W911WN23B####

Upper Ohio Navigation Project New River Chamber Montgomery Locks & Dam Beaver County, PA

100% CONSISTENCY REVIEW

PRELIMINARY NOT FOR CONSTRUCTION

TECHNICAL SPECIFICATIONS

JUNE 2023

PRELIMINARY NOT FOR CONSTRUCTION

Upper Ohio Montgomery Locks and Dam Lock Chamber Contract

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

0001 REIMBURSEMENT FOR ACTUAL

PERFORMANCE AND PAYMENT BONDS

PREMIUMS, BASE CONTRACT

1 JOB

0002 DIGITAL PROGRESS IMAGES, MONTHLY,

BASE CONTRACT

96 SET

0003 DIGITAL AERIAL PROGRESS IMAGES,

QUARTERLY, BASE CONTRACT

32 SET

0004 MOBILIZATION AND PREPARATORY WORK 1 JOB

0005 DEMOBILIZATION 1 JOB

0006 MAINTAIN GOVERNMENT FIELD OFFICES,

BASE CONTRACT

96 MONTHS

0007 RECONSTRUCTION STATE ROUTE,

MONTGOMERY DAM ROAD

SQUARE YARDS

0008 EXPLORATORY PROGRAM 1 JOB

0009 INSTRUMENTATION INSTALLATION 1 JOB

0010 INSTRUMENTATION MONITORING PROGRAM 96 MONTHS

0011 RELOCATE GOVERNMENT TRAILER 1 JOB

0012 DEVELOP DATA MANAGEMENT SYSTEM 1 JOB

0013 MAINTAIN DATA MANAGEMENT SYSTEM 96 MONTHS

0014 ENVIRONMENTAL COMPLIANCE

MEASUREMENTS, SAMPLING, TESTING AND

REPORTING, CONCRETE BATCH PLANT

96 MONTHS

0015 REMOVE AND DISPOSE EXISTING

FOOTBRIDGE

1 JOB

0016 DEMOLITION OF FIXED CREST WEIR 1 JOB

0017 DEMOLITION OF APRON 1 JOB

0018 REMOVAL OF EXISTING TIMBER PILES, DAM

APRON

136 EACH

0019 REMOVAL OF GRANULAR FILL UNDER

APRON

1 JOB

0020 REMOVE DERRICK STONE 1 JOB

0021 INSTALLATION OF FLASHBOARDS 1 JOB

0022 COMBINATION WALL, JET GROUTING CUBIC YARDS

0023 COMBINATION WALL, 48-INCH DIAMETER BY

1/2-INCH THICK PIPE PILE

LINEAR FEET

0024 COMBINATION WALL, PZ 27 METAL SHEET

PILING

LINEAR FEET

0025 COMBINATION WALL, W24x162 KING PILES EACH

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

0026 COMBINATION WALL, ALLUVIUM

EXCAVATION

LINEAR FEET

0027 COMBINATION WALL, 42-INCH DIAMETER

ROCK SOCKET

LINEAR FEET

0028 COMBINATION WALL, CONCRETE FOR CAST-

IN-PLACE CONCRETE PILES

CUBIC YARDS

0029 REMOVE AND DISPOSE OF EXISTING

SHEETPILING AT APRON TOE

2115 LINEAR FEET

0030 REMOVAL OF EXISTING RIVER CHAMBER

FLOOR PAVERS

1 JOB

0031 DEMOLITION OF UPPER GUARD WALL

EXTENSION CELLS

1 JOB

0032 DEMOLITION OF UPPER GUARD WALL 1 JOB

0033 DEMOLITION OF LOWER GUARD WALL 1 JOB

0034 CLOSE UPPER AND LOWER FILLING AND

EMPTYING PORTS

1 JOB

0035 REMOVE AND SALVAGE FILLING AND

EMPTYING SYSTEM

1 JOB

0036 FILL DOWNSTREAM RIVERSIDE MITER

GATES AND OTHER RECESSES WITH

CONCRETE ON EXISTING MIDDLE WALL.

CUBIC YARDS

0037 GRAVEL ACCESS ROAD AREA

IMPROVEMENTS, TEMPORARY

DOWNSTREAM BRIDGE

1 JOB

0038 TEMPORARY DOWNSTREAM BRIDGE 1 JOB

0039 DEMOLITION OF RIVER WALL BUILDING 1 JOB

0040 DEMOLITION OF RIVER WALL 1 JOB

0041 REMOVAL OF EXISTING TIMBER PILES, LOCK

RIVER WALL

1766 EACH

0042 REMOVE AND DISPOSE UPPER MITER GATE 1 JOB

0043 REMOVE AND DISPOSE LOWER MITER GATE 1 JOB

0044 DEMOLITION OF LOCK FLOOR CONCRETE 1 JOB

0045 DREDGE RIVER ALLUVIUM 336290 CUBIC YARDS

0046 DEMOLITION OF SILLS 1 JOB

0047 INSTALL ROCK ANCHORS, PIER 1 807 LINEAR FEET

0048 DEMONSTRATION - DRILLED SHAFT 1 JOB

0049 DEMONSTRATION - UNDERWATER

CONCRETE

1 JOB

0050 DEMONSTRATION - MASS CONCRETE LIFT 1 JOB

0051 DEMONSTRATION - COLD WEATHER

PLACEMENT

1 JOB

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

0052 EXCAVATE ALLUVIUM INSIDE COFFERDAM

CELLS

7449 CUBIC YARDS

0053 CONSTRUCT PERMANENT DRILLED SHAFTS,

TYPE RC-1

197 EACH

0054 CONSTRUCT PERMANENT DRILLED SHAFTS,

TYPE RC-2

EACH

0055 CONSTRUCT PERMANENT DRILLED SHAFTS,

TYPE RC-3

EACH

0056 PORTLAND CEMENT CWT

0057 FLY ASH CWT

0058 BLAST FURNACE SLAG CWT

0059 SILICA FUME CWT

0060 TREMI MASS CONCRETE FOR NEW LOCK

MONOLITHS, PRODUCE, DELIVER AND PLACE

CUBIC YARDS

0061 EXTERIOR MASS CONCRETE FOR NEW LOCK

MONOLITHS, PRODUCE, DELIVER AND PLACE

CUBIC YARDS

0062 INTERIOR MASS CONCRETE FOR NEW LOCK

MONOLITHS, PRODUCE, DELIVER AND PLACE

CUBIC YARDS

0063 INTERIOR STRUCTURAL CONCRETE FOR

NEW LOCK MONOLITHS, PRODUCE, DELIVER

AND PLACE

CUBIC YARDS

0064 TOP OF WALL MASS CONCRETE FOR NEW

LOCK MONOLITHS, DESIGN, PRODUCE,

DELIVER AND PLACE

CUBIC YARDS

0065 DENTAL EXCAVATION AND DENTAL

CONCRETE, EXCAVATE,PRODUCE, DELIVER

AND PLACE DENTAL CONCRETE

100 CUBIC YARDS

0066 MUD MATT CONCRETE, PRODUCE, DELIVER

AND PLACE

CUBIC YARDS

0067 REINFORCING STEEL, NEW LOCK WALL

MONOLITHS

3925 TONS

0068 ROCK EXCAVATION CUBIC YARDS

PRELIMINARY CLEANUP, ROCK EXCAVATION SQUARE YARDS

FINAL CLEANUP, ROCK EXCAVATION SQUARE YARDS

0069 COFFERDAM SHEETPILING, FURNISH AND

INSTALL

LINEAR FEET

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

0070 EXCAVATE ALLUVIUM INSIDE COFFERDAM

AREA

116402 CUBIC YARDS

0071 COFFERDAM TREMIE SEAL, PRODUCE,

DELIVER AND PLACE

18168 CUBIC YARDS

0072 INSTALL COFFERDAM PIPE PILES 324 EACH

0073 COFFERDAM CONNECTION ARC CONCRETE,

PRODUCE, DELIVER AND PLACE

CUBIC YARDS

0074 PLACE COFFERDAM FREE DRAINING

FILL(ALLUVIUM ON SITE)

