W911SA22Q3029 Solicitation.pdf

PDF 1 MB Posted

Attached to
Grounds Services Multi-site UT034; UT010 & UT032 Federal contract opportunity
Solicitation number
W911SA22Q3029
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort McCoy

View the file

Other files for this federal contract opportunity

Other files attached to Grounds Services Multi-site UT034; UT010 & UT032, newest first.
File Type Posted
W911SA22Q3029 Attachment 3 (UT032 Drawing) updated.pdf PDF
W911SA22Q3029 Amendment 1.pdf PDF
W911SA22Q3029 Attachment 1 (Price Schedule -blank) CUI.xlsx XLSX spreadsheet
W911SA22Q3029 Attachment 2 (UT010 Drawing).pdf PDF
W911SA22Q3029 Attachment 3 (UT032 Drawing).pdf PDF
W911SA22Q3029 Attachment 5 (Grounds Sample Service Ticket).docx DOCX document
W911SA22Q3029 Attachment 4 (AT OPSEC) CUI.pdf PDF
W911SA22Q3029 Attachment 6 (Universal Pest Management Form).docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W911SA22Q3029 15-Jun-2022

b. TELEPHONE NUMBER 8. OFFER DUE DATE/LOCAL TIME

10:00 AM 24 Jun 2022

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W911SA9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

AMY LEWELLEN

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

0011654964

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

W6QM MICC FT MCCOY (RC)

KO DIRECTORATE OF CONTRACTIN

BLDG 1108 SOUTH R STREET

FORT MCCOY WI 54656-5142

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE W919H3 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

W6KG 88 RSC FTS TDA

W6KG 88 RSC FTS TDA

60 SOUTH O STREET

FORT MCCOY WI 54656-5137

TEL: 910-570-9420 FAX:

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$8,000,000

NAICS:

561730

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF85

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W911SA22Q3029

Section SF 1449 - CONTINUATION SHEET

SUPPLEMENTAL

1. An Award for this requirement will be made pursuant to FAR 13, Simplified Acquisition Procedures.

2. The period of performance is anticipated to be July 1, 2022 to June 30, 2023, with four (4) one (1) year options periods, and a six (6) month option to extend services.

3. Quotes shall be emailed to amy.e.lewellen.civ@army.mil. Quotes are due to the Government on or before the date/time listed on the solicitation in central time. It is the contractor’s responsibility to ensure their quote is received by the due date and time. As an Addendum to FAR 52.212-1, contractor shall submit all items in accordance with the Supplemental Information by the solicitation closing date and time. The contractor SHALL provide all required documents with submission of quotes.

Signed SF 1449

Completed information from the Supplemental Information section of the solicitation

Completed Price Schedule Attachment 1

Signed Amendments (if applicable)

If all required documents are not provided with the quote submission, your quote MAY NOT be considered for award.

4. If a quote is based on a teaming/partnering relationship or a joint venture, the contractor shall provide, with the quote, all required solicitation information for all parties including a copy of the teaming/partnering or joint venture agreement. The agreement shall include information, which identifies the responsibilities for each entity under this contract. The agreement shall demonstrate the relationship between firms and identify contractual relationships and authorities to bind each entity of the teaming/partnering or joint venture relationship.

5. This procurement is Set Aside as 100% Total Small Business NAICS Code 561730 with a size standard of

$8 Million.

6. Prior Contract Information Location UT010

Previous Contract Number for UT010: W911SA-17-P-3013

Incumbent Contractor for UT010: Bailey’s Premier Services LLC

As of 27 June 2017, Total Contract Value (TCV): $32,500.00*

*TCV calculated with base, all options and a six (6) month option to extend services.

Prior Contract Information Location UT0032

Previous Contract Number for UT032: W911SA-17-P-3017

Incumbent Contractor for UT032: Bailey’s Premier Services LLC

As of 27 June 2017, Total Contract Value (TCV): $91,870.22*

*TCV calculated with base, all options and a six (6) month option to extend services.

7. Period for acceptance of quotes. The contractor agrees to hold the prices in its quote firm for 90 calendar days from the date specified for receipt of quotes.

