OSUT_1_01_57_20_Environmental_Protection.pdf

PDF 55 KB Posted

Attached to
Armor OSUT 1 Federal contract opportunity
Solicitation number
W911SF-19-R-0018
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Benning

About this file

Enviro Protection

View the file

Other files for this federal contract opportunity

Other files attached to Armor OSUT 1, newest first.
File Type Posted
Attachment_4_Performance_Assessment_Questionnaire.pdf PDF
OSUT_1_31_31_16_Soil_Treatment_for_Subt_Termites_Control.pdf PDF
W911SF-19-R-0018-0002,_ARMOR_OSUT_1,_Amend_0002.pdf PDF
OSUT_1_07_27_26_Fluid_Applied_Air_and_Moisture_Barrier.pdf PDF
OSUT_1_08_71_00_Door_Hardware.pdf PDF
OSUT_1_10_14_02_Interior_Signage.pdf PDF
OSUT_1_31_11_00_Clearing_and_Grubbing.pdf PDF
OSUT_1_01_78_23_Operation_an_Maintenace_Data.pdf PDF
OSUT_1_23_07_00_Thermal_Insulation_for_Mechanical_Systems.pdf PDF
OSUT_1_32_31_13_High-Security_Chain_Link_Fences.pdf PDF
OSUT_1_04_21_13_13_Nonbearing_Masonry_Veneer_Steel_Stud_Walls.pdf PDF
OSUT_1_07_42_13_Metal_Wall_Panels.pdf PDF
OSUT_1_08_81_00_Glazing.pdf PDF
OSUT_1_23_37_13_Diffusers,_Registers,_and_Grills.pdf PDF
OSUT_1_04_20_00B_Masonry.pdf PDF
OSUT_1_C2_Facility_Combined.pdf PDF
OSUT_1_07_61_14_Steel_Standing_Seam_Roofing.pdf PDF
OSUT_1_Covered_Mess_Combined.pdf PDF
OSUT_1_03_31_00.00_10_Cast-In-Place_Sturctural_Concrete.pdf PDF
OSUT_1_23_82_02_Unitary_Heating_and_Cooling_Equip.pdf PDF
OSUT_1_07_21_16_Mineral_Fiber_Blanket_Insulation.pdf PDF
OSUT_1_09_90_00_Paints_and_Coatings.pdf PDF
OSUT_1_44026_Stevon_Booker_Oscar_14_Nad_83_Site_Plan_Mod.pdf PDF
OSUT_1_09_51_00_Acoustical_Ceilings.pdf PDF
OSUT_1_32_01_19_Field_Molded_Sealants_for_Sealing_Jts_In_Rigid_Pavg.pdf PDF
OSUT_1_01_35_29_Safety_and_Occupational_Health_Requirements.pdf PDF
OSUT_1_23_00_00_Air_Supply_Venti_and_Exhaust_Sys.pdf PDF
OSUT_1_08_33_13.00_10_Metal_Rolling_Counter_Doors.pdf PDF
OSUT_1_09_68_00_Carpet.pdf PDF
OSUT_1_13_34_19_Metal_Building_Systems.pdf PDF
OSUT_1_31_23_00_Excavation_and_Fill.pdf PDF
OSUT_1_03_11_13_00_10_Structural_Concrete_Formwork.pdf PDF
OSUT_1_08_51_13_Aluminum_Windows.pdf PDF
OSUT_1_26_00_00_Basic_Electrical_Materials_and_Methods.pdf PDF
OSUT_1_31_32_11_Soil_Surface_Erosion_Control.pdf PDF
OSUT_1_Lafayette_Pool_Oscar_15_Nad_83_Grading_Plan_Sheet_1_Mode.pdf PDF
OSUT_1_01_62_35_Recycled_Recovered_Materails.pdf PDF
OSUT_1_07_60_00_Flashing_And_Sheet_Metal.pdf PDF
OSUT_1_Lafayette_Pool_Oscar_15_Nad_83_Site_Plan_Sheet_1Model_(.pdf PDF
OSUT_1_1_Spec_Cover_and_Table_of_Contents_FT_Benn.docx DOCX document
AR_OSUT__1_General_Requirements.pdf PDF
Statement_of_Work_-_CTA_Covered_Bleachers.pdf PDF
Statement_of_Work_-_Covered_Mess.pdf PDF
Statement_of_Work_-_Latrine_(flushable)_and_leach_field.pdf PDF
Statement_of_Work_-_OSCAR_15.pdf PDF
SOW_Cover_Sheet_-_Warner_Range.pdf PDF
Statement_of_Work_-_Control_Tower_(Small_Arms)_CMU_Version.pdf PDF
Statement_of_Work_-_C2_Facility.pdf PDF
Statement_of_Work_-_Ammo_Point_(single).pdf PDF
W911SF-19-R-0018,_ARMOR_OSUT_1,_wdr,_26Jun19.pdf PDF
Show all 50

