Amendment 0001 The purpose of this amendment is to: 1) Provide responses to questions received; 2) Revise two (2) Sections of the Technical Specifications; 3) Incorporate the current Wage Determination; 4) Revise the Submission of Contract Documentation and 5) Extend the Bid Due Date.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81ET491059667
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
1. CONTRACT ID CODE PAGE OF PAGES
J 1 8
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Aug-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911WN19B8008
X 9B. DATED (SEE ITEM 11)
01-Aug-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
RE: Replace Gate Operating Machinery, Cooked Creek Dam, Armstrong County, Pennsylvania
The purpose of this amendment is to: 1) Provide responses to questions received; 2) Revise two (2) Sections of the Technical Specifications; 3) Incorporate the current Wage Determination; 4) Revise the Submission of Contract Documentation and 5) Extend the Bid Due Date, as indicated in the Summary of Changes to this Amendment.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Aug-2019
CODE
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
ATTN CELRP-RC-P
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE ROOM 2203
PITTSBURGH PA 15222-4186
W911WN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911WN19B8008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
Technical Specifications: Replace Gate Operating Machinery, Crooked Creek Dam, Armstrong County, Pennsylvania, Certified Final, May 2019 (Attachment 1 to the Solicitation)
The following Sections have been revised:
35 01 41.00 08 ELECTROMECHANICAL OPERATING MACHINERY
Paragraph 3.6 Hoisting Machinery and Drum Shop Load Test Updated the load testing for wire rope.
35 01 70.13 WIRE ROPE FOR GATE OPERATING DEVICES
Paragraph 2.1.1.3 Diameter Updated diameter for wire rope.
Paragraph 2.1.1.5 Minimum Breaking Strength Updated minimum breaking strength and diameter for wire rope.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 03-Sep-2019 11:00 AM to 05-Sep-2019 11:00 AM.
SECTION 00 21 00 - INSTRUCTIONS
The following have been added by full text:
QUESTIONS AND ANSWERS
RESPONSES TO QUESTIONS RECEIVED (1-5)
Q1: We request an extension for the due date for the proposal in order to price this correctly.
A1: An extension to the bid due date has been considered. Sealed offers will be due 05 September 2019 in lieu of 03 September 2019.
Q2: The spec calls out for load testing with the actual wire rope, the load test is supposed to be done when the rope is on the drum grooves (no overwrapping) which means that the hoist needs to be 111’ in the air and that means that we either build a test stand that high or use a mobile crane to lift the hoist by 110’. The mobile crane option will be cheaper than building a test structure. We recommend using a test wire rope for the load test, as per ASME the rope need not be load tested (rope will be tested by the manufacturer for breaking strength). This will allow a cheaper option to USACE for load test, as with a shorter test rope we do not need to go 111’ up in the air and we can just lift the hoist by 10-15’ for the testing purpose and this will require a lower capacity mobile crane which is cheaper.
A2: The recommendation is acceptable to USACE. The Specifications have been updated to remove the erroneous requirement to test with the actual service rope.
Q3: Please provide the capacity of the access bridge.
A3: The access bridge has a 30 ton capacity. See Drawing Sheet, M-303 located in the Drawings as Attachment 2 to the Solicitation.
Q4: From the drum design, it looks like the hoist is a true vertical lift, please confirm. There is usually an equalizer sheave in the unit at parallel to the drum. Is that required?
A4: Yes, a true vertical lift is required. Achieving a true vertical lift is the responsibility of the Contractor. The machinery shown in the drawings is simply conceptual and not intended as a final design, as noted in Note 1 of Drawing Sheet M-604 in Attachment 2 (Drawings) to the Solicitation.
Q5: As per the specs, the rope diameter is 0.75”, for a 115 Ton crane and 5 part double reeving, the given rope will have a factor of safety of 2:1, for overhead cranes the minimum requirement is 5:1, this means that the drum and wire rope needs to change and reeving might change as well. Will USACE update the design?
A5: The rope diameter in the Specifications is incorrect. The specified rope diameter should be 1.25 inch. USACE will not update the design; per Note 1of Drawing Sheet M-604 in Attachment 2 (Drawings) to the Solicitation. The machinery shown in the plans, Drawing Sheet M-604, is a conceptual design and the final design is the responsibility of the Contractor. The Specifications have been updated.
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
The following have been modified:
SECTION 00 73 00
ADDENDUM TO SECTION 00 73 00 – SUPPLEMENTARY CONDITIONS
00 73 00 - 01 WAGE RATES
The wage rates identified in the below General Decision Number are incorporated into this solicitation and any resultant contract. The rates apply to all performed work.
General Decision Number: PA20190002 08/16/2019
Superseded General Decision Number: PA20180004
State: Pennsylvania
Construction Types: Heavy, Highway
Counties: Allegheny, Armstrong, Beaver, Bedford, Blair, Butler, Cambria, Cameron, Centre, Clarion, Clearfield, Clinton, Crawford, Elk, Erie, Fayette, Forest, Franklin, Fulton, Greene, Huntingdon, Indiana, Jefferson, Lawrence, McKean, Mercer, Mifflin, Potter, Somerset, Venango, Warren, Washington and Westmoreland Counties in Pennsylvania.