8. Site visit: *** A site visit will be held on Tuesday, June 21, 2022 at the following places of performance:

DATE: Tuesday, June 21, 2022 at 10:00 A.M. Local Time

ARMY RESERVE FACILITY UT010

4550 S. 1300 E.

SALT LAKE CITY, UT 84117

mailto:amy.e.lewellen.civ@army.mil

AND

DATE: Tuesday, June 21, 2022 at 11:00 A.M. Local Time

ARMY RESERVE FACILITY UT032

5290 W. 700 S.

SALT LAKE CITY, UT 84104

The POC for the solicitation is Amy Lewellen, phone: (608) 388-6509, email: amy.e.lewellen.civ@army.mil

For Site Visit information, see Site Visit clause 52.237-1. Unless you already have a permanent vehicle pass, you will be required to obtain a one-day vehicle pass. You will be required to present the following information: (1) vehicle registration, (2) valid driver’s license, (3) or car rental agreement (if applicable).

Attendees at the pre-proposal conference/site visit are cautioned that the Government will not wait for anyone who is late or lost and will not hold another pre-proposal conference/site visit. Remarks, explanations and answers provided by Government representatives before, during and after the site visit shall not change or qualify any of the terms or conditions of the solicitation. The solicitation can only be changed by a formal written amendment issued by the Fort McCoy Contracting Office.

9. Written questions must be furnished to the Government no later than June 22, 2022 at 1:00pm local time; in order to ensure a timely response is provided by the solicitation closing date. All questions are to be submitted in writing at the time indicated in the solicitation or they may not be addressed before solicitation closing date; therefore, contractors are advised to submit questions as soon as possible. Please provide your company name, telephone, point of contact, e-mail address, and solicitation number on all questions.

The Government will respond to questions via the issuance of an amendment which incorporates the question and the Government’s response.

10. SAM Unique Entity ID: ______________________________.

11. TAXPAYER ID #______________________________.

12. CAGE CODE __________________________________.

13. SYSTEM for AWARD MANAGEMENT (SAM) REGISTRATION: An Active SAM Registration is required of all Department of Defense contractors. SAM registration enables electronic funds transfer of contract payments. If your company is not already actively registered, please register in the SAM database at www.sam.gov. If your company is currently registered and close to expiring, begin/complete the process for SAM registration renewal.

a. A SAM Unique Entity ID is required for SAM registration. If your company does not have a DUNS #, obtain one by calling 800-333-0505.

b. Whether your company is a current or new registrant in the SAM database, your registration must indicate that you are a provider of NAICS 561730, or a NAICS of similar business size, under the

Goods – Services section of the registration to be eligible to receive a contract for this solicitation.

c. If the prospective awardee for this request for quotes is not actively registered in the SAM database by close of solicitation, including NAICS 561730, or a NAICS of similar business size, under the Goods –

Services section, depending on mission requirements, the government reserves the right to proceed to award to the next otherwise successful actively registered contractor.

d. Within the SAM Representations and Certifications, please ensure you company has selected that you wish to bid on, or currently hold Department of Defense (DoD) issued or DoD funded Contracts. The

DFARS provisions in SAM must also be completed by solicitation closing date and time.

mailto:amy.e.lewellen.civ@army.mil http://www.sam.gov/

e. Prospective contractors who have not completed electronic annual representations and certifications at http://www.sam.gov/ in conjunction with required registration in the System for Award Management

(SAM) database, shall complete and submit FAR 52.212-3 Alternative 1 Offeror Representations and

Certifications - Commercial Items and DFARS Representations and Certifications in SAM to be eligible to receive an award for this solicitation.

14. Contract Administrator: TBD at time of award.

If you have questions pertaining to this contract after contract award (i.e. questions regarding delivery, invoice procedures, etc.), please request assistance from the Contract Administrator. Be sure to include the contract number in your request for assistance. Requesting contract administration assistance from any other individual could result in a delayed response.

15. Contracting Officer: TBD at time of award.

16. Contracting Officer’s Representative (COR): TBD at the time of Award.

17. The Government intends to evaluate quotes and award a contract without discussions. Therefore, the contractor’s initial offer should contain the contractor’s best terms from a price and technical standpoint.

However, the Government reserves the right to conduct discussions if later determined by the Contracting

Officer to be necessary. The Government may reject any or all quotes if such action is in the public interest and waive informalities and minor irregularities in quotes received.

