Attachment_1,_Technical_Specifications,_revised_8-28-17,_Amend_0001.pdf
PDF 948 KB Posted
- Attached to
- Repair Work along Elk Creek, Borough of Ridgeway
- Solicitation number
- W911WN-17-B-8004
About this file
Technical Specifications, revised 8-28-17 Revised Attachment 1 to Solicitation Updates include, 1. Revision to Specs Section 01 32 23, Para. 3.2.1 to state that bench marks need to be placed throughout the project with a minimum on one at each area of work with locations being determined in the field with coordination with the Government Quality Assurance personnel. 2. Removal of Para. 1.9 in Specs Section 01 35 00.00 08 regarding Maintenance and Protection of Railroad Traffic. Work will not be within.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911WN-17-B-8004
Ridgway PL 84-99 Flood Protection Project May 2014 Flood Channel Improvement Rehabilitation And Debris Removal Project Elk Creek Elk County, Pennsylvania
Certified Final Documents RTA – W911WN-17-B-8004 Technical Specifications August 2017
Ridgway Channel Improvement Rehabilitation and Debris Removal
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 73 09 VETERANS EMPLOYMENT EMPHASIS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00.00 10 MEASUREMENT AND PAYMENT
01 32 17 CONSTRUCTION PROGRESS SCHEDULE
01 32 23 SURVEY AND ALIGNMENT CONTROL
01 32 33 DIGITAL PROGRESS IMAGES
01 33 00 SUBMITTAL PROCEDURES
01 35 00.00 08 SPECIAL PROCEDURES
01 35 26.00 08 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 45 01 USACE QUALITY CONTROL
01 50 10 PROJECT AND SAFETY SIGNS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 57 23.00 08 STORM WATER POLLUTION CONTROL
01 78 02.00 15 CLOSEOUT SUBMITTALS (AS-BUILT DRAWINGS)
DIVISION 02 - EXISTING CONDITIONS
02 30 00.00 08 DEBRIS SAMPLING AND TESTING
02 41 00 DEMOLITION
02 42 00.00 08 DISPOSAL OF MATERIALS
DIVISION 03 - CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 52 00.00 08 MISCELLANEOUS METAL
DIVISION 31 - EARTHWORK
31 05 22 GEOTEXTILES USED AS FILTERS
31 11 00.00 08 CLEARING AND GRUBBING
31 23 00 EARTHWORK
31 23 00.10 08 BANK EXCAVATION
31 37 16.00 08 STONE PROTECTION
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 23 AGGREGATE SUBBASE AND BASES
32 22 16 BITUMINOUS PAVEMENT CONSTRUCTION
32 30 00 INCIDENTAL CONSTRUCTION
32 32 23 SEGMENTAL CONCRETE BLOCK RETAINING WALL
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1 Certified Final Documents -Revised by Amendment 0001
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 73 09
VETERANS EMPLOYMENT EMPHASIS
PART 1 GENERAL
1.1 REFERENCES
1.2 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
DOCUMENT 00 73 09 Page 1
SECTION 00 73 09
VETERANS EMPLOYMENT EMPHASIS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
USACE ACQUISITION INSTRUCTION (UAI)
UAI (March 18, 2013) U.S. Army Corps of Engineers USACE Acquisition Instruction
1.2 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
UAI 5122.1302-100. In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S.
Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
U.S. Department of Labor Veterans employment: www.vets.gov/
Federal veteran employment information: www.fedshirevets.gov/index.aspx
Veterans' Employment and Training Service (VETS):
http://www.dol.gov/vets/
Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/
U.S. Army Warrior Transition Command Employment Index:
wtc.army.mil/modules/employers/index.html
Hiring Our Heroes initiative:
www.uschamberfoundation.org/hiring-our-heroes
Guide to Hiring Veterans:
www.whitehouse.gov/sites/default/files/docs/white_house_business_counc il_-_guide_to_hiring_veterans_0.pdf
PART 2 PRODUCTS
NOT USED
DOCUMENT 00 73 09 Page 2
PART 3 EXECUTION
NOT USED
-- End of Section --
DOCUMENT 00 73 09 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
The work is located along Elk Creek, in the Borough of Ridgway, Elk County, Pennsylvania. The general description of the work is to furnish all material, equipment, labor, layout of work, and supervision and perform the following work:
a. Excavate, remove, and dispose of, approximately 1,120 cubic yards of vegetation and other debris from 6 scour areas, 2 debris areas, 1 bridge abutment, and 1 wall area along Elk Creek.
b. Replace approximately 3,220 cubic yards of streambank protection, consisting of clearing, structural fill placement, regrading, furnishing and placing geotextile fabric and R-5 stone protection for approximately 1,830 linear feet along Elk Creek as directed by the Contracting Officer.
c. Demolish, remove and dispose of a 100 foot +/- length segmental block wall as designated by the Contracting Officer.
d. Design and replace approximately 100 linear feet of existing masonry stone retaining wall, from approximately Sta. 17+75 to Sta.