HEAVY AND HIGHWAY CONSTRUCTION PROJECTS (excluding sewer grouting projects and excluding sewage and water treatment plant projects) https://beta.sam.gov/wage-determination/PA20190002/7?index=wd&date_filter_index=0&date_rad_selection=date&wdType=dbra&state=PA &county=14561&page=1
00 73 00 - 02 PAYMENT FOR PERFORMANCE AND PAYMENT BONDS
a. In order to ensure that sufficient funds have been set-aside for payment of performance and payment bond premiums, bidders shall insert in Bid Item Nos. 0001, 1001, 2001, and 3001, an appropriate not-to-exceed dollar amount. Failure of bidders to insert a not-to-exceed dollar amount in Bid Item Nos. 0001, 1001, 2001, and 3001 will cause the bid to be rejected as non-responsive.
b. The Contractor shall be reimbursed the actual bond costs only, as established by evidence of full payment to the surety, up to the dollar amount set forth in Bid Item Nos. 0001, 1001, 2001, and 3001. In no case will the Contractor be reimbursed an amount which exceeds the dollar amount set forth in Bid Item Nos. 0001, 1001, 2001, and 3001.
c. The Government will reimburse only the Prime Contractor for actual paid bond premiums. The Government will not reimburse any subcontractor's paid bond premiums.
00 73 00 - 03 REQUIRED INSURANCE
a. The Contractor shall procure and maintain during the entire performance period of this contract, the following minimum insurance. (See also Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.228-5 Insurance – Work On A Government Installation (JAN 1997).)
Type Bodily Injury Amount Property Damage
Comprehensive General Liability $500,000 Per Occurrence $100,000
Automobile Liability $200,000 Each Person -- $500,000 Per Occurrence $ 20,000
Workmen’s Compensation and Employers Liability As required by State
b. The Contracting Officer will notify the Contractor of any noncompliance with the foregoing provisions. The Contractor shall, after receipt of such notice, immediately comply. Such notice, when delivered to the Contractor or his representative at the site or mailed to the Contractor's address, will be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until the Contractor complies. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor. Compliance with the provisions of this article by subcontractors will be the responsibility of the Contractor.
c. Longshoreman and Harbor Worker's Insurance MAY be required for this work. Please consult with your insurance carrier and applicable statutes (33 USC 901, et. seq.).
00 73 00 - 04 SAFETY AND HEALTH REQUIREMENTS MANUAL
A copy of the current US Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 and its changes are available at http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.aspx .
The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
00 73 00 - 05 WORK UNDER OTHER CONTRACTS
Attention is directed to the fact that other Contractors may be employed by the Government or by local interests at or in the vicinity of the work covered by these specifications. All Contractors shall have equal rights to the use of all roads and grounds so far as practicable and this Contractor shall cooperate with other Contractors so that the work may be performed with the maximum efficiency. Should a disagreement occur between Contractors as to the use of facilities or in other matters, the decision of the Contracting Officer shall govern. (See also the Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-8 Other Contracts (APR 1984).)
00 73 00 - 06 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with FAR clause 52.249-10 entitled "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.
(1) The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. This delay must be beyond the control and without the fault or negligence of the Contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
18 10 8 8 9 8 7 7 6 5 7 9
c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more on the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b. above, the Contracting Officer will convert any qualifying delays to work days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with FAR clause 52.249-10 entitled, "Default (Fixed-Price Construction)".
d. The anticipated adverse weather work days listed above are based on days with precipitation greater than 0.1 inch and/or maximum temperature below 32 degrees F. The numbers shown represent the number of work days (not calendar days) normally expected to have these particular weather conditions based on historical data obtained from the "Climatography of the United States No. 20". The actual number of days will vary. This information is furnished for computation of possible time extensions due to weather delays and is not intended to imply that no work can be done on these days. The Contractor shall make his own determination of the effect of these conditions on his operations under this contract, and schedule his work accordingly.
00 73 00 - 07 COPYING, DISSEMINATION OR DISTRIBUTION OF INFORMATION.
Those who disseminate information contained on this CD-ROM or in the solicitations and/or drawings must ensure that the recipients have a legitimate need for the information and maintain a record of each recipient. Legitimate need means recognized business entities seeking to do business, or having business, with the Government as prime contractors, subcontractors or suppliers. You shall maintain a record of the following information on each recipient:
Business name and address, the Unique Entity Identifier (formerly DUNS) Number, and name and telephone number of person receiving the information
00 73 00 - 08 SUBMISSION OF CONTRACT DOCUMENTATION
Provide contract documentation in an electronic format to the greatest extent practicable. Contract documentation to be submitted electronically includes, but is not limited to, the following:
Submittals, including ENG 4025 transmittal form Meeting Minutes Construction Photographs Correspondence Requests for Information Payroll Documents Statement and Acknowledgement Forms (SF 1413) Request for Additional Classification (SF 1444) Progress Payment Requests and Supporting Documentation Contract Modification Documentation, including SF 30, Contractor’s Offer, Cost/Pricing Audit Report, and
Certificate of Current Cost or Pricing Data Contractor Quality Control Reports (with attachments) Accident Reports Schedules and Schedule Updates Closeout Documentation, including Release of Claims
Electronic files must be of sufficient quality that all information is legible. Electronic format shall be in Adobe.PDF format, unless otherwise specified or directed by the Contracting Officer. Whenever possible, PDF files shall be generated from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Files exceeding 30 pages shall be indexed and bookmarked to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic documents to an email address as directed by the Contracting Officer or their designated representative. Provide large electronic documents over 8.0 GB on an optical disc or for documents up to 8.0 GB through an electronic file sharing system which will be by invitation from the Contracting Officer or their designated representative through a file sharing application. The file sharing system to be used is the Department of Defense (DoD) Secure Access File Exchange (SAFE) Web Application. The DoD SAFE site is located at the following website: https://safe.apps.mil/ .
