W56MES90962389
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is issued to incorporate FAR Clause 52.228-5, Insurance Work on a Government Installation. Also, the Wage Determinations WI 19 and IL 18 have been revised 26 Jun 09 and are incorporated in the solicitation. The due date has not been extended.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 30
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Jun-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911XK-09-B-0007
X 9B. DATED (SEE ITEM 11)
28-May-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Jun-2009
CODE
CONTRACTING DIVISION
DETROIT DISTRICT, USAED
477 MICHIGAN AVE.
DETROIT MI 48226
W911XK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911XK-09-B-0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0005
Liability Insurance
FAR 28.307-2 -- Liability.
(a) Workers’ compensation and employer’s liability. Contractors are required to comply with applicable Federal and State workers’ compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers. (See 28.305(c) for treatment of contracts subject to the Defense Base Act.)
(b) General liability.
(1) The contracting officer shall require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.
(2) Property damage liability insurance shall be required only in special circumstances as determined by the agency.
(c) Automobile liability. The contracting officer shall require automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
SECTION 00700 - CONTRACT CLAUSES
52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.
(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
(End of clause)
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
WAGE DET IL 18 DTD 26 JUN 09
General Decision Number: IL080018 06/26/2009 IL18
Superseded General Decision Number: IL20070018
State: Illinois
Construction Types: Heavy (Dredging and Marine)
Counties: Illinois Statewide.
MECHANICAL DREDGING (CLAMSHELL, DRAGLINE, AND BACKHOE) AND
MARINE CONSTRUCTION):
ILLINOIS, INDIANA, MICHIGAN, MINNESOTA, NEW YORK, OHIO,
PENNSYLVANIA AND WISCONSIN DREDGING AND MARINE CONSTRUCTION
Dredging and Marine Construction Projects: floating/land equipment engaged in clamshell, backhoe and dragline dredging, marine construction, bridges,salvage operations and cranes, loaders, dozers, or other equipment used for disposal of dredge spoils or marine construction materials on land at the slip or dock, at the project site, where the above material/spoils is being handled, and all equipment utilized on breakwall/breakwater structures on the Great Lakes, Islands therein, their connecting and tributary waters, including the Illinois Waterway to the Lock at Lockport, Illinois, the New York State Barge Canal System between Tonawanda, New York and Waterford, New York and Oswego, New York, the Duluth-Superior area to the Fond du Lac Bridge Crossing (Minnesota State Highway 23) on the St. Louis River and on the St. Lawrence River eastward to the International Boundary near St. Regis, New York.
Modification Number Publication Date 0 02/08/2008 1 02/22/2008
2 03/07/2008 3 03/14/2008 4 06/26/2009
* SUIL2003-001 01/01/2005
MECHANICAL DREDGING (CLAMSHELL, DRAGLINE, AND BACKHOE) AND
MARINE CONSTRUCTION):
Rates Fringes
Dredging:
Fireman, Oiler, Deckhand, & Scowman (with dipper, hydraulic or other floating equipment engaged in hydraulic and dipper dredging operations) Pipeline men (both afloat & ashore including loading, unloading, maintaining, and handling pipelines for hydraulic dredges and sandboats Rangeman, Tankerman, Sweepman and service Truck Driver......................$ 22.51 7.61+a+b Lead Deckhand...............$ 29.68 7.61+a+b
Hydraulic Dredging LAUNCH OPERATOR - Vessel 800 Horse- Power Or Less....$ 25.15 7.61+a+b TUG ENGINEER................$ 26.49 7.61+a+b TUG OPERATOR - Vessel Over 800 Horse-Power.............$ 26.49 7.61+a+b TUG WORKERS: Fireman, Lineman, Oiler, Deckhand, Tankerman. Scowman, (on/or with tugboats, launches, or other self-propelled boats)......................$ 22.51 7.61+a+b
MECHANIC
FLOATING EQUIPMENT:
Illinois Class I....................$ 48.40 17.05+b&c Class II...................$ 46.90 17.05+b&c Class III..................$ 41.70 17.05+b&c Class IV...................$ 34.70 17.05+b&c FLOATING EQUIPMENT: Indiana Class I....................$ 42.45 15.55+b&c Class II...................$ 40.95 15.55+b&c Class III..................$ 36.45 15.55+b&c Class IV...................$ 30.30 15.55+b&c
FLOATING EQUIPMENT:
Michigan Class I....................$ 33.85 20.18+b&c Class II...................$ 32.35 20.18+b&c Class III..................$ 28.80 20.18+b&c Class IV...................$ 23.95 20.18+b&c
FLOATING EQUIPMENT:
Minnesota Class I....................$ 36.20 12.95+b&c Class II...................$ 34.70 12.95+b&c Class III..................$ 30.90 12.95+b&c Class IV...................$ 25.70 12.95+b&c
FLOATING EQUIPMENT:
New York:(Cattaraugus, Chautauga, Erie and Orleans Counties) Class I....................$ 37.15 18.56+b&c Class II...................$ 35.65 18.56+b&c Class III..................$ 31.75 18.56+b&c Class IV...................$ 26.40 18.56+b&c
FLOATING EQUIPMENT:
New York:(Cayuga, Jefferson, Oswego, and St.