227828 CUBIC YARDS

0075 COFFERDAM CELL DEWATERING SYSTEM 1 JOB

0076 DEWATERING COFFERDAM CELLS 72 MONTHS

0077 INITIAL UNWATER COFFERDAM 1 JOB

0078 DEWATER COFFERDAM AREA 72 MONTHS

0079 COFFERDAM AGGREGATE CAP, PENNDOT

3A, INSTALL

CUBIC YARDS

0080 PLACE FILL WITHIN CHAMBER - MISC

CHAMBER FLOOR FILL

20100 CUBIC YARDS

0081 PLACE R-5 RIPRAP FOR LOCK FLOOR

BACKFILL

5171 CUBIC YARDS

0082 BEDDING UNDER LOCK FLOOR 5464 CUBIC YARDS

0083 CONSTRUCT COFFERDAM SPLASH PAD AND

FLOOD WAY

1 JOB

0084 DRILL EXISTING RIVER WALL WEEP HOLES LINEAR FEET

0085 PVC WATERSTOPS 6984 LINEAR FEET

0086 LAND WALL EQUIPMENT BUILDING 1 JOB

0087 COMPRESSOR AND LANDWALL AIRLINE 1 JOB

0088 TEMPORARY POWER GENERATORS 1 JOB

0089 TEMPORARY POWER SUPPLY 1 JOB

0090 CONCRETE LOCK FLOOR, PRODUCE,

DELIVER AND PLACE

5909 CUBIC YARDS

0091 CULVERT BULKHEAD RECESS LINERS,

FABRICATE AND INSTALL

1 JOB

0092 UPSTREAM CHAMBER STOPLOG RECESS

LINERS, FABRICATE AND INSTALL

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

0093 DOWNSTREAM CHAMBER STOPLOG RECESS

LINERS, FABRICATE AND INSTALL

1 JOB

0094 MITER GATES - ASSOCIATED

APPURTENANCES, FABRICATE AND DELIVER

1 JOB

0095 SILL SEAL ANGLE, WALL QUOIN POSTS,

PINTLE BASE AND PINTLE, INSTALLATION

1 JOB

0096 WALL ARMOR, FABRICATE AND INSTALL 29582 LINEAR FEET

0097 R3 HORIZONTAL CORNER PROTECTION,

FABRICATE AND INSTALL

1940 LINEAR FEET

0098 R8 VERTICAL CORNER PROTECTION,

FABRICATE AND INSTALL

2060 LINEAR FEET

0099 R24 VERTICAL CORNER PROTECTION,

FABRICATE AND INSTALL

143 LINEAR FEET

0100 CORNER CASTINGS, FABRICATE AND

INSTALL

EACH

0101 REMOVAL OF PROTECTION CELLS IN

NAVIGATION CHANNEL

1 JOB

0102 REPLACE DERRICK STONE PROTECTION

PREVIOUSLY REMOVED FOR COFFERDAM

CONSTRUCTION

1 JOB

0103 FLOATING MOORING BITT ANCHORAGES,

FABRICATE AND INSTALL

1 JOB

0104 FLOATING MOORING BITTS, FABRICATE AND

INSTALL

8 EACH

0105 LINE HOOKS AND GUARDS, FABRICATE AND

INSTALL

65 EACH

0106 CHECK POSTS, FABRICATE AND INSTALL 35 EACH

0107 HANDRAIL - WIRE RAIL, FABRICATE AND

INSTALL

1 JOB

0108 HANDRAIL - TUBE RAIL, FABRICATE AND

INSTALL

1 JOB

0109 EXCAVATE ALLUVIUM INSIDE MIDDLE WALL

BULL NOSE

CUBIC YARDS

0110 MIDDLE WALL BULL NOSE SHEETPILING,

FURNISH AND INSTALL

4000 LINEAR FEET

0111 MIDDLE WALL BULL NOSE TREMI CONCRETE,

PRODUCE, DELIVER AND PLACE

CUBIC YARDS

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

0112 MIDDLE WALL BULL NOSE MASS CONCRETE,

PRODUCE, DELIVER AND PLACE

CUBIC YARDS

0113 ON SITE PAINTING 1 JOB

0114 CONSTRUCTION OF TRANSITION WALL 1 JOB

0115 INSTALL UPSTREAM ROCK DIKES CUBIC YARDS

0116 INSTALL DOWNSTREAM ROCK DIKE CUBIC YARDS

0117 INSTALL LOCK SIGNAGE 1 JOB

0118 STOPLOGS, TEST FIT 1 JOB

0119 DEWATER AND CLEANUP OF COFFERDAM

POST FLOOD EVENT

1 EACH

0120 GOVERNMENT DIRECTED EVACUATION OF

COFFERDAM

2 EACH

0121 FURNISH AND INSTALL ELECTRICAL AND

MECHANICAL SYSTEMS EMBEDDED ITEMS,

BASE CONTRACT

1 JOB

0122 SITE RESTORATION 1 JOB

0123 AS-BUILT DRAWINGS, BASE CONTRACT 1 JOB

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

OPTION 1, GUARD WALLS

1001 REIMBURSEMENT FOR ACTUAL

PERFORMANCE AND PAYMENT BONDS

PREMIUMS, AWARDABLE OPTION 1

1 JOB

1002 DIGITAL PROGRESS IMAGES, MONTHLY,

AWARDABLE OPTION 1

12 SET

1003 DIGITAL AERIAL PROGRESS IMAGES,

QUARTERLY, AWARDABLE OPTION 1

32 SET

1004 MAINTAIN GOVERNMENT FIELD OFFICES,

OPTION 1

96 MONTHS

1005 NOSE CELLS SHEETPILING, FURNISH AND

INSTALL

LINEAR FEET

1006 NOSE CELLS TREMI CONCRETE, PRODUCE,

DELIVER AND PLACE

CUBIC YARDS

1007 NOSE CELLS MASS CONCRETE, PRODUCE,

DELIVER AND PLACE

CUBIC YARDS

1008 NOSE CELL WALK WAY 1 JOB

1009 PORTLAND CEMENT CWT

1010 FLY ASH CWT

1011 BLAST FURNACE SLAG CWT

1012 SILICA FUME CWT

1013 UPPER GUARD WALL DRILLED SHAFTS 16 EACH

1014 PRECAST CAP SHELL UPPER GUARD WALL,

FABRICATE, DELIVER AND INSTALL

1 JOB

1015 PIER CAP INFILL UPPER GUARD WALL,

PRODUCE, DELIVER AND PLACE

1 JOB

1016 PRECAST BOX BEAMS UPPER GUARD WALL,

FABRICATE, DELIVER AND INSTALL

1 JOB

1017 PRECAST SKIRT PANEL UPPER GUARD

WALL, FABRICATE, DELIVER AND INSTALL

1 JOB

1018 THRUST BLOCK UPPER GUARD WALL,

PRODUCE, DELIVER AND PLACE

1 JOB

1019 LOWER GUARD WALL DRILLED SHAFTS 22 EACH

1020 PRECAST SHAFT ENCLOSURE LOWER

GUARD WALL, FABRICATE, DELIVER AND

INSTALL

1 JOB

1021 PRECAST WALL PANEL LOWER GUARD

WALL, FABRICATE, DELIVER AND INSTALL

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

1022 RETAINING WALL SECTION LOWER GUARD

WALL

1 JOB

1023 SHEETPILE CUT OFF WALL GUARD WALLS LINEAR FEET

1024 EXCAVATE ALLUVIUM INSIDE NOSE CELLS CUBIC YARDS

1025 EMBEDDED CONDUIT AND LIGHT POLE

BASES, GUARD WALLS

CUBIC YARDS

1026 AS-BUILT DRAWINGS, AWARDABLE OPTION 1 1 JOB

OPTION 2, HSS COMPONENTS

2001 REIMBURSEMENT FOR ACTUAL

PERFORMANCE AND PAYMENT BONDS

PREMIUMS, AWARDABLE OPTION 2

1 JOB

2002 DIGITAL PROGRESS IMAGES, MONTHLY,

AWARDABLE OPTION 2

24 SET

2003 DIGITAL AERIAL PROGRESS IMAGES,

QUARTERLY, AWARDABLE OPTION 2

32 SET

2004 MAINTAIN GOVERNMENT FIELD OFFICES,

OPTION 2

MONTHS

2005 FILLING AND EMPTYING VALVES, FABRICATE

AND INSTALL

4 EACH

