This document provides responses to industry inquiries regarding solicitation number W911WN23Q1196 for the Montgomery Lock and Dam concrete supply and delivery project. The U.S. Army Corps of Engineers Engineering District Pittsburgh will accept Type 1L cement in lieu of Type II cement as specified. Material sources must be consistent with the approved mix design. The submittal deadline for a new mix design, if needed, is reduced to 15 business days before the first concrete placement to accommodate the project schedule. Prices quoted must be inclusive of all applicable costs and taxes, which should not be broken out separately. Bidders are advised to coordinate with the concrete specialist Brian Lucarelli during mix design testing to help ensure suitability prior to submittal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911WN-23-Q-1196 Amendment I: Response to Industry Inquiries
The mix design in Attachment A has Type II cement which is no longer available as the industry has switched to Type 1L cement. Would Type 1L Cement be acceptable in lieu of Type II? Also can the material sources be provided as the specification requires that it is the same.
Reference: Combined Synopsis Solicitation
Section 03 31 25 Page 9-10, Part 2 “Products”
2.1 Materials
Cementitious materials shall conform to appropriate specifications listed below.
Use one manufacturer of each type of Portland cement, pozzolan, silica fume, and/or slag cement.
2.2.1
“ASTM C150/C150M, Type II, or ASTM C595 Type 1L.”
If we are unable to use the attached mix design, a new mix design will require approximately 6 weeks after award, and there is a requirement to submit for approval 30 business days before the first placement. Based upon the provided schedule, there is insufficient time allowed. Please review.
We can reduce the requirement to submit for approval to 15 business days before the first placement. We ask that the vendor works with our concrete specialist Brian Lucarelli during the batch design/testing to make sure the mix will likely be suitable before the test breaks and submittal.
POC: Brian Lucarelli, Civil Engineer (Concrete Materials)
Email: Brian.A.Lucarelli@usace.army.mil
How will sales tax be handled? Is it exempt? Will it be added to our prices that we quote or must we add it in.
The price should be inclusive of all applicable costs. Taxes should not be broken out or visible as separate from the rest of the quoted price. taxes should be included in the quoted price.
SSG Hill, Andrew