Lawrence Counties) Class I....................$ 34.45 18.65+b&c Class II...................$ 32.95 18.65+b&c Class III..................$ 29.30 18.65+b+c Class IV...................$ 24.40 18.65+b&c
FLOATING EQUIPMENT:
New York:(Monroe and Wayne Counties and the City of Rochester) Class I....................$ 35.90 17.38+b&c Class II...................$ 34.45 17.38+b&c Class III..................$ 33.65 17.38+b&c Class IV...................$ 30.35 17.38+b&c
FLOATING EQUIPMENT:
New York:(Niagara) Class I....................$ 34.60 18.15+b&c Class II...................$ 33.10 18.15+b&c Class III..................$ 29.45 18.15+b&c Class IV...................$ 24.50 18.15+b&c
FLOATING EQUIPMENT:
Ohio:(Ashtabula, Cuyahoga, Erie,Lake, and Lorain Counties) Class I....................$ 35.34 10.10+b&c Class II...................$ 33.84 10.10+b&c Class III..................$ 30.12 10.10+b&c Class IV...................$ 25.04 10.10+b&c
FLOATING EQUIPMENT:
Ohio:(Lucas, Henry, Ottawa, Wood and Sandusky Counties) Class I....................$ 33.63 10.10+b&c Class II...................$ 32.13 10.10+b&c Class III..................$ 28.60 10.10+b+c Class IV...................$ 23.78 10.10+b&c
FLOATING EQUIPMENT:
Pennsylvania:(Erie County):
Class I....................$ 30.90 12.69+b&c Class II...................$ 29.40 12.69+b&c Class III..................$ 26.20 12.69+b&c Class IV...................$ 21.80 12.69+b&c
FLOATING EQUIPMENT:
Wisconsin:Includes all marine/floating type work on projects in the Superior/Duluth Harbor, Lake Superior.
Class I....................$ 35.40 15.75+b&c Class II...................$ 33.90 15.75+b&c Class III..................$ 30.20 15.75+b&c Class IV...................$ 25.10 15.75+b&c
PAID HOLIDAYS (WHERE APPLICABLE):
A- NEW YEAR'S DAY
B- MEMORIAL DAY
C- INDEPENDENCE DAY
D- LABOR DAY
E- THANKSGIVING DAY
F- CHRISTMAS DAY
G- PRESIDENT'S DAY
H- VETERAN'S DAY.
FOOTNOTES:
a. $30.10 per day per employee for medical
b. Eight paid holidays: A thru H
c. Hazardous/Toxic Waste Material:
*Level A $2.50 per hour *Level B 2.00 per hour *Level C 1.00 per hour *Level D 0.50 per hour
Such wages shall be above the classifications of work listed under mechanical dredging and Marine construction of this general wage decision. *Working with Hazardous Waste at this level as defined by the U. S. Enviromental Protection Agency.
CLASSIFICATION DESCRIPTIONS
Class I - Master Mechanic - assist and direct Class II, Class III, and Class IV, diver/wet tender, engineer (hydraulic dredge) Class II - Crane/Backhoe Operator and Mechanic/Welder, assistant engineer(hydraulic dredge), leverman (hydraulic dredge), diver tender Class III - Deck Equipment Operator (Machineryman) Maintenance of Crane (over 50 ton capacity) or Backhoe (115,000 pounds or more), Tug/launch operator, Loader/dozer and like equipment on Barge, breakwater wall, slip/dock, Scow, Deck Machinery, etc.
Class IV - Deck Equipment Operator(Machineryman/Fireman) (Four equipment units or more) Deck Hand, Deck Engineer and Crane Maintenance 50 ton capacity and under or Backhoe weighing 115,000 pounds or less, assistant tug operator.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
WAGE DET WI 19 DTD 26 JUN 09
General Decision Number: WI080019 06/26/2009 WI19
Superseded General Decision Number: WI20070019
State: Wisconsin
Construction Type: Heavy
Counties: Wisconsin Statewide.
HEAVY CONSTRUCTION PROJECTS (Excluding Tunnel, Sewer, and Water Lines), AND HOPPER DREDGE PROJECTS
Modification Number Publication Date 0 02/08/2008 1 02/29/2008
2 05/02/2008 3 06/13/2008 4 06/27/2008 5 07/11/2008 6 07/25/2008 7 08/08/2008 8 08/15/2008 9 08/22/2008 10 08/29/2008 11 09/12/2008 12 10/03/2008 13 11/07/2008 14 12/19/2008 15 02/20/2009 16 03/13/2009 17 03/20/2009 18 05/29/2009 19 06/05/2009 20 06/26/2009
BOIL0107-001 07/01/2007
Rates Fringes
BOILERMAKER
Boilermaker.................$ 30.69 18.12 Small Boiler Repair (under 25,000 lbs/hr)..............$ 24.55 13.10
BRWI0001-002 06/01/2008
CRAWFORD, JACKSON, JUNEAU, LA CROSSE, MONROE, TREMPEALEAU, AND
VERNON COUNTIES
BRICKLAYER.......................$ 29.24 13.80
BRWI0002-002 06/01/2008
ASHLAND, BAYFIELD, DOUGLAS, AND IRON COUNTIES
Rates Fringes
BRICKLAYER.......................$ 35.24 13.35
