Attachment 1 - Scope of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W911WN19T8008_0003.pdf | ||
| W911WN19T8008_0002.pdf | ||
| Attachment_2_-_Photos.pdf | ||
| Attachment_3_-_Accident_Prevention_Plan.docx | DOCX document | |
| Attachment_4_-_Quality_Control_Plan.docx | DOCX document | |
| Attachment_5_-_Wage_Determination.pdf | ||
| W911WN19T8008.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 11 00.00 08
SUMMARY OF WORK
PART 1 GENERAL REQUIREMENTS
1.1 LOCATION AND DESCRIPTION OF WORK
The work is located at the Bossard Nature Area, 22000 PA Route 198, Saegertown PA 16433, near Woodcock Dam. The site of the work may be reached from state roads.
The general description of the work is to furnish all equipment, labor, materials, layout of work, and supervision to improve the existing bituminous-surfaced entrance road and parking area in accordance with the following specifications and as shown contract drawings.
The proposed improvements include placing leveling course to level existing surface, placement of new wearing course asphalt, furnishing new parking bumpers, and repainting all parking lanes.
All work, including cleanup of the premises, shall be completed as follows no later than 60 calendar days after the date of receipt of the Notice to Proceed.
1.2 SAFETY
All work shall be performed in accordance with the Corps of Engineers Safety Manual EM385-1-1. Latest version includes updates 1 through 15 and is available online at:
http://www.usace.army.mil/CESO/pages/home.aspx.
The Contractor shall complete and submit an Accident Prevention Plan. A template/example of an Accident Prevention Plan is included in this specification as a separate attachment. The Contractor shall modify and edit the attached Accident Prevention Plan to reflect the project's scope of work.
Safety features shall include, but not be limited to:
- Safety Shoes: All employees engaged in construction operations shall wear safety shoes meeting the requirements of EM 385-1-1, Section 05.E.
- Protective Eyewear: All workers on the site shall wear, as a minimum, protective eyewear meeting the requirements of EM 385-1-1, Section 05.A. Additional eye protection may be required in accordance with EM 385-1-1, Section 05.B.
- Hearing Protection: Hearing protection shall be provided for workers in accordance with EM 385-1-1, Section 05.C.
- Protective Headgear: All workers on the site shall wear protective headgear in accordance with EM 385-1-1, Section 05.D.
http://www.usace.army.mil/CESO/pages/home.aspx.
- Employee Acknowledgement: All personnel used during this contract, including those of subcontractors, shall sign a formal written notice supplied by the Contractor, attesting that they have been provided and will utilize the above required safety equipment. Copies of these signed acknowledgements shall be furnished to the Contracting Officer.
- Safe Access: Safe access shall be continuously provided for project personnel and personnel of the Contracting Officer. Access shall be provided and maintained during every phase of the operations.
1.3 PROJECT SUBMITTALS
The Contractor shall provide submittals for Government review. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications.
1.3.1 Submittals
The following is a list of submittals required under each section of the Specifications. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Accident Prevention Plan; G, RO
Environmental Protection Plan; G, RO
Traffic Control Plan; G, RO
Verification of Field Conditions; G, RO E-Verify; G, RO
Bituminous Tack and Prime Coat Waybills and Delivery Tickets
Hot Mix Bituminous Materials Certificates; G, RO
Hot Mix Surface Smoothness Test Field Reports; G, RO
Hot Mix Waybills and Delivery Tickets; G, RO
Pavement Marking Paint Product Data; G, RO
Pavement Marking Paint Safety Data Sheets
Pavement Marking Paint Manufacturer's Instructions
1.4 Environmental Protection Plan
The Contractor shall submit an Environmental Protection Plan for review.
The Environmental Protection Plan shall include procedures to provide for safe conduct of the work, protection of property, equipment and machinery which is to remain undisturbed, protection and support of existing features. The plan shall include a detailed description of the proposed method(s) and equipment to be used.
1.5 Traffic Control Plan
The Contractor shall submit a Traffic Control Plan for review. The Traffic Control Plan shall include procedures to provide for safe conduct of the work, protection of the Public, protection of property, and equipment and machinery. The plan shall include a detailed description of the proposed method(s) and equipment to be used. The plan shall comply with the appropriate provisions of PennDOT Publication 213, “Temporary Traffic Control Guidelines”.