18+75 with segmental block retaining wall. The Contractor shall perform soil sampling and testing that is required to design the foundation and structure of the wall.
e. Perform all routine surveying operations related to the work, including: establishing vertical survey control from two USGS bench marks, setting four bench mark monuments along the project, and surveying all areas requiring excavation for determining quantities related to various pay items.
f. Perform debris characterization to include sampling, laboratory analysis and reporting. This work shall be completed first and prior to commencement of work.
g. Repair approximately 100 linear feet of Project Access Ramp located between project Sta. 49+00 and Sta. 50+00.
h. Excavate, remove, and dispose of approximately 225 cubic yards of material from the upstream, left abutment of the Tanner Street bridge.
Replace with flowable fill, structural backfill, select fill, and R-7 stone protection. Diversion of Elk Creek stream flow may be required to perform the work in dry conditions.
SECTION 01 11 00 Page 2
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section --
SECTION 01 11 00 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 1.1 REFERENCES
1.2 JOB PAYMENT ITEMS
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.2.1.3 Payment Item
1.2.2 Protection and Maintenance of Traffic During Construction
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.2.3 Payment Item
1.2.3 Erosion and Sediment Control
1.2.3.1 Payment
1.2.3.2 Unit of Measure
1.2.3.3 Payment Item
1.2.4 Field Survey and Set Bench Marks
1.2.4.1 Payment
1.2.4.2 Unit of Measure
1.2.4.3 Payment Item
1.2.5 Debris Sampling and Testing
1.2.5.1 Payment
1.2.5.2 Unit of Measure
1.2.5.3 Payment Item
1.2.6 Clearing
1.2.6.1 Payment
1.2.6.2 Unit of Measure
1.2.6.3 Payment Item
1.2.7 Demolition and Disposal of Debris
1.2.7.1 Payment
1.2.7.2 Unit of Measure
1.2.7.3 Payment Items
1.2.8 Design and Certification of Retaining Wall
1.2.8.1 Payment
1.2.8.2 Unit of Measure
1.2.8.3 Payment Item
1.2.9 Precast Concrete Block Retaining Wall
1.2.9.1 Payment
1.2.9.2 Unit of Measure
1.2.9.3 Payment Item
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 Digital Progress Images
1.3.1.1 Payment
1.3.1.2 Measurement
1.3.1.3 Unit of Measure
1.3.1.4 Payment Item
1.3.2 Debris Removal
1.3.2.1 Payment
SECTION 01 22 00.00 10 Page 1
1.3.2.2 Measurement
1.3.2.3 Unit of Measure
1.3.2.4 Payment Items
1.3.3 Earthwork
1.3.3.1 Payment
1.3.3.2 Measurement
1.3.3.3 Unit of Measure
1.3.3.4 Payment Items
1.3.4 Geotextile
1.3.4.1 Payment
1.3.4.2 Measurement
1.3.4.3 Unit of Measure
1.3.4.4 Payment Items
1.3.5 Stone Protection
1.3.5.1 Payment
1.3.5.2 Measurement
1.3.5.3 Unit of Measure
1.3.5.4 Payment Items
1.3.6 Concrete
1.3.6.1 Payment
1.3.6.2 Measurement
1.3.6.3 Unit of Measure
1.3.6.4 Payment Item
1.3.7 Railing Replacement
1.3.7.1 Payment
1.3.7.2 Measurement
1.3.7.3 Unit of Measure
1.3.7.4 Payment Item
1.3.8 Bituminous Pavement
1.3.8.1 Payment
1.3.8.2 Measurement
1.3.8.3 Unit of Measure
1.3.8.4 Payment Item
-- End of Section Table of Contents --
SECTION 01 22 00.00 10 Page 2
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
PENNSYLVANIA DEPARTMENT OF TRANSPORTATION (PDT)
PDT 408 (2016) Specifications
1.2 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BID SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
Payment will be made for all costs associated with the mobilization and demobilization of equipment to complete the contract. Mobilization and demobilization will be paid in accordance with Section 00700 CONTRACT
CLAUSES, DFARS 252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION.
