Base
DEMOLITION IDIQ CONTRACT FY20 - FY22
FORT MCCOY, WISCONSIN
| Contractor | WORK ORDER | |||||
| W911SA-xx-D-xxxx | DESCRIPTION | |||||
| FILE NUMBER 47-zzz-zz | DATE | |||||
| (Base Year) | ESTIMATED YEAR | UNIT | TOTAL | |||
| CLIN 0001 | DESCRIPTION | QUANTITY | UNIT | PRICE | AMOUNT | |
| 0001 | A | Removal of Walls | 80000 | SF | $ - 0 | |
| 0002 | B | Removal of Ceilings | 50000 | SF | $ - 0 | |
| 0003 | C | Removal of Floors | 65000 | SF | $ - 0 | |
| 0004 | D | Removal of Chimney | 200 | VLF | $ - 0 | |
| 0005 | E | Removal of Concrete Slabs < 7" | 10000 | SF | $ - 0 | |
| 0006 | F | Removal of Concrete Slabs > 7" | 5000 | SF | $ - 0 | |
| 0007 | G | Removal of Concrete Frost Walls | 10000 | LF | $ - 0 | |
| 0008 | H | Removal of Concrete Footings | 2500 | LF | $ - 0 | |
| 0009 | I | Removal of Concrete Frost Piers | 500 | EA | $ - 0 | |
| 0010 | J | Removal of Asphalt Pad | 9000 | SY | $ - 0 | |
| 0011 | K | Removal of Water Lateral | 4000 | LF | $ - 0 | |
| 0012 | L | Removal of Sewer Lateral | 2500 | LF | $ - 0 | |
| 0013 | M | Removal of buried Power Conductors | 250 | LF | $ - 0 | |
| 0014 | N | Removal of buried Comm Lines | 3000 | LF | $ - 0 | |
| 0015 | O | Removal of buried Gas Lines | 3000 | LF | $ - 0 | |
| 0016 | P | Removal of Chain Link Fence | 300 | LF | $ - 0 | |
| 0017 | Q | Provide ACM Inspection / Permit | 20 | EA | $ - 0 | |
| 0018 | R | Removal of buried ACM Pipe | 100 | LF | $ - 0 | |
| 0019 | S | Removal of ACM Pipe Insulation | 400 | LF | $ - 0 | |
| 0020 | T | Removal of ACM Flooring | 10000 | SF | $ - 0 | |
| 0021 | U | Removal of ACM Walls | 3000 | SF | $ - 0 | |
| 0022 | V | Removal of ACM Ceilings | 3000 | SF | $ - 0 | |
| 0023 | W | Removal of ACM Siding | 15000 | SF | $ - 0 | |
| 0024 | X | Removal of ACM Siding, Selective | 10000 | SF | $ - 0 | |
| 0025 | Y | Provide Septic / Holding Tank Pumping | 10 | TG | $ - 0 | |
| 0026 | Z | Provide Cap and Seal Mains | 5 | EA | $ - 0 | |
| 0027 | AA | Provide Compacted Base Course | 1500 | CY | $ - 0 | |
| 0028 | BB | Provide Compacted Fill Material | 1500 | CY | $ - 0 | |
| 0029 | CC | Provide Topsoil Fill | 1000 | CY | $ - 0 | |
| 0030 | DD | Provide Seeding | 5000 | SY | $ - 0 | |
| 0031 | EE | Provide Chain Link Fence | 400 | LF | $ - 0 | |
| 0032 | FF | Provide 12' Gate | 1 | EA | $ - 0 | |
| EA | ||||||
| EA | ||||||
| EA | ||||||
| EA | ||||||
| CLIN 0001 Total | $0.00 |
Contract Total $0.00
Opt Year 1
DEMOLITION IDIQ CONTRACT FY20 - FY22
FORT MCCOY, WISCONSIN
| Contractor | WORK ORDER | |||||
| W911SA-xx-D-xxxx | DESCRIPTION | |||||
| FILE NUMBER 47-zzz-zz | DATE | |||||
| (Opt Year 1) | ESTIMATED YEAR | UNIT | TOTAL | |||
| CLIN 1001 | DESCRIPTION | QUANTITY | UNIT | PRICE | AMOUNT | |
| 1001 | A | Removal of Walls | 80000 | SF | $ - 0 | |
| 1002 | B | Removal of Ceilings | 50000 | SF | $ - 0 | |
| 1003 | C | Removal of Floors | 65000 | SF | $ - 0 | |
| 1004 | D | Removal of Chimney | 200 | VLF | $ - 0 | |
| 1005 | E | Removal of Concrete Slabs < 7" | 10000 | SF | $ - 0 | |
| 1006 | F | Removal of Concrete Slabs > 7" | 5000 | SF | $ - 0 | |
| 1007 | G | Removal of Concrete Frost Walls | 10000 | LF | $ - 0 | |
| 1008 | H | Removal of Concrete Footings | 2500 | LF | $ - 0 | |
| 1009 | I | Removal of Concrete Frost Piers | 500 | EA | $ - 0 | |
| 1010 | J | Removal of Asphalt Pad | 9000 | SY | $ - 0 | |
| 1011 | K | Removal of Water Lateral | 4000 | LF | $ - 0 | |
| 1012 | L | Removal of Sewer Lateral | 2500 | LF | $ - 0 | |
| 1013 | M | Removal of buried Power Conductors | 250 | LF | $ - 0 | |
| 1014 | N | Removal of buried Comm Lines | 3000 | LF | $ - 0 | |