18. Service Contract Reporting (SCR): Contractors will report manpower data relating to the performance of service contracts into the system for Award Management (SAM) (https://sam.gov) consistent with existing service contract reporting requirement under the federal acquisition regulation subpart 4.17- Service

Contracts Inventory. SAM will only enable reporting for entities with contract that meet the SCR threshold at FAR 4.1703. As part of its quote, the vendor must include the estimated total cost (if any) incurred to comply with the Service Contract Reporting requirement.

19. Post Award Conference: In the event the Contracting Officer decides to conduct a Post Award Conference in accordance with DFARS 242.5, the awardee will be notified and will be required to attend. The

Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.

20. ABILITYONE DESIGNATED ITEMS: In accordance with 52.208-9, contractors are referred to the web site of the Committee for Purchase from People Who Are Blind or Severely Disabled, the independent federal agency that administers the AbilityOne (formerly Javits-Wagner-O'Day or JWOD) Program for the lists of designated products and services http://abilityone.gov/procurement_list/product_buy.html

21. In accordance with FAR 52.223-2, Affirmative Procurement of Bio-based Products under Services and

Construction Contracts, contractors are required to submit annual bio-based reports to the reporting module in the System for Award Management (SAM) at https://www.sam.gov.

22. The “Equal Employment Opportunity Is The Law” notice (poster) referenced in FAR Clause 52.222-

26(b)(3), is located at http://www.dol.gov/ofccp/regs/compliance/posters/pdf/eeopost.pdf .

23. In accordance with FAR Clause 52.222-41(g), the contractor must notify each service employee working on this contract of the minimum wage and fringe benefits required to be paid pursuant to this contract, or shall post a copy of the wage determination and Department of Labor Form WH-1313 in a prominent place at the worksite. The applicable wage determination is incorporated into the contract. The WH-1313 poster is located at http://www.dol.gov/whd/regs/compliance/posters/sca.htm.

24. In accordance with FAR 52.222-42, In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor (29 CFR part 4), this clause identifies the classes of service http://www.sam.gov/ https://sam.gov/ http://www.dol.gov/ofccp/regs/compliance/posters/pdf/eeopost.pdf http://www.dol.gov/whd/regs/compliance/posters/sca.htm employees expected to be employed under the contract states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C. 5341 or 5 332.

This Statement is for Information Only. It is not a Wage Determination.

Employee Class Monetary Wage -- Fringe Benefits

Laborer--Grounds Maintenance WG-3; Step 2

25. Required insurance:

The contractor shall provide, within ten (10) calendar days after contract award. The Contractor shall provide the Certificate of Insurance (COI) via email to the Post Award Contracting Officer and Post Award Contract

Specialist. The COI shall be updated and sent to the Post Award Team on an annual basis.

In accordance with FAR clause 52.228-5 entitled, “Insurance--Work on a

Government Installation” the following minimum amounts of insurance are required.

Workmen’s Compensation As required by state laws

Employer’s Liability Insurance $100,000 per accident

General Liability Insurance - Bodily

Injury Liability $500,000 per occurrence

Auto Liability Insurance $200,000 per person

Bodily Injury $500,000 per occurrence

Property Damage $20,000 per occurrence

Contractor shall require the insurance company to specify contract number in the Description of Operation block of the Certificate of

Insurance (COI) and the below statement.

"The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective- (1) For such period as the laws of the State in which this contract is to be performed prescribe; or (2) Until 30 days after the Insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer."

26. Legal compliance: The Contractor shall comply with all Federal, State, and Local Laws, codes and regulations applicable to his performance under this contract, and shall be solely responsible for all costs associated with said compliance.

27. Contract performance:

Purpose. IAW with FAR Subpart 42.1500 contractor past performance information (PPI) is relevant information for future source selection purposes regarding a contractor’s actions under previously awarded contracts. It includes, for example, the contractor's record of conforming to contract requirements and to standards of good workmanship; the contractor's record of forecasting and controlling costs; the contractor's adherence to contract schedules, including the administrative aspects of performance; the contractor's history of reasonable and cooperative behavior and commitment to customer satisfaction; and generally, the contractor's business-like concern for the interest of the customer. Contractor past performance information is one of the tools that support Army efforts to acquire best value and is used to evaluate performance risk in source selection. The feedback provided by the government to the contractor in collecting PPI, and the knowledge that PPI will be used in future source selection decisions, should result in improved performance and a greater contractor focus on customer satisfaction.