1.6 QUALITY CONTROL PLAN
The Contractor shall complete and submit the Quality Control Plan (separate attachment) included with this specification. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements, covers all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer
1.7 COORDINATION MEETING AND POINTS OF CONTACT
Prior to commencement of any work being performed on site, the Contractor shall participate in the preconstruction meeting with the Administrative Contracting Officer (ACO) and the Resident Engineer.
Ms. Denise M. Polizzano, Resident Engineer Upper Ohio Area Office 3510 Grand Ave.
Pittsburgh, PA 15225
(412) 395-7680
1.8 VERIFICATION OF FIELD CONDITIONS
The Contractor shall verify all dimensions and condition in the field and shall advise the Contracting Officer of any discrepancy before performing any work.
1.9 PROJECT/SITE CONDITIONS
1.9.1 Work Areas
As required by 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-10 OPERATIONS AND STORAGE AREAS, all operations of the Contractor shall be confined to areas shown on the drawings required to accomplish the work under this contract, and as authorized and approved by the Contracting Officer. All work areas shall be coordinated with the Contracting Officer prior to commencement of work.
1.9.2 Storage Areas
A storage area for materials and equipment will be provided as shown on the drawings at a location designated by the Contracting Officer. Use of the storage area shall not interfere with Government personnel in the operation of the project.
1.9.3 Utilities
The Contractor shall provide all necessary utilities.
1.9.4 Time of Performance
The Contractor shall confine all operations at the work site between 7:30 AM and 4:00 PM, Monday through Friday, unless otherwise approved. Work will not be permitted on weekends or Federal Holidays unless otherwise approved.
1.10 DUST CONTROL
Dust resulting from site activities shall be controlled to prevent the spread of dust to avoid creation of a nuisance in the surrounding area.
Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding, and pollution.
1.11 ENVIRONMENTAL PROTECTION
Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction and associated activities. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.
Minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work must be protected during the entire duration of this contract. Comply with all applicable environmental Federal, State, and local laws and regulations.
Any delays resulting from failure to comply with environmental laws and regulations will be the Contractor's responsibility.
Waste water from construction activities will not be allowed to enter waterways or to be discharged prior to being treated to remove pollutants.
Dispose of the construction related waste water off-Government property in accordance with Federal, State, and Local laws and regulations. Secondary containment will be required for debris or waste water. Spill containment and cleanup supplies shall be furnished by the Contractor and kept onsite.
Any spills or releases of debris into the water or other environmental violations shall be immediately reported to the Contracting Officer.
1.12 PROTECTION OF GOVERNMENT PROPERTY
The Contractor shall protect all Government property during the performance of this contract. All damage to existing Government property as a result of Contractor's work shall be repaired or replaced to the satisfaction of the Contracting Officer. Work area shall be cleaned by the Contractor daily as needed and after construction is complete. Before beginning any concrete saw cutting work, carefully survey the structure to determine the extent of the work. Take all necessary precautions to insure against damage to existing concrete or other structures to remain in place, and repair or replace any damage to such items as approved by the Contracting Officer at no additional cost to the Government.
1.13 PROTECTION OF PERSONNEL
Ensure that adequate measures are in place to protect workers, facility operation personnel, and the public from injury due to operations being performed. All protective measures shall be in accordance with EM 385-1-1.
1.14 IDENTIFICATION OF EMPLOYEES
The Contractor shall be responsible for furnishing an identification badge/card to each employee prior to the employee working onsite and for requiring each employee engaged on the work to display identification.
Identification shall consist of name tags with the name of the Contractor and the employee's name. Additionally, a valid state driver's license or other Government issued photo identification card is required for positive identification.
1.15 SECURITY REQUIREMENTS
This paragraph contains information for security requirements for work on Government property. The purpose of these security requirements is to ensure that all Contractor and subcontractor employees working on this contract have received proper clearance for access to Government property.
Identification of critical infrastructure and submission of required employee identification will be discussed at the Preconstruction Meeting.
Required employee information shall be submitted to the Contracting Officer or Pittsburgh Office of Security and Law Enforcement, as applicable, at least 15 calendar days prior to required employee access to the project.