The Contractor shall be prepared to provide up to five (5) additional paper hard copies of any contract document at the discretion of the Contracting Officer, at no additional cost to the Government. In addition to the electronic file format described above, the following list of documents shall be provided in their original format because law or other regulations require signed originals be kept in accordance with FAR 4.805 -- Storage, Handling, and Disposal of Contract Files:
Advance Payment Bond Bid Bond including Annual Bid Bond Performance Bond including Annual Performance Bond Payment Bond Patent Infringement Bond Any performance security instruments Certificate of Insurance Novation/Change of Name Agreement Assignment of Claims Any document containing a raised seal. Examples include o Notarized documents o Architecture Drawings
Paper Payroll Documents Physical signatures on contracts and modifications o SF 1442 o SF 30
00 73 00 - 09 WORK PERFORMED BY CONTRACTOR
Within ten (10) calendar days after award of the contract, the successful bidder will be required to furnish a description of the work which he intends to perform with his own organization, the percentage of the total work this represents, and the estimated cost thereof.
00 73 00 - 10 AWARDABLE OPTIONS
Only the basic contract items, Items Nos. 0001 thru 0003, will be awarded initially. Awardable Option Items (1001 thru 1003, 2001 thru 2003, and 3001 thru 3003) will be made based upon availability and receipt of funds.
Awardable Option Items within each of these groupings will be awarded as a group. The Not-to-Exceed amount for Items 1001, 2001 and 3001 should reflect bond costs for all awardable option items within each respective group.
The determination to award these awardable option items will be made no later than the following dates:
Awardable Option 1, Items 1001 thru 1003 -1 April 2020 Awardable Option 2, Items 2001 thru 2003 - 1 April 2021 Awardable Option 3, Items 3001 thru 3003 - 1 April 2021
The contract completion time will be extended 365 calendar days after receipt of Notice to Proceed for Awardable Option 1. Awardable Options 2 and 3 will exercised consecutively and the contract completion date will be extended 365 calendar days after receipt of Notice to Proceed.
00 73 00 - 11 CONTRACTOR QUALITY CONTROL
Section 01 45 00.00 08, QUALITY CONTROL, of this specification requires that the Contractor's Quality Control System Manager or person responsible for Contractor Quality Control complete the Corps of Engineers' "Construction Quality Management for Contractors" course not later than 90 calendar days after receipt of the Notice to Proceed. The course consists of approximately 12 hours of classroom instruction and is offered periodically by the Pittsburgh District. For additional information on scheduling and location of the training, contact U.S. Army Engineer District, Pittsburgh, Theresa Bonanno, U.S. Army Engineer District, Pittsburgh, Upper Ohio Area Office, 3510 Grand Avenue, Pittsburgh, Pennsylvania 15225, telephone (412) 395-7677. Certification of course completion is valid for 5 years. Completion of training offered by other Corps of Engineers Districts will be acceptable provided a valid certification is presented.
00 73 00 - 12 ELECTRONIC EMAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 calendar days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use e-mail to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple e-mail addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.
(End of Addendum)
(End of Summary of Changes)
"General Decision Number: PA20190002 08/16/2019
Superseded General Decision Number: PA20180004
State: Pennsylvania
Construction Types: Heavy and Highway
Counties: Allegheny, Armstrong, Beaver, Bedford, Blair, Butler, Cambria, Cameron, Centre, Clarion, Clearfield, Clinton, Crawford, Elk, Erie, Fayette, Forest, Franklin, Fulton, Greene, Huntingdon, Indiana, Jefferson, Lawrence, McKean, Mercer, Mifflin, Potter, Somerset, Venango, Warren, Washington and Westmoreland Counties in Pennsylvania.