Contractor Performance Assessment Reports System (CPARS): CPARS shall be prepared IAW AFARS

Subpart 42 upon physical completion of the contract. If the period of performance will exceed 18 months, an “interim” assessment report shall be prepared at the completion of 12 months performance and annually thereafter until the contract is physically complete. An out-of-cycle or “addendum” report may be prepared if there is a need to record an extraordinary event prior to the next regularly scheduled evaluation or if it is necessary to report a meaningful occurrence during the period between physical completion of the contract and contract closeout. Additionally, addendum reports may be prepared to record contractor’s performance relative to contract closeout and other administrative requirements (e.g.

final indirect cost proposals, technical data, etc.).

Completion Due Date. The government will complete the CPARS within 60 days after the end of the assessment rating period (if applicable).

Evaluators. The Contracting Officer and the Contracting Officer’s Representative will jointly complete the performance assessment.

Contracts Performance Elements. The contractor’s performance shall be assessed in accordance with elements and rating system set forth in AFARS Subpart 42.

Contractor Review. The Contracting Officer will furnish a copy of the CPARS to the contractor requesting that the contractor submit comments, rebutting statements, and/or additional information to the

Contracting Officer within 30 calendar days of receipt. Failure to respond within the designated timeframe will be taken as agreement with the assessment.

Contract Concurrence. Where a contractor concurs with, or takes no exception to a CPARS, such report shall be considered final and releasable for use in source selection and other deliberative purposes.

Contractor Rebuttal. Where a contractor takes exception to a performance report, the Contracting Officer will review the contractor’s rebuttal or comments and make appropriate changes. If the Contracting

Officer makes changes, the changed rating will be reflected in the narrative. The Contracting Officer will make all reasonable efforts to reconcile the report and the contractor’s comments. However, it is not necessary that they reach agreement on the report where such is clearly impracticable. The contractor’s rebuttal or comments shall be made part of the CPARS.

Resolving Disagreements between the Government and the Contractor. In the event disagreements between the parties regarding the CPARS occur, the Contracting Officer will review the rebuttal and make appropriate changes. If no agreement is reached, the CPARS is forwarded to the Reviewing Official

(Director of Contracting) along with the Contracting Officer’s Findings and Recommendation and supporting documentation. The decision of the Reviewing Official is final. Copies of the CPARS and the contractor’s response and review comments, if any, shall be retained as part of the evaluation.

Release of Contractor Performance Evaluation Information. The evaluation will not be released to other than government personnel and the contractor whose performance is evaluated. The performance evaluation information will be input into the applicable module within Contractor Performance

Assessment Reporting System (CPARS) database (or Government system in use at time of the evaluation).

Source Selection Information. Departments and agencies will electronically access the CPARS information to support future award decisions.

28. Alternate disputes resolution: In furtherance of Federal policy and the Administrative Dispute Resolution

Act of 1990 (ADR Act), Public Law 101-552 and FAR Clause 52.233-1, Subparagraph (d) (2) (1) (B) (2), the Contracting Officer will try to resolve all post award acquisition issues in controversy by mutual agreement of both parties. Interested parties are encouraged to use alternative dispute resolution procedures to the maximum extent practicable, in accordance with the authority and requirements of the

ADR Act.

PWS

PERFORMANCE WORK STATEMENT (PWS)

Version 1.5; 16 NOV 2020

UT034 (MS) GROUNDS MAINTENANCE

PART 1

GENERAL INFORMATION

1. General: This is a non-personal services contract to provide grounds maintenance services as defined in this

Performance Work Statement (PWS) at Army Reserve Facility UT010 located at 4550 S. 1300 E., Salt Lake City, UT 84117-4126 and Army Reserve Facility UT032 located at 5290 W. 700 S., Salt Lake City, UT 84104-4416. The

Government will not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services/Introduction: The Contractor shall provide all personnel, labor, equipment, supplies, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform grounds maintenance services as defined in the Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

1.2 Background: The 88th Army Reserve Readiness Division (RD) was established and sited in 2006 at Fort

McCoy, Wisconsin. The command supports approximately 50,000 Soldiers in 19 states to provide the best in class base operations support for Soldiers in the Northwest region.

1.3 Objectives: The objective of this contract is for the contractor to perform necessary grounds maintenance services in a manner that will maintain satisfactory lawn, tree, shrub, and other exterior flora in a condition that presents a clean, neat, and professional appearance as defined in the Performance Work Statement.