| 1015 | O | Removal of buried Gas Lines | 3000 | LF | $ - 0 | |
| 1016 | P | Removal of Chain Link Fence | 300 | LF | $ - 0 | |
| 1017 | Q | Provide ACM Inspection / Permit | 20 | EA | $ - 0 | |
| 1018 | R | Removal of buried ACM Pipe | 100 | LF | $ - 0 | |
| 1019 | S | Removal of ACM Pipe Insulation | 400 | LF | $ - 0 | |
| 1020 | T | Removal of ACM Flooring | 10000 | SF | $ - 0 | |
| 1021 | U | Removal of ACM Walls | 3000 | SF | $ - 0 | |
| 1022 | V | Removal of ACM Ceilings | 3000 | SF | $ - 0 | |
| 1023 | W | Removal of ACM Siding | 15000 | SF | $ - 0 | |
| 1024 | X | Removal of ACM Siding, Selective | 10000 | SF | $ - 0 | |
| 1025 | Y | Provide Septic / Holding Tank Pumping | 10 | TG | $ - 0 | |
| 1026 | Z | Provide Cap and Seal Mains | 5 | EA | $ - 0 | |
| 1027 | AA | Provide Compacted Base Course | 1500 | CY | $ - 0 | |
| 1028 | BB | Provide Compacted Fill Material | 1500 | CY | $ - 0 | |
| 1029 | CC | Provide Topsoil Fill | 1000 | CY | $ - 0 | |
| 1030 | DD | Provide Seeding | 5000 | SY | $ - 0 | |
| 1031 | EE | Provide Chain Link Fence | 400 | LF | $ - 0 | |
| 1032 | FF | Provide 12' Gate | 1 | EA | $ - 0 | |
| EA | ||||||
| EA | ||||||
| EA | ||||||
| EA | ||||||
| CLIN 0001 Total | $0.00 |
Contract Total $0.00
Opt Year 2
DEMOLITION IDIQ CONTRACT FY20 - FY22
FORT MCCOY, WISCONSIN
| Contractor | WORK ORDER | |||||
| W911SA-xx-D-xxxx | DESCRIPTION | |||||
| FILE NUMBER 47-zzz-zz | DATE | |||||
| (Opt Year 2) | ESTIMATED YEAR | UNIT | TOTAL | |||
| CLIN 2001 | DESCRIPTION | QUANTITY | UNIT | PRICE | AMOUNT | |
| 2001 | A | Removal of Walls | 80000 | SF | $ - 0 | |
| 2002 | B | Removal of Ceilings | 50000 | SF | $ - 0 | |
| 2003 | C | Removal of Floors | 65000 | SF | $ - 0 | |
| 2004 | D | Removal of Chimney | 200 | VLF | $ - 0 | |
| 2005 | E | Removal of Concrete Slabs < 7" | 10000 | SF | $ - 0 | |
| 2006 | F | Removal of Concrete Slabs > 7" | 5000 | SF | $ - 0 | |
| 2007 | G | Removal of Concrete Frost Walls | 10000 | LF | $ - 0 | |
| 2008 | H | Removal of Concrete Footings | 2500 | LF | $ - 0 | |
| 2009 | I | Removal of Concrete Frost Piers | 500 | EA | $ - 0 | |
| 2010 | J | Removal of Asphalt Pad | 9000 | SY | $ - 0 | |
| 2011 | K | Removal of Water Lateral | 4000 | LF | $ - 0 | |
| 2012 | L | Removal of Sewer Lateral | 2500 | LF | $ - 0 | |
| 2013 | M | Removal of buried Power Conductors | 250 | LF | $ - 0 | |
| 2014 | N | Removal of buried Comm Lines | 3000 | LF | $ - 0 | |
| 2015 | O | Removal of buried Gas Lines | 3000 | LF | $ - 0 | |
| 2016 | P | Removal of Chain Link Fence | 300 | LF | $ - 0 | |
| 2017 | Q | Provide ACM Inspection / Permit | 20 | EA | $ - 0 | |
| 2018 | R | Removal of buried ACM Pipe | 100 | LF | $ - 0 | |
| 2019 | S | Removal of ACM Pipe Insulation | 400 | LF | $ - 0 | |
| 2020 | T | Removal of ACM Flooring | 10000 | SF | $ - 0 | |
| 2021 | U | Removal of ACM Walls | 3000 | SF | $ - 0 | |
| 2022 | V | Removal of ACM Ceilings | 3000 | SF | $ - 0 | |
| 2023 | W | Removal of ACM Siding | 15000 | SF | $ - 0 | |
| 2024 | X | Removal of ACM Siding, Selective | 10000 | SF | $ - 0 | |
| 2025 | Y | Provide Septic / Holding Tank Pumping | 10 | TG | $ - 0 | |
| 2026 | Z | Provide Cap and Seal Mains | 5 | EA | $ - 0 | |
| 2027 | AA | Provide Compacted Base Course | 1500 | CY | $ - 0 | |
| 2028 | BB | Provide Compacted Fill Material | 1500 | CY | $ - 0 | |
| 2029 | CC | Provide Topsoil Fill | 1000 | CY | $ - 0 | |
| 2030 | DD | Provide Seeding | 5000 | SY | $ - 0 | |
| 2031 | EE | Provide Chain Link Fence | 400 | LF | $ - 0 | |
| 2032 | FF | Provide 12' Gate | 1 | EA | $ - 0 | |
| EA | ||||||
| EA | ||||||
| EA | ||||||
| EA | ||||||
| CLIN 0001 Total | $0.00 |
Contract Total $0.00