Attachment 2 – Deliverables
GENERAL Deliverables (Apply to all tasks)
Deliverable Frequency # of Copies Medium/Format Submit To Post Award Planning Conference presentation.
(Ref. Para.1.5.10)
NLT C - 15
1 Original and 2 copies
In person - CD & Hardcopy in PPT and word.
COR - @
WHINSEC,
FBGA
Contract Kick - off conference presentation.
(Ref. Para. 1.5.10)
NLT C + 5
1 Original and 2 copies
In person - CD & Hardcopy in PPT and word.
COR - @
WHINSEC,
FBGA
Contractor provides information briefing to the Government outlining Contractor plan of action to complete all tasks.
(Ref. Para. 1.5.10)
NLT C + 5 1 Original and 2 copies
At Kick-off conference, for all tasks - CD & Hardcopy in PPT, excel, and Word.
COR - @
WHINSEC,
FBGA
Contractor delivers fully qualified and capable contractor personnel.
(Ref. para. 1.5.9)
NLT C + 5 At least 1 personnel at start.
COR - @
FBGA
Provide Quality Control Plan (Ref. Para. 1.5.1)
NLT C + 5 1 Original Signed hardcopy word document & electronic
COR - @
WHINSEC,
FBGA
Invoice (Ref. Para. 1.5.11)
NLT 5
business days after the end of every 30-day performance
1 Original electronic WAWF(iRAPT)
Preliminary Design Review (Ref. Para. 5.7.1)
NLT C + 30 1 Original and 2 copies
CD &
Hardcopy in PPT and word.
COR - @
FBGA
Administrative Requirements (Apply to all tasks)
Provide staffing plan (Ref. Para. 1.5.10)
NLT C + 5 1 Original and 2 copies
CD /Hardcopy in PPT and word.
COR - @
Provide Project / Task Order Manager (Ref. 1.5.12)
NLT C + 5 COR - @
Provide certificates of completion of all required training by contractor personnel. AT Training, IWATCH Training, Cyber Awareness Training (Ref. para. 1.6)
NLT C+5
days
1 copy Hard Copy or digital
COR - @
Bi-weekly Meetings (Ref. Para. 1.5.6)
NLT C+30,
and then Bi- Wkly.
In person WHINSEC, FBGA
Monthly report-Status (Ref. Para. 1.5.11)
NLT noon on the first business day of the following Month.
1 Original Digital in MS word format via email
COR - @
Contractor Manpower Report (Ref. Para. 5.8)
Prior to 1 Oct or at the end of the work performance period which ever come first.
Submitted electronically http://www.ecmra.mil