1.2.1.2 Unit of Measure
Unit of measure: Job
1.2.1.3 Payment Item
0003 MOBILIZATION AND DEMOBILIZATION
1.2.2 Protection and Maintenance of Traffic During Construction
1.2.2.1 Payment
Payment will be made for costs associated with developing and implementing traffic control maintenance and protection measures (signing, lighting, channelization devices, etc.), including provisions for protecting and accommodating vehicular and pedestrian traffic, and any additional requirements necessary (including all required PADOT permits) to maintain
SECTION 01 22 00.00 10 Page 3 traffic within the project area, as required throughout the life of the contract. Price shall be in accordance with PDT 408, Section 901, and include all materials, labor, and equipment, and supplies associated with this work.
1.2.2.2 Unit of Measure
Unit of measure: Job
1.2.2.3 Payment Item
0004 PROTECTION AND MAINTENANCE OF TRAFFIC DURING CONSTRUCTION
1.2.3 Erosion and Sediment Control
1.2.3.1 Payment
This work is specified in Section 01 57 23.00 08 STORM WATER POLLUTION CONTROL and Section 32 92 19 SEEDING. Payment will be made for costs associated with furnishing, installing, maintaining and removing sediment and erosion controls measures; including but not limited to rock construction entrances, turf reinforcement mat, cofferdams, seeding and mulching, and pumped sediment filter bags for dewatering as shown on the drawings or as defined in the Erosion and Sediment Control Plan. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.2.3.2 Unit of Measure
Unit of measure: Job
1.2.3.3 Payment Item
0005 EROSION AND SEDIMENT CONTROLS
1.2.4 Field Survey and Set Bench Marks
1.2.4.1 Payment
This work is specified in Section 01 11 00 SUMMARY OF WORK; paragraph "Surveying Services" as a minimum. Payment shall be made for pre and post survey cross section to verify quantities. This price shall constitute full compensation for all professional surveying costs, as described, in connection with the work required under this Contract.
1.2.4.2 Unit of Measure
Unit of measure: Job
1.2.4.3 Payment Item
0006 FIELD SURVEY AND BENCH MARKS
1.2.5 Debris Sampling and Testing
1.2.5.1 Payment
This work is specified in Section 02 30 00.00 08 DEBRIS SAMPLING AND TESTING. Payment will be made for all costs associated with developing an
SECTION 01 22 00.00 10 Page 4 approved Debris Sampling and Testing Plan, all equipment, materials and labor for obtaining samples and determining the location of the samples, transportation of samples to the laboratory, all equipment, materials and labor required by the laboratory for testing and results reporting and all costs to develop, submit, revise and resubmit the Draft and Final Debris Characterization Reports.
1.2.5.2 Unit of Measure
Unit of measure: Job
1.2.5.3 Payment Item
0007 DEBRIS SAMPLING & TESTING
1.2.6 Clearing
1.2.6.1 Payment
This work is specified in Section 31 11 00.00 08 CLEARING AND GRUBBING; and Section 02 42 00.00 08 DISPOSAL OF MATERIALS. Payment will be made for costs associated with clearing, removal, and disposal of all woody debris, bushes, trees, stumps, etc., encountered within the scour repair, debris removal, and wall repair work area limits shown on the drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.2.6.2 Unit of Measure
Unit of measure: Job
1.2.6.3 Payment Item
0009 CLEARING OF VEGETATION, SCOUR REPAIR CHANNEL WITH VEGETATED SIDE
SLOPE
1.2.7 Demolition and Disposal of Debris
1.2.7.1 Payment
This work is specified in Section 02 41 00 DEMOLITION and Section 02 42 00.00 08 DISPOSAL OF MATERIALS. Payment will be made for costs associated with demolition, loading, hauling and disposal of unsuitable materials assocaited with existing stone wall, building foundation material, and exsiting railing, as well as excavation for construction for precast concrete block retaining wall. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.2.7.2 Unit of Measure
Unit of measure: Job
1.2.7.3 Payment Items
0029 DEMOLITION, REMOVAL, AND DISPOSAL PORTION OF EXISTING STONE WALL
AND BUILDING FOUNDATION MATERIAL
SECTION 01 22 00.00 10 Page 5
1.2.8 Design and Certification of Retaining Wall
1.2.8.1 Payment
Payment will be made for costs associated with the design and certification of the new segmental retaining wall.
Payment of 75% of the job price will be made after initial submittal of shop drawings and design. Remaining 25% will be paid after approval and certification of shop drawings and design.