1.4 Scope: The Contractor shall be responsible for performing lawn maintenance, aeration, fertilization, weed control, and general spring and fall cleanup. The contractor shall perform to the standards and specifications outlined in the PWS. Note that any drawings or maps provided to the Contractor, either before or after the contract is awarded, are for reference purposes only and may not be to scale. Any square footage, or other measurement provided, may be an approximation. It is the sole responsibility of the Contractor to determine or verify the actual site conditions and measurements.

1.5 Period of Performance: The period of performance shall be for one (1) Base Period and four (4) 12-month option periods. Active performance periods of eight (8) months are from April through November of each year.

Non-active performance period will be from December through March of each year. Exception: Spring clean-up may be performed 2 weeks prior to the start of the active performance period and Fall clean-up may be completed 2 weeks after the end of the active performance period.

1.6 General Information:

1.6.1 Quality Control: Quality Control is the responsibility of the contractor. The contractor is responsible for the delivery of quality services/supplies to the Government (see FAR 52.212-4, Contractor Inspection Requirements). A formal Quality Control Plan (QCP) is not required for this commercial service. However, the contractor shall maintain an inspection system commensurate with commercial practices to ensure the Contractor only tenders for acceptance those items or services that conform to the requirements of this contract.

1.6.2 Quality Assurance: The Contracting Officer Representative (COR) will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is a Government only document focused on what the COR must do to assure that the contractor has performed in accordance with the performance requirements within this PWS.

1.6.2.1 Non-conforming Services: When a contractor’s performance is identified as unsatisfactory (e.g. does not meet contract PWS requirements and/or work schedules and/or timeframes) it is considered a non-conformance. The contractor shall reply within the specified timeframe upon receipt of a non-conformance report (NCR) from the

COR or Contracting Officer (KO). Non-conformance shall be classified in one of three categories:

1.6.2.1.1 Level I (Minor) non-conformance: is defined as a non-conformance that is a departure from established standards having little bearing on the effective use or operation of the services. Minor non-conformance usually can be corrected by the contractor within a short timeframe, where no further corrective action (CA) response is necessary, and can be issued by the COR to the contractor either through a verbal or written NCR. Minor non-conforming services shall be re-performed within a specified time frame at no increase in contract price. If minor non-conformances are recurring or re-performance is not completed in full and within the specified time a Level II non-conformance may be issued to the contractor by the KO.

1.6.2.1.2 Level II (Major) non-conformance: is defined as a non-conformance, other than critical, that is likely to result in failure of services, or to materially reduce the usability of the services for their intended purpose, or it is a recurring Minor non-conformances, or a non-responsive contractor indicating a trend or failure of the contractor’s quality control. Major non-conformance’s shall result in the issuance of a written NCR from the KO to the contractor requiring a response by the contractor by a specified timeframe identifying the reasons for the unsatisfactory performance, corrective action(s) taken and date resolution has/will occur, and procedures to preclude recurrence of unsatisfactory performance. The KO may also reduce the payment to the contractor in accordance with

(IAW) the performance requirements summary (PRS), or reduce payment to reflect the value of the services performed if re-performance is not possible, or may have the identified non-conforming service performed and charge the contractor for any related cost incurred.

1.6.2.1.3 Level III (Critical) non-conformance: is defined as a non-conformance that is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the services; is likely to prevent performance of a vital agency mission; is for a repeated or uncorrected level II NCR’s; or is for a non-responsive contractor to a level II NCR. Critical non-conformance’s shall result in the issuance of a written NCR from the KO to the contractor requiring a response by the contractor by a specified timeframe identifying the reasons for the unsatisfactory performance, corrective action(s) taken and date resolution has/will occur, and procedures to preclude recurrence of unsatisfactory performance. The KO may also reduce the payment to the contractor IAW the PRS, or reduce payment to reflect the value of the services performed if re-performance is not possible, or may have the identified non-conforming service performed and charge the contractor for any related cost incurred.

1.6.2.2 The contractor will be notified of Government inspection results within 5 business days. The contractor shall acknowledge receipt of the inspection results via email or letter within 2 business days. The contractor may be notified of inspection results verbally or via email. Verbal notifications of defective work will be confirmed in writing. When Government inspectors are unable to contact the contractor to notify the contractor of inspection results, acceptance or rejection of work will be made on the basis of the initial inspection.