BRWI0002-005 06/01/2008
ADAMS, ASHLAND, BARRON, BROWN, BURNETT, CALUMET, CHIPPEWA,
CLARK, COLUMBIA, DODGE, DOOR, DUNN, FLORENCE, FOND DU LAC,
FOREST, GREEN LAKE, IRON, JEFFERSON, KEWAUNEE, LANGLADE,
LINCOLN, MANITOWOC, MARATHON, MARINETTE, MARQUETTE, MENOMINEE,
OCONTO, ONEIDA, OUTAGAMIE, POLK, PORTAGE, RUSK, ST CROIX, SAUK,
SHAWANO, SHEBOYGAN, TAYLOR, VILAS, WALWORTH, WAUPACA, WAUSHARA,
WINNEBAGO, AND WOOD COUNTIES
CEMENT MASON/CONCRETE FINISHER...$ 28.15 12.80
BRWI0003-002 06/01/2008
BROWN, DOOR, FLORENCE, KEWAUNEE, MARINETTE, AND OCONTO COUNTIES
Rates Fringes
BRICKLAYER.......................$ 29.24 13.80
BRWI0004-002 06/01/2008
KENOSHA, RACINE, AND WALWORTH COUNTIES
Rates Fringes
BRICKLAYER.......................$ 32.88 14.50
BRWI0006-002 06/01/2008
ADAMS, CLARK, FOREST, LANGLADE, LINCOLN, MARATHON, MENOMINEE,
ONEIDA, PORTAGE, PRICE, TAYLOR, VILAS AND WOOD COUNTIES
BRICKLAYER.......................$ 29.74 13.30
BRWI0007-002 06/01/2008
GREEN, LAFAYETTE, AND ROCK COUNTIES
Rates Fringes
BRICKLAYER.......................$ 30.41 14.30
BRWI0008-002 06/01/2008
MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES
Rates Fringes
BRICKLAYER.......................$ 32.71 14.54
BRWI0009-001 06/01/2008
GREEN LAKE, MARQUETTE, OUTAGAMIE, SHAWANO, WAUPACA, WASHARA,
AND WINNEBAGO COUNTIES
BRICKLAYER.......................$ 29.24 13.80
BRWI0011-002 06/01/2008
CALUMET, FOND DU LAC, MANITOWOC, AND SHEBOYGAN COUNTIES
Rates Fringes
BRICKLAYER.......................$ 29.24 13.80
BRWI0013-002 06/01/2008
DANE, GRANT, IOWA, AND RICHLAND COUNTIES
Rates Fringes
BRICKLAYER.......................$ 30.61 14.10
BRWI0019-002 06/01/2008
BARRON, BUFFALO, BURNETT, CHIPPEWA, DUNN, EAU CLAIRE, PEPIN,
PIERCE, POLK, RUSK, ST. CROIX, SAWYER AND WASHBURN COUNTIES
BRICKLAYER.......................$ 28.99 14.05
BRWI0021-002 06/01/2008
DODGE AND JEFFERSON COUNTIES
Rates Fringes
BRICKLAYER.......................$ 30.88 13.85
BRWI0034-002 06/04/2007
COLUMBIA AND SAUK COUNTIES
Rates Fringes
BRICKLAYER.......................$ 30.66 14.05
CARP0087-001 05/01/2007
BURNETT (W. of Hwy 48), PIERCE (W. of Hwy 29), POLK (W. of Hwys 35, 48 & 65), AND ST. CROIX (W. of Hwy 65) COUNTIES
Carpenter & Piledrivermen........$ 26.76 11.61
CARP0252-002 06/01/2009
ADAMS, BARRON, BAYFIELD (Eastern 2/3), BROWN, BUFFALO, BURNETT (E. of Hwy 48), CALUMET, CHIPPEWA, CLARK, COLUMBIA, CRAWFORD, DANE, DODGE, DOOR, DUNN, EAU CLAIRE, FLORENCE (except area bordering Michigan State Line), FOND DU LAC, FOREST, GRANT, GREEN, GREEN LAKE, IOWA, IRON, JACKSON, JEFFERSON, JUNEAU, KEWAUNEE, LA CROSSE, LAFAYETTE, LANGLADE, LINCOLN, MANITOWOC, MARATHON, MARINETTE (except N.E. corner), MARQUETTE, MENOMINEE, MONROE, OCONTO, ONEIDA, OUTAGAMIE, PEPIN, PIERCE (E.
of Hwys 29 & 65), POLK (E. of Hwys 35, 48 & 65), PORTAGE, PRICE, RICHLAND, ROCK, RUSK, SAUK, SAWYER, SHAWANO, SHEBOYGAN, ST CROIX (E. of Hwy 65), TAYLOR, TREMPEALEAU, VERNON, VILAS, WALWORTH, WASHBURN, WAUPACA, WAUSHARA, WINNEBAGO, AND WOOD
COUNTIES
CARPENTER
CARPENTER...................$ 29.06 13.36
MILLWRIGHT..................$ 30.66 13.36
PILEDRIVER..................$ 29.56 13.36
CARP0252-010 05/27/2007
ASHLAND COUNTY
Rates Fringes
Carpenters Carpenter...................$ 23.82 11.26 Millwright..................$ 27.71 11.26 Pile Driver.................$ 24.81 10.43
CARP0264-003 06/01/2008
KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WAUKESHA, AND WASHINGTON
CARPENTER........................$ 30.52 14.41
CARP0361-004 05/01/2008
BAYFIELD (Western 1/3) AND DOUGLAS COUNTIES
Rates Fringes
CARPENTER........................$ 29.77 13.40
CARP2337-001 06/01/2008
ZONE A: MILWAUKEE, OZAUKEE, WAUKESHA AND WASHINGTON
ZONE B: KENOSHA & RACINE
PILEDRIVERMAN
Zone A......................$ 27.25 19.46 Zone B......................$ 24.47 19.46
CARP2337-003 06/02/2008
Rates Fringes
MILLWRIGHT
Zone A......................$ 27.92 19.08 Zone B......................$ 26.82 19.08
ZONE DEFINITIONS
ZONE A: MILWAUKEE, OZAUKEE, WAUKESHA AND WASHINGTON COUNTIES
ZONE B: KENOSHA & RACINE COUNTIES
ELEC0014-002 06/01/2007
ASHLAND, BARRON, BAYFIELD, BUFFALO, BURNETT, CHIPPEWA, CLARK
(except Maryville, Colby, Unity, Sherman, Fremont, Lynn & Sherwood), CRAWFORD, DUNN, EAU CLAIRE, GRANT, IRON, JACKSON, LA