1.2.8.2 Unit of Measure
Unit of measure: Job
1.2.8.3 Payment Item
0030 DESIGN AND CERTIFICATION OF PRECAST CONCRETE BLOCK RETAINING WALL
1.2.9 Precast Concrete Block Retaining Wall
1.2.9.1 Payment
This work is specified in Section 32 32 23 SEGMENTAL CONCRETE BLOCK RETAINING WALL; Section 31 23 00 EARTHWORK; and Section 33 40 00 STORM DRAINAGE UTILITIES. Payment will be made for costs associated with installation of precast wall units to construct new concrete retaining wall, expansion joint material, installation of PVC pipe and weep holes with stainless steel screens for drainage, placement and compaction of structural and drainage backfill, placement of geotextile, soil sampling and testing, and any other work related to the retaining wall construction. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.2.9.2 Unit of Measure
Unit of measure: Job
1.2.9.3 Payment Item
0031 PRECAST CONCRETE BLOCK WALL RETAINING WALL, INCLUDING FOUNDATION,
DRAINAGE, AND STRUCTURAL BACKFILL (COMPLETE)
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.3.1 Digital Progress Images
1.3.1.1 Payment
This work is specified in Section 01 32 33 DIGITAL PROGRESS IMAGES.
SECTION 01 22 00.00 10 Page 6
Payment will be made for costs associated with furnishing monthly digital progress images, as specified. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.3.1.2 Measurement
Measurement will be made of the number of sets of photographs taken and delivered to the Contracting Officer as approved or directed by the Contracting Officer or authorized representative. Each set shall consist of all specified hard copies and electronic copies of each photographic session as specified.
1.3.1.3 Unit of Measure
Unit of measure: Sets
1.3.1.4 Payment Item
0002 DIGITAL PROGRESS IMAGES
1.3.2 Debris Removal
1.3.2.1 Payment
This work is specified in Section 31 23 00 EARTHWORK; and Section 02 42 00.00 08 DISPOSAL OF MATERIALS. Payment will be made for costs associated with common excavation, hauling, and disposal of debris from within the project as shown on the contract drawings and as specified.
Price shall include all materials, labor, equipment, and supplies associated with this work.
Debris will be tested to determine if the material is clean fill or regulated fill. Regulated fill may require special handling, transportation and disposal requirements.
1.3.2.2 Measurement
Measurement of quantities will be made for the actual volume of debris removal completed. The volume of material removed shall be determined by the average-end-area method, based on cross sections taken by field survey prior to and after completion of common excavation, or other method approved by the Contracting Officer. The cross section surveys shall be obtained by the Contractor at a maximum 50-foot interval over the length of channel disturbance prior to and after excavation to determine the actual amount of debris removed. Volume computations shall be performed by the Contractor, and copies of all cross section data and computations shall be submitted to the Contracting Officer within 48 hours following completion of the field cross sections.
1.3.2.3 Unit of Measure
Unit of measure: Cubic Yard
1.3.2.4 Payment Items
0008 REMOVAL AND DISPOSAL OF DEBRIS IN CHANNEL
SECTION 01 22 00.00 10 Page 7
1.3.3 Earthwork
1.3.3.1 Payment
This work is specified in Section 31 23 00 EARTHWORK. Payment will be made for costs associated with scour hole and levee excavation, bank grading;
and hauling, placing, and compacting backfill material as shown in the contract drawings and as specified. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.3.3.2 Measurement
Measurement of quantities will be made for the actual volume of common excavation completed and backfill placed within the limits, lines and grades shown on the contract drawings. No allowance will be made for overdepth excavation of for the removal of any material outside the required lines unless authorized by the Contracting Officer. The volume of material removed and placed shall be determined by the average-end-area method, based on cross sections taken by field survey prior to and after completion of common excavation, or other method approved by the Contracting Officer. The cross section surveys shall be obtained by the Contractor at a maximum 50-foot interval over the length of channel disturbance prior to and after excavation to determine the actual amount of material removed. Volume computations shall be performed by the Contractor, and copies of all cross section data and computations shall be submitted to the Contracting Officer within 48 hours following completion of the field cross sections.
1.3.3.3 Unit of Measure
Unit of measure: Cubic Yard
1.3.3.4 Payment Items
0010 SLOUGHED TOE REMOVAL, SCOUR REPAIR CHANNEL WITH VEGETATED SIDE
SLOPE
0012 SELECT FILL, SCOUR REPAIR CHANNEL WITH VEGETATED SIDE SLOPE
0013 SLOUGHED TOE REMOVAL, SCOUR REPAIR CHANNEL WITH ROCK-PROTECTED
SIDE SLOPE
0014 SELECT FILL, SCOUR REPAIR CHANNEL WITH ROCK-PROTECTED SIDE SLOPE
0018 EXCAVATION, RAMP REPAIR
0022 REMOVE AND DISPOSE EXISTING ROCK AND FILL, BRIDGE ABUTMENT REPAIR
0024 STRUCTURAL BACKFILL, BRIDGE ABUTMENT REPAIR
0025 SELECT FILL, BRIDGE ABUTMENT REPAIR
1.3.4 Geotextile
1.3.4.1 Payment
This work is specified in Section 31 05 22 GEOTEXTILES USED AS FILTERS.