1.15.1 Access and General Protection/Security Policy and Procedures
The contractor and all associated subcontractors' employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government Representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation the U.S. Army Corps of Engineers (USACE) Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
The contractor must submit the full name, Social Security Number or valid state driver's license number (with state of issue), Date of Birth, and Place of Birth for all associated contractor or subcontractor employees to the USACE Security Office, Stephen Davidson, 412-395-7504, stephen.davidson@usace.army.mil or Joseph M. Bali, 412-395-7162, joseph.m.bali@usace.army.mil . The information may be submitted via email directly to the security office or by fax at 412-395-7173, all requests for background checks must contain the required identifying information, the location of work (USACE Project Name), and the USACE COR. The District retains the right to deny any contractor and subcontractor employee from working on one of its contracts based on final background investigation results.
1.15.2 Access Control
All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
1.15.3 Anti-Terrorism (AT) Level I Training
All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:
https://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the Requiring Activity Antiterrorism Officer (RA ATO) in presentation form which will be documented via memorandum."
1.15.4 Suspicious Activity Reporting Training
The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
1.15.5 Employee Identification and Background Check
The Contractor shall be responsible for furnishing an identification badge/card to each employee prior to the employee working on-site and for requiring each employee engaged on the work to display identification.
Identification shall consist of name tags with the name of the Contractor and the employee's name. Additionally, a valid state driver's license or other Government-issued photo identification card is required for positive identification. Each employee will be subject to a background check in accordance with "Homeland Security Presidential Directive (HSPD) 12:
Policy for a Common Identification Standard for Federal Employees and Contractors" (HSPD-12). Only those individual employees that were specifically identified and approved will be cleared to work on Government property.
1.15.6 E-Verify
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
1.15.7 Changes in Security Requirements
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, US Army Force Protection Measures, regulation or policy changes, etc. Changes to any security requirements shall be added to the contract by modification.
The Pittsburgh District Office of Security and Law Enforcement may be contacted by phone or e-mail at the following number/address:
Steve Davidson Phone: 412-395-7504 E-mail: stephen.davidson@usace.army.mil https://jko.jten.mil/courses/atl1/launch.html http://www.uscis.gov/e-verify) mailto:stephen.davidson@usace.army.mil
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.1.1 General
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.2 Reimbursement For Actual Performance And Payment Bond Premiums
Payment for reimbursement for actual performance and payment bond premiums will be made as specified in 00 73 00 SUPPLEMENTARY CONDITIONS, clause
PAYMENT FOR PERFORMANCE AND PAYMENT BONDS.
1.1.2.1 Unit of Measure
Unit of Measure: Job
1.1.2.2 Payment Items
0001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BONDS PREMIUMS
1001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BONDS PREMIUMS,
AWARDABLE OPTION
1.1.3 Pavement Markings and Bumpers
The quantities of pavement striping or markings and furnishing of new parking bumpers will be paid for at the contract unit price. The payment constitutes full compensation for furnishing all labor, materials, tools, equipment, appliances, and doing all work involved in preparing and marking the pavements and furnishing parking bumpers to return them to their current condition. Remove and replace striping or markings which do not conform to the required physical characteristics, alignment or location required at no cost to the Government.
1.1.3.1 Unit of Measure
Unit of Measure: Job
1.1.3.2 Payment Items
1004 PARKING AREA: REPAINT PARKING LANES AND FURNISH NEW BUMPERS
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 General
Payment items for the work of this contract on which the contract progress payments will be based are listed in the PRICE SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.2.3 Bituminous Pavement
1.2.3.1 Payment
This work is specified in Section 32 12 16.00 08 BITUMINOUS PAVEMENT CONSTRUCTION. Payments for bituminous binder course and bituminous wearing course shall constitute full compensation for furnishing all materials, equipment, plant, and tools; and for labor and other incidentals necessary to complete the work required as specified, including, but not limited to, base preparation (aggregate) and joint treatment at the interfaces of new paving with existing paving. No separate payment will be made for bituminous tack coat, and all costs in connection therewith shall be included in the applicable pavement to which the work applies.
1.2.3.2 Measurement
The area of bituminous binder or wearing course in place and accepted will be determined by a two-dimensional measurement of the actual area of pavement, properly placed and compacted to the specified thickness. The Contracting Officer shall approve all methods and procedures for quantity surveys. Quantities shall be calculated in square yards in place.
1.2.3.3 Unit of Measure
Unit of measure: Square Yards.