CROSSE, MONROE, PEPIN, PIERCE, POLK, PRICE, RICHLAND, RUSK, ST
CROIX, SAWYER, TAYLOR, TREMPEALEAU, VERNON, AND WASHBURN
Electricians:....................$ 28.91 27.8%+6.60
ELEC0127-002 06/01/2008
KENOSHA COUNTY
Rates Fringes
Electricians:....................$ 33.59 28%+7.56
ELEC0158-002 06/02/2008
BROWN, DOOR, KEWAUNEE, MANITOWOC (except Schleswig), MARINETTE(Wausuakee and area South thereof), OCONTO, MENOMINEE (East of a ine 6 miles West of the West boundary of Oconto County), SHAWANO (Except Area North of Townships of Aniwa and Hutchins) COUNTIES
Electricians:....................$ 27.27 26.75%+7.62
ELEC0159-003 06/01/2008
COLUMBIA, DANE, DODGE (Area West of Hwy 26, except Chester and Emmet Townships), GREEN, LAKE (except Townships of Berlin, Seneca, and St. Marie), IOWA, MARQUETTE (except Townships of Neshkoka, Crystal Lake, Newton, and Springfield), and SAUK
Electricians:....................$ 31.00 3%+15.77
ELEC0219-004 06/02/2008
FLORENCE COUNTY (Townships of Aurora, Commonwealth, Fern, Florence and Homestead) AND MARINETTE COUNTY (Township of Niagara)
Electricians:
Electrical contracts over $90,000.....................$ 27.61 15.03 Electrical contracts under $90,000.....................$ 25.42 14.96
* ELEC0242-005 05/31/2009
DOUGLAS COUNTY
Rates Fringes
Electricians:....................$ 31.24 63.5%
ELEC0388-002 03/01/2007
ADAMS, CLARK (Colby, Freemont, Lynn, Mayville, Sherman, Sherwood, Unity), FOREST, JUNEAU, LANGLADE, LINCOLN, MARATHON, MARINETTE (Area North of the town of Wausaukee), MENOMINEE (Area West of a line 6 miles West of the West boundary of Oconto County), ONEIDA, PORTAGE, SHAWANO (Area North of the townships of Aniwa and Hutchins), VILAS AND WOOD COUNTIES
Electricians:....................$ 27.68 15.23
ELEC0430-002 06/01/2008
RACINE COUNTY (Except Burlington Township)
Rates Fringes
Electricians:....................$ 32.212 17.18
* ELEC0494-005 06/01/2009
MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES
Rates Fringes
Electricians:....................$ 31.10 14.85%+$15.70
ELEC0494-006 06/01/2008
CALUMET (Township of New Holstein), DODGE (East of Hwy 26 including Chester Township), FOND DU LAC, MANITOWOC (Schleswig), and SHEBOYGAN COUNTIES
Electricians:....................$ 28.33 3%+$17.21
ELEC0577-003 06/01/2008
CALUMET (except Township of New Holstein), GREEN LAKE (N. part including Townships of Berlin, St Marie, and Seneca), MARQUETTE (N. part including Townships of Crystal Lake, Neshkoro, Newton, and Springfield), OUTAGAMIE, WAUPACA, WAUSHARA, AND WINNEBAGO
Electricians:....................$ 27.40 26.5%+7.65
ELEC0890-003 12/01/2007
DODGE (Emmet Township only), GREEN, JEFFERSON, LAFAYETTE, RACINE (Burlington Township), ROCK AND WALWORTH COUNTIES
Electricians:....................$ 28.34 26.45%+8.11
ELEC0953-001 06/01/2008
Line Construction:
(1) Lineman.................$ 34.57 4.75+29%
(2) Heavy Equipment Operator....................$ 31.11 4.75+29%
(3) Equipment Operator......$ 27.66 4.75+29%
(4) Heavy Groundman Driver..$ 24.20 4.75+29%
(5) Light Groundman Driver..$ 22.47 4.75+29%
(6) Groundsman..............$ 19.01 4.75+29%
ENGI0139-001 06/01/2008
KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WASHINGTON, AND WAUKESHA
Power Equipment Operator Group 1.....................$ 35.26 16.60 Group 2.....................$ 34.76 16.60 Group 3.....................$ 34.26 16.60 Group 4.....................$ 33.97 16.60 Group 5.....................$ 32.09 16.60 Group 6.....................$ 26.94 16.60
EPA PREMIUMS:
Level "A" Protection: $3.00 per hour Level "B" Protection: $2.00 per hour Level "C" Protection: $1.00 per hour
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Cranes, Tower Cranes, Pedestal Tower Cranes and Derricks with or w/o attachments with a lifting capacity of over 100 tons; or Cranes, Tower Cranes, Pedestal Tower Cranes and Derricks with boom, leads, and/or jib lengths measuring 176 feet or longer; Self-Erecting Tower Cranes over 4000 lbs lifting capacity; All Cranes with Boom Dollies; Boring Machines (directional); Master Mechanic.
$0.50 additional per hour per 100 tons or 100 ft of boom over 200 ft or lifting capacity of crane over 200 tons to a maximum of 300 tons or 300 ft. Thereafter an increase of $0.01 per ft or ton, whichever is greater.