Payment will be made for costs associated with placement of geotextile fabric as indicated on the contract drawings. Price shall include all
SECTION 01 22 00.00 10 Page 8 materials, labor, equipment, and supplies associated with this work.
1.3.4.2 Measurement
Measurement for payment shall be by the actual area of geotextile acceptably installed based on the surface area of slope covered. All measurements for payment shall be made by or in presence of the Contracting Officer.
1.3.4.3 Unit of Measure
Unit of measure: Square Yard
1.3.4.4 Payment Items
0011 GEOTEXTILE, SCOUR REPAIR CHANNEL WITH VEGETATED SIDE SLOPE
0015 GEOTEXTILE, SCOUR REPAIR CHANNEL WITH ROCK-PROTECTED SIDE SLOPE
0019 GEOTEXTILE, RAMP REPAIR
0027 GEOTEXTILE, BRIDGE ABUTMENT REPAIR
1.3.5 Stone Protection
1.3.5.1 Payment
This work is specified in Section 31 37 16.00 08 STONE PROTECTION. Payment will be made for costs associated with furnishing and placing geotextile, aggregate material, stone rip-rap, and grout as shown in the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.3.5.2 Measurement
Measurement for payment will be made for the actual volume of stone placed within the limits, lines and grades shown on the contract drawings. The volume of material installed shall be determined by the average-end-area method based on cross sections taken by field survey prior to and after completion of stone installation or other method approved by the Contracting Officer. The cross section surveys shall be obtained by the Contractor at a maximum 50-foot interval over the length of channel disturbance prior to and after stone installation to determine the actual amount of material placed. Volume computations shall be performed by the Contractor, and copies of all cross section data and computations shall be submitted to the Contracting Officer within 48 hours following completion of the field cross sections.
1.3.5.3 Unit of Measure
Unit of measure: Cubic Yard
1.3.5.4 Payment Items
0016 AASHTO NO. 3 COARSE AGGREGATE FILL, SCOUR REPAIR CHANNEL WITH
ROCK-PROTECTED SIDE SLOPE
0017 PDT R-5 RIPRAP, SCOUR REPAIR CHANNEL WITH ROCK-PROTECTED SIDE
SLOPE
SECTION 01 22 00.00 10 Page 9
0020 AASHTO NO. 3 COARSE AGGREGATE FILL, RAMP REPAIR
0021 PDT R-4 STONE, GROUTED, RAMP REPAIR
0026 AASHTO NO. 1 COARSE AGGREGATE, BRIDGE ABUTMENT REPAIR
0028 PDT R-7 RIPRAP, BRIDGE ABUTMENT REPAIR
1.3.6 Concrete
1.3.6.1 Payment
This work is specified in Section 03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE. Payment will be made for costs associated with the installation in place of concrete for repairs at the Tanner Street bridge abutment;
including, but not be limited to, formwork, bedding, ready mix concrete, etc. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.3.6.2 Measurement
Measurement for payment shall be based upon the actual volume of concrete delivered and placed within to the limits as shown on the contract drawings and as accepted by the Contracting Officer.
1.3.6.3 Unit of Measure
Unit of measure: Cubic Yard
1.3.6.4 Payment Item
0023 FLOWABLE FILL, BRIDGE ABUTMENT REPAIR
1.3.7 Railing Replacement
1.3.7.1 Payment
This work is specified in Section 05 52 00.00 08 MISCELLANEOUS METAL.
Payment will be made for costs associated with the furnishing and installation of new railing, including concrete foundations, and all appurtenances and hardware for the execution of this work. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.3.7.2 Measurement
Measurement for payment shall be by the length of railing installed and accepted by the Contracting Officer.
1.3.7.3 Unit of Measure
Unit of measure: Linear Foot
1.3.7.4 Payment Item
0032 RAILING REPLACEMENT, PRECAST CONCRETE BLOCK RETAINING WALL
SECTION 01 22 00.00 10 Page 10
1.3.8 Bituminous Pavement
1.3.8.1 Payment
This work is specified in Section 32 22 16 BITUMINOUS PAVEMENT CONSTRUCTION. Payment will be made for costs associated with placement and compaction of aggregate base, bituminous binder course, and bituminous wearing course to the depth specified in the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.
1.3.8.2 Measurement
Measurement for pavement will be the actual area of bituminous paved surface constructed and accepted.
