This document contains details for two federal contract opportunities issued by the U.S. Army Corps of Engineers Pittsburgh District. The first opportunity is solicitation number W911WN24Q3005 for building and grounds maintenance and services at Loyalhanna Lake. Services required include grounds maintenance, cleaning, solid waste removal, and sewage and sludge removal. The period of performance is 1 May 2024 to 30 April 2025 with four optional one-year extensions. A pre-quote meeting and site visit is scheduled for 17 January 2024 with an alternate date of 24 January 2024. The second opportunity is solicitation number W911WN24Q3008 for similar services at Conemaugh River Lake. Both opportunities are set aside 100% for small businesses with a NAICS code of 561730 and size standard of $9.5 million. Interested parties must register in the System for Award Management and have an active registration prior to receiving an award.

View the file

Other files

File Type Posted
Attachments 1-7 W911WN24Q3005 0001.pdf PDF
W911WN24Q3005 0001.pdf PDF
Attachment 8 - Price Schedule.xlsx XLSX spreadsheet
Attachments 1-7.pdf PDF
W911WN24Q3005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appendix II

Electronic Invoicing Instructions for the USACE Finance Center

In lieu of submitting a hardcopy invoice to the USA CE Finance Center (UFC) in Millington, TN via the United States Postal Service per the contract instructions in Block 18a, you may submit an electronic version via email per the instructions below:

1. Save or scan the invoice so that it is an electronic (pdf) file.

2. Circle the amount to be paid. See Attached Example.

3. File name of the INVOICE must be the obligation number. (ex: W911 WN-00-X-0000).

4. Attach the Invoice (see# 3) to an email. Make sure the file name is the obligation number.

5. The subject line of the email should contain only the OBLIGATION number (same as the INVOICE file name)

6. Email the PDF file to: CEFC-H4 Invoices@usace.army.mil and CC your contracting POC as well as the USACE project POC to whom the goods or services were delivered to confirm receipt.

7. You can only submit ! invoice per email to the UFC. If you need to submit 3 invoices then you must send 3 separate emails.

8. See below for a sample email submission to the UFC.

9. This process does not apply to ENG93 payments; i.e. Progress payments for construction and Architect/Engineer contracts.

BILL TO

U S _"'u:,ny Corps ofE.ogineers Acc:ounis Pay:ible Ftnanc.e Cenrer 5722 Integrity Drive Millington.. TN 38054-50<)5

SITE-OJ\.iR.

SOL-UPG-R-C::

RTU-C-VZ

TERMS REP

_ �et 30

Sen.-ic:es @S2.910.00 eriz.on �ular data service allowance_ priced per year On-site servic:e for deplo removal of exSens sy Parts @ $2_ 790.00 Upgrade of an SOL SDL500C cellul labor Cellular

SHIP TO

US Anny Corps of Engineers Water Quality Field Office Carl im

3500 Grand Avenue Pinsburgh, P'eni:isvi.r'ania

Total

1.095.00

1.295.00

1.495.00

720.00

2.190.00

1.295.00

1.495.00

Appendix II

Mon 8119/2019 2:53 PM

Walters, Patricia A CIV USARMY CELRP (US)

W911WN-16-C-3001

o CEFC-H4 InvOtCes c Falvo, Anthony J CIV USARMY Ca.RP (USA)

Message � W911WN-16-C-3001.pdf (98 KB)

Good Afternoon, Please process for payment.

Thanks, Patricia A. Walters

Accountant

Resource Management Division

US Army Corps of Engineers, Pittsburgh Distri

Office: {412) 395-7481

Patricia.a. walters@usace .army .mil

Items to Note:

1. Circle the dollar amount to be paid on the invoice

2. If you are sending multiple invoices to the Finance Center, each invoice must be sent down in a separate email. Only 1 invoice per email.