2006 FILLING AND EMPTYING CULVERT

BULKHEADS, FABRICATE AND DELIVER

8 EACH

2007 UPSTREAM CHAMBER STOPLOG RECESS

FILLERS, FABRICATE AND INSTALL

1 JOB

2008 DOWNSTREAM CHAMBER STOPLOG RECESS

FILLERS, FABRICATE AND INSTALL

1 JOB

2009 MITER GATES, FABRICATE AND DELIVER 1 JOB

2010 MITER GATE LEAVES, INSTALLATION 4 EACH

2011 INTAKE SCREEN ASSEMBLIES 1 JOB

2012 LOCK WALL RECESS LADDERS, FABRICATE

AND INSTALL

10 EACH

2013 UTILITY ACCESS SHAFT LADDERS,

FABRICATE AND INSTALL

11 EACH

2014 AS-BUILT DRAWINGS, AWARDABLE OPTION 2 1 JOB

OPTION 3, SILLS AND CULVERTS

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

3001 REIMBURSEMENT FOR ACTUAL

PERFORMANCE AND PAYMENT BONDS

PREMIUMS, AWARDABLE OPTION 3

1 JOB

3002 DIGITAL PROGRESS IMAGES, MONTHLY,

AWARDABLE OPTION 3

18 SET

3003 DIGITAL AERIAL PROGRESS IMAGES,

QUARTERLY, AWARDABLE OPTION 3

32 SET

3004 MAINTAIN GOVERNMENT FIELD OFFICES,

OPTION 3

MONTHS

3005 REINFORCING STEEL, SILLS TONS

3006 INTERIOR MASS CONCRETE FOR NEW SILLS,

PRODUCE, DELIVER AND PLACE

CUBIC YARDS

3007 EXTERIOR STRUCTURAL CONCRETE FOR

NEW SILLS, PRODUCE, DELIVER AND PLACE

CUBIC YARDS

3008 CONCRETE CHAMBER CULVERT

FOUNDATION, PRODUCE, DELIVER AND

PLACE

CUBIC YARDS

3009 PORTLAND CEMENT CWT

3010 FLY ASH CWT

3011 BLAST FURNACE SLAG CWT

3012 SILICA FUME CWT

3013 CONSTRUCT CHAMBER CULVERTS 1 JOB

3014 AS-BUILT DRAWINGS, AWARDABLE OPTION 3

OPTION 4 - BUILDINGS, ELECTRICAL AND MECHANICAL FEATURES

4001 REIMBURSEMENT FOR ACTUAL

PERFORMANCE AND PAYMENT BONDS

PREMIUMS, AWARDABLE OPTION 4

1 JOB

4002 DIGITAL PROGRESS IMAGES, MONTHLY,

AWARDABLE OPTION 4

12 SET

4003 DIGITAL AERIAL PROGRESS IMAGES,

QUARTERLY, AWARDABLE OPTION 4

32 SET

4004 MAINTAIN GOVERNMENT FIELD OFFICES,

OPTION 4

MONTHS

4005 NEW STAIR TOWER DRILLED SHAFTS 6 EACH

4006 INSTALL NEW PERMANENT STAIR TOWERS 1 JOB

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

4007 INSTALL PERMANENT UTILITY BRIDGE 1 JOB

4008 MIDDLE WALL EQUIPMENT BUILDING 1 JOB

4009 RIVER WALL EQUIPMENT BUILDING 1 JOB

4010 MIDDLE WALL CONTROL SHELTERS

STRUCTURES

1 JOB

4011 FILLING AND EMPTYING VALVE OPERATING

MACHINERY, FABRICATE AND INSTALL

4 EACH

4012 MITER GATE OPERATING MACHINERY,

FABRICATE AND INSTALL

4 EACH

4013 COMPRESSED AIR PIPING SYSTEM 1 JOB

4014 POTABLE WATER PIPING SYSTEM 1 JOB

4015 SERVICE WATER PIPING SYSTEM 1 JOB

4016 SANITARY SEWAGE PIPING SYSTEM 1 JOB

4017 ELECTRICAL WORK 1 JOB

4018 TOW HAULAGE SYSTEM, FABRICATE AND

INSTALL

1 JOB

4019 RIVER WALL CRANE, FABRICATE AND

INSTALL

1 JOB

4020 COMMISSIONING - FULLY INTEGRATED

SYSTEM TESTING

1 JOB

4021 AS-BUILT DRAWINGS, AWARDABLE OPTION 4 1 JOB

OPTION 5 - COFFERDAM REMOVAL

5001 REIMBURSEMENT FOR ACTUAL

PERFORMANCE AND PAYMENT BONDS

PREMIUMS, AWARDABLE OPTION 5

5 SET

5002 DIGITAL PROGRESS IMAGES, MONTHLY,

AWARDABLE OPTION 5

12 MONTHS

5003 DIGITAL AERIAL PROGRESS IMAGES,

QUARTERLY, AWARDABLE OPTION 5

32 SET

5004 MAINTAIN GOVERNMENT FIELD OFFICES,

OPTION 5

MONTHS

5005 DEMOLITION OF COFFERDAM 1 JOB

5006 AS-BUILT DRAWINGS, AWARDABLE OPTION 5 1 JOB

OPTION 5 - PAVE MOTGOMERY DAM ROAD

Bid Schedule/Specifications Section Cross Reference

Bid Items

Item Description Measurement Unit of Measure

6001 REIMBURSEMENT FOR ACTUAL

PERFORMANCE AND PAYMENT BONDS

PREMIUMS, AWARDABLE OPTION 5

5 SET

6002 DIGITAL PROGRESS IMAGES, MONTHLY,

AWARDABLE OPTION 5

6 MONTHS

6003 DIGITAL AERIAL PROGRESS IMAGES,

QUARTERLY, AWARDABLE OPTION 5

32 SET

6004 MAINTAIN GOVERNMENT FIELD OFFICES,

OPTION 6

MONTHS

6005 POST CONSTRUCTION MILL AND OVERLAY

MONTGOMERY DAM ROAD

SQUARE YARDS

Montgomery Locks and Dam New River Chamber

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 13.00 08 SUMMARY OF WORK

01 22 00.00 08 PRICE AND PAYMENT PROCEDURES

01 30 00.00 08 ADMINISTRATIVE REQUIREMENTS

01 31 00.00 08 DATA MANAGEMENT

01 32 01.00 08 PROJECT SCHEDULE NETWORK ANALYSIS

01 32 23.00 08 SURVEY AND ALIGNMENT CONTROL

01 32 25.00 08 LiDAR AND IMAGERY

01 32 33.00 08 DIGITAL PROGRESS IMAGES

01 33 00 SUBMITTAL PROCEDURES

01 35 00.00 08 SPECIAL PROCEDURES

01 35 26.00 08 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 26.13 08 DIVING SERVICES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 08 QUALITY CONTROL

01 45 00.15 08 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 50 10.00 08 PROJECT AND SAFETY SIGNS

01 54 00.00 08 GOVERNMENT EQUIPMENT AVAILABLE FOR USE IN PERFORMANCE OF

CONTRACT

01 57 19.00 08 TEMPORARY ENVIRONMENTAL CONTROLS

01 73 19.00 08 GOVERNMENT-FURNISHED PROPERTY

01 74 19.00 08 DISPOSAL

01 78 02.00 08 CLOSEOUT SUBMITTALS (AS-BUILT DRAWINGS)

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 FACILITY DATA REQUIREMENTS

01 78 43.00 08 SPARE PARTS

01 91 00.15 10 GENERAL COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 32 00 FOUNDATION VERIFICATION DRILLING, SAMPLING, AND RECORDING

02 41 00.00 08 DEMOLITION

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 00 ASBESTOS REMEDIATION

02 83 00 LEAD REMEDIATION

02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs

AND MERCURY

02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)