GROUP 2: Cranes, Tower Cranes, Pedestal Tower Cranes and Derricks with or without attachments with a lifting capacity of 100 tons or less; or Cranes, Tower Cranes Portable Tower Cranes, Pedestal Tower Cranes and Derricks with boom, leadsand/or jib lengths measuring 175 feet or less; Backhoes (excavators) 130,000 lbs and over; Caisson Rigs; Pile Drivers; Boring Machines (vertical or horizontal), Versi-Lift, Tri-Lift, Gantry 20,000 lbs & over.
GROUP 3: Backhoe (excavator) under 130,000 lbs;Self-erecting Tower Crane 4000 lbs & under lifting capacity;Traveling
Crane (bridge type); Skid Rigs; Dredge Operator; Mechanic;
Concrete Paver (over 27E); Concrete Spreader and Distributor; Forklift/ Telehandler (machinery- moving / steel erection); Hydro Blaster, 10,000 psi and over
GROUP 4: Material Hoists; Stack Hoists; Hydraulic Backhoe (tractor or truck mounted); Hydraulic Crane, 5 tons or under (tractor or truck mounted); Hoist (tuggers 5 tons & over); Hydro-Excavators/Daylighters; Concrete Pumps Rotec type Conveyors; Tractor/Bulldozer/End Loader (over 40 hp);
Motor Patrol; Scraper Operator; Sideboom; Straddle Carrier;
Welder; Bituminous Plant and Paver Operator; Roller over 5 tons; Rail Leveling Machine (Railroad); Tie Placer; Tie Extractor; Tie Tamper; Stone Leveler; Rotary Drill Operator and Blaster; Percussion Drill Operator; Air Track Drill and/or Hammers; Gantrys (under 20,000 lbs); Tencher (wheel type or chain type having 8 inch or larger bucket); Milling Machine; Off-Road Material Haulers.
GROUP 5: Backfiller; Concrete Auto Breaker (large); Concrete Finishing Machines (road type); Rubber Tired Roller;
Concrete Batch Hopper; Concrete Conveyor Systems; Grout Pumps; Concrete Mixers (14S or over); Screw Type Pumps and Gypsum Pumps; Tractor, Bulldozer, End Loader (under 40 hp);
Trencher (chain type, bucket under 8 inch); Industrial Locomotives; Rollers under 5 tons; Stump Grinder/Chipper (Large); Timber Equipment; Firemen (pile drivers and derricks); Personnel Hoist, Telehandler over 8000 lbs;
Robotic Tool Carrier with or without attachments
GROUP 6: Tampers - Compactors (riding type); Assistant Engineer; A-Frames and Winch Trucks; Concrete Auto Breaker;
Hydrohammers (small); Brooms and Sweepers; Hoist (tuggers under 5 tons); Boats (Tug, Safety, Work Barges, Launch);
Shouldering Machine Operator; Prestress Machines; Screed Operator; Stone Crushers and Screening Plants; Screed Operators (milling machine), Farm or Industrial Tractor Mounted Equipment; Post Hole Digger; Fireman (asphalt plants); Air Compressors over 400 CFM; Generators, over 150 KW; Augers (vertical and horizontal); Air, Electric, Hydraulic Jacks (slipform); Skid Steer Loaders (with or without attachments); Boiler Operators (temporary heat);
Refrigeration Plant/Freeze Machines; Power Pack Vibratory/Ultra Sound Drivers and Extractors; Welding Machines; Heaters (mechanical); Pumps; Winches (small electric); Oiler and Greaser; Rotary Drill Tender;
Conveyor; Forklifts/Telehandler 8000 lbs & under;
Elevators: Automatic Hoists; Pumps (well points);
Combination Small Equipment Operators
* ENGI0139-003 06/01/2009
REMAINING COUNTIES
Power Equipment Operator Group 1.....................$ 33.37 16.95 Group 2.....................$ 32.37 16.95 Group 3.....................$ 31.42 16.95 Group 4.....................$ 30.89 16.95 Group 5.....................$ 28.82 16.95 Group 6.....................$ 28.19 16.95
EPA PREMIUMS:
Level "A" Protection: $3.00 per hour Level "B" Protection: $2.00 per hour Level "C" Protection: $1.00 per hour
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Cranes, Tower Cranes and Derricks with or without attachments with a lifting capacity of over 100 tons;
Cranes, Tower Cranes, and Derricks with boom, leads and/or jib lengths 176 ft or longer.
GROUP 2: Backhoes (Excavators) weighing 130,00 lbs and over;
Cranes, Tower Cranes and Derricks with or without attachments with a lifting capacity of 100 tons or less;
Cranes, Tower Cranes, and Derricks with boom, leads, and/or jib lengths 175 ft or less; Caisson Rigs; Pile Driver
GROUP 3: Backhoes (Excavators) weighing under 130,000 lbs;
Travelling Crane (bridge type); Milling Machine; Concrete Paver over 27 E; Concrete Spreader and Distributor;
Concrete Laser Screed; Concrete Grinder and Planing Machine; Slipform Curb and Gutter Machine; Boring Machine (Directional); Dredge Operator; Skid Rigs; over 46 meter Concrete Pump.
GROUP 4: Hydraulic Backhoe (tractor or truck mounted);
Hydraulic Crane, 10 tons or less; Tractor, Bulldozer, or End Loader (over 40 hp); Motor Patrol; Scraper Operator;
Bituminous Plant and Paver Operator; Screed-Milling Machine; Roller over 5 tons; Concrete pumps 46 meter and under; Grout Pumps; Rotec type machine; Hydro Blaster, 10,000 psi and over; Rotary Drill Operator; Percussion Drilling Machine; Air Track Drill with or without integral hammer; Blaster; Boring Machine (vertical or horizontal);
Side Boom; Trencher, wheel type or chain type having 8 inch or larger bucket; Rail Leveling Machine (Railroad); Tie Placer; Tie Extractor; Tie Tamper; Stone Leveler; Straddle Carrier; Material Hoists; Stack Hoist; Man Hoists; Mechanic and Welder; Off Road Material Haulers.