HEAVY AND HIGHWAY CONSTRUCTION PROJECTS (excluding sewer grouting projects and excluding sewage and water treatment plant projects)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the
Page 1 of 26beta.SAM.gov
8/20/2019https://beta.sam.gov/wage-determination/PA20190002/7/document wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/04/2019 1 01/11/2019 2 02/15/2019 3 05/17/2019 4 06/07/2019 5 06/14/2019 6 07/05/2019 7 08/16/2019
BOIL0013-005 03/01/2018
CENTRE, FRANKLIN, POTTER, CLINTON, FULTON, HUNTINDON AND
MIFFLIN COUNTIES
Rates Fringes
BOILERMAKER......................$ 45.89 33.39
BOIL0154-004 01/01/2017
ALLEGHENY, ARMSTRONG, BEAVER, BEDFORD, BLAIR, BUTLER, CAMBRIA,
CAMERON, CLARION, CLEARFIELD, CRAWFORD, ELK, FAYETTE, FOREST,
Page 2 of 26beta.SAM.gov
GREENE, INDIANA, JEFFERSON, LAWRENCE, MCKEAN, MERCER, SOMERSET,
VENANGO, WARREN, WASHINGTON AND WESTMORELAND COUNTIES
Rates Fringes
BOILERMAKER......................$ 40.90 27.27
BOIL0744-003 07/01/2008
ERIE COUNTY
Rates Fringes
BOILERMAKER......................$ 35.34 18.48
BRPA0005-033 05/01/2018
MIFFLIN COUNTY
Rates Fringes
Bricklayer, Stonemason...........$ 31.36 17.73
BRPA0005-046 05/01/2016
FRANKLIN COUNTY
Rates Fringes
Bricklayer, Stonemason...........$ 32.21 14.18
BRPA0005-071 05/01/2018
CLINTON COUNTY
Rates Fringes
Page 3 of 26beta.SAM.gov
BRICKLAYER.......................$ 33.16 16.31
BRPA0009-004 12/01/2018
BEDFORD, BLAIR,CAMBRIA, CENTRE COUNTY (Halfmoon, Houston, Patton, Rush,Taylor and Worth Townships),FULTON, HUNTINGDON, and SOMERSET COUNTIES
Rates Fringes
Bricklayer, Stonemason & Marble Setter....................$ 29.46 19.58
BRPA0009-006 12/01/2018
CLEARFIELD, FOREST, JEFFERSON, VENANGO, AND CLARION (Except Brady, Madison, Perry, Porter, Redbank, and Toby Townships)
COUNTIES
Rates Fringes
Bricklayer, Stonemason...........$ 29.90 19.91 Marble mason.....................$ 29.90 19.91
BRPA0009-023 06/01/2018
BEAVER COUNTY
Rates Fringes
BRICKLAYER.......................$ 30.16 21.41
* BRPA0009-025 06/01/2019
Page 4 of 26beta.SAM.gov
BUTLER, LAWRENCE, AND MERCER COUNTIES
Rates Fringes
BRICKLAYER.......................$ 30.51 21.94
BRPA0009-032 06/01/2017
FAYETTE (Jefferson & Washington Twps), GREENE (Except Cumberland, Dunkirk, Greene, Monongahelia Twps), INDIANA, AND WESTMORELAND (Rostraver Twp) COUNTIES
Rates Fringes
BRICKLAYER.......................$ 31.00 20.66
* BRPA0009-033 06/01/2019
ARMSTRONG, CLARION (Brady, Madison, Perry, Tobe, Porter, Redbank Twps), FAYETTE (Except Jefferson & Washington Twps), GREENE (Cumberland, Dunkirk, Greene, Monongahelia Twps), INDIANA, AND WESTMORELAND (Except Rostrave Twp) COUNTIES
Rates Fringes
BRICKLAYER.......................$ 32.35 22.26
BRPA0009-034 11/01/2017
ERIE COUNTY
Rates Fringes
BRICKLAYER.......................$ 27.55 19.76
Page 5 of 26beta.SAM.gov
BRPA0009-058 12/01/2017
ALLEGHENY, WASHINGTON (Cross Creek, Hanover, Jefferson, Mt Pleasant, Nottingham, Peters, Robinson, Smith, Union Twps)
COUNTIES
Rates Fringes
BRICKLAYER.......................$ 31.69 21.27
* BRPA0009-059 06/01/2019
CAMERON, ELK, McKEAN, POTTER AND WARREN COUNTIES
Rates Fringes
BRICKLAYER.......................$ 27.86 20.17
CARP2235-005 01/01/2019
Rates Fringes
PILEDRIVERMAN
Piledriverman (welder)......$ 35.25 19.30 Piledriverman...............$ 34.30 19.30
CARP2235-006 01/01/2019
Rates Fringes
Diver............................$ 51.45 19.30 Tender...........................$ 34.30 19.30
CARP2274-001 01/01/2019
Rates Fringes
Page 6 of 26beta.SAM.gov
CARPENTER (ALLEGHENY,
ARMSTRONG, BEAVER, BUTLER,
ERIE, FAYETTE, GREENE,
LAWRENCE, MERCER, WASHINGTON,
AND WESTMORELAND COUNTIES)
Carpenters (Welders)........$ 34.97 18.42 Carpenters..................$ 34.02 18.42
CARPENTER (BEDFORD, BLAIR,
CAMBRIA, CAMERON, CENTRE,
CLARION, CLINTON, CLEARFIELD,
CRAWFORD, ELK, FOREST,
FRANKLIN, FULTON, HUNTINGDON,
INDIANA, JEFFERSON, MCKEAN,
MIFFLIN, POTTER, SOMERSET,
VENANGO, AND WARREN COUNTIES)
Carpenters (Welders)........$ 34.72 18.42 Carpenters..................$ 33.77 18.42
ELEC0005-006 12/21/2018
ALLEGHENY, ARMSTRONG, BEDFORD, BLAIR, BUTLER CAMBRIA, CAMERON,
CENTRE (Remainder), CLARION, CLEARFIELD, ELK, FAYETTE, FULTON, GREENE, HUNTINGDON, INDIANA, JEFFERSON, MCKEAN, SOMERSET, VENANGO, WASHINGTON, AND WESTMORELAND COUNTIES
Rates Fringes
ELECTRICIAN......................$ 40.76 26.34