3. The attached invoice's file name must be the obligation number.

4. The subject of the email to the UFC must also be the obligation number.

5. Email is sent to CEFC-H4 Invoices@usace.army.mil AND

6. CC the USACE contracting POC and the USACE Project POC to whom the goods or services were provided.

7. This new process does not apply to ENG93 payments; i.e. Progress payments for construction and Architect/Engineer contracts.

Appendix IV Contract Overview Workbook

Appendix VII

CUI

Contract Location: Company P0C Name:

Contract Number: Army C0R Name:

Please do not send multiple 1-2 person requests in a single day

NAME (Last, First Middle) DOB (mm/dd/yyyy) SSN (no dashes)

CUI

Controlled by: USAGE

Controlled by: CELRP-SM

Category: PRVCY

Distribution: FED ONLY

POC: See below

CUI

Primary Contact: Ivan Russell - Security Specialist

412-39S-7S91 ivan.r.russell@usace.army.mil

Alternate Contact: Andrew Wasko - Security Specialist

412-39S-7643 andrew.j.wasko@usace.army.mil

Chief of Security: Joe Bali

412-395-7162 joseph.m.bali@usace.army.mil

CUI

Appendix IX Actual Services Performed

Base Year Actual Services Performed

Hours for one employee to

Description Of Service JAN FEB MAR APR MAY JUN JULY AUG SEP OCT NOV DEC TOTAL(EST) perform a single service

Appendix X

ANNUAL PEST CONTROL PLAN

FOR CALENDAR YEAR __ _

ANTICIPATED USAGE REPORT _ACTUAL USAGE REPORT _DATE OF REPORT: ___ _

FIELD OFFICE: _____________ DISTRICT: __ ___._P

ITT

S=B

U=R=G=H

APPLICATION INFORMATION:

APPLICATE ACCOMPLISHMENT: IN-HOUSE _CONTRACT _NEGATIVE REPORT

NAME OF APPLICATOR/CONTRACTOR: __________________ _

APPLICATOR LICENSE NO. _________ _

PESTICIDE INFORMATION:

*PESTICIDE TRADE NAME: ___________ EPA REG. NO. _______ _

EPA CLASS: GENERAL-USE PESTICIDE__ RESTRICTED-USE PESTICIDE __ _

% ACTIVE INGREDIENT: _______________________ _

DILUTENT: ________ MIXING RATE: ________ _

APPLICATION RATE: METHOD OF APPLICATION: __________ _

NO. OF APPLICATIONS ___ ACTIVITY HAZARD ANALYSIS WILL BE CONDUCTED: __ _

SITE INFORMATION:

DESCRIPTION OF TREATMENT SITE (S):

TOTAL ESTIMATED ACREAGE TREATED: ___ QUANTITY OF PESTICIDE USED: ___ _

TARGET PEST (S): ________________________ _

PLAN SUBMITTED BY: _________ PLAN APPROVED BY: ______ _

• Pesticides include fungicides, herbicides, insecticides, larvicides and rodenticides (See ER 1130-2-540, dated 15 November 96).

Appendix XI

PESTICIDE APPLICATION RECORD 11. START DATE (YYYYMMDD)