GROUP 5: Tractor, Bulldozer, or Endloader (under 40 hp);
Tampers -Compactors, riding type; Stump Chipper, large;
Roller, Rubber Tire; Backfiller; Trencher, chain type (bucket under 8 inch); Concrete Auto Breaker, large;
Concrete Finishing Machine (road type); Concrete Batch Hopper; Concrete Conveyor Systems; Concrete Mixers, 14S or over; Pumps, Screw Type and Gypsum); Hydrohammers, small;
Brooms and Sweeeprs; Lift Slab Machine; Roller under 5 tons; Industrial Locomotives; Fireman (Pile Drivers and Derricks); Pumps (well points); Hoists, automatic; A-Frames and Winch Trucks; Hoists (tuggers); Boats (Tug, Safety, Work Barges and Launches); Assistant Engineer
GROUP 6: Shouldering Machine Operator; Farm or Industrial Tractor mounted equipment; Post Hole Digger; Auger (vertical and horizontal); Skid Steer Loader with or without attachments; Robotic Tool Carrier with or without attachments; Power Pack Vibratory/Ultra Sound Driver and Extractor; Fireman (Asphalt Plants); Screed Operator; Stone Crushers and Screening Plants; Air, Electric, Hydraulic Jacks (Slip Form); Prestress Machines; Air Compressor, 400 CFM or over; Refrigeration Plant/Freese Machine; Boiler Operators (temporary heat); Forklifts; Welding Machines;
Generators; Pumps over 3"; Heaters, Mechanical; Combination small equipment operator; Winches, small electric; Oiler;
Greaser; Rotary Drill Tender; Conveyor; Elevator Operator
IRON0008-002 06/01/2008
BROWN, CALUMET, DOOR, FOND DU LAC, KEWAUNEE, MANITOWOC,
MARINETTE, OCONTO, OUTAGAMI, SHAWANO, SHEBOYGAN, AND WINNEBAGO
COUNTIES:
IRONWORKER.......................$ 27.73 19.04
IRON0008-003 06/01/2009
KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WALWORTH (N.E. 2/3),
WASHINGTON, AND WAUKESHA COUNTIES
IRONWORKER.......................$ 30.51 20.59
IRON0383-001 06/01/2008
ADAMS, COLUMBIA, CRAWFORD, DANE, DODGE, FLORENCE, FOREST,
GRANT, GREENE, (Excluding S.E. tip), GREEN LAKE, IOWA, JEFFERSON, JUNEAU, LA CROSSE, LAFAYETTE, LANGLADE, MARATHON, MARQUETTE, MENOMINEE, MONROE, PORTAGE, RICHLAND, ROCK (Northern area, vicinity of Edgerton and Milton), SAUK, VERNON, WAUPACA, WAUSHARA, AND WOOD COUNTIES
IRONWORKER.......................$ 30.30 15.73
IRON0512-008 05/01/2009
BARRON, BUFFALO, CHIPPEWA, CLARK, DUNN, EAU CLAIRE, JACKSON,
PEPIN, PIERCE, POLK, RUSK, ST CROIX, TAYLOR, AND TREMPEALEAU
IRONWORKER.......................$ 33.80 20.44
IRON0512-021 05/01/2009
ASHLAND, BAYFIELD, BURNETT, DOUGLAS, IRON, LINCOLN, ONEIDA,
PRICE, SAWYER, VILAS AND WASHBURN COUNTIES
IRONWORKER.......................$ 29.76 19.50
LABO0113-002 06/01/2008
MILWAUKEE AND WAUKESHA COUNTIES
Rates Fringes
Laborers:
Group 1.....................$ 23.26 14.18 Group 2.....................$ 23.41 14.18 Group 3.....................$ 23.61 14.18 Group 4.....................$ 23.76 14.18 Group 5.....................$ 23.91 14.18 Group 6.....................$ 19.75 14.18
LABORERS CLASSIFICATIONS
GROUP 1: General Laborer; Tree Trimmer; Conduit Layer;
Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;
Stone Handler; Bituminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;
Bituminous Worker (Dumper, Ironer, Smoother, and Tamper);
Concrete Handler
GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated); Chain Saw Operator; Demolition Burning TOrch Laborer
GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk, and Pavement); Strike Off Man
GROUP 4: Line and Grade Specialist
GROUP 5: Blaster and Powderman
GROUP 6: Flagperson; traffic control person
LABO0113-003 06/01/2008
OZAUKEE AND WASHINGTON COUNTIES
Rates Fringes
Laborers:
Group 1.....................$ 22.51 14.18 Group 2.....................$ 22.61 14.18 Group 3.....................$ 22.66 14.18 Group 4.....................$ 22.86 14.18 Group 5.....................$ 22.71 14.18 Group 6.....................$ 19.60 14.18
LABORERS CLASSIFICATIONS
GROUP 1: General Laborer; Tree Trimmer; Conduit Layer;
Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;
Stone Handler; Bituminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;
Bituminous Worker (Dumper, Ironer, Smoother, and Tamper);
Concrete Handler
GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated);
GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk, and Pavement); Strike Off Man
GROUP 4: Line and Grade Specialist
GROUP 5: Blaster; powderman
GROUP 6: Flagperson and Traffic Control Person
LABO0113-011 06/01/2008
KENOSHA AND RACINE COUNTIES
Rates Fringes