DIVISION 03 - CONCRETE

03 00 00 GENERAL CONCRETE REQUIREMENTS

03 11 14.01 CONCRETE: FORMWORK (IN-THE-WET)

03 11 14.02 CONCRETE: FORMWORK (IN-THE-DRY)

03 15 14 WATERSTOPS IN CONCRETE FOR CIVIL WORKS

03 20 02 CONCRETE REINFORCEMENT FOR CIVIL WORKS

03 23 00 STRESSED TENDON REINFORCING

03 30 00 CAST-IN-PLACE CONCRETE

03 30 00.20 08 CONCRETE: FIELD DEMONSTRATIONS

03 37 06.00 08 JET GROUTING

03 37 26.10 08 CONCRETE: UNDERWATER AND FLOWABLE

03 37 26.20 08 TEMPORARY UNDERWATER CONCRETE

03 41 33.02 PRECAST STRUCTURAL PRETENSIONED CONCRETE (VERTICAL

CONSTRUCTION)

PROJECT TABLE OF CONTENTS Page 1

100% CONSISTENCY REVIEWPRELIMINARY NOT FOR CONSTRUCTION

03 45 33 PRECAST PRESTRESSED STRUCTURAL CONCRETE

03 62 16 METALLIC NON-SHRINK GROUTING

03 70 00 MASS CONCRETE

03 70 05.00 08 ALTERNATE COLD WEATHER PROTECTION

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 05 20.00 27 POST-INSTALLED CONCRETE AND MASONRY ANCHORS FOR LOCK

COMPONENTS

05 05 20.01 27 POST-INSTALLED CONCRETE AND MASONRY ANCHORS (VERTICAL

CONSTRUCTION)

05 12 00 GENERAL STRUCTURAL STEEL - VERTICAL CONSTRUCTION

05 12 00.02 BRIDGE STRUCTURAL STEEL - VERTICAL CONSTRUCTION

05 12 10 ELASTOMERIC BEARING PADS

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 50 15 CIVIL WORKS FABRICATIONS

05 51 00 METAL STAIRS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

05 59 20 FABRICATION OF HYDRAULIC STEEL STRUCTURES

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 73 01 FIBERGLASS REINFORCED PLASTIC (FRP) GRATING AND TREADS

06 82 14 FIBERGLASS REINFORCED PLASTIC (FRP) PIPE AND TUBE RAILINGS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 22 00 RIGID INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 60 00 FLASHING AND SHEET METAL

07 61 14.00 20 STEEL STANDING SEAM ROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 36 13 SECTIONAL OVERHEAD DOORS

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 45 23 INSULATED TRANSLUCENT FIBERGLASS SANDWICH PANEL WALL SYSTEM

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR GYPSUM BOARD

PROJECT TABLE OF CONTENTS Page 2

09 29 00 GYPSUM BOARD

09 90 00 PAINTS AND COATINGS

09 97 02 PAINTING: HYDRAULIC STEEL STRUCTURES AND APPURTENANCES

DIVISION 10 - SPECIALTIES

10 14 00.10 EXTERIOR SIGNAGE

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

DIVISION 13 - SPECIAL CONSTRUCTION

13 50 00 INSTRUMENTATION PROGRAM

13 50 10 MOVEMENT PINS

13 50 15 AUTOMATED SURVEY EQUIPMENT

13 50 20 ELECTRONIC INCLINOMETERS

13 50 30 ELECTRONIC PIEZOMETERS

13 50 35 MANUAL PIEZOMETERS

13 50 45 MANUAL CRACKMETERS

13 50 50 AUTOMATED CRACKMETERS

13 53 20 LOAD CELLS MOUNTED ON ROCK ANCHORS

13 70 00 AUTOMATED DATA ACQUISITION SYSTEM (ADAS)

DIVISION 14 - CONVEYING EQUIPMENT

14 46 00 VERTICAL RECIPROCATING CONVEYOR

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 11 13.00 08 PLUMBING, SERVICE WATER SYSTEM

22 15 14.00 40 GENERAL SERVICE COMPRESSED-AIR SYSTEMS, LOW PRESSURE

22 15 19.19 08 AIR COMPRESSOR

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 35 19.00 20 INDUSTRIAL VENTILATION AND EXHAUST

23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 82 46.00 40 ELECTRIC UNIT HEATERS

23 82 46.00 41 ELECTRIC UNIT HEATERS - RECIRCULATION AIR ONLY

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 28 CYBERSECURITY

25 05 11.02 28 CYBERSECURITY FOR CIVIL WORKS OPERATIONAL TECHNOLOGY

25 05 11.03 28 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS

DIVISION 26 - ELECTRICAL

26 05 19.10 08 INSULATED WIRE AND CABLE

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 28 00.00 10 MOTOR CONTROL CENTERS, SWITCHBOARDS AND PANELBOARDS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 29 23 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS UNDER 600 VOLTS

PROJECT TABLE OF CONTENTS Page 3

26 32 14.00 10 ELECTRIC GENERATOR SET

26 36 23 AUTOMATIC TRANSFER SWITCHES AND BY-PASS/ISOLATION SWITCH

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00.00 08 EXTERIOR LIGHTING

26 56 13.00 POLES AND STANDARDS

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 13 23.00 08 COMMUNICATIONS OPTICAL BACKBONE CABLING

27 21 10.00 08 FIBER OPTIC DATA TRANSMISSION SYSTEM

27 51 16 PUBLIC ADDRESS SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING

28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)

28 10 05.00 08 CLOSED CIRCUIT TELEVISION (CCTV)

28 31 70 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 00 00.71 08 ROADWAY EARTHWORK

31 05 19.13 GEOTEXTILES FOR EARTHWORK

31 11 00 CLEARING AND GRUBBING

31 23 05 MASS EXCAVATION

31 23 06 BLASTING

31 33 01.00 08 ROCK LINING

31 41 16 METAL SHEET PILING

31 42 00 COFFERDAM

31 45 00 DIVERSION AND CARE OF WATER

31 60 00 FOUNDATION PREPARATION

31 62 16.13 DRILLED IN PLACE STEEL PIPE PILES

31 62 23.13 CAST-IN-PLACE CONCRETE PILES

31 63 29 DRILLED CONCRETE PIERS AND SHAFTS

31 68 13 SOIL AND ROCK ANCHORS

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 16.71 08 COLD MILLING ASPHALT PAVING

32 01 16.76 08 COLD-MIX REUSED ASPHALT PAVING

32 01 19.61 FIELD MOLDED JOINT SEALANTS FOR CIVIL WORKS

32 11 23 AGGREGATE BASE COURSES

32 11 25 LOCK FLOOR DRAINAGE LAYER

32 12 13.15 08 ASPHALT TACK AND PRIME COATS

32 12 16.00 08 ASPHALT PAVEMENT CONSTRUCTION

32 13 73.19 COMPRESSION JOINT SEALS FOR CIVIL WORKS

32 15 00 AGGREGATE SURFACING

32 17 23 PAVEMENT MARKINGS

32 31 13 CHAIN LINK FENCES AND GATES

32 34 13 FABRICATED PEDESTRIAN BRIDGES

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

PROJECT TABLE OF CONTENTS Page 4

33 31 23.00 10 SANITARY SEWER FORCE MAIN PIPING

33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS

33 40 00 STORMWATER UTILITIES

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 01 41.00 10 ELECTROMECHANICAL OPERATING MACHINERY FOR LOCKS AND DAMS

35 05 40.14 10 HYDRAULIC POWER SYSTEMS FOR CIVIL WORKS STRUCTURES

35 08 40 MITER GATE COMMISSIONING

35 11 50 TOW HAULAGE MACHINERY

35 20 16.33 MITER GATES

35 20 16.45 MITER GATE ANCHORAGE

35 20 16.46 CULVERT VALVES

35 20 23 COFFERDAM AND CHANNEL EXCAVATION

35 31 19 RIVERINE STRUCTURES

35 49 23.23 25 GUARD WALLS

35 59 29 FLOATING MOORING BITTS

DIVISION 40 - PROCESS INTERCONNECTIONS

40 05 13.96 WELDING PROCESS PIPING

40 60 00 PROCESS CONTROL

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.16 JIB CRANES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 13.00 08

SUMMARY OF WORK

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 BASE CONTRACT

1.3 OPTION ONE

1.4 OPTION TWO

1.5 OPTION THREE

1.6 OPTION FOUR

1.7 OPTION FIVE

1.8 OPTION SIX

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 11 13.00 08 Page 1

SECTION 01 11 13.00 08

SUMMARY OF WORK

PART 1 GENERAL

1.1 GENERAL INFORMATION

This contract is for a new lock chamber and has been divided into a base contract and six options. Award of the awardable options will be made in accordance with Section 00 73 00 SUPPLEMENTARY CONDITIONS.

