This document is an amendment to a solicitation providing answers to questions received from potential vendors for a construction project. The amendment revises drawings and clarifies that both upstream and downstream channels must be regraded 200 feet from culvert edges. Dimensions shown in plans have been revised to match New Mexico Department of Transportation standards for precast concrete box culverts. The 8-barrel 12x10 culverts must be precast. Temporary materials will be retained by the government. The project involves construction of 8 prefabricated concrete box culverts using 2019 New Mexico Department of Transportation specifications and standards. Borrow material may be used for earth berms and asphalt pavement will be laid in one lift.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this amendment is as follow s:
A. This amendment w ill provide answ er to all questions received during the solicitation phase.
B. All questions received from potential vendors and answ ers from the contracting office are verbatim.
C. This amendment w ill also provide revised draw ings.
D. All other terms and conditions remain the same.
-Please see continuation page 14 for all questions and answ er.
-Revised Draw ings w ill be included as an attachment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-Sep-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911SG23B0003
X 9B. DATED (SEE ITEM 11)
31-Aug-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-Sep-2023
CODE
MICC - FORT BLISS (919TH CBN)
111 PERSHING RD
FT BLISS TX 79916
W911SG 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911SG23B0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
QUESTIONS AND ANSWERS
Sheet 05 – Pre‐Cast Box Culvert Item 4: “Approved Waterproofing membrane and adhesive shall extend to outside barrels and one foot lap down out wall.”
Question: Is there a list of Approved waterproofing membrane & adhesive?
Answer: Yes NMDOT APL (Approved Product List)
Question: Are there any details on the Waterproofing membrane?
Answer: NMDOT Standard Drawings 511‐66‐5/6, 2019 Edition Standard Specifications for Highway and Bridge Construction section 511
Sheet 05 – Pre‐Cast Box Culvert Item 8: “Re‐grade and compact upstream and downstream channel bed 200’ from edge of apron and full width.”
Question: Drawing only shows downstream side just want to confirm both sides need the 200’?
Answer: Yes, both sides require 200’ of re‐grading.
Sheet 07 ‐ Under Guardrail Notes Item 2: “Accepted systems, on the Departments Approved Product List, shall be installed according to manufactures’ installation instructions.”
Question: Which Department?
Answer: NMDOT
Question: Where is Approved Product List located?
Answer: NMDOT website.
Question: Can the Prebid attendance sheet be released with the Q/A’s?
Answer: Yes, the sign in sheet will be posted to SAM.gov with all redacted government personnel information.
Question: The drawings call for precast culverts, however the dimensions shown on Plan Sheet 5 do not reflect precast boxes. Dimensions for the interior walls show 12” total or 6” for each box and the exterior walls show 9”. And there is no space between the boxes. Pre‐casting this size box is not advised since the walls will not be sufficient to withstand the forces from casting, loading, hauling, unloading and setting.
There is adequate time in the contract, and casting the boxes in place would provide a better, more cost‐effective solution. However, we feel the dimensions should be revised to reflect NMDOT standards which the drawings do reference. The comparison of the drawings versus NMDOT standards are as follows:
Answer: NMDOT standards call for the following (NMDOT Standard drawings 511):
NMDOT
Top slab 13.5
Bottom Slab 14.5
Exterior walls 11
Interior walls 9.5
Question: Please consider allowing a cast‐in‐place option to construct the 8 barrel 12 x 10 box culverts. And please consider revising the dimensions to reflect the NMDOT standards.
Answer: Plans have been revised to reflect NMDOT standards (Sheet 5). The 8‐12X10 culverts shall be pre‐cast.
Question: Does the bypass road get asphalt paved? If so, Can you please provide a roadway detail?
Answer: The bypass does not get paved.
Question: Does the contractor need to provide a meter to connect at the fire hydrant (water supply)?
Answer: Yes
Question: Are the temporary 48” CMPs going to be retained by the government after the completion of the project?
Answer: The temporary 48” CMPs shall be retained by the Government.
Question: Can we use material from the borrow pit to construct the earth berms?
Answer: Yes
Question: Can we pave back the 3” HMA pavement in one lift?
Answer: Yes
Question: What edition of the NMDOT specs and standards apply to this project?
Answer: STANDARD SPECIFICATION FOR HIGHWAY AND BRIDGE CONSTRUCTION NEW MEXICO DEPARTMENT OF TRANSPORTATION 2019 EDITION and New Mexico Department of Transportation Standard Drawings for Highway and Bridge Construction 2019 Edition. Per SOW Part 13 & 14.
Question: Do the NMDOT standard drawings apply to the project?
Answer: Yes
Question: Should we backfill the box culvert/wing walls based on the NMDOT standard drawing 210‐01‐1/1?
Answer: Yes
(End of Summary of Changes)