1.6.3 Performance Evaluation Meetings: The Contractor Point of Contact (POC) shall meet with the COR prior to start of the contract. However, meetings may be held whenever deficiencies are noted by the COR. A mutual effort shall be made to resolve all problems identified.

1.6.4 Federal Government Holidays: Except as noted in the Schedule of Work, work shall not be performed on the following holidays or on holidays observed in lieu thereof. When required services occur on holidays, work will be performed on either the previous or following work day, unless specified otherwise.

New Year’s Day 1st day of January

Martin Luther King Jr.'s Birthday 3rd Monday of January

Presidents Day 3rd Monday of February

Memorial Day Last Monday of May

Independence Day 4th day of July

Labor Day 1st Monday of September

Columbus Day 2nd Monday of October

Veterans Day 11th day of November

Thanksgiving Day 4th Thursday of November

Christmas Day 25th day of December

1.6.5 Unforeseen Installation Closures: When the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closing; the Contractor will be notified by the COR of an installation closure. The Contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons.

When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential. When an unforeseen installation closure occurs on a regularly scheduled day of work, the Government shall have the following options:

1.6.5.1 To require the Contractor to perform the work on the following day unless the following day is a Saturday or

Sunday and routine work is not scheduled for Saturday or Sunday.

1.6.5.2 To reschedule the work on any day satisfactory to both parties.

1.6.5.3 Hours of Operation: The Contractor shall normally perform work during normal duty hours, 7:30a.m. to

4:00p.m. Periodic work, such as tree pruning and Spring/Fall cleanup may be performed other than normal duty hours. Arrangements for work performed during other than normal duty hours shall be made with the COR or DR.

1.6.6 Key Control: The Contractor shall establish and implement methods of ensuring that all keys issued to the

Contractor by the Government are not lost, or misplaced, and are not used by unauthorized persons. No keys issued to the Contractor by the Government shall be duplicated. NOTE: All references to keys include key cards.

1.6.6.1 In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the KO, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the

Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the

Government and the total cost deducted from the monthly payment due the Contractor.

1.6.6.2 The Contractor may be required to replace, re-key or reimburse the Government for replacement of locks or re-keying as a result of Contractor losing keys. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due.

1.6.6.3 The Contractor shall report the occurrences of a lost key immediately to the COR no later than the next business day.

1.6.6.4 It is the responsibility of the Contractor to prohibit the use of keys issued by the Government by any persons other than the Contractor’s employees. It is also the responsibility of the Contractor to prohibit the opening of locked areas by the Contractor’s employees to permit entrance of persons other than Contractor’s employees engaged in the performance of assigned work in those areas.

1.6.6.5 Lock Combinations; the Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations.

1.6.7 Conservation of Utilities: The Contractor shall be directly responsible for instructing employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions, which preclude the waste of utilities, which shall include but shall not necessarily be limited to:

1.6.7.1 Lights shall be used only in areas where and at the time when work is actually being performed.

1.6.7.2 Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by contracted workers.

1.6.7.3 Water faucets or valves shall be turned off after the required usage has been accomplished.

1.6.7.4 Government telephones shall be used by Contractor employees only for emergencies.

1.6.8 Damages Caused by the Contractor: The Contractor shall be held accountable and liable to the Government for any damages to Government facilities, furnishings, equipment or grounds caused by the Contractor or his employees. The Contractor shall instruct his employees to immediately inform the building manager or DR of any damages to property resulting from the performance of their duties.

1.6.9 Parking for Contractor’s Employees & Contractor Vehicles: Contractor employees shall park their personal and Contractor’s vehicles during the times and in the area designated by the COR or DR.

1.6.10 Circumstances to Be Reported: The Contractor or the Contractor’s employees shall report any circumstances of needed repair of the facility or unusual soiling of an area which may affect the performance of the work, present unhealthy or hazardous conditions, or create any delays or interference with the work caused by the employees of the Government. Such report shall be made immediately upon discovery by the Contractor to the COR or DR.

1.6.11 Hazardous Materials: The Contractor shall maintain onsite and have readily available an inventory listing of all hazardous materials used onsite. Safety Data Sheets (SDS) will be maintained and readily available for any chemicals or hazardous materials used onsite. It is the Contractor’s responsibility to properly train his personnel on the existence and safe use and storage of chemicals and hazardous materials.