The following paragraphs are for information only to describe the general work to be performed. Actual work performed under the Base Contract and Awardable Options shall be identified on the Contract Drawings and as further herein described in the specifications.

1.2 BASE CONTRACT

The Base Contract consists of completion of a new Lock Chamber. Specific features of work under the base contract include, but are not limited to the following:

a. Pre-excavate as needed for construction.

b. Install temporary service bridge.

c. Disconnect dam side power while maintaining lock power.

d. Intall flashboards.

e. Construction the in water combination wall.

f. Demolition Upper and Lower Guard walls.

g. Construct foundation drilled shafts, and in the wet monoliths.

Construction of monoliths includes all concrete, reinforcing steel, waterstops, and associated embedded metal items.

h. Construct cofferdam.

i. Dewater the coffer area.

j. Construct Land Wall Equipment Buildings.

k. Construct in the dry monoliths. Construction of monoliths includes all concrete, reinforcing steel, waterstops, and associated embedded metal items.

l. Install Construction Instrumentation.

m. Demolition of original River Wall and Fixed Crest Weir.

n. Excavate alluvium and rock for emptying and filling culverts.

o. Construct River Wall facing.

SECTION 01 11 13.00 08 Page 2

p. Construct chamber floor.

q. Flood the coffer area.

r. Install handrails, and top of wall features and waterway signs on lock structure.

s. Install permanent instrumentation.

t. Flood River Chamber area.

u. Construction of Middle wall bull nose cell.

v. Test fit of existing Stoplogs.

w. Install waterway signs upstream and downstream of the lock.

x. Install upstream dikes.

y. Install downstream dikes.

z. Demolition of temporary downstream bridge.

aa. Construct downstream transition wall.

1.3 OPTION ONE

Option One consists of construction of the guard walls and associated items.

Specific features of work under option one include, but are not limited to the following:

a. Complete Upper and Lower Guard Walls, including structural and electrical features.

1.4 OPTION TWO

Option Two consists of Fabrication and installation of the hydraulic Steel Structure components. Specific features of work under option two include, but are not limited to the following:

a. Furnish and install filling and emptying valves, culvert bulkheads and related features.

b. Furnish and install miter gates and related features including.

1.5 OPTION THREE

Option Three consists of construction of the sills and culverts. Specific features of work under option three include, but are not limited to the following:

a. Construct upper miter sill and bulkhead sill.

b. Construct lower miter/bulkhead sill.

c. Construct filling and emptying culverts.

SECTION 01 11 13.00 08 Page 3

1.6 OPTION FOUR

Option Four consists of construction buildings, bridge, electrical and mechanical features. Specific features of work under option four, but are not limited to the following:

a. Construct Middle Wall and River Wall Equipment Buildings.

b. Construct Middle Wall Control Shelters.

c. Installation of drilled shafts, towers and permanent utility bridge.

d. Install electrical, mechanical and plumbing systems for lock and verify operation.

e. Installation of jib crane.

f. Installation of tow haulage system.

1.7 OPTION FIVE

Option Five consists of completion of removal of the cofferdam. Specific features of work under option five include, but are not limited to the following:

a. Remove cofferdam.

1.8 OPTION SIX

Option six consists of milling and overlay paving of montgomery dam road post construction.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

