About this file

Revised Specification 01 22 00.00 10 - W911WN09B0014-0004 Mahoning Guard Rails

View the file

Other files

File Type Posted
BidResults for W911WN09B0014.pdf PDF
HPIM5225.JPG JPG image
HPIM5228.JPG JPG image
100_0229.jpg JPG image
HPIM5217.JPG JPG image
BidSched-Am0004.pdf PDF
W911WN-09-B-0014-0004.zip ZIP file
32 30 00.pdf PDF
W911WN09B0014-0004.pdf PDF
CC Bid Sheet 09B00014.doc DOC document
W911WN09B0014-0003.pdf PDF
W911WN09B0014-0002.pdf PDF
W911WN09B0014-0001.pdf PDF
W911WN-09-B-0014.zip ZIP file
Specs MAH Guard Rails.pdf PDF
W911WN09B0014.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mahoning Dam, Guardrail Replacement

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 LUMP SUM PAYMENT ITEMS

1.1.1 Project Sign

1.1.1.1 Payment

1.1.1.2 Unit of Measure

1.1.1.3 Payment Item

1.2 UNIT PRICE PAYMENT ITEMS

1.2.1 Digital Progress Images

1.2.1.1 Payment

1.2.1.2 Measurement

1.2.1.3 Unit of Measure

1.2.1.4 Payment Item

1.2.2 Guardrail Replacement

1.2.2.1 Payment

1.2.2.2 Measurement

1.2.2.3 Unit of Measure

1.2.2.4 Payment Item

1.2.3 Steel Handrail Replacement and Installation

1.2.3.1 Payment

1.2.3.2 Measurement

1.2.3.3 Unit of Measure

1.2.3.4 Payment Item

1.2.4 Posts

1.2.4.1 Payment

1.2.4.2 Measurement

1.2.4.3 Unit of Measure

1.2.4.4 Payment Item

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section Table of Contents --

SECTION 01 22 00.00 10 Page 1 W911WN-09-B-0014 Revised by Amendment 0004

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 LUMP SUM PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE in Section 00010 SUPPLIES OR SERVICES AND PRICES/COSTS and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Project Sign

1.1.1.1 Payment

Payment will be made for costs associated with furnishing, installing, maintaining and removing project sign as specified in Section 01 50 10

PROJECT SIGNS.

1.1.1.2 Unit of Measure

Unit of measure: lump sum.

1.1.1.3 Payment Item

0002 ARRA - Project Sign

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular unit price payment item, shall be included in the listed unit price item most closely associated with the work involved. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.2.1 Digital Progress Images

1.2.1.1 Payment

Payment for monthly progress images shall constitute full compensation for all labor, equipment, material and supply costs for furnishing monthly digital progress images, as specified in Section 01 32 33 DIGITAL PROGRESS

IMAGES.

SECTION 01 22 00.00 10 Page 2

1.2.1.2 Measurement

Measurement will be made of the number of sets of progress images satisfactorily furnished as specified or directed.

1.2.1.3 Unit of Measure

Unit of measure: Sets.

1.2.1.4 Payment Item

0003 ARRA - DIGITAL PROGRESS IMAGES

1.2.2 Guardrail Replacement

1.2.2.1 Payment

This work is specified in Section 32 30 00 INCIDENTAL CONSTRUCTION.

Payment will be made for costs associated with removal and disposing of existing guardrail (chain link fence, damaged rail elements, and hardware, and posts where required) and furnishing and installing the new steel beam guardrail as specified and new posts as required. Payment shall include drilling guardrail element as required to match existing post spacing and repair of damaged galvanizing.

1.2.2.2 Measurement

Guardrail will be measured for payment by the linear foot. Measurement shall be made along the top edge of the completed guardrail in place and to the end of terminal elements. Length measured at terminal elements shall not include the portion of the terminal element that curves back on itself from the extreme end of the terminal element. No extra length will be given or payment made for overlaps of rail elements or between rail elements and terminal elements.

1.2.2.3 Unit of Measure

Unit of Measure: Linear Feet.

1.2.2.4 Payment Item

0004 ARRA - REPLACE CHAIN LINK FENCE GUARDRAIL

0005 ARRA - REPLACE DAMAGED GUARDRAIL

1.2.3 Steel Handrail Replacement and Installation

1.2.3.1 Payment

This work is specified in Section 05 52 00 METAL RAILINGS. Payment for rail replacement will be made for costs associated with removal and disposing of existing steel pipe rail (top and/or bottom rails as indicated) and furnishing and installing steel pipe rail as shown on the drawings and as specified. Payment for new steel handrail will be made for costs associated with furnishing and installing new steel pipe handrail at the steps as shown on the drawings and as specified.

SECTION 01 22 00.00 10 Page 3

1.2.3.2 Measurement

Replacement of rail and new handrail will be measured for payment by the linear foot. Measurement shall be made along the top edge of the rail in place and to the end of new rail. Measurement of new handrail will be made along the top rail.

1.2.3.3 Unit of Measure

Unit of Measure: Linear Feet.

1.2.3.4 Payment Item

0006 ARRA - REPLACE DAMAGED STEEL PIPE HANDRAIL, TOP RAIL

0007 ARRA - REPLACE DAMAGED STEEL PIPE HANDRAIL, TOP RAIL

0008 ARRA - FURNISH AND INSTALL NEW STEEL PIPE HANDRAIL

1.2.4 Posts

1.2.4.1 Payment

This work is specified in Section 32 30 00 INCIDENTAL CONSTRUCTION.

Payment will be made for costs associated with removal and disposing of existing guardrail posts for the chain link fence guard rail and for damaged steel beam guardrail where required and approved by the Contracting Officer.

1.2.4.2 Measurement

Posts replaced will be measured by the number of new posts installed as approved by the Contracting Officer.

1.2.4.3 Unit of Measure

Unit of Measure: Linear Feet, Each.

1.2.4.4 Payment Item

0009 ARRA - NEW GUARDRAIL POSTS

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 22 00.00 10 Page 4

01 22 00.00 10 - MEASUREMENT AND PAYMENT
01 22 00.00 10 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENT ITEMS
1.1.1 Project Sign
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.1.3 Payment Item
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Digital Progress Images
1.2.1.1 Payment
1.2.1.2 Measurement
1.2.1.3 Unit of Measure
1.2.1.4 Payment Item
1.2.2 Guardrail Replacement
1.2.2.1 Payment
1.2.2.2 Measurement
1.2.2.3 Unit of Measure
1.2.2.4 Payment Item
1.2.3 Steel Handrail Replacement and Installation
1.2.3.1 Payment
1.2.3.2 Measurement
1.2.3.3 Unit of Measure
1.2.3.4 Payment Item
1.2.4 Posts
1.2.4.1 Payment
1.2.4.2 Measurement
1.2.4.3 Unit of Measure
1.2.4.4 Payment Item
PART 2 PRODUCTS NOT APPLICABLE
PART 3 EXECUTION NOT APPLICABLE