1.2.3.4 Payment Items
0002 ENTRANCE ROAD: BITUMINOUS BINDER COURSE, 2-1/2" THICK (SUPERPAVE HMA 19.0 MM) 0003 ENTRANCE ROAD: BITUMINOUS WEARING COURSE, 1-1/2" THICK (SUPERPAVE HMA 9.5 MM) 1002 PARKING AREA: BITUMINOUS BINDER COURSE, 2-1/2" THICK (SUPERPAVE HMA 19.0 MM), AWARDABLE OPTION
1003 PARKING AREA: BITUMINOUS WEARING COURSE, 1-1/2" THICK (SUPERPAVE HMA 9.5 MM), AWARDABLE OPTION
SECTION 01 30 00.00 08
ADMINISTRATIVE REQUIREMENTS
1.1 SUMMARY
This sections contains contract administrative requirements which are not covered in Section 00 70 00 CONDITIONS OF THE CONTRACT or Section 00 73 00
SUPPLEMENTARY CONDITIONS.
1.2 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual
1.3 ACRONYMS
DFARS - Defense Federal Acquisition Regulations Supplement EP - Engineer Pamphlet FAR - Federal Acquisition Regulations SAT - Simplified Acquisition Threshold UAI - USACE Acquisition Instructions
1.6 SUPERVISION
1.7.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.7.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years’ experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.7.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.7.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.8 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, the contractor shall participate in a pre-work conference with the ACO to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.9 WORK UNDER OTHER CONTRACTS
Attention is directed to the fact that other Contractors may be employed by the Government or by local interests at or in the vicinity of the work covered by these specifications. All Contractors shall have equal rights to the use of all roads and grounds so far as practicable and this Contractor shall cooperate with other Contractors so that the work may be performed with the maximum efficiency. Should a disagreement occur between Contractors as to the use of facilities or in other matters, the decision of the Contracting Officer shall govern.
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the clause entitled "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.
(1) The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. This delay must be beyond the control and without the fault or negligence of the Contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON (5) DAY
WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
15 12 8 7 6 5 5 5 4 5 7 13
c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more on the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b. above, the Contracting Officer will convert any qualifying delays to work days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the clause entitled, "Default (Fixed-Price Construction)".
d. The anticipated adverse weather work days listed above are based on days with precipitation greater than 0.1 inch and/or maximum temperature below 32 degrees F. The numbers shown represent the number of work days (not calendar days) normally expected to have these particular weather conditions based on historical data. The actual number of days will vary. This information is furnished for computation of possible time extensions due to weather delays and is not intended to imply that no work can be done on these days. The Contractor shall make his own determination of the effect of these conditions on his operations under this contract, and schedule his work accordingly.
1.11 WORK PERFORMED BY CONTRACTOR
Within ten (10) calendar days after award of the contract, the successful Contractor will be required to furnish a description of the work which he intends to perform with his own organization, the percentage of the total work this represents, and the estimated cost thereof.
1.12 PAYMENT FOR PERFORMANCE AND PAYMENT BONDS
a. In order to ensure that sufficient funds have been set-aside for payment of performance and payment bond premiums, bidders shall insert in Items No. 0001 and 1001, an appropriate not-to-exceed dollar amount. Failure of bidders to insert a not-to-exceed dollar amount in Item No. 0001 and 1001 will cause the quote to be rejected as non-responsive.
b. The Contractor shall be reimbursed the actual bond costs only, as established by evidence of full payment to the surety, up to the dollar amount set forth in Item No. 0001 and 1001. In no case will the Contractor be reimbursed an amount which exceeds the dollar amount set forth in Item No. 0001 or 1001.
c. The Government will reimburse only the Prime Contractor for actual paid bond premiums. The Government will not reimburse any subcontractor's paid bond premiums.
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
NOT USED
-- End of Section --
SECTION 32 12 13 Page 2
SECTION 32 12 13
BITUMINOUS TACK AND PRIME COATS
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D2995 (1999; R 2009) Determining Application
Rate of Bituminous Distributors
PENNSYLVANIA DEPARTMENT OF TRANSPORTATION (PDT)
PDT 213 (2014) Temporary Traffic Control Guidelines PDT 408 (2016) Specifications
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
SD-03 Product Data
Waybills and Delivery Tickets
1.3 QUALITY ASSURANCE
Certificates of compliance for asphalt materials delivered will be obtained and checked to ensure that specification requirements are met. Quantities of applied material will be determined. Payment will be for amount of residual asphalt applied. Tack coat materials will not be diluted. Prime coat materials when emulsions are used can be diluted on site with potable water up to 1 part emulsion to 1 part water.