1.3.8.3 Unit of Measure
Unit of measure: Square Yard
1.3.8.4 Payment Item
0033 BITUMINOUS PAVEMENT BEHIND RETAINING WALL
-- End of Section --
SECTION 01 22 00.00 10 Page 11
DIVISION 01 - GENERAL REQUIREMENTS
01 32 17
CONSTRUCTION PROGRESS SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
1.2 QUALIFICATIONS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 MONITORING CONSTRUCTION PROGRESS
3.3 PROGRESS SCHEDULE - BAR CHART
-- End of Section Table of Contents --
SECTION 01 32 17 Page 1
01 32 17
CONSTRUCTION PROGRESS SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Bar Chart; G, RO
1.2 QUALIFICATIONS
The Contractor shall designate an authorized representative who shall be responsible for the preparation of all required project schedule reports.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Pursuant to the Section 00700 CONTRACT CLAUSES, FAR 52.236-15 SCHEDULE FOR CONSTRUCTION CONTRACTS, a Project Schedule as described below shall be prepared. The scheduling of construction shall be the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. A bar chart shall be prepared in accordance with paragraph PROGRESS SCHEDULE - BAR CHART. The schedule shall be submitted within 20 days after receipt of Notice to Proceed.
3.2 MONITORING CONSTRUCTION PROGRESS
The schedule shall be the basis for measuring Contractor progress. Lack of an approved schedule or scheduling personnel will result in an inability of the Contracting Officer to evaluate Contractor's progress. Failure of the Contractor to provide all information, as specified below, shall result in the disapproval of the entire Project Schedule submission and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes. In the case where Project Schedule revisions have been directed by the Contracting Officer and those revisions have not been included in the Project Schedule, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until revisions to the Project Schedule have been made.
3.3 PROGRESS SCHEDULE - BAR CHART
The progress chart to be prepared by the Contractor pursuant to Section
SECTION 01 32 17 Page 2
00700 CONTRACT CLAUSE, FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS
shall consist of a bar chart as described herein. In preparing this schedule, the scheduling of construction is the responsibility of the Contractor and contractor management personnel shall actively participate in its development. The chart may be prepared in a format proposed by the Contractor and approved by the Contracting Officer. Each activity shall include the applicable Bid Schedule item number and show the estimated cost. The chart shall be prepared in sufficient detail to clearly show the Contractor's planned progress and the relationship of the various items of work. Larger activities shall be broken down into smaller activities with clearly defined limits (i.e. Excavation between STA xx and STA yy). In general, the estimated cost of any individual activity should not exceed $50,000. The selection and number of activities shall be subject to the Contracting Officer's approval. The chart shall be updated monthly to show actual progress and percentage of work completed for each activity. The Contractor shall submit, as part of his monthly request for payment, updated copies of his progress schedule identifying the work completed during the reporting period. If the Government issues changes to the existing work or adds additional work items to the contract, the Contractor shall revise his progress schedule accordingly. All costs associated with revising the schedule shall be included as part of the modification of the contract. If the Contractor's progress falls behind his planned work effort, a revised schedule shall be furnished to show how the Contractor proposes to complete the remaining work within the contract time. If the Contractor fails to submit updates as required, the Contracting Officer may withhold approval of partial payment estimates, until such submittals are made.
-- End of Section --
SECTION 01 32 17 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 23
SURVEY AND ALIGNMENT CONTROL
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 GENERAL REQUIREMENTS
1.4.1 Existing Project Survey Control
1.4.2 Contractor Survey Controls
1.4.3 Responsibilities
1.5 QUALIFICATIONS AND EXPERIENCE
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 PROCEDURES AND METHODOLOGIES
3.2 SURVEYS
3.2.1 Surveying Services
-- End of Section Table of Contents --
SECTION 01 32 23 Page 1
SECTION 01 32 23
SURVEY AND ALIGNMENT CONTROL
PART 1 GENERAL
1.1 SUMMARY
This section addresses the overall project survey control and procedure requirements to meet all survey/positional accuracy requirements for this contract.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-1005 (2007) Control and Topographic Surveying
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Qualifications and Experience; G, RO
The Contractor shall submit for approval evidence of the Professional Land Surveyor who will oversee all surveying as required under this contract.
Survey Plans; G, RO
The Contractor shall submit a detailed plan showing the equipment and calibration records, field data collection and data processing procedures, and QC procedures.
1.4 GENERAL REQUIREMENTS
1.4.1 Existing Project Survey Control
Existing project baseline stationing has been established for this work.
Existing horizontal and vertical control to be used to layout the project baselines is shown on the drawings.
1.4.2 Contractor Survey Controls
All new work to be constructed under this contract shall be constructed accurately from measurements made from project baselines and survey control
SECTION 01 32 23 Page 2 points established by the Contractor as necessary to construct all work within the proper alignment. The Contractor shall establish the project baselines shown and any other temporary survey control as may be necessary to carry out the requirements of this contract. All temporary control shall be based off the existing project control. The Contractor shall verify the elevations and positions of the existing project controls before using them to establish the project baselines and his survey control points, and shall notify the Contracting Officer of any discrepancies prior to commencing work. Any questions or problems concerning the survey control may be directed to the Land Surveyor, Geospatial Section, Dam and Levee Safety Branch, Engineering and Construction Division at 412-395-7564.
