having an interest and furnish written approval of these agencies for use of such source(s).
j. The proposed reduction, if any, in the applicable unit or lump-sum prices in the BIDDING SCHEDULE if the request were to be approved by the Government.
Utility Location Findings; G-AOF.
Submit a copy of the utility location findings prior to commencing work on the site.
SD-06 Test Reports
SD-07 Certificates
As-Built Technician's Qualifications
Submit the identity and qualifications of the persons assigned to prepare the as-built information at least 10 calendar days in advance of preparing the drawings.
As-built Drawings; G-AOF.
Within ten (10) calendar days after the substantial completion date as established by the Contracting Officer, submit the as-built details of the work performed under this contract on a set of blue-line prints of the contract drawings marked in red. Following review and approval by the Government, the Contractor shall prepare electronic and mylar copies of as-built drawings for submittal within 15 calendar days following receipt of comments from the Government. Electronic files shall be submitted in
SECTION 01 35 13.10 Page 4 latest version of Microstation, CADD file format, suitable for plotting with Intergraph IPLOT Software. The electronic medium for file transfers shall be agreed to prior to the time of submittal and shall be compatible with current industry standards and hardware configurations.
1.3 REGULATORY REQUIREMENTS
1.3.1 Additional Work Proposed and Not Authorized
1.3.1.1 Work Subject to 33 CFR 320-330
Any additional work (not specifically shown on the plans or delineated in the specifications) proposed by the Contractor in or affecting navigable waters, including wetlands (as defined in 33 CFR 320-330, http://ecfr.gpoaccess.gov) shall not be performed without a Department of the Army Permit. This requirement shall be applicable to all work, permanent or temporary, and/or fill(s). The Department of the Army Permit shall be approved by the District Engineer or Deputy District Engineer in accordance with the laws of the United States and the regulations promulgated thereunder, including, but not limited to, the River and Harbor Act of 1899, the Clean Water Act and the National Environmental Policy Act of 1969, as amended. Corps employees (Contracting Officer's Representatives (COR) or inspectors) are not delegated authority to authorize such work. Information on making application for such permit(s) may be obtained by contacting one of the offices as listed hereinafter.
When applying for information or a permit, a copy of any correspondence should be directed to the Contracting Officer of this contract. If a permit is not obtained, the additional work cannot be accomplished. Any delay in processing the permit will not constitute the basis of a claim under this contract. The fact that the Contractor is performing work under a Department of the Army Contract will give the Contractor no greater rights than any other applicant for a Department of the Army Permit.
MICHIGAN-INDIANA
Regulatory Branch Engineering and Technical Services Division U.S. Army Engineer District, Detroit 477 Michigan Ave Detroit, MI 48226 Telephone: 313-226-6813
1.3.1.2 Work Subject to 40 CFR 233
Any additional work (not specifically shown on the plans or included in the specifications), proposed by the Contractor, in or affecting waters of the United States, including wetlands, in the State of Michigan (as defined in 40 CFR 233, published in the Federal Register, Vol. 49 No. 192, Tuesday October 2, 1984) shall not be performed without a State of Wisconsin regulatory permit. Information on making an application for such permit may be obtained by contacting the office listed hereinafter. When applying for a permit or for information, a copy of any correspondence shall be furnished to the Contracting Officer. If a permit is not obtained, the additional work shall not be performed. Any delay in obtaining or processing the permit will not constitute a basis for a claim under this contract.
STATE OF MICHIGAN
SECTION 01 35 13.10 Page 5
Department of Environmental Quality Land & Water Management Division P.O. Box 30458 Constitution Hall Lansing, MI 48909 Telephone: 517-373-1170
1.4…