1.4 DELIVERY, STORAGE, AND HANDLING
Inspect the materials delivered to the site for contamination and damage.
Unload and store the materials with a minimum of handling.
1.5 EQUIPMENT, TOOLS AND MACHINES
1.5.1 General Requirements
Equipment, tools and machines used in the work are subject to approval.
Maintain in a satisfactory working condition at all times. Calibrate equipment such as asphalt distributors, scales, batching equipment, spreaders and similar equipment within 12 months of their use. If the calibration expires during project, recalibrate the equipment before work
SECTION 32 12 13 Page 3 can continue.
1.5.2 Bituminous Distributor
Provide a self-propelled distributor with pneumatic tires of such size and number to prevent rutting, shoving or otherwise damaging the surface being sprayed. Calibrate the distributer in accordance with ASTM D2995. Design and equip the distributor to spray the bituminous material in a uniform coverage at the specified temperature, at readily determined and controlled total liquid rates from 0.03 to 1.0 gallons per square yard, with a pressure range of 25 to 75 psi and with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths. Include with the distributor equipment a separate power unit for the bitumen pump, full-circulation spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor. The distributor will be capable of circulating and agitating the bituminous material during the heating process.
1.5.3 Heating Equipment for Storage Tanks
Use steam, electric, or hot oil heaters for heating the bituminous material. Provide steam heaters consisting of steam coils and equipment for producing steam, so designed that the steam cannot come in contact with the bituminous material. Fix an armored thermometer to the tank with a temperature range from 40 to 400 degrees F so that the temperature of the bituminous material may be determined at all times.
1.5.4 Power Brooms and Power Blowers
Use power brooms and power blowers suitable for cleaning the surfaces to which the bituminous coat is to be applied.
1.6 ENVIRONMENTAL REQUIREMENTS
Apply bituminous coat only when the surface to receive the bituminous coat is dry. A limited amount of moisture (approximately 0.03 gallon/square yard ) can be sprayed on the surface of unbound material when prime coat is used to improve coverage and penetration of asphalt material. Apply bituminous coat only when the atmospheric temperature in the shade is 50 degrees F or above and when the temperature has not been below 35 degrees F for the 12 hours prior to application, unless otherwise directed.
2.1 PRIME COAT
Prime coating of aggregate base course is NOT required for this project.
2.2 TACK COAT
Bituminous tack coat shall conform to PDT 408, Section 460, with the exception that the application rate shall be not less than 0.05 gallons per square yard of surface area, and no dry fine aggregate to blot excess prime coat will be necessary. Application rate may be varied to suit actual field conditions as directed by the Contracting Officer.
SECTION 32 12 13 Page 4
2.3 WAYBILLS AND DELIVERY TICKETS
Submit waybills and delivery tickets, during progress of the work. Before the final statement is allowed, file with the Contracting Officer certified waybills and certified delivery tickets for all bituminous materials used in the construction of the pavement covered by the contract. These submittals are required for Unit Pricing bid only. Do not remove bituminous material from storage until the initial outage and temperature measurements have been taken. The delivery or storage units will not be released until the final outage has been taken.
PART 3 EXECUTION
3.1 PREPARATION OF SURFACE
Immediately before applying the bituminous coat, remove all loose material, dirt, clay, or other objectionable material from the surface to be treated by means of a power broom or blower supplemented with hand brooms. Apply treatment only when the surface is dry and clean.
3.2 APPLICATION RATE
The exact quantities within the range specified, which may be varied to suit field conditions, will be determined by the Contracting Officer.
3.2.1 Tack Coat
Apply bituminous material for the tack coat in quantities of not less than
0.03 gallons nor more than 0.10 gallons per square yard of residual asphalt onto the pavement surface as approved by the Contracting Officer. Do not dilute asphalt emulsion when used as a tack coat.
3.3 APPLICATION TEMPERATURE
3.3.1 Viscosity Relationship
Apply asphalt at a temperature that will provide a viscosity between 10 and 60 seconds, Saybolt Furol, or between 20 and 120 centistokes, kinematic.
Furnish the temperature viscosity relation to the Contracting Officer.