ELEC0056-004 06/03/2019
ERIE, FOREST AND WARREN COUNTIES
Rates Fringes
Page 7 of 26beta.SAM.gov
ELECTRICIAN......................$ 34.34 22.27
ELEC0126-005 05/24/2019
ALLEGHENY, ARMSTRONG, BEAVER, BEDFORD, BLAIR, CAMBRIA, CENTRE,
CLARION, CLEARFIELD, FAYETTE, FULTON, GREENE, HUNTINGDON,
INDIANA, JEFFERSON, SOMERSET, WASHINGTON AND WESTMORELAND
Rates Fringes
Line Construction:
Cable Splicer...............$ 47.38 30.25%+11.50 Groundman...................$ 28.43 30.25%+11.50 Lineman.....................$ 47.38 30.25%+11.50 Truck Driver................$ 30.80 30.25%+11.50 Winch Truck Operator........$ 33.17 30.25%+11.50
ELEC0126-007 05/28/2018
FRANKLIN AND MIFFLIN COUNTIES
Rates Fringes
Line Construction:
Cable Splicer...............$ 45.25 29.25%+11.25 Groundman...................$ 27.15 29.25%+11.25 Lineman.....................$ 45.25 29.25%+11.25 Truck Driver................$ 29.41 29.25%+11.25 Winch Truck Operator........$ 31.68 29.25%+11.25
ELEC0143-007 06/01/2019
FRANKLIN and MIFFLIN COUNTIES
Rates Fringes
Page 8 of 26beta.SAM.gov
ELECTRICIAN......................$ 31.60 24.07
ELEC0712-003 12/31/2018
CRAWFORD, BEAVER, LAWRENCE AND MERCER COUNTIES
Rates Fringes
ELECTRICIAN......................$ 38.55 23.49
ELEC0812-008 06/01/2017
CLINTON COUNTY
Rates Fringes
ELECTRICIAN......................$ 33.59 18.61
ELEC0812-009 06/01/2017
POTTER COUNTY
Rates Fringes
ELECTRICIAN......................$ 34.60 18.64
ELEC0812-011 06/01/2017
CENTRE COUNTY (Burnside, Curtin, Liberty, Howard, Marion, Walker, Miles, Haines Townships)
Rates Fringes
ELECTRICIAN......................$ 33.59 18.61
ELEC1319-004 09/02/2018
Page 9 of 26beta.SAM.gov
BUTLER, CAMERON, CLINTON, CRAWFORD, ELK, ERIE, FOREST,
LAWRENCE, MCKEAN, MERCER, VENANGO, WARREN AND POTTER COUNTIES
Rates Fringes
Line Construction:
Equipment Operator..........$ 56.43 19.84 Groundmen...................$ 34.99 11.28 Linemen.....................$ 56.43 22.84 Truck Driver................$ 36.68 11.41
ENGI0066-016 01/01/2019
Rates Fringes
Power equipment operators:
(ALLEGHENY, ARMSTRONG,
BEAVER, BLAIR, BUTLER,
CAMBRIA, CENTRE, CLARION,
CLEARFIELD, CRAWFORD, ERIE,
ELK, FAYETTE, GREENE,
INDIANA, JEFFERSON, LAWRENCE,
MCKEAN, MERCER, SOMERSET,
VENANGO, WARREN, WASHINGTON,
AND WESTMORELAND COUNTIES)
GROUP 1.....................$ 31.89 21.68
GROUP 2.....................$ 31.63 21.68
GROUP 3.....................$ 27.98 21.68
GROUP 4.....................$ 27.52 21.68
GROUP 5.....................$ 27.27 21.68
Power equipment operators:
(BEDFORD, CAMERON, CLINTON,
FOREST, FRANKLIN, FULTON,
HUNTINGDON, MIFFLIN, AND
POTTER COUNTIES)
Page 10 of 26beta.SAM.gov
GROUP 1.....................$ 31.60 21.68
GROUP 2.....................$ 31.32 21.68
GROUP 3.....................$ 27.68 21.68
GROUP 4.....................$ 27.19 21.68
GROUP 5.....................$ 26.98 21.68
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1 - Asphalt Paving Machine (Spreader), Autograde (C.M.I. and similar); Backfiller, Compactor with Blade, Backhoe - 360 and 180 degree Swing; Cableway; Caisson Drill (similar to Hugh Williams), Central Mix Plant; Cooling Plant; Concrete Paving Mixer, Concrete Pump (self-propelled); Cranes; Cranes (boom or mast over 101ft.$.50 per each additional 50 feet inclusive of jib), Cranes (Tower Stationary- Climbing Tower Crane); Derrick; Derrick Boat; Dozer(greater than 25,000 lbs.); Dragline; Dredge;
Dredge Hydraulic; Elevating Grader; Franki Pile Machine;
Gradall (remote control or otherwise),Grader (power-fine grade); Hllift (4 cy. and over); Hoist 2 Drums or more (in one unit); Hydraulic Boom Truck with pivotal cab (single motor-Pitman or similar), (Boom and Mast over 101 feet will be paid an additional 50 feet inclusive of jib if used;)
Kocal; Mechanic, Locomotive (std. Gauge); Metro-chip Harvester or similar; Milling Machine (Roto Mill or similar); Mix Mobile; Mix Mobile (with Self Loading Attachment), Mucking Machine (tunnel); Pile Driver Machine;
Pipe Extrusion Machine; Prespliter Drill (self contained);
Refrigeration Plant (soil Stablization) Rough Terrain Crane (25 ton over) (Boom and Mast over 101 feet will be paid an additional 50 feet inclusive of jib if used); Rough Terrain Crane (under 25 ton), Scrapers; Shovel-Power; Slip form Paver (C.M.I. and similar); Trenching Machine (30,000 lbs.
