July 2022 Repair Precision Driving Course
Scope Of Work - 1
SCOPE OF WORK
Seed Project, Repair Precision Driving Course, Fort McCoy, WI W.O # 3032
FILE # 47-018-2022
Contractor shall provide all tools, labor, equipment, supervision, transportation and materials necessary to
Repair Precision Driving Course, Fort McCoy, Wisconsin, per the attached drawings and the contract specifications. Work is to be done in accordance with all existing Federal, State and local codes.
1. Remove all existing chip-sealed pavement and a portion of existing asphalt pavement as shown on the drawings. Saw-cut existing asphalt areas to be removed and make a clean, continuous, sealed joint where concrete joins with existing remaining asphalt.
2. Excavate along entire route of driving course, for the entire width of the new pavement plus an additional 2’-0” on both sides of the pavement, down to 16” and remove from site and prepare sub-base for base course material installation. Maintain super-elevated corners as close to existing as possible. Maintain existing simulated railroad crossing, signs, bollards, posts and simulated dock if possible. If existing simulated railroad crossing, signs, bollards, posts or simulated dock require removal in order to complete the paving, restore to like condition.
3. Provide 8” compacted gravel base course to include the entire width of paved area plus 2’-0” of compacted base course on both sides of paved area.
4. Provide 8” cast-in-place concrete roadway with doweled contraction joints every 17.5’ of roadway. Apply a broomed finish perpendicular to the axis of travel on the roadway. When work stops at the end of a day, end work at a doweled contraction joint. Square off the end of the poured slab to provide a clean joint at the start of the next day’s concrete placement.
5. Provide a 2’-0” wide compacted gravel shoulder on both sides of concrete roadway for the full depth of the concrete slab.
6. Fill disturbed areas with clean black dirt level with existing grade and seed per specifications.
7. Saw-cut pavement at doweled contraction joints and install expansion joint material and joint sealer.
8. Provide expansion joint material and joint sealer where proposed new concrete joins up with existing concrete surfaces.
PHYSICAL SECURITY STATEMENT
1. Access and General Protection/Security Policy and Procedures. This provision/contract text is for contractor employees with an area performance as defined by AR 190-13, UFC, and local standard operating procedures (SOP), will add the following language in the PWS. “The contractor and all associated subcontractors’ employees shall provide all information required for background checks to meet installation access requirements to be accomplished by Director of Emergency Services Physical
Security Office or the Visitor Control Center (VCC) building 35. The contractors will be required to comply with all AR 190-13 requirements and any other policy and procedures pertaining to the security of the installation. The work area must remain secure when no work is being performed.
Contractor workforce must comply with all personal identity verification requirements (FAR
Clause52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA, July 2022 Repair Precision Driving Course
Scope Of Work - 2 and/or local policy. The contractor an all associated subcontractors’ employees shall also comply with adjudication standards and procedures using the National Crime Information Center Interstate
Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-
05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection
Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The Government may require monthly participation in the Installation Random Antiterrorism Program”.