Text version
W81ET483375045
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
RE: Fabrication of Dow nstream Auxiliary Miter Gate at New Cumberland L/D This amendment is being issued to:
1. Provide responses to additional questions that w ere received after the intial cut-off time,
2. Revise the technical specifications of the Certif ied Final Documents - W911WN19B002 as detailed in the Summary of Changes,
3. Revise the Contract Draw ings contained in the Certified Final Documents - W911WN19B0002 as detailed in the Summary of Changes,
4. All other terms and conditions remain unchanged and in full force and effect.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-May-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911WN19B0002
X 9B. DATED (SEE ITEM 11)
08-May-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-May-2019
CODE
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
ATTN CELRP-RC-P
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE ROOM 2203
PITTSBURGH PA 15222-4186
W911WN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911WN19B0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS AND ANSWERS VOL. 2
Q1. In reference with miter gate anchorage assemblies as per drawings S-5029 thru S-5032 and fracture critical notes #2 & 3 on drawing S-5030 & S-5031. Does the fracture critical requirement apply to all forgings for miter gate anchorage or just the items associated with see note statement under details for anchor bar 1, anchor bar 2 & gudgeon link only?
A1. Note #2 and #3 on drawings S-5030 and S-5031 apply to anchor bar 1, anchor bar 2, and gudgeon link only.
In regards to Note #2, all other forgings are to be tested using industry/ASTM standards for ensuring quality materials, unless otherwise specified in the specifications.
In regards to Note #3, the location of the HSS identification numbers is shown on the drawings for each of the applicable components.
Q2. In reference with miter gate 3-D model drawings as per drawings S-9051 thru S-9052, can you provide the 3-D model drawings for checking weights?
In reference with S-9052 miter & quoin assemblies, the diaphragm plates are part of the quoin assembly detail and the diaphragm plates are not shown on the miter assembly. Was the diaphragm plates not shown on miter assembly for reference clarification or is the miter assembly section fabricated without diaphragms?
A2. The Government will not provide the 3-D model.
The diaphragm plates are not shown for clarity. The intent of the 3-D model views shown on drawings S-9049 thru S-9052 is to aid in visualizing the 2-D drawings. These drawings are not intended to dictate fabrication means, methods, assemblies, or sequencing.
Q3. In reference with miter gate anchorage assemblies as per drawings S-5029 thru S-5032 and fracture critical notes# 2 on drawing S-5030 & S-5031. Does the fracture critical requirement apply to all forgings for miter gate anchorage or just the items associated with FCM & see note statement under details for anchor bar 1, anchor bar 2 & gudgeon link only? Note #2 fracture critical requirement note states radiographic testing of material.
What are the CVN requirements needed on the A668 Class K material to meet FCM?
W911WN19B0002
A3. Note that the material class of the anchor bars and gudgeon links has been revised to Class D as part of Amendment 2. The minimum CVN requirements for the FCM needs to match that of ASTM A709 Grade 50F Zone 2.
CERTIFIED FINAL DOCUMENTS – W911WN19B0002 TECHNICAL SPECIFICATIONS
The following Sections have been revised:
35 20 16.33 MITER GATES
Paragraph 2.4.6.3 – Class of pintle ball material has been revised to Class D.
Paragraph 2.4.6.4 – Class of gudgeon anchorage bars and links has been revised to Class D.
Paragraph 2.4.6.6 – Diagonal bar material has been revised to ASTM A709 Grade 50T Zone 2.
01 33 00 SUBMITTAL PROCEDURES
Paragraph 1.3 – Added “Approved Full Size Hard Copy Set of Shop Drawings”.
Paragraph 1.6 – Added “and one approved full size hard copy set of shop drawings”.
CERTIFIED FINAL DOCUMENTS – W911WN19B0002 CONTRACT DRAWINGS
The following drawings have been revised:
G-0021 Contract Drawings and Reference Drawing Index
S-5017 Horizontal strut pin tolerances have been revised.
S-3018 Vertical strut pin horizontal bore tolerances have been revised.
S-3021 Diagonal bar material has been revised to ASTM A709 Grade 50T Zone 2. Hole diameter in diagonal connection block has been increased.
S-3023 Pintle bushing outer diameter tolerances have been revised. Added dimensions to Detail 1 to clarify
1/8” rabbet notch.
S-5024 Class of pintle material has been revised to Class D. Added two additional holes in pintle for pintle cover bolts.
S-5030 Anchor bar 1 material has been revised to Class D. Anchor bar 2 material has been revised to Class D.
Anchor bar 2 link pin hole diameter has been revised.
S-5031 Gudgeon link material has been revised to Class D. Gudgeon link hole diameter tolerances have been revised.
S-5032 Wedge pin material has been revised to Class J.
(End of Summary of Changes)