LABORERS
Group 1.....................$ 21.52 14.98 Group 2.....................$ 21.67 14.98 Group 3.....................$ 21.87 14.98 Group 4.....................$ 21.84 14.98 Group 5.....................$ 22.17 14.98 Group 6.....................$ 18.66 14.98
LABORERS CLASSIFICATIONS:
GROUP 1: General laborer; Tree Trimmer; Conduit Layer;
Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;
Stone Handler; Bituminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;
Bituminous worker (Dumper, Ironer, Smoother, and Tamper);
Concrete Handler
GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated); Chain Saw Operator; Demolition Burning Torch Laborer
GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk, and Pavement); Strike Off Man
GROUP 4: Line and Grade Specialist
GROUP 5: Blaster and Powderman
GROUP 6: Flagman; traffic control person
LABO0140-002 06/01/2008
ADAMS, ASHLAND, BARRON, BAYFIELD, BROWN, BUFFALO, BURNETT,
CALUMET, CHIPPEWA, CLARK, COLUMBIA, CRAWFORD, DODGE, DOOR,
DOUGLAS, DUNN, EAU CLAIRE, FLORENCE, FOND DU LAC, FOREST,
GRANT, GREEN, GREEN LAKE, IRON, JACKSON, JUNEAU, IOWA,
JEFFERSON, KEWAUNEE, LA CROSSE, LAFAYETTE, LANGLADE, LINCOLN,
MANITOWOC, MARATHON, MARINETTE, MARQUETTE, MENOMINEE, MONROE,
OCONTO, ONEIDA, OUTAGAMIE, PEPIN, PIERCE, POLK, PORTAGE, PRICE,
RICHLAND, ROCK, RUSK, SAUK, SAWYER, SHAWANO, SHEBOYGAN, ST.
CROIX, TAYLOR, TREMPEALEAU, VERNON, VILLAS, WALWORTH, WASHBURN,
WAUPACA, WAUSHARA, WINNEBAGO, AND WOOD COUNTIES
Laborers:
Group 1.....................$ 23.87 11.75 Group 2.....................$ 23.97 11.75 Group 3.....................$ 24.02 11.75 Group 4.....................$ 24.22 11.75 Group 5.....................$ 24.07 11.75 Group 6.....................$ 20.50 11.75
LABORERS CLASSIFICATIONS
GROUP 1: General Laborer; Tree Trimmer; Conduit Layer;
Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;
Stone Handler; Bitminous Worker (Shoveler, Loader, and
Utility Man); Batch Truck Dumper or Cement Handler;
Bituminous Worker (Dumper, Ironer, Smoother and Tamper);
Concrete Handler
GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated)
GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk and Pavement); Strike Off Man
GROUP 4: Line and Grade Secialist
GROUP 5: Blaster; powderman
GROUP 6: Flagperson; Traffic Control
LABO0464-003 06/01/2008
DANE COUNTY
Rates Fringes
Laborers:
Group 1.....................$ 24.15 11.75 Group 2.....................$ 24.25 11.75 Group 3.....................$ 24.30 11.75 Group 4.....................$ 24.50 11.75 Group 5.....................$ 24.35 11.75 Group 6.....................$ 20.50 11.75
LABORERS CLASSIFICATIONS:
GROUP 1: General Laborer; Tree Trimmer; Conduit Layer;
Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;
Stone Handler; Bituminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;
Bituminious Worker (Dumper, Ironer, Smoother, and Tamper);
Concrete Handler
GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated); Chain Saw Operator; Demolition Burning Torch Laborer
GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk, and Pavement); Strike Off Man
GROUP 4: Line and Grade Specialist
GROUP 5: Blaster; Powderman
GROUP 6: Flagperson and Traffic Control Person
PAIN0106-008 05/01/2008
ASHLAND, BAYFIELD, BURNETT, AND DOUGLAS COUNTIES
Rates Fringes
Painters:
New:
Brush, Roller..............$ 27.41 12.52 Spray, Sandblast, Steel....$ 28.01 12.52 Repaint:
Brush, Roller..............$ 25.91 12.52 Spray, Sandblast, Steel....$ 26.51 12.52
PAIN0108-002 06/01/2008
RACINE COUNTY
Rates Fringes
Painters:
Brush, Roller...............$ 27.10 14.14 Spray & Sandblast...........$ 28.10 14.14
PAIN0259-002 05/01/2008
BARRON, CHIPPEWA, DUNN, EAU CLAIRE, PEPIN, PIERCE, POLK, RUSK,
SAWYER, ST. CROIX, AND WASHBURN COUNTIES
PAINTER..........................$ 24.11 12.15
PAIN0259-004 05/01/2008
BUFFALO, CRAWFORD, JACKSON, LA CROSSE, MONROE, TREMPEALEAU, AND
PAINTER..........................$ 20.43 8.40
PAIN0781-002 06/01/2008
JEFFERSON, MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES
Rates Fringes
Painters:
Bridge......................$ 27.47 14.09 Brush.......................$ 27.12 14.09 Spray & Sandblast...........$ 27.87 14.09
* PAIN0802-002 06/01/2009
COLUMBIA, DANE, DODGE, GRANT, GREEN, IOWA, LAFAYETTE, RICHLAND,
ROCK, AND SAUK COUNTIES
PAINTER
Brush.......................$ 25.65 13.10
PREMIUM PAY:
Structural Steel, Spray, Bridges = $1.00 additional per hour.