and over), Trenching Machine (under 30,000 lb.), Tunnell Machine (Mark XXI Jarva or similar), Vermeer Saw, Whirley, Mechanic, Compactor with blade
Page 11 of 26beta.SAM.gov
GROUP 2: Asphalt plant operator; auger (tractor mtd.); auger (truck mtd.); belt loader (euclid or similar); boring machine; cable placer or layer; Directional drill over 3,000 lbs thrust; concrete batch plant (electronically synchronized); concrete belt placer (C.M.I. and similar);
concrete finishing machine and spreader, concrete mixer (over 1 cy.) concrete pump (stationary); core drill (truck or skid mtd. - similar to penn drill), dozer (25,000 lbs or less); Ditch Witch Saw, force feedloader; fork lift (lull or similar); grader - power; grease unit opertor (head);
guard rail post driver (truck mounted) guard rail post driver (skid type); hilift (under 4 cy.); skid steer loader; hydraulic boom truck (non-pivotal cab); job work boat (powered), jumbo operator; locomotive (narrow guage);
minor equipment operator (accumulative four units); mucking machine; multi-head saw (groover); overhead crane; roller -power- asphalt; ross carrier; side boom or tractor mounted boom; shuttle buggy (asphalt), stone crusher (screening-washing plants); stone spreader (self propelled) truck mounted drill (davey or similar); welder and repairman; well point pump operator; bidwell concrete finishing machine (or similar).
GROUP 3: Broom Finisher (C.M.I. or similar);
Compactors/Rollers (static or vibratory (Self-propelled) on dirt or stone; Curb Builder; Minor Equipment Opertor (two or three units); Multi-head Tie Tamper; Pavement Breaker (self-propelled or ridden); Soil Stablizer Machine; Tire Repairman; Tractor (snaking and hauling); Well Driller and Horizontal: Winch or ""A"" Frame Truck (when hoisting and lowering).
GROUP 4: Ballast Regulator; Compressor; Concrete Mixer (1
cy. & under with skip); Concrete Saw (Ridden or selp-propelled); Conveyor; Elevator (Material hauling only); Fork-lift (Ridden or self-propelled); Form Line Machine; Generator; Groute Pump; Heater (Machinical); Hoist
Page 12 of 26beta.SAM.gov
(single Drum); Ladavator, Light Plant; Mulching Machine;
Personnel Boat (Powered), Pulverizer, Pumps, Seeding Machine, spray Cure Machine (powered Driven); Subgrader;
Tie Puller; Tugger; Welding Machine (Gas or Diesel).
GROUP 5: Deck Hand; Farm Tractor; Fireman on Boiler; Oiler;
Power Broom; Side Delivery Shoulder Spreader (attachment);
IRON0003-001 06/01/2019
ALLEGHENY, FAYETTE, WESTMORELAND, CAMBRIA, INDIANA, ARMSTRONG,
BUTLER, BEAVER, CLARION, AND WASHINGTON COUNTIES
Rates Fringes
IRONWORKER.......................$ 35.49 31.84
IRON0003-007 06/01/2019
BLAIR, CAMERON, CENTRE, CLEARFIELD, CLINTON, ELK, JEFFERSON,
MCKEAN, AND POTTER COUNTIES
Rates Fringes
IRONWORKER.......................$ 29.58 29.92
IRON0003-011 06/01/2019
CRAWFORD, ERIE, FOREST, AND WARREN COUNTIES
Rates Fringes
IRONWORKER.......................$ 30.75 29.70
Page 13 of 26beta.SAM.gov
IRON0207-002 06/01/2018
LAWRENCE, MERCER, AND VENANGO COUNTIES
Rates Fringes
IRONWORKER.......................$ 28.92 24.90
IRON0404-008 07/01/2019
FRANKLIN (Remainder), HUNTINGDON (Remainder), AND MIFFLIN
COUNTIES
Rates Fringes
IRONWORKER, STRUCTURAL...........$ 32.76 29.88
IRON0549-002 12/01/2012
GREENE COUNTY
Rates Fringes
IRONWORKER.......................$ 30.45 16.04
IRON0568-004 05/01/2018
BEDFORD, FRANKLIN (Southwest 1/3), FULTON, HUNTINGDON (Western
2/3), AND SOMERSET COUNTIES
Rates Fringes
IRONWORKER
Structural, Ornamental, Reinforcing, Machinery
Page 14 of 26beta.SAM.gov
Mover, Rigger & Machinery Erector, Welder, Fence Erector.....................$ 28.56 20.61
LABO1058-001 01/01/2019
Rates Fringes
LABORER (BEDFORD, CAMERON,
CENTRE, CLINTON, CRAWFORD,
FOREST, FRANKLIN, FULTON,
HUNTINGDON, JEFFERSON,
MIFFLIN, AND POTTER COUNTIES)
GROUP 1.....................$ 25.35 23.25
GROUP 2.....................$ 25.51 23.25
GROUP 3.....................$ 26.00 23.25
GROUP 4.....................$ 26.45 23.25
GROUP 5.....................$ 26.86 23.25