-- End of Section --

SECTION 01 11 13.00 08 Page 4

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 08

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 SINGLE JOB PAYMENT ITEMS

1.3.1 Reimbursement For Actual Performance And Payment Bond Premiums

1.3.2 Mobilization and Preparatory Work

1.3.2.1 Payment

1.3.2.2 Unit of Measure

1.3.2.3 Payment Item (s)

1.3.3 Demobilization

1.3.3.1 Payment

1.3.3.2 Unit of Measure

1.3.3.3 Payment Item (s)

1.3.4 Exploratory Program

1.3.4.1 Payment

1.3.4.2 Unit of Measure

1.3.4.3 Payment Item (s)

1.3.5 Instrumentation Installation

1.3.5.1 Payment

1.3.5.2 Unit of Measure

1.3.5.3 Payment Item (s)

1.3.6 Relocate Government Trailer

1.3.6.1 Payment

1.3.6.2 Unit of Measure

1.3.6.3 Payment Item (s)

1.3.7 Develop Data Management System

1.3.7.1 Payment

1.3.7.2 Unit of Measure

1.3.7.3 Payment Item (s)

1.3.8 Demolition of Existing Lock Structure

1.3.8.1 Payment

1.3.8.2 Unit of Measure

1.3.8.3 Payment Items

1.3.9 Demolition

1.3.9.1 Payment

1.3.9.2 Unit of Measure

1.3.9.3 Payment Items

1.3.10 Underwater Excavation

1.3.10.1 Payment

1.3.10.2 Unit of Measure

1.3.10.3 Payment Items

1.3.11 Remove Derrick Stone

1.3.11.1 Payment

1.3.11.2 Unit of Measure

1.3.11.3 Payment Items

SECTION 01 22 00.00 08 Page 1

1.3.12 Install Flashboards

1.3.12.1 Payment

1.3.12.2 Payment Item (s)

1.3.12.3 Unit of Measure

1.3.13 Removal of existing river chamber floor pavers

1.3.13.1 Payment

1.3.13.2 Unit of Measure

1.3.13.3 Payment Items

1.3.14 Removal and Salvage Filling and Emptying System

1.3.14.1 Payment

1.3.14.2 Unit of Measure

1.3.14.3 Payment Items

1.3.15 Port Closures

1.3.15.1 Payment

1.3.15.2 Unit of Measure

1.3.15.3 Payment Item

1.3.15.4 Gravel Access Road Area Improvements

1.3.15.4.1 Payment

1.3.15.4.2 Unit of Measure

1.3.15.4.3 Payment Item

1.3.16 Temporary Service Bridge

1.3.16.1 Payment

1.3.16.2 Unit of Measure

1.3.16.3 Payment Item

1.3.17 Demolition of Sills

1.3.17.1 Payment

1.3.17.2 Unit of Measure

1.3.17.3 Payment Items

1.3.18 Demonstration

1.3.18.1 Payment

1.3.18.2 Unit of Measure

1.3.18.3 Payment Items

1.3.19 Miter Gate Removal

1.3.19.1 Payment

1.3.19.2 Unit of Measure

1.3.19.3 Payment Items

1.3.20 Cofferdams and Closures

1.3.20.1 Payment

1.3.20.2 Unit of Measure

1.3.20.3 Payment Items

1.3.21 Cofferdam and Chamber Dewatering

1.3.21.1 Payment

1.3.21.2 Unit of Measure

1.3.21.3 Payment Items

1.3.22 New Stair Tower

1.3.22.1 Payment

1.3.22.2 Unit of Measure

1.3.22.3 Payment Items

1.3.23 Permanent Utility Bridge

1.3.23.1 Payment

1.3.23.2 Unit of Measure

1.3.23.3 Payment Item

1.3.24 Middle Wall Control Shelters

1.3.24.1 Payment

1.3.24.2 Unit of Measure

1.3.24.3 Payment Items

1.3.25 Buildings

1.3.25.1 Payment

1.3.25.2 Unit of Measure

SECTION 01 22 00.00 08 Page 2

1.3.25.3 Payment Items

1.3.26 Construct Chamber Culverts

1.3.26.1 Payment

1.3.26.2 Unit of Measure

1.3.26.3 Payment Items

1.3.27 Fabricate and Deliver Miter Gates

1.3.27.1 Payment

1.3.27.2 Unit of Measure

1.3.27.3 Payment Item (s)

1.3.28 Fabricate and Deliver Miter Gate Appurtenances

1.3.28.1 Payment

1.3.28.2 Unit of Measure

1.3.28.3 Payment Item (s)

1.3.29 Installation of Sill Seal Angle, Wall Quoin Posts, Pintle

Base and Pintle

1.3.29.1 Payment

1.3.29.2 Unit of Measure

1.3.29.3 Payment Items

1.3.30 Miscellaneous Metals

1.3.30.1 Payment

1.3.30.2 Unit of Measure

1.3.30.3 Payment Items

1.3.31 Piping Systems

1.3.31.1 Payment

1.3.31.2 Unit of Measure

1.3.31.3 Payment Item

1.3.32 Air Compressor

1.3.32.1 Payment

1.3.32.2 Unit of Measure

1.3.32.3 Payment Item

1.3.33 Temporary Power Generators

1.3.33.1 Payment

1.3.33.2 Unit of Measure

1.3.33.3 Payment Item

1.3.34 Temporary Power Supply

1.3.34.1 Payment

1.3.34.2 Unit of Measure

1.3.34.3 Payment Item

1.3.35 Electrical Work

1.3.35.1 Payment

1.3.35.2 Unit of Measure

1.3.35.3 Payment Item

1.3.36 Embedded Items for Electrical and Mechanical Systems

1.3.36.1 Payment

1.3.36.2 Unit of Measure

1.3.36.3 Payment Items

1.3.37 Intake Screen Assemblies

1.3.37.1 Payment

1.3.37.2 Unit of Measure

1.3.37.3 Payment Item

1.3.38 Removal of Protection Cell in Navigation Channel

1.3.38.1 Payment

1.3.38.2 Unit of Measure

1.3.38.3 Payment Items

1.3.39 Replace Derrick Stone

1.3.39.1 Payment

1.3.39.2 Unit of Measure

1.3.39.3 Payment Item (s)

1.3.40 Tow Haulage System

SECTION 01 22 00.00 08 Page 3

1.3.40.1 Payment

1.3.40.2 Unit of Measure

1.3.40.3 Payment Item

1.3.41 Jib Crane

1.3.41.1 Payment

1.3.41.2 Unit of Measure

1.3.41.3 Payment Item

1.3.42 Nose Cell Walkway

1.3.42.1 Payment

1.3.42.2 Unit of Measure

1.3.42.3 Payment Item

1.3.43 Guard Wall Precast Items

1.3.43.1 Payment

1.3.43.2 Unit of Measure

1.3.43.3 Payment Items

1.3.44 Pier Cap Infill

1.3.44.1 Payment

1.3.44.2 Unit of Measure

1.3.44.3 Payment Items

1.3.45 Thrust Block

1.3.45.1 Payment

1.3.45.2 Unit of Measure

1.3.45.3 Payment Items

1.3.46 Construction of Retaining Wall

1.3.46.1 Payment

1.3.46.2 Unit of Measure

1.3.46.3 Payment Items

1.3.47 Floating Mooring Bitt Anchorages

1.3.47.1 Payment

1.3.47.2 Unit of Measure

1.3.47.3 Payment Items

1.3.48 Handrail

1.3.48.1 Payment

1.3.48.2 Unit of Measure

1.3.48.3 Payment Items

1.3.49 On Site Painting

1.3.49.1 Payment

1.3.49.2 Unit of Measure

1.3.49.3 Payment Items

1.3.50 Construction of Transition Wall

1.3.50.1 Payment

1.3.50.2 Unit of Measure

1.3.50.3 Payment Items

1.3.51 Safety Critical Waterway Signs

1.3.51.1 Payment

1.3.51.2 Unit of Measure

1.3.51.3 Payment Items

1.3.52 Test Fitting of Stoplogs

1.3.52.1 Payment

1.3.52.2 Unit of Measure

1.3.52.3 Payment Item

1.3.53 Commissioning

1.3.53.1 Payment

1.3.53.2 Unit of Measure

1.3.53.3 Payment Item

1.3.54 Site Restoration

1.3.54.1 Payment

1.3.54.2 Unit of Measure

1.3.54.3 Payment Item (s)

SECTION 01 22 00.00 08 Page 4

1.3.55 Preparation of Final As-Built Drawings

1.3.55.1 Payment

1.3.55.2 Unit of Measure

1.4 UNIT PRICE PAYMENT ITEMS

1.4.1 Digital Progress Images

1.4.1.1 Payment

1.4.1.2 Measurement

1.4.1.3 Unit of Measure

1.4.1.4 Payment Items

1.4.2 Maintain Government Facilities and Government Access

1.4.2.1 Payment

1.4.2.2 Measurement

1.4.2.3 Unit of Measure

1.4.2.4 Payment Items

1.4.3 Instrumentation Monitoring Program

1.4.3.1 Payment

1.4.3.2 Measurement

1.4.3.3 Unit of Measure

1.4.3.4 Payment Items

1.4.4 Maintaining Data Management System

1.4.4.1 Payment

1.4.4.2 Measurement

1.4.4.3 Unit of Measure

1.4.4.4 Payment Items

1.4.5 Environmental Compliance Measurement, Sampling, Testing and

Reporting

1.4.5.1 Payment

1.4.5.2 Measurement

1.4.5.3 Unit of Measure

1.4.5.4 Payment Items

1.4.6 Underwater Excavation

1.4.6.1 Payment

1.4.6.2 Measurement

1.4.6.3 Unit of Measure

1.4.6.4 Payment Items

1.4.7 Rock Excavation

1.4.7.1 Payment

1.4.7.2 Measurement

1.4.7.3 Unit of Measure

1.4.7.4 Payment Items

1.4.8 Rock Excavation

1.4.8.1 Payment

1.4.8.2 Measurement

1.4.8.3 Unit of Measure

1.4.8.4 Payment Items

1.4.9 Rock Excavation

1.4.9.1 Payment

1.4.9.2 Measurement

1.4.9.3 Unit of Measure

1.4.9.4 Payment Items

1.4.10 Timber Pile Removal

1.4.10.1 Payment

1.4.10.2 Measurement

1.4.10.3 Unit of Measure

1.4.10.4 Payment Item (s)

1.4.11 Jet Grouting

1.4.11.1 Payment

1.4.11.2 Measurement

1.4.11.3 Unit of Measure

SECTION 01 22 00.00 08 Page 5

1.4.11.4 Payment Items

1.4.12 Combination wall Sheet and Pipe Piles

1.4.12.1 Payment

1.4.12.2 Measurement

1.4.12.3 Unit of Measure

1.4.12.4 Payment Items

1.4.13 Combination Wall King Piles

1.4.13.1 Payment

1.4.13.2 Measurement

1.4.13.3 Unit of Measure

1.4.13.4 Payment Item

1.4.14 Combination Wall Alluvium Excavation and Rock Sockets

1.4.14.1 Payment

1.4.14.2 Measurement

1.4.14.3 Unit of Measure

1.4.14.4 Payment Item

1.4.15 Combination Wall Concrete Infill

1.4.15.1 Payment

1.4.15.2 Measurement

1.4.15.3 Unit of Measure

1.4.15.4 Payment Items

1.4.16 Install Rock Anchors

1.4.16.1 Payment

1.4.16.2 Measurement