* PAIN0802-003 06/01/2009
ADAMS, BROWN, CALUMET, CLARK, DOOR, FOND DU LAC, FOREST, GREEN
LAKE, IRON, JUNEAU, KEWAUNEE, LANGLADE, LINCOLN, MANITOWOC,
MARATHON, MARINETTE, MARQUETTE, MENOMINEE, OCONTO, ONEIDA,
OUTAGAMIE, PORTAGE, PRICE, SHAWANO, SHEBOYGAN, TAYLOR, VILAS,
WAUSHARA, WAUPACA, WINNEBAGO, AND WOOD COUNTIES
PAINTER..........................$ 21.87 10.07
PAIN0934-001 06/01/2008
KENOSHA AND WALWORTH COUNTIES
Rates Fringes
Painters:
Brush.......................$ 27.10 14.14 Spray.......................$ 28.10 14.14 Structural Steel............$ 27.15 14.14
PAIN1011-002 06/01/2008
FLORENCE COUNTY
Rates Fringes
Painters:........................$ 22.60 7.90
PLAS0599-010 06/01/2007
Rates Fringes
CEMENT MASON/CONCRETE FINISHER
Area 1......................$ 28.27 12.73 Area 2 (BAC)................$ 28.15 12.80 Area 3......................$ 26.10 13.65
Area 4......................$ 26.82 12.93 Area 5......................$ 26.97 12.78 Area 6......................$ 24.08 15.67
AREA DESCRIPTIONS
AREA 1: BAYFIELD, DOUGLAS, PRICE, SAWYER, AND WASHBURN
COUNTIES
AREA 2: ADAMS, ASHLAND, BARRON, BROWN, BURNETT, CALUMET,
CHIPPEWA, CLARK, COLUMBIA, DODGE, DOOR, DUNN, FLORENCE,
FOND DU LAC, FOREST, GREEN LAKE, IRON, JEFFERSON, KEWAUNEE,
LANGLADE, LINCOLN, MANITOWOC, MARATHON, MARINETTE,
MARQUETTE, MENOMINEE, OCONTO, ONEIDA, OUTAGAMIE, POLK,
PORTAGE, RUSK, ST CROIX, SAUK, SHAWANO, SHEBOYGAN, TAYLOR,
VILAS, WALWORTH, WAUPACA, WAUSHARA, WINNEBAGO, AND WOOD
COUNTIES
AREA 3: BUFFALO, CRAWFORD, EAU CLAIRE, JACKSON, JUNEAU, LA
CROSSE MONROE, PEPIN, PIERCE, RICHLAND, TREMPEALEAU, AND
AREA 4: MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES
AREA 5: DANE, GRANT, GREEN, IOWA, LAFAYETTE, AND ROCK
AREA 6: KENOSHA AND RACINE COUNTIES
PLUM0011-003 05/01/2008
ASHLAND, BAYFIELD, BURNETT, DOUGLAS, IRON, SAWYER, AND WASHBURN
PLUMBER..........................$ 33.70 14.35
PLUM0075-002 06/01/2008
MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES
Rates Fringes
PLUMBER..........................$ 35.18 13.71
PLUM0075-004 06/01/2008
DODGE (Watertown), GREEN, JEFFERSON, LAFAYETTE, AND ROCK
PLUMBER/PIPEFITTER...............$ 35.43 13.71
PLUM0075-009 06/01/2008
COLUMBIA, DANE, IOWA, MARQUETTE, RICHLAND AND SAUK COUNTIES
Rates Fringes
PLUMBER..........................$ 34.78 12.76
PLUM0118-002 06/01/2008
KENOSHA, RACINE, AND WALWORTH COUNTIES
Rates Fringes
Plumber and Steamfitter..........$ 34.31 14.84
PLUM0400-003 06/02/2008
ADAMS,BROWN, CALUMET, DODGE (except Watertown), DOOR, FOND DU LAC, GREEN LAKE,KEWAUNEE, MANITOWOC, MARINETTE (except Niagara), MENOMINEE, OCONTO, OUTAGAMIE, SHAWANO, SHEBOYGAN, WAUPACA, WAUSHARA, AND WINNEBAGO COUNTIES
PLUMBER/PIPEFITTER...............$ 31.43 13.56
PLUM0434-002 11/30/2008
BARON, BUFFALO, CHIPPEWA, CLARK, CRAWFORD, DUNN, EAU CLAIRE,
FLORENCE, FOREST, GRANT, JACKSON, JUNEAU, LA CROSSE, LANGLADE,
LINCOLN, MARATHON, MONROE, ONEIDA, PEPIN, PIERCE, POLK,
PORTAGE, PRICE, RUSK, ST. CROIX, TAYLOR, TREMPEALEAU, VERNON,
VILAS, AND WOOD COUNTIES
PIPEFITTER.......................$ 32.24 13.63
PLUM0506-007 06/01/2003
MARINETTE COUNTY (Niagara only)
Rates Fringes
PLUMBER/PIPEFITTER
(1) Jobs where plumbing bid is $50,000 or less......$ 20.56 12.05
(2) All other work..........$ 25.71 12.05
TEAM0039-002 05/01/2009
TRUCK DRIVER
1 & 2 Axle Trucks...........$ 23.84 14.70 3 or more axles; Euclids or Dumptor, Articulated Truck, Mechanic.............$ 23.99 14.70
SELF-PROPELLED HOPPER DREDGE:
Drag Tender $ 8.78 $4.23+A
FOOTNOTE:
A. Paid Holidays: New years Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Paul Hall's Birthday (August 20), Veteran,s Day, Thanksgiving Day, and Christmas Day
WELL DRILLER $16.52 $3.70
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
The following have been deleted:
WAGE DETERMINATION IL18
WAGE DETERMINATION WI19