3.3.2 Temperature Ranges
The viscosity requirements determine the application temperature to be used. The following is a normal range of application temperatures:
Cutback Asphalts
MC-30 85-190 degrees F
SC-70, MC-70,
RC-70
120-225 degrees F
SC-250, MC-250,
RC-250
165-270 degrees F
Asphalt Emulsion
All Grades 70-160 degrees F
SECTION 32 12 13 Page 5
Cutback Asphalts
Asphalt Cement
All Grades 275-350 degrees F
Some of these temperatures for rapid cure cutbacks are above the flash point of the material and care should be taken in their heating.
3.4 APPLICATION
3.4.1 General
Following preparation and subsequent inspection of the surface, apply the bituminous prime or tack coat with the bituminous distributor at the specified rate with uniform distribution over the surface to be treated.
Properly treat all areas and spots, not capable of being sprayed with the distributor, with the hand spray. Until the succeeding layer of pavement is placed, maintain the surface by protecting the surface against damage and by repairing deficient areas at no additional cost to the Government.
If required, spread clean dry sand to effectively blot up any excess bituminous material. No smoking, fires, or flames other than those from the heaters that are a part of the equipment are permitted within 25 feet of heating, distributing, and transferring operations of cutback materials. Prevent all traffic, except for paving equipment used in constructing the surfacing, from using the underlying material, whether primed or not, until the surfacing is completed. The bituminous coat requirements are described herein.
3.4.2 Tack Coat
Apply tack coat at the locations as indicated. A tack coat should be applied to every bound surface (asphalt or concrete pavement) that is being overlaid with asphalt mixture and at transverse and longitudinal joints.
Apply the tack coat when the surface to be treated is clean and dry.
Immediately following the preparation of the surface for treatment, apply the bituminous material by means of the bituminous distributor, within the limits of temperature specified herein and at a rate as specified above in paragraph APPLICATION RATE. Apply the bituminous material so that uniform distribution is obtained over the entire surface to be treated. Treat lightly coated areas and spots missed by the distributor by spraying with a hand wand or using other approved method. Following the application of bituminous material, allow the surface to cure without being disturbed for period of time necessary to permit setting of the tack coat. Apply the bituminous tack coat only as far in advance of the placing of the overlying layer as required for that day's operation. Maintain and protect the treated surface from damage until the succeeding course of pavement is placed.
3.5 CURING PERIOD
Following application of the bituminous material and prior to application of the succeeding layer of asphalt mixture allow the bituminous coat to cure and water or volatiles to evaporate prior to overlaying. Maintain the tacked surface in good condition until the succeeding layer of pavement is placed, by protecting the surface against damage and by repairing and recoating deficient areas.
SECTION 32 12 13 Page 6
3.6 FIELD QUALITY CONTROL
Obtain certificates of compliance for all asphalt material delivered to the project. Obtain samples of the bituminous material under the supervision of the Contracting Officer. The sample may be retained and tested by the Government at no cost to the Contractor.
3.7 TRAFFIC CONTROLS
Traffic Control Plan shall follow all the requirements of PennDOT Publication 213. Keep traffic off surfaces freshly treated with bituminous material. Provide sufficient warning signs and barricades so that traffic will not travel over freshly treated surfaces.
SECTION 32 12 17 Page 1
SECTION 32 12 17
HOT MIX BITUMINOUS PAVEMENT
extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D3381/D3381M (2013) Viscosity-Graded Asphalt Cement for
Use in Pavement Construction
PENNSYLVANIA DEPARTMENT OF TRANSPORTATION (PDT)
PDT 408 (2016) Specifications
1.2 SUBMITTALS
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
SD-07 Certificates
Bituminous Materials; G, RO
Certificates from the manufacturers attesting that bituminous materials meet specification requirements shall be submitted.
Certificates are required for all bituminous material.
SD-09 Manufacturer's Field Reports
Surface Smoothness; G, RO
Finished surfaces of bituminous courses, when tested as specified, shall conform to the grade lines and elevations shown and to the surface smoothness requirements specified.
SD-11 Closeout Submittals
Waybills and Delivery Tickets
Certified copies of waybills and delivery tickets for all materials actually used shall be submitted during the progress of the work.