GROUP 6.....................$ 23.70 23.25
GROUP 7.....................$ 26.35 23.25
GROUP 8.....................$ 27.85 23.25
Laborers: (ALLEGHENY, ARMSTRONG, BEAVER, BLAIR, BUTLER, CAMBRIA, CLARION, CLEARFIELD, ELK, ERIE, FAYETTE, GREENE, INDIANA, LAWRENCE, MCKEAN, MERCER, SOMERSET, VENANGO, WARREN, WASHINGTON, AND WESTMORELAND
COUNTIES)
GROUP 1.....................$ 25.45 23.25
GROUP 2.....................$ 25.61 23.25
GROUP 3.....................$ 26.00 23.25
GROUP 4.....................$ 26.45 23.25
GROUP 5.....................$ 26.86 23.25
GROUP 6.....................$ 23.70 23.25
GROUP 7.....................$ 26.45 23.25
Page 15 of 26beta.SAM.gov
GROUP 8.....................$ 27.95 23.25
LABORERS CLASSIFICATIONS
GROUP 1: Asphalt curb sealer; Asphalt tamper; Batcherman (weigh) Blaster,Boatman, Brakeman, Change house attendant, Coffer dam, Concrete curing pitman, Puddler, Drill Runner's helper (Includes Drill Mounted on Truck, Track, or similar and Davey Drill Spots, Clean up, helps to maintain), Electric Brush and or Grinder, Fence Construction (Including Fence Machine Operator) Form stripper and Mover, Gabion (Erectors and Placers) Hydro jet blaster nozzleman;
Landscape laborer, Manually moved emulusion sprayer, Radio actuated traffic control operator Rip rap work, scaffolds and Runways, Sheeters and Shorers (includes lagging) structural concrete Top Surfacer, Walk Behind Street Sweeper, and Wood Chipper; water boy
GROUP 2: Air tool operator (all types); Asphalt, batch & concrete plant operator (manually operated) Burner, Caisson; men (open air); Carryable pumps; Chain saw operator including attachments, Cribbing, (concrete or steel); Curb machine operator (asphalt or concrete walk behind); Diamond head Core Drller, Drill runner's helper (tunnel) Fork Lift, (walk behind), Form Setter (Road Forms Line man) Highway Slab reinforcement placers (including joint and Basket Setters) Hydraulic pipe pusher; Liner plates (Tile or Vitrified Clay) Mechanical compacting equipment operators, Mechanical joint sealer, Dope pot and Tar Kettle, Mortar mixer (hand or machine) Muckers, Brakemen & all other Labor, (Includes installation of utility lines) Pipe Layers /Fusion /Heating Iron (Regardless of materials) Portable Single Unit Conveyor, Post Hole Auger, (2 or 4 cycle hand operated) Power wheelbarrows and buggies, Rail porter or similar; Sand blaster;Signal Man,Vibrator operator, All RAILROAD TRACK WORK TO INCLUDE THE FOLLOWING: adzing machine, ballast
Page 16 of 26beta.SAM.gov
Router, Bolting Machine, Power Jacks, Rail Drills, Railroad Brakeman,Rail Saws, Spike Drivers (Manually or hand held tool) Spike Pullers Tamping Machine, Thermitweld
GROUP 3: Asphalt Luteman/Raker,Blacksmith, Blaster, Brick, stone and block pavers and block cutters (wood, belgian and asphalt); Cement mortar lining car pusher; Cement mortar mixer (pipe relining); Cement mortar pipe reliners;
concrete saw operator (walk behind); Curb cutters and setters; Elevated roadway drainage construction; erector of overhead signs, Form setter (road forms-lead man); Grout machine operator; Gunite or dry pack gun (nozzle and machine man); Manhole or catch basin builder (Brick block concrete or any prefabrication) Miners and drillers (including lining, supporting and form workmen, setting of shields, miscellaneous equipment and jumbos); Multi-plate pipe (aligning and securing); Placing wire mesh on gunite projects; Wagon drill operators (air track or similar);
Walk behind ditching machine (trencher or similar);crown screed adjuster and welder
GROUP 4: Reinforcing Steel Placer (Bending, aligning, and securing, Cadweld)
GROUP 5:High Burner, (Any burning not done from deck), Welder (Pipeline)
GROUP 6: Uniformed Flagperson, Watchman
GROUP 7: Toxic/Hazardous Waste Removal Laborer Levels C & D
GROUP 8: Toxic/Hazardous Waste Removal Laborer Levels A & B
PAIN0021-019 05/01/2018
CLINTON COUNTY
Page 17 of 26beta.SAM.gov
Rates Fringes
Painters:
Bridge......................$ 36.67 18.80 Brush & Roller..............$ 27.67 18.80 Spray.......................$ 28.67 18.80