1.4.3 Responsibilities
The Contractor has the overall responsibility to determine the procedures, equipment, and methodologies to perform all survey requirements outlined in these plans and specifications. The Government has the right to review and approve all survey plans but approval does not relieve the Contractor of the responsibility to satisfy all positional accuracy and tolerance requirements of these plans and specifications.
1.5 QUALIFICATIONS AND EXPERIENCE
The Contractor shall have a Professional Land Surveyor licensed in the Commonwealth of Pennsylvania on staff who responsible for all survey work performed as part of this contract.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 PROCEDURES AND METHODOLOGIES
The Contractor shall use the appropriate survey equipment and procedures as deemed necessary to assure the positional accuracy requirements are met or exceeded as called for throughout this contract. The Contractor will be required to submit survey plans throughout this contract in accordance with other technical sections of this specification. These plans shall include detailed descriptions of the procedures and equipment that will be used for that requirement.
3.2 SURVEYS
All surveys performed as part of this contract shall be done in accordance with EM 1110-1-1005. Where requirements in other sections of these specifications exceed those outlined in the referenced EM, the requirements in these specifications shall take precedence over the EM and the Contractor shall be required to establish a plan to meet or exceed the requirements.
3.2.1 Surveying Services
The Contractor shall set four vertical control bench marks along the Elk Creek Project as indicated by the Contracting Officer. Bench marks shall be placed at each work area as directed by the Contracting Officer.
The Contractor shall use United States Geological Survey (USGS) bench marks KX1213 and KX1211 as starting or ending points to set the elevations. The above USGS bench marks were last found to be in good condition by PennDoT
SECTION 01 32 23 Page 3 in 2001. If both of the above USGS bench marks cannot be found, the Contractor shall establish vertical elevations for the four (4) bench marks by GPS Real-Time Kinematic(RTK)Positioning Method.
Vertical elevations shall be set using NAVD 29. The accuracy of the vertical control survey shall be in accordance with the construction survey accuracy standards in EM 1110-1-1005. The survey work shall be performed by a land surveyor licensed in the State of Pennsylvania.
A 1/2" diameter steel rod (6 inches in length) shall be set, drilled, and epoxy grouted, 1/2" above the top of the concrete structure shown on the drawings or indicated by the Contracting Officer.
The Contractor shall provide a report with maps, drawings, elevations, coordinates and field survey data that describes and shows the location of the USGS bench marks and the four newly established bench marks.
-- End of Section --
SECTION 01 32 23 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 33
DIGITAL PROGRESS IMAGES
PART 1 GENERAL
1.1 SCOPE
1.2 SUBMITTALS
1.3 GENERAL REQUIREMENTS
1.3.1 Description
1.3.2 Digital Photographs
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 EQUIPMENT
3.2 PHOTOGRAPHY
-- End of Section Table of Contents --
SECTION 01 32 33 Page 1
SECTION 01 32 33
DIGITAL PROGRESS IMAGES
PART 1 GENERAL
1.1 SCOPE
The work under this section includes furnishing digital photographs showing the progress of the construction operations throughout the contract period.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having an "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-11 Closeout Submittals
Thumbnail Hard Copy Prints of Progress Images; G, RO Glossy Prints of Selected Official Progress Images; G, RO Electronic Copy of Selected Official Progress Images; G, RO Electronic Copy of All Other Progress Images
Copies of digital progress images in electronic form and hard copy form shall be submitted monthly for approval in accordance with paragraph PHOTOGRAPHY. Progress images shall be submitted in a timely manner as coordinated with the Contracting Officer.
1.3 GENERAL REQUIREMENTS
1.3.1 Description
The Contractor shall, during the progress of the project (including progress of fabrication), furnish the Contracting Officer progress photographs to depict progress of construction throughout the life of the contract. The photographs shall be taken using digital photography equipment furnished by the Contractor. Electronic copies of approved photographs shall be furnished on CD-ROM or other storage media as approved by the Contracting Officer.