1.3 DELIVERY, STORAGE, AND HANDLING
Inspect materials delivered to the site for damage and store with a minimum of handling. Store aggregates in such a manner as to prevent segregation, contamination, or intermixing of the different aggregate sizes.
SECTION 32 12 17 Page 2
1.4 ENVIRONMENTAL CONDITIONS
Place bituminous mixture only during dry weather and on dry surfaces. Place courses only when the surface temperature of the underlying course is greater than 45 degrees F for course thicknesses greater than one inch and 55 degrees F for course thicknesses one inch or less.
1.5 CONSTRUCTION EQUIPMENT
All plant, equipment and tools used in the work shall be PennDOT certified and subject to approval before the work is started and shall be maintained in satisfactory working condition at all times. The equipment shall be adequate and have the capability of meeting grade controls, thickness control, and smoothness requirements specified herein. The bituminous plant shall be of such capacity to produce the quantities of bituminous mixtures required. Hauling equipment, paving machines, rollers, miscellaneous equipment, and tools shall be provided in sufficient numbers and capacity and in proper working condition to place the bituminous paving mixtures at a rate which will support the requirements governed by the project. The mixing plant shall be an automatic or semi-automatic controlled commercially manufactured unit designed and operated to consistently produce a mixture within the material requirements specified herein. The plant shall have a minimum production capacity (tons per hour) which will support the requirements governed by the project. Bitumen distributor shall be equipped with flow controls and metering gauges to regulate and monitor application rate of prime and tack coat material. The distributor shall be designed and equipped to spray the bituminous material in a uniform coverage at the specified temperature, at readily determined and controlled rates with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths.
1.5.1 Paving Equipment
1.5.1.1 Spreading Equipment
Self-propelled pneumatic-tired rollers supplemented by three-wheel and tandem type steel wheel rollers. The number, type and weight of rollers shall be sufficient to compact the mixture to the required density without detrimentally affecting the compacted material. Rollers shall be suitable for rolling hot-mix bituminous pavements and capable of reversing without backlash. Pneumatic-tired rollers shall be capable of being operated both forward and backward without turning on the mat, and without loosening the surface being rolled. Equip rollers with suitable devices and apparatus to keep the rolling surfaces wet and prevent adherence of bituminous mixture. Vibratory rollers especially designed for bituminous concrete compaction may be used provided rollers do not impair stability of pavement structure and underlying layers. Repair depressions in pavement surfaces resulting from use of vibratory rollers. Rollers shall be self-propelled, single or dual vibrating drums, and steel drive wheels, as applicable;
equipped with variable amplitude and separate controls for energy and propulsion as well as roll-over protection.
1.5.1.2 Rolling Equipment
Self-propelled pneumatic-tired rollers supplemented by three-wheel and tandem type steel wheel rollers. The number, type and weight of rollers shall be sufficient to compact the mixture to the required density without
SECTION 32 12 17 Page 3 detrimentally affecting the compacted material. Rollers shall be suitable for rolling hot-mix bituminous pavements and capable of reversing without backlash. Pneumatic-tired rollers shall be capable of being operated both forward and backward without turning on the mat, and without loosening the surface being rolled. Equip rollers with suitable devices and apparatus to keep the rolling surfaces wet and prevent adherence of bituminous mixture.
Vibratory rollers especially designed for bituminous concrete compaction may be used provided rollers do not impair stability of pavement structure and underlying layers. Repair depressions in pavement surfaces resulting from use of vibratory rollers. Rollers shall be self-propelled, single or dual vibrating drums, and steel drive wheels, as applicable; equipped with variable amplitude and separate controls for energy and propulsion.
1.5.1.3 Hand Tampers
Minimum weight of 25 pounds with a tamping face of not more than 50 square inches.
1.5.1.4 Mechanical Hand Tampers
Commercial type, operated by pneumatic pressure or by internal combustion.
2.1 BITUMINOUS MATERIALS - HOT MIX
Asphalt concrete shall consist of coarse aggregate, fine aggregate, mineral filler, bituminous material, and approved additives, if required, of the qualities and in the proportions specified by the requirements of PDT 408 as given herein. Binder and wearing courses shall be placed to the final compacted thicknesses as indicated and graded to accommodate drainage as indicated. Asphalt binder shall be Performance Grade 64-22.
2.1.1 Bituminous Binder Course
Bituminous binder course shall be in accordance with PDT 408, Section 409.