1.6.12 Loss of Contractor Property: If applicable, the Contractor shall be responsible to retain supplies and equipment within each building, in a safe and secure manner. Storage rooms shall be kept clean. The Government will not be held liable for any loss of supplies or equipment owned by the Contractor; nor the loss of any personal property belonging to employees of the Contractor.

1.6.13 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal

Acquisition Regulation Subpart 42.5, Post Award Orientation. The Contracting Officer, COR, and other

Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the Contracting Officer, COR, or DR will apprise the contractor of how the government views the Contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.6.14 Contracting Officer Representative (COR): The COR will be identified by a separate letter and in the

Supplemental Information of the contract. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, and specifications; monitor Contractor's performance and notify both the Contracting Officer and Contractor of any deficiencies; coordinate availability of Government furnished property. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.15 Key Personnel: The following personnel are considered key personnel by the government: designated Point

Of Contact (POC) and an alternate Point of Contact: The Contractor shall provide a designated POC who shall be responsible for the competent performance of the work required under the specifications of this contract NLT 5 business days after contract award and as changes occur. The name and contact information of the POC and an alternate, who shall act for the contractor when the POC is absent, shall be designated in writing to the COR. The

POC or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The POC or alternate shall be available between 7:30 a.m. to 4:00 p.m. Monday thru Friday except

Federal holidays or when the government facility is closed for administrative reasons. The POC(s) and alternates shall be able to read, write, speak, and understand English.

1.6.15.1 The POC shall meet with COR to discuss immediate problems areas. The POC shall respond by phone or email to the COR within two (2) hours after notification of deficiencies and correct the deficiency(s) the next business day. The Contractor shall provide the telephone number and email of the POC to the COR.

1.6.16 Identification of Contractor Employees: The Contractor (to include subcontractors) shall provide each employee an Identification (ID) Badge, which includes at a minimum, the Company Name, Employee Name and a recent color photo of the employee, prior to them entering Government facilities. ID Badges for Key Personnel shall also indicate their job title. ID Badges shall be worn at all times during which the employee is performing work under this contract. Each Contractor (to include subcontractors) employee shall wear the ID Badge in a conspicuous place on the front of exterior clothing and above the waist except when safety or health reasons prohibit. The

Contractor (to include subcontractors) shall be responsible for collection of ID Badges upon completion of the contract or termination of employee. A listing of issued identification cards shall be furnished to the COR prior to the listed employees entering Government facilities and updated as needed to reflect Contractor and Subcontractor personnel changes. All contract personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials.

They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

1.6.17 Supervision of Contractor Employees: The Government will not exercise any supervision or control over

Contractor or subcontractor employees while performing work under the contract. Such employees shall be accountable solely to the Contractor, not the Government. The Contractor, in turn, shall be accountable to the

Government for Contractor or Subcontractor employees.

1.7 Antiterrorism (AT) and Operations Security (OPSEC).

1.7.1 AT Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date, new employee hire, or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 60 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil

1.7.2. Access and general protection/policy and procedures. Contract personnel will be escorted at all times when working inside a Motor Equipment Park (MEP) and when accessing Army Reserve buildings.

1.7.3 iWATCH Training. All Contractor employees, including subcontractor employees, to be briefed on the local iWATCH program. The training standards provided by the requiring activity Anti-terrorism Officer (ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. The Contractor shall coordinate with the COR to get the current copy of this training within 5 days of contract start. This power point training shall be completed within 30 calendar days of contract performance start date and within 30 calendar days of new employees’ commencing performance.

The contractor shall electronically submit attendance rosters for each contractor employee and subcontractor employee to the COR within 30 calendar days after completion of training. This is an annual requirement.

1.7.4 Activity Regulations for Contractor Access and Use of Premises

1. Follow all current Army Security Regulations concerning strict visitor control and preservation of all Government assets. Immediately report all security concerns to the COR, who will notify the Security Office.

2. The Contractor shall adhere to requirements as directed in Federal Acquisition Regulation – 52.222-54;

Employment Eligibility Verification. Contractors shall be enrolled in the Department of Homeland Security E-

Verify Program. Information on registration for and use of the E-Verify program can be obtained via the Internet at the Department of Homeland Security Web site: http://www.dhs.gov/E-Verify.