1.3.2 Digital Photographs
Digital photographs shall comply with the requirements of paragraph PHOTOGRAPHY. The Contractor shall furnish, using Microsoft Word 97 or later version, a file with each set of photographs which lists the following identifying information for each photographic image:
Name and location of project Contract number Date taken Contractor (and subcontractor, if applicable) Orientation of view and brief description of work depicted
SECTION 01 32 33 Page 2
Each photograph shall be sequentially numbered. The identifying data shall be placed in the document accompanying the photographs. No identifying data, except the date stamp, shall appear on the photographs.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 EQUIPMENT
The Contractor shall be responsible for furnishing all photographic equipment to perform the work specified by this section. The camera shall have a CCD resolution no less than 7.0 million pixels per image (3072 by 2304) which will provide enough detail to print an 8" by 10" high-resolution photograph. The camera shall produce files that allows the user to download the images onto an IBM-compatible personal computer running Windows XP, and allow the images to be saved in one of the following graphic formats: JPG (Joint Photographic Experts Group), TIFF (Tagged Image File Format) or BMP (Windows Bitmap).
3.2 PHOTOGRAPHY
The Contractor shall, during the progress of the work, furnish the Contracting Officer digitally produced progress photographs to depict the progress of the work both on-site and off-site at fabrication facilities.
All progress images shall be taken at the camera's highest resolution. In coordination with the Contracting Officer, one set of progress photographs per month shall be taken over the full duration of this contract, except photographs will not be required for periods when no work is in progress.
Thumbnail Hard Copy Prints of Progress Images shall be submitted to the Contracting Officer for approval between the first and fifth day of each month. The Contracting Officer will select from the thumbnail views, unless directed otherwise, at least ten views to become official progress images. The selected official progress images shall be printed in color in 8" by 10" format, shall be identified on the back in accordance with paragraph Digital Photographs, and shall be submitted for approval. Glossy Prints of Selected Official Progress Images and Electronic Copy of Selected Official Progress Images shall be furnished within ten days of approval of the thumbnail images. Electronic copies shall be furnished on CD-ROM with file of required photographic information. Electronic Copy of All Other Progress Images (including those not selected) shall be furnished on separate CD-ROM with file of required photographic information with the selected official progress images. Digital photographs shall be taken continuously throughout each month in which work is in progress. Unless otherwise directed by the Contracting Officer, photographs will not be required for periods of time in which work is not being performed.
Additional sets of photographs shall be taken as directed by the Contracting Officer. Enough digital photographs shall be taken to adequately depict each phase of the work and shall show progress made during those phases and at the completion of the project. Digital photographs shall show work accomplished since the previous photographs.
Progress photographs shall be submitted as specified herein and in paragraph SUBMITTALS.
The area between Station 103+00 and Station 118+00 on Sheet Identification Number C-104 shall have pre-condition documentation to include photographs and video of the area. Photographs shall be taken of this area as construction progresses at intervals not to exceed more than 1 month or more often as deemed necessary by the Contracting Officer. Additionally, SECTION 01 32 33 Page 3 any areas where construction activities occurred but may have been excluded in the pre-condition photos and video shall also be documented with photos and video.
-- End of Section --
SECTION 01 32 33 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved
1.4.2 Information Only
1.5 PREPARATION OF CONSTRUCTION SUBMITTALS
1.5.1 Transmittal Form
1.5.2 Electronic File Format
1.6 QUANTITY OF SUBMITTALS
1.7 INFORMATION ONLY SUBMITTALS
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting That Variations Are Compatible
1.8.4 Review Schedule Is Modified
1.9 SUBMITTAL REGISTER
1.9.1 Use of Submittal Register
1.9.2 Contractor Use of Submittal Register
1.9.3 Approving Authority Use of Submittal Register
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations samples remaining upon completion of the work.
All submittals shall be in English.
Section 00700 CONTRACT CLAUSES, FAR 52.236-5, MATERIAL AND WORKMANSHIP, paragraph (b) and FAR 52.236-21, Specifications and Drawings for Construction, paragraphs (d), (e), and (f) apply to all submittals.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to a start of construction work.
Submittals required prior to the start of the next major phase of the construction on a multi-phase contract. Schedules or tabular list of data or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work, submitted prior to commencement of construction to
SECTION 01 33 00 Page 2 which the submittal applies.
Certificates of insurance
Surety bonds
List of proposed subcontractors
List of proposed products
Submittal register
Schedule of prices
Health and safety plan
Work plan
Quality control(QC) plan
Environmental protection plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
Unless otherwise specified, shop drawings shall be 22" x 34". Approved shop drawings shall also be submitted electronically on CD-ROM or DVD.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish
SECTION 01 33 00 Page 3 standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
SECTION 01 33 00 Page 4
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G, RO
Submit the Submittal Register within 30 days after receipt of the Notice to Proceed.
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Within the terms of Section 00700 CONTRACT CLAUSES, FAR 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."
1.4.2 Information Only
Submittals not requiring Government approval will be for information only.
They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 PREPARATION OF CONSTRUCTION SUBMITTALS
1.5.1 Transmittal Form
Use the attached sample transmittal form (ENG Form 4025) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form.