Binder course shall utilize 19.0 mm or 25.0 mm HMA mixture as indicated.
2.1.2 Bituminous Wearing Course
Bituminous wearing course shall be in accordance with PDT 408, Section 409.
Binder course shall utilize 9.5 mm HMA mixture as indicated.
2.1.3 Waybills and Delivery Tickets
Certified copies of waybills and delivery tickets for all materials actually used shall be submitted during the progress of the work.
3.1 REMOVAL OF EXISTING PAVEMENT
Existing pavement and aggregate base course shall be removed to the extent indicated. Edges of pavement removal shall be sawcut, and removal shall be performed in a manner to prevent damage to pavement which is to remain.
3.2 PREPARATION OF AGGREGATE BASE COURSE
Before constructing the pavement, the existing subgrade or previously
SECTION 32 12 17 Page 4 constructed aggregate base course shall be cleaned of foreign substances and unsuitable materials. The prepared surface shall meet the specified compaction and surface tolerances. The prepared surface shall conform to Section 32 11 23 AGGREGATE BASE COURSE. The prepared surface shall not be disturbed by traffic or other operations and shall be maintained in a satisfactory condition until pavement is placed.
3.3 BITUMINOUS HOT MIX
3.3.1 Placement
Bituminous courses shall be constructed only when the subgrade, aggregate base course and/or existing pavement at interface areas have no free water on the surface. Bituminous mixtures shall not be placed without ample time to complete spreading and compaction during daylight hours. Compaction and rolling equipment shall follow as closely behind the paving machine as possible. Areas inaccessible to rollers shall be compacted by mechanical vibratory tampers. Compaction shall continue until no marks or tracks are left from the compaction or rolling equipment. Bituminous binder and wearing courses shall be placed in accordance with the applicable requirements of PDT 408. Bituminous binder and wearing courses shall be constructed in compacted lifts to the depth as indicated. When static steel-wheeled rollers are used, the maximum compacted lift thickness shall not exceed 3-inches.
3.3.2 New Paving - Existing Paving Interface
Where new bituminous pavement meets the existing pavement, a straight, smooth butt joint shall be constructed. Joints indicated to be vertically sawcut into the existing pavement shall be sawcut to the full depth for the entire length of the pavement interface. The surfaces of the existing pavement at the interface shall be cleaned of all loose material and dirt and painted with a suitable bituminous joint sealant material conforming to ASTM D3381/D3381M, AC-20. The feathering of new pavement over existing pavement at interfaces will not be permitted. Joints between old and new pavement shall be made in accordance with the applicable requirements of PDT 408 and as indicated to insure continuous bond between the old and new sections. All joints shall have the same texture and smoothness as other sections of the course. After completion of the new bituminous pavement, a hot-applied bituminous sealant, conforming to ASTM D3381/D3381M, AC-20, shall be applied along each joint between the new and existing pavement sections for a minimum width of six inches on each side of the joint.
3.3.3 New Paving - Existing Structures Interface
Where new bituminous pavement meets curbs, sidewalks, manholes, inlets and other structures, all surfaces at the interface shall be cleaned of all loose material and dirt and painted with a suitable bituminous joint sealant material conforming to ASTM D3381/D3381M, AC-20. Joints at these interfaces shall be compacted to provide the same density, texture and smoothness as other sections of the course. Vibratory hand tampers shall be utilized for compaction, where rolling is not practicable. After completion of the new bituminous pavement, a bituminous hot-applied sealant, conforming to ASTM D3381/D3381M, AC-20, shall be applied along each joint interface for a minimum width of six inches. The transitions to all walkways slope shall be no greater than 8%.
SECTION 32 12 17 Page 5
3.3.4 Cold Joints
Joints between successive work days, or joints that have become cold (less than 175 degrees F) shall be made in accordance with the applicable requirements of PDT 408 to insure continuous bond between the old and new sections. The feathering of new pavement over existing pavement at joints will not be permitted. All joints shall be compacted to provide the same density, texture and smoothness as other sections of the course.
After completion of the new bituminous pavement, a suitable hot-applied bituminous sealant, conforming to ASTM D3381/D3381M, AC-20, shall be applied along each joint interface for a minimum width of six inches on each side of the joint.
3.4 TESTING OF PAVEMENTS - IN PROGRESS WORK
The Contracting Officer reserves the right to sample and test any area which…