2 INSTALLATION

3 SITE TREATED

4. PEST TREATED

5. PURPOSE

SECTION I - CONDITIONS DURING TREATMENT

1. AIR TEMPERATURE (Fahrenheit Deareesl 12. WATER TEMPERATURE (Fahrenheit De grees if applicable)

3. OVERCAST (Percen tage %) 14. WIND DIRECTION (N, NE, E, SE, S, SW, WorNvJ,1 15. WIND VELOCITY (mph)

1. COMMON NAME

2 ACTIVE INGREDIENT AND PERCENTAGE%

3. MANUFACTURER

5. REGISTRERED USE

C,,LU"CC:TC

SECTION II - PESTICIDE RECORD

14. REGISTRATION NUMBER

AVAILABLE 0 YES ONO

6. MATERIAL SAFETY DATA (MSDS) □ BREATHING APPARATUS

n11□11\1� .o.cc1 11"'11.Tlf"II\I f"I ••Ac-v

7. PERSONAL PROTECTION EQUIPMENT DEVICE WORN (Dust Unfiltered)

0 MASK (Filtered) Q EYEWEAR Q GLOVES O BOOTS 0 HOOD Q PROTECTIVE SUIT 0 TREATED AREA ENCLOSED

Q TREATED AREA OPEN (Ventilated) Q NONE REQUIRED OR WORN PER MSDS DATA Q OTHER SAFETY REQUIREMENTS

8. MIXTURE OR FORM APPLIED (e. g., 20 to 1, Spray, paste, poured, fumigation or Solid)

9. APPLICATION RATE 110. APPLICATION METHOD

11. SPECIAL PRECAUTIONS TAKEN (if none so state)

1? NI JMRl=A f"II= - ''IIFI I 1ci::n IN II.COi 11'"'1\. Tlf"II\I //fof nfhor ~~ • in rorn<>rlrc, ho/nwl

13. OTHER EQUIPMENT USED NOT PREVIOUSLY LISTED

14.A C C U M U L A T I V E T R E A T M E N T�dfts'i:m�, ti a 15. CXXFERl\llt--G JIG3'.tES give n are a dur in g t h e Of8Mn d ar

a. UNITS TREATED b. QUANTITY USED

(1) PREVIOUS (1) PREVIOUS

(2) PRESENT (2) PRESENT

(3) TOTAL (3)TOTAL

16. REMARKS

SECTION 111- CERTIFIED APPLICATOR'S Sl�ATURE CERTIFICATION

I HEREBY CERTIFY THAT THIS INFORMATION IS A TRUE AND CORRECT RECORD OF THE PESTICIDE APPLICATION.

1. OTHER DOCUMENTATION ATTACHED 2a. DATE (YYYYMMDD) b. SIGNATURE (Certified Applicator)

0 YES 0 NO

CELRI FORM 1031, APR 2010 PREVIOUS EDITIONS ARE OBSOLETE. VERSION 11

Form PPQ -0 (9/30/11)

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

CAGE Code: ______________ DUNs Number: _______________________

1. Contractor Information Firm Name: _______________________________________________ Address: ________________________________________________ Phone Number: __________________________________________ Email Address: ____________________________________________ Point of Contact: ___________________________________________ Contact Phone Number: ______________

Sub Contractor Joint Venture Other (Explain)2. Work Performed as: Prime Contractor Percent of project work performed: _________ If subcontractor, who was the prime (Name/Phone #): ___________________________________________________

Cost Reimbursement Other (Please specify):

3. Contract Information Contract Number: ____________________________________ Delivery/Task Order Number (if applicable): ________________________________________ Contract Type: Firm Fixed Price ____________________ Contract Title: ______________________________________________________________________ Contract Location: __________________________________________________________________

Award Date (mm/dd/yy): ________________________ Contract Completion Date (mm/dd/yy): _________________ Actual Completion Date (mm/dd/yy): ___________________ Explain Differences: _______________________________________________________________________________

Original Contract Price (Award Amount): _________________ Final Contract Price (to include all modifications, if applicable): ___________________ Explain Differences: _______________________________________________________________________________

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.) __________________________________________________________________________________

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name: _________________________________________ Title: __________________________________________ Phone Number: _________________________________ Email Address: ______________________________________________

6. Describe the client’s role in the project: ___________________________________________________________

7. Date Questionnaire was completed (mm/dd/yy): _____________________

8. Client’s Signature: ______________________________________________

NOTE: NAVFAC/USACE requests that the client completes this questionnaire and submits directly back to the offeror.