Armor OSUT 1 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OUST-AR RANGE PROJECTS FY19

SECTION 01 57 20.00 10

ENVIRONMENTAL PROTECTION

USE FILE COPY

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. AIR FORCE (USAF)

AFI 32-1053 (1999) Pest Management Program

U.S. ARMY (DA)

DA AR 200-5 (1999) Pest Management

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2008) Safety and Health Requirements Manual

WETLAND MANUAL Corps of Engineers Wetlands Delineation Manual Technical Report Y-87-1

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

33 CFR 328 Definitions of Waters of the United States

40 CFR 150 - 189 Pesticide Programs

40 CFR 260 Hazardous Waste Management System: General

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 262 Standards Applicable to Generators of Hazardous Waste

40 CFR 279 Standards for the Management of Used Oil

40 CFR 302 Designation, Reportable Quantities, and Notification

40 CFR 355 Emergency Planning and Notification

40 CFR 68 Chemical Accident Prevention Provisions

49 CFR 171 - 178 Hazardous Materials Regulations

1.2 DEFINITIONS

1.2.1 Environmental Pollution and Damage

Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life;

affect other species of importance to humankind; or degrade the environment aesthetically, culturally and/or historically.

1.2.2 Environmental Protection

Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.

1.2.3 Contractor Generated Hazardous Waste

Contractor generated hazardous waste means materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e. methyl ethyl ketone, toluene etc.), waste thinners,excess paints, excess solvents, waste solvents, and excess pesticides, and contaminated pesticide equipment rinse water.

1.2.4 Installation Pest Management Coordinator

Installation Pest Management Coordinator (IPMC) is the individual officially designated by the Installation Commander to oversee the Installation Pest Management Program and the Installation Pest Management Plan.

1.2.5 Project Pesticide Coordinator

The Project Pesticide Coordinator (PPC) is an individual that resides at a Civil Works Project office and that is responsible for oversight of pesticide application on Project grounds.

1.2.6 Land Application for Discharge Water

The term "Land Application" for discharge water implies that the Contractor must discharge water at a rate which allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "waters of the United States" must occur. Land Application must be in compliance with all applicable Federal, State, and local laws and regulations.

1.2.7 Pesticide

Pesticide is defined as any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, or intended for use as a plant regulator, defoliant or desiccant.

1.2.8 Pests

The term "pests" means arthropods, birds, rodents, nematodes, fungi, bacteria, viruses, algae, snails, marine borers, snakes, weeds and other organisms (except for human or animal disease-causing organisms) that adversely affect readiness, military operations, or the well-being of personnel and animals; attack or damage real property, supplies, equipment, or vegetation; or are otherwise undesirable.

1.2.9 Surface Discharge

The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers,creeks, and/or "waters of the United States" and would require a permit to discharge water from the governing agency.

1.2.10 Waters of the United States

All waters which are under the jurisdiction of the Clean Water Act, as defined in 33 CFR 328.

1.2.11 Wetlands

Those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, and bogs. Official determination of whether or not an area is classified as a wetland must be done in accordance with WETLAND MANUAL.

1.3 GENERAL REQUIREMENTS

Minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work must be protected during the entire duration of this contract. Comply with all applicable environmental Federal, State, and local laws and regulations.

Any delays resulting from failure to comply with environmental laws and regulations will be the Contractor's responsibility.

1.4 SUBCONTRACTORS

Ensure compliance with this section by subcontractors.

1.5 PAYMENT

No separate payment will be made for work covered under this section.

Payment of fees associated with environmental permits, application, and/or notices obtained by the Contractor, and payment of all fines/fees for violation or non-compliance with Federal, State, Regional and local laws and regulations are the Contractor's responsibility. All costs associated with this section must be included in the contract price.

1.6 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Environmental Protection Plan; G

The environmental protection plan.

-- End of Section --