1.4.16.3 Unit of Measure

1.4.16.4 Payment Item

1.4.17 Drilled Shafts

1.4.17.1 Payment

1.4.17.2 Measurement

1.4.17.3 Unit of Measure

1.4.17.4 Payment Items

1.4.18 Pipe Piles

1.4.18.1 Payment

1.4.18.2 Measurement

1.4.18.3 Unit of Measure

1.4.18.4 Payment Items

1.4.19 Portland Cement

1.4.19.1 Payment

1.4.19.2 Measurement

1.4.19.3 Unit of Measure

1.4.19.4 Payment Items

1.4.20 Fly Ash

1.4.20.1 Payment

1.4.20.2 Measurement

1.4.20.3 Unit of Measure

1.4.20.4 Payment Items

1.4.21 Blast Furnace Slag

1.4.21.1 Payment

1.4.21.2 Measurement

1.4.21.3 Unit of Measure

1.4.21.4 Payment Items

1.4.22 Silica Fume

1.4.22.1 Payment

1.4.22.2 Measurement

1.4.22.3 Unit of Measure

1.4.22.4 Payment Items

1.4.23 Production, Transportation and Placement of Concrete

1.4.23.1 Payment

1.4.23.2 Measurement

SECTION 01 22 00.00 08 Page 6

1.4.23.3 Unit of Measure

1.4.23.4 Payment Items

1.4.24 Design, Production, Transportation and Placement of Concrete

1.4.24.1 Payment

1.4.24.2 Measurement

1.4.24.3 Unit of Measure

1.4.24.4 Payment Items

1.4.25 Dental Excavation and Dental Concrete

1.4.25.1 Payment

1.4.25.2 Measurement

1.4.25.3 Unit of Measure

1.4.25.4 Payment Items

1.4.26 Steel Piling

1.4.26.1 Payment

1.4.26.2 Measurement

1.4.26.3 Unit of Measure

1.4.26.4 Payment Items

1.4.27 Rock Fill

1.4.27.1 Payment

1.4.27.2 Measurement

1.4.27.3 Unit of Measure

1.4.28 Aggregate Cap

1.4.28.1 Payment

1.4.28.2 Measurement

1.4.28.3 Unit of Measure

1.4.29 Monthly Dewatering

1.4.29.1 Payment

1.4.29.2 Measurement

1.4.29.3 Unit of Measure

1.4.29.4 Payment Items

1.4.30 Drill Weep Holes

1.4.30.1 Payment

1.4.30.2 Measurement

1.4.30.3 Unit of Measure

1.4.30.4 Payment Items

1.4.31 Waterstops

1.4.31.1 Payment

1.4.31.2 Measurement

1.4.31.3 Unit of Measure

1.4.31.4 Payment Items

1.4.32 Furnish and Install Filling and Emptying Valves

1.4.32.1 Payment

1.4.32.2 Measurement

1.4.32.3 Unit of Measure

1.4.32.4 Payment Items

1.4.33 Fabricate and Deliver Bulkheads

1.4.33.1 Payment

1.4.33.2 Measurement

1.4.33.3 Unit of Measure

1.4.33.4 Payment Items

1.4.34 Furnish and Install Gate Operating Machinery

1.4.34.1 Payment

1.4.34.2 Measurement

1.4.34.3 Unit of Measure

1.4.34.4 Payment Item

1.4.35 Miter Gates

1.4.35.1 Payment

1.4.35.2 Measurement

1.4.35.3 Unit of Measure

SECTION 01 22 00.00 08 Page 7

1.4.35.4 Payment Items

1.4.36 Wall Armor

1.4.36.1 Payment

1.4.36.2 Measurement

1.4.36.3 Unit of Measure

1.4.36.4 Payment Items

1.4.37 Corner Protection

1.4.37.1 Payment

1.4.37.2 Measurement

1.4.37.3 Unit of Measure

1.4.37.4 Payment Items

1.4.38 Corner Castings

1.4.38.1 Payment

1.4.38.2 Measurement

1.4.38.3 Unit of Measure

1.4.38.4 Payment Items

1.4.39 Floating Mooring Bitts

1.4.39.1 Payment

1.4.39.2 Measurement

1.4.39.3 Unit of Measure

1.4.39.4 Payment Items

1.4.40 Line Hooks and Guards

1.4.40.1 Payment

1.4.40.2 Measurement

1.4.40.3 Unit of Measure

1.4.40.4 Payment Items

1.4.41 Check Posts

1.4.41.1 Payment

1.4.41.2 Measurement

1.4.41.3 Unit of Measure

1.4.41.4 Payment Items

1.4.42 Riprap

1.4.42.1 Payment

1.4.42.2 Measurement

1.4.42.3 Unit of Measure

1.4.42.4 Payment Item (s)

1.4.43 Deformed Steel Bars for Concrete Reinforcement

1.4.43.1 Payment

1.4.43.2 Measurement

1.4.43.3 Unit of Measure

1.4.43.4 Payment Item (s)

1.4.44 Bituminous Pavement

1.4.44.1 Payment

1.4.44.2 Measurement

1.4.44.3 Unit of Measure

1.4.44.4 Payment Item

1.4.45 Ladders

1.4.45.1 Payment

1.4.45.2 Measurement

1.4.45.3 Unit of Measure

1.4.45.4 Payment Item

1.4.46 Rock Dikes

1.4.46.1 Payment

1.4.46.2 Measurement

1.4.46.3 Unit of Measure

1.4.46.4 Payment Items

1.4.47 Dewater and Cleanup of Cofferdam Post Flood Event

1.4.47.1 Payment

1.4.47.2 Measurement

SECTION 01 22 00.00 08 Page 8

1.4.47.3 Unit of Measure

1.4.47.4 Payment Items

1.4.48 Government Directed Evacuation of Cofferdam

1.4.48.1 Payment

1.4.48.2 Measurement

1.4.48.3 Unit of Measure

1.4.48.4 Payment Items

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 CONTRACT COST BREAKDOWN

-- End of Section Table of Contents --

SECTION 01 22 00.00 08 Page 9

SECTION 01 22 00.00 08

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A615/A615M (2020) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Weight Certificates

1.3 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the SCHEDULE and described below.

All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.3.1 Reimbursement For Actual Performance And Payment Bond Premiums

Payment for reimbursement for actual performance and payment bond premiums will be made as specified in 00 70 00 CONDITIONS OF THE CONTRACT, clause

PAYMENT FOR PERFORMANCE AND PAYMENT BONDS.

0001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

BASE CONTRACT

1001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

AWARDABLE OPTION 1

2001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

SECTION 01 22 00.00 08 Page 10

AWARDABLE OPTION 2

3001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

AWARDABLE OPTION 3

4001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

AWARDABLE OPTION 4

5001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

AWARDABLE OPTION 5

6001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

AWARDABLE OPTION 5

1.3.2 Mobilization and Preparatory Work

1.3.2.1 Payment

Payment will be made for costs associated with mobilization of plant equipment for work preparatory to beginning actual construction of the cutoff wall, as defined in Section 00 73 00 SUPPLEMENTARY CONDITIONS, paragraph DFARS 252.236-7003 PAYMENT FOR MOBILIZATION AND PREPARATORY WORK.

The Contractor shall provide supporting documentation for payment of each item in accordance with Section 00 70 00 CONDITIONS OF THE CONTRACT, paragraph DFARS 252.236-7003 PAYMENT FOR MOBILIZATION AND PREPARATORY WORK, and shall not receive payment until the Contracting Officer has receipts to prove that payment for all items claimed have been validated.

All construction plant, material, equipment, and the mobilization and preparatory work shall be performed and determined to be suitable for efficiency in performing the work before payment is made.

Payment for mobilization and preparatory work will include, but not limited to:

a. Mobilization and setup of Contractor-furnished plant and equipment

b. Furnishing and setup of temporary Contractor facilities including offices, storage, and testing facilities (including furnishing and validating QC/QA Lab)

d. Construction of temporary access and haul roads

e. Construction of slurry ponds, and associated facilities

f. Development of laydown areas

g. Initial survey and mapping

h. Construction of environmental protection and temporary storm water pollution control features and instrumentation

i. Other site development needed for the job prior to construction of the new lock chamber and other associated features

j. Disposal of any necessary materials associated with mobilization and preparatory work in accordance with Section 01 74 19.00 08 DISPOSAL

k. Development of major submittals in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Payment for development of a submittal will not be made until approval of the submittal by the Contracting Officer or designated representative.

1.3.2.2 Unit of Measure

Unit of measure: Job.

1.3.2.3 Payment Item (s)

0004 MOBILIZATION AND PREPARATORY WORK

SECTION 01 22 00.00 08 Page 11

1.3.3 Demobilization

1.3.3.1 Payment

Payment will be made for costs associated with removal and demobilization of plant, equipment and temporary facilities upon completion of construction of the required features. Payment shall include disassembly and removal from the site of plant, equipment and facilities and transportation of excess and unused materials. Payment shall also include removal of the three Government field office trailers. Payment for restoration of work areas will be made as specified for Site Restoration

1.3.3.2 Unit of Measure

Unit of measure: Job.

