W911SA-21-Q-3027 Amendment 0004 SF30.docx
DOCX document 28 KB Posted
- Attached to
- Industrial Wood Waste Grinding at Fort McCoy, WI
- Solicitation number
- W911SA-21-Q-3027
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W911SA-21-Q-3027 Amendment 0003 SF30.docx | DOCX document | |
| W911SA-21-Q-3027 Amendment 0002 SF30.docx | DOCX document | |
| W911SA-21-Q-3027 Wood Waste Grinding Amendment 0001 SF30.docx | DOCX document | |
| W911SA-21-Q-3027 Wood Waste Grinding Solicitation SF1449.docx | DOCX document | |
| W911SA-21-Q-3027 Attachment 5 SUS Trifold.pdf | ||
| W911SA-21-Q-3027 Attachment 4 Historical Service Annual Workload 17-Nov-2020.docx | DOCX document | |
| W911SA-21-Q-3027 Attachment 2 ATOPSEC Cover Sheet.pdf | ||
| W911SA-21-Q-3027 Attachment 1 Price Schedule 16-Nov-2020.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911SA21Q3027
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
VENDOR QUESTIONS
Q1: In PWS 5.2.1 of specific tasks it is required of the contractor to “ establish routes” to the wood chip piles. Could you please add some more detail to that and explain the demographics of the site?
A1: The sites are open and the contractor will be able to drive/maneuver right up to the woody material.
Q2: In PWS 5.2.1 the contract ask that wood chips be ground to 2 to 4 inch material. Usually a primary grind uses 6 in screens, could you please confirm 2-4 in material on a primary grind?
A2: 2-4 inch is the primary grind.
Q3: Could you please confirm that the wood chips are not the responsibility of the contractor for removal, only size and dimension of the piles?
A3: The wood chips are not the responsibility of the contractor. They will be left on site in piles of the correct size and dimension.
Q4: Other than the attachment #1 price schedule what forms do we need to fill out and sign?
A4: Page 1 of SF1449, Supplemental Information page 3, signed page 1 of any Amendment SF30, and the price schedule excel form.
Q5: When COR spoke with me last month, we talked about leaving all the material on site, I did not see that or maybe missed it. I assume that is still the same?
A5: All grinded material will be left on site.
Q6: How do you plan on measuring the finished mulch material? our machines all have laser scanner computer volumetric measuring meters on them which are 98.5% actuate and we prefer that route over measuring the piles after they have had a chance to sit and compact and start composting process, we lose total yds and costs us money when that happens. Can we use our devices to measure output as it keeps our pricing lower because we trust our system?
A6: If the laser scanner is that accurate (98.5%), that would be acceptable.
Q7: I see that the yearly total yards over the past 5 years are somewhere around 800-900 yds? Do you expect an increase of those yards over the next 5 years?
A7: Yearly totals are anticipated to be between 800-1500 cubic yards per year.
(End of Summary of Changes) image1.wmf