The offeror will submit the completed questionnaire to USACE with their proposal, and may duplicate this questionnaire for future submission on USACE solicitations. Clients are highly encouraged to submit questionnaires directly to the offeror. However, questionnaires may be submitted directly to USACE. Please contact the offeror for USACE POC information. The Government reserves the right to verify any and all information on this form.

Appendix XII NAVFAC / USACE Past Performance Questionnaire (PPQ)

NAVFAC / USACE Past Performance Questionnaire (PPQ) Form PPQ -0 (9/30/11)

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit.

The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable No information or did not apply to your contract Rating will be neither positive nor negative.

TO BE COMPLETED BY CLIENT

PLEASE SELECT THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

E VG S M U N

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U N

3. CUSTOMER SATISFACTION

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

E VG S M U N

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer? E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force? E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes E VG S M U N

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)? E VG S M U N

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

E VG S M U N

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

E VG S M U N

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section. Yes No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

Yes No

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below. Yes No

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?

(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

E VG S M U N

b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

E VG S M U N

b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N

c) Would you hire or work with this firm again? (If no, please explain below) Yes No

d) In summary, provide an overall rating for the work performed by this contractor. E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

Appendices I-XII
Appendix I
Appendix II
Appendix III
Appendix IV
Appendix V
Appendix VI
Appendix VII
Appendix VIII
Appendix IX
Appendix X
Appendix XI
Appendix XII Past Performance Questionnaire
CONTRACT INFORMATION Contractor to complete Blocks 14:
CAGE Code:
Firm Name:
DUNs Number:
Address:
Phone Number:
Email Address:
Point of Contact:
Contact Phone Number:
Prime Contractor: Off
Sub Contractor: Off
Joint Venture: Off
Other Explain: Off
Percent of project work performed:
If subcontractor who was the prime NamePhone:
Contract Number:
DeliveryTask Order Number if applicable:
Firm Fixed Price: Off
Cost Reimbursement: Off
undefined: Off
Other Please specify:
Contract Title:
Contract Location:
Award Date mmddyy:
Contract Completion Date mmddyy:
Actual Completion Date mmddyy:
Explain Differences:
Original Contract Price Award Amount:
Final Contract Price to include all modifications if applicable:
Explain Differences_2:
High: Off
Med: Off
Routine: Off
conditions etc 1:
conditions etc 2:
conditions etc 3:
CLIENT INFORMATION Client to complete Blocks 58:
5 Client Information Name Title Phone Number Email Address:
Name:
Title:
Phone Number_2:
Email Address 1:
Email Address 2:
6 Describe the clients role in the project 1:
6 Describe the clients role in the project 2:
undefined_2:
7 Date Questionnaire was completed mmddyy:
undefined_3:
8 Clients Signature:
A: Choice10
B: Choice16
PPQ: Choice16
C: Off
D: Off
E: Off
F: Off
G: Off
H: Off
I: Off
J: Off
K: Off
L: Off
M: Off
N: Off
O: Off
P: Off
Q: Off
R: Off
which may assist our office in evaluating performance risk please attach additional pages if necessary 1:
which may assist our office in evaluating performance risk please attach additional pages if necessary 2:
which may assist our office in evaluating performance risk please attach additional pages if necessary 3:
which may assist our office in evaluating performance risk please attach additional pages if necessary 4:
which may assist our office in evaluating performance risk please attach additional pages if necessary 5:
which may assist our office in evaluating performance risk please attach additional pages if necessary 6:
which may assist our office in evaluating performance risk please attach additional pages if necessary 7:
which may assist our office in evaluating performance risk please attach additional pages if necessary 8:
which may assist our office in evaluating performance risk please attach additional pages if necessary 9:
which may assist our office in evaluating performance risk please attach additional pages if necessary 10:
which may assist our office in evaluating performance risk please attach additional pages if necessary 11:
S: Off
T: Off
U: Off
V: Off
W: Off
X: Off
Y: Off
Z: Off
AA: Off
AB: Off
AC: Off

File details come from the government source that posted it. Updated .