1.3.3.3 Payment Item (s)

0005 DEMOBILIZATION

1.3.4 Exploratory Program

1.3.4.1 Payment

Payment will as specified in Section 02 32 00 FOUNDATION VERIFICATION DRILLING, SAMPLING, AND RECORDING and be made for costs associated with operations necessary for all exploratory drilling the contractor has to conduct prior to construction.

1.3.4.2 Unit of Measure

Unit of measure: Job.

1.3.4.3 Payment Item (s)

0008 EXPLORATORY PROGRAM

1.3.5 Instrumentation Installation

1.3.5.1 Payment

Payment will be made for costs associated with installation of instrumentation equipment, as specified in Section 13 50 00 INSTRUMENTATION PROGRAM. Payment for this item shall constitute full compensation for all labor, equipment, material and supply costs to install all required monitoring instrumentation.

1.3.5.2 Unit of Measure

Unit of measure: Job.

1.3.5.3 Payment Item (s)

0009 INSTRUMENTATION INSTALLATION

SECTION 01 22 00.00 08 Page 12

1.3.6 Relocate Government Trailer

1.3.6.1 Payment

Payment will be made for costs associated with operations necessary for relocation of the existing single wide government trailer that is already on site. Payment will constitute full compensation all labor, equipment, materials and supplies required to move the trailer, reconnect electrical and telecom lines to the trailer.

1.3.6.2 Unit of Measure

Unit of measure: Job.

1.3.6.3 Payment Item (s)

0011 RELOCATE GOVERNMENT TRAILER

1.3.7 Develop Data Management System

1.3.7.1 Payment

Payment will be made for costs associated with developing the data management system, as specified in Section 01 31 00.00 08 DATA MANAGEMENT.

Related costs include all preconstruction submittals, data management planning meeting with the Government, development of the enterprise database and REST services, developing scripts for uploading data into the data management system, and transferring data files and reports to the

SFTP.

1.3.7.2 Unit of Measure

Unit of measure: Job.

1.3.7.3 Payment Item (s)

0012 DEVELOP DATA MANAGEMENT SYSTEM

1.3.8 Demolition of Existing Lock Structure

1.3.8.1 Payment

Payment for these items shall constitute full compensation for all labor, equipment, material and supply costs to demolish and remove the features as indicated and specified to the extent shown, and to protect adjacent features to remain. Payment shall also include all costs for transporting and disposal of all debris. Payment shall include all advanced planning and engineering and all other incidental costs to perform the demolition, as shown on the contract drawings and specified. The individual demolition items are defined as follows:

a. REMOVE FOOTBRIDGE SPAN includes termination of existing electrical and communications lines, modifying and recapping the existing compressed air line, removal of the footbridge from the original Middle Wall support tower to Dam Pier 1, and removal of support beams as indicated.

b. DEMOLITION OF RIVER WALL BUILDING includes removal of the River Wall building and all associated utilities.

SECTION 01 22 00.00 08 Page 13

1.3.8.2 Unit of Measure

Unit of Measure: JOB

1.3.8.3 Payment Items

0015 REMOVE AND DISPOSE EXISTING FOOTBRIDGE

0039 DEMOLITION OF RIVER WALL BUILDING

1.3.9 Demolition

1.3.9.1 Payment

Payment for these items shall constitute full compensation for all labor, equipment, material and supply costs to demolish and remove the features as indicated and specified in Section 02 41 00.00 08 DEMOLITION and to the extent shown, and to protect adjacent features to remain. Payment shall also include all costs for removal of the rubble from the river and transporting and disposal of all debris per specification 01 74 19.00 08 DISPOSAL. Payment shall include all advanced planning and engineering and all other incidental costs to perform the demolition, as shown on the contract drawings and specified. Payment shall also include removal of miscellaneous metals, steel H-piles, and steel sheet piling.

1.3.9.2 Unit of Measure

Unit of Measure: Job.

1.3.9.3 Payment Items

0016 DEMOLITION OF FIXED CREST WEIR

0017 DEMOLITION OF APRON

0031 DEMOLITION OF UPPER GUARD WALL EXTENSION CELLS

0032 DEMOLITION OF UPPER GUARD WALL

0033 DEMOLITION OF LOWER GUARD WALL

0040 DEMOLITION OF RIVER WALL

0044 DEMOLITION OF LOCK FLOOR CONCRETE

1.3.10 Underwater Excavation

1.3.10.1 Payment

Payment for these items shall constitute full compensation for all labor, equipment, material and supply costs for performing the work including:

excavating; transportation and disposal of material as described in 31 23 05 MASS EXCAVATION, control of effluents from the Contractor's operations; performing measurements for payment; and all other incidental costs in connection with these aspects of the work under this contract.

1.3.10.2 Unit of Measure

Unit of Measure: Job.

1.3.10.3 Payment Items

0019 REMOVAL OF GRANULAR FILL UNDER APRON

SECTION 01 22 00.00 08 Page 14

1.3.11 Remove Derrick Stone

1.3.11.1 Payment

Payment for these items shall constitute full compensation for all labor, equipment, material and supply costs for performing the excavating of derrick stone; transportation and temporarily storing of excavated materials, control of effluents from the Contractor's operations;

performing measurements for payment; and all other incidental costs in connection with these aspects of the work under this contract.

1.3.11.2 Unit of Measure

Unit of Measure: Job.

1.3.11.3 Payment Items

0020 REMOVE DERRICK STONE

1.3.12 Install Flashboards

1.3.12.1 Payment

Work shall be performed as specified in section 01 35 00.00 08 SPECIAL PROCEDURES. Payment will be made for reuse of existing flashboards or the costs associated with purchasing all supplies, as the contractor chooses, and installation of flashboards on top of fixed crest portion of the dam and removal upon completion of work and placement in Government designated area on-site.

1.3.12.2 Payment Item (s)

0021 INSTALLATION OF FLASHBOARDS

1.3.12.3 Unit of Measure

Unit of measure: job.

1.3.13 Removal of existing river chamber floor pavers

1.3.13.1 Payment

Payment for this items shall constitute full compensation for all labor, equipment, material and supply costs to demolish and remove the features as specified and as shown on the contract drawings.

1.3.13.2 Unit of Measure

Unit of Measure: JOB

1.3.13.3 Payment Items

0030 REMOVAL OF EXISTING RIVER CHAMBER FLOOR PAVERS

1.3.14 Removal and Salvage Filling and Emptying System

1.3.14.1 Payment

Payment for this items shall constitute full compensation for all labor, SECTION 01 22 00.00 08 Page 15 equipment, material and supply costs to demolish and remove the features as specified and as shown on the contract drawings.

1.3.14.2 Unit of Measure

Unit of Measure: JOB

1.3.14.3 Payment Items

0035 REMOVE AND SALVAGE FILLING AND EMPTYING SYSTEM

1.3.15 Port Closures

1.3.15.1 Payment

Payment for construction of the port closures at original Middle Wall shall constitute full compensation for all labor, equipment, material and supply costs for shop and field fabrications; performing measurements for payment; testing of materials and products incorporated into the work; all advanced planning and engineering; and all other incidental costs in connection with these aspects of the work under this contract.

1.3.15.2 Unit of Measure

Unit of measure: JOB.

1.3.15.3 Payment Item

0034 CLOSE UPPER AND LOWER FILLING AND EMPTYING PORTS

1.3.15.4 Gravel Access Road Area Improvements

1.3.15.4.1 Payment

Payment for the gravel access road area improvements shall constitute full compensation for all labor, equipment, material and supply costs to construct the temporary downstream bridge gravel access road, including required fill, new storm drainage system including piping, manhole, inlets, and endwall, and riprap out fall. All work completed as shown on the plans and specified.

1.3.15.4.2 Unit of Measure

Unit of measure: Job.

1.3.15.4.3 Payment Item

0037 GRAVEL ACCESS ROAD AREA IMPROVEMENTS,…