PAIN0021-024 05/01/2018
FRANKLIN COUNTY
Rates Fringes
PAINTER
Brush.......................$ 23.92 14.23
PAIN0057-014 06/01/2019
ALLEGHENY, FAYETTE, GREENE, WASHINGTON COUNTIES
Rates Fringes
Painters:
Bridge......................$ 35.25 19.82 Brush & Roller..............$ 28.50 19.82 Spray.......................$ 28.50 19.82
PAIN0057-015 06/01/2019
ARMSTRONG, BEAVER, BEDFORD, BLAIR, BUTLER,CAMBRIA, CENTRE,
CLARION, CLEARFIELD, ELK, FULTON, HUNTINGTON, INDIANA,
JEFFERSON, LAWRENCE, MERCER, MIFFLIN, SOMERSET, VENANGO AND
WESTMORELAND COUNTIES
Rates Fringes
Page 18 of 26beta.SAM.gov
Painters:
Bridge......................$ 35.25 19.82 Brush and Roller............$ 28.50 19.82 Spray.......................$ 28.50 19.82
PAIN0057-022 05/01/2019
Rates Fringes
Painters: (ERIE, McKEAN, AND WARREN (Including Columbus and Freehold twps) COUNTIES) Bridges,Stacks,Towers.......$ 25.37 18.71 Brush and Roller............$ 22.87 18.71 Spray and Sandblasting......$ 23.62 18.71
PAIN0057-027 06/01/2019
CAMERON, CRAWFORD, POTTER, WARREN, (Excluding Columbus and Freehold twps)
Rates Fringes
PAINTER
Brush and Roller............$ 25.11 19.14
PLAS0526-002 01/01/2019
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 31.94 20.50
PLUM0027-001 06/01/2019
ALLEGHENY, ARMSTRONG, GREENE (Except extreme Eastern portion), Page 19 of 26beta.SAM.gov
WASHINGTON (Except extreme Eastern portion) and WESTMORELAND (City of Arnold and City of New Kensington Only) COUNTIES
Rates Fringes
Plumbers and Pipefitters (Bridge Drain Pipe)..............$ 42.30 22.47
PLUM0047-005 05/01/2013
BEAVER, BUTLER, MCKEAN, MERCER, VENANGO, CLARION, LAWRENCE,
FOREST, WARREN, CRAWFORD, AND ERIE COUNTIES
Rates Fringes
Plumbers and Pipefitters (Bridge Drain Pipe)..............$ 38.52 20.11
PLUM0354-005 06/01/2012
BEDFORD, BLAIR, CAMBRIA, CAMERON, CLEARFIELD, ELK, FAYETTE,
GREENE (Extreme Eastern portion), HUNTINGDON, INDIANA, JEFFERSON, SOMERSE, WASHINGTON (Extreme Eastern portion), AND
WESTMORELAND COUNTIES
Rates Fringes
Plumbers and Pipefitters (Bridge Drain Pipe)..............$ 35.54 19.97
TEAM0040-001 01/01/2019
Rates Fringes
Page 20 of 26beta.SAM.gov
TRUCK DRIVER (ALLEGHENY,
ARMSTRONG, BEAVER, BLAIR,
BUTLER, CAMBRIA, CENTRE,
CLARFIELD, CRAWFORD, ERIE,
FAYETTE, GREENE, INDIANA,
JEFFERSON, LAWRENCE, MCKEAN,
MERCER, SOMERSET, VENANGO,
WARREN, WASHINGTON, AND
WESTMORELAND)
GROUP 1.....................$ 28.99 19.43
GROUP 2.....................$ 29.13 19.51
GROUP 3.....................$ 29.59 19.82
Truck drivers: (BEDFORD, CAMERON, CLAIRON, CLINTON, ELK, FOREST, FRANKLIN, FULTON, HUNTINGDON, MIFFLIN, AND POTTER COUNTIES)
GROUP 1.....................$ 28.83 19.32
GROUP 2.....................$ 28.99 19.43
GROUP 3.....................$ 29.45 19.73
FOOTNOTES: A. Hazardous/toxic waste material/work level A & B receive additional $2.50 per hour above classification rate
B. Hazardous/toxic waste materials/Work level C & D receive $1.00 per hour above classification
TRUCK DRIVERS CLASSIFICATIONS
GROUP 1 - Single Axle (2 axles including steering axle);
Includes partsman and warehoueman
GROUP 2 - Tandem - Tri-Axle - Semi-Tractor Trailer (combination) (3 axles or more including steering axle)
GROUP 3 - Specialty Vehicles; Heavy equipment whose capacity
Page 21 of 26beta.SAM.gov exceeds that for which state licenses are issued specifically refers to units in excess of eight (8) feet width (such as Euclids, Atley Wagon, Payloder, Tournawagons, and similar equipment when not self loaded);
Tar and Asphalt Distributors Trucks, Heavy Duty Trailer, such as Low Boy, High Boy
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
Page 22 of 26beta.SAM.gov
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and
Page 23 of 26beta.SAM.gov the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
Page 24 of 26beta.SAM.gov
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Page 25 of 26beta.SAM.gov
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board).
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.