3. The Contractor shall ensure that its employees entering Army-controlled installations or facilities have obtained access badges and passes in accordance with facility regulations and that these badges and passes are obtained in advance so as not to delay the accomplishment of contracted services.

4. The Contractor shall comply with all personnel identity verification procedures. Employees must be accompanied by an authorized Government employee at all times while providing services in secure areas.

5. During Force Protection Conditions (FPCON) Charlie and Delta, services are discontinued and services shall resume when the FPCON level is reduced to level Bravo or lower.

1.7.5 Lost and Found Property: It is the responsibility of the Contractor to ensure that all items of possible personal or monetary value found by the Contractor’s employees are turned in to the Contracting Officer Representative

(COR) or DR.

PART 2

DEFINITIONS & ACRONYMS

2. Definitions and Acronyms:

2.1 Definitions: As used throughout this performance work statement, the following terms shall have the meaning set forth below:

2.1.1 Business Day: Shall mean any day banking transactions can be conducted in New York City, NY, USA and does not include any day which is a federal or state holiday in such location.

2.1.2 Contract Administrator. The official Government representative delegated authority by the Contracting

Officer to administer a contract. This individual is normally a member of the appropriate Contracting/Procurement career field and advises on all technical contractual matters.

2.1.3 Contractor. A supplier or vendor awarded a contract to provide specific supplies or services to the government. The term used in this contract refers to the prime.

2.1.4 Contracting Officer (KO). A person with the authority to enter into, administer, and/or terminate contracts, and make related determinations and findings on behalf of the government. Note: The KO is the only individual who can legally bind the Government.

2.1.5 Contracting Officer's Representative (COR). An employee of the U.S. Government appointed by the KO to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations.

This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. Note: This individual does

NOT have authority to change the terms and conditions of the contract.

2.1.6 Cultivated Areas. Any area of earth within the boundaries of the facility that has been improved or intentionally planted such as: mulched areas, flower beds, hedge rows, or parking lot green spaces.

2.1.7 Defective Service. A service output that does not meet the standard of performance associated with the PWS.

2.1.8 Deliverable. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.9 Designated Representative. A Government employee or Contractor employee performing duties in the position of Area Facility Operations Specialist (aFOS), Facility Coordinator (FC) or Acting Facility Coordinator or otherwise approved by the COR to assist the COR with duties such as coordinating schedules with Contractors to perform work at a facility, provide facility access to Contractors, and perform inspection of Contractor’s work and provide results of their inspections back to the COR, both orally and in writing. A Designated Representative does not have the authority to assign work to Contractors or discuss Contractor performance issues; but may discuss these issues with the COR for potential further action. The only individuals with the authority to discuss Contractor performance issues are warranted Contracting Officers and Contracting Officer Representatives specifically delegated this authority by a warranted KO via an appointment letter.

2.1.10 Government-Furnished Property (GFP), Government-Furnished Equipment (GFE), or Government-Furnished

Facility (GFF). Property or area in the possession of, or directly acquired by, the Government and subsequently made available to the Contractor.

2.1.11 His/Her. Wherever used in the Performance Work Statement, the term “his” is meant to be synonymous with

“her” unless otherwise stated. The same shall be true for him and her.

2.1.12 Key Personnel. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.13 Mechanically remove (vegetation). Means utilizing physical activity to remove or inhibit the growth of unwanted vegetation. Mechanical, or manual, vegetation control techniques manage vegetation populations through physical methods that remove, injure, kill, or make the growing conditions unfavorable. Some of these methods cause direct damage to unwanted vegetation through complete removal or causing a lethal injury. Other techniques, such as trimming to the height of desirable vegetation (generally grass or turf), may alter the growing environment by increasing the temperature of the soil and depriving the plants of carbon dioxide or oxygen. Mechanical control techniques shall be selective so as to have a minimal impact on non-targeted (desirable) vegetation.

2.1.14 Physical Security. Actions that prevent the loss or damage of Government property.

2.1.15 Policing (of Facility). Means to remove loose or wind-blown litter, debris, dead tree branches, brush, and leaves from all readily accessible grounds and parking areas.

2.1.16 Quality Assurance. The government procedures to verify that services being performed by the Contractor are acceptable in accordance with established standards and requirements of this contract.

2.1.17 Quality Assurance Specialist. An official Government representative concerned with matters pertaining to the contract administration process and quality assurance/quality control. Acts as technical advisor to the