SCOPE OF WORK
TX114 REPAIR EROSION ISSUES
DINNING HALL & ADMINISTRATIO BUILDINGS 8000 & 301
GRAND PRAIRIE, TEXAS 75051-2473
1. GENERAL PRE-AWARD:
1.1 The intent of this project is to provide the Government with a complete and usable product at the completion.
1.2 The Contractor shall furnish and install all plant, labor, materials; tools, equipment, and supervision necessary to provide a complete and usable project per the Scope of Work (SOW), Plans, Specifications and manufacturers recommendations. All work shall be free from defects.
1.3 The Plans and Specifications are to prescribe the details for the construction and completion of the SOW, which the Contractor undertakes to perform in accordance with the terms of the contract.
1.4 The Contractor shall visit the work site to verify the site condition. If the Contractor discovers any errors or omissions in the SOW, Plans or Specifications, the Contractor shall immediately call it to the attention of the Contracting Officer (KO) and the Contracting Officer’s Representative (COR).
1.5 Where the Specifications and Plans describe portions of the work in general terms, but not in complete detail, it is understood that all work and materials will be of the highest standard using generally accepted industry practices.
1.6 The Contractor shall not interrupt the service function or disturb the support of any utilities without prior coordination with the COR/Area Facility Operations Specialist (AFOS). If any utilities are disturbed or damaged, the Contractor shall bear costs of repair or replacement.
1.7 The Contractor shall be responsible for and repair any damage to the grounds and structures caused by the Contractor or his/her sub-contractors during the performance of this project.
1.8 Any said work in the Plans and Specifications and not in the written SOW or in the SOW and not in the Plans or Specifications shall be as though shown or mentioned in both.
1.9 The Contractor shall verify all dimensions, site conditions, and any other items required to install a complete and ready to use product, prior to submitting a bid proposal for construction.
1.10 Prior to bidding, the Contractor shall provide to the KO and COR a written list of all exclusions, omissions, and any other work that he/she considers not in the scope of work that would prevent this from being a complete and ready-to-use product. If the Contractor does not provide a list of exclusions or omissions, it will be considered that all work is be completed to provide a complete and ready to use product.
1.11 The Contractor shall provide a project manager and alternate that is able to read, write, speak, and understand English.
1.12 The Contractor shall perform all the services of this contract during the normal operating hours of 7:30 A.M. to 4:30 P.M. (0730 to 1630) Monday-Friday. Facilities will be closed on all Federal Holidays.
1.12.1 Federal Holidays are as follows;
New Year’s Day – January 1 Martin Luther King Jr. Birthday – third Monday of January Washington’s Birthday – third Monday of February Memorial Day – final Monday of May Independence Day – July 4 Labor Day – first Monday of September Columbus Day – second Monday of October Veterans Day – November 12 Thanksgiving Day – fourth Thursday of November Christmas Day – December 25
1.12.2 Actual day observed for the following holidays is subject to change when the holiday date falls on a weekend; New Year’s Day, Independence Day, Veterans Day and Christmas Day.
1.13 The Contractor shall provide signs, barriers, and barricades to provide a safe working area.
Requirements of Occupational Safety and Health Act, latest edition and U.S. Army Corps of Engineers "Safety and Health Requirements Manual", latest edition, shall be strictly enforced and adhered to at all times at the job site.
1.14 The Contractor shall comply with Army Regulation (AR) 600-63, Army Health Promotion, for controlling smoking in Government buildings and facilities. In general NO SMOKING is allowed within building or within 50’ of any exit or door. Facility personnel can direct personnel to authorized smoking areas.
1.15 The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. This can include storm water permits, US Army Corps of Engineers permits, state water resources permits, US Fish and Wildlife permits, etc.
1.16 Antiterrorism (AT) Level I Training. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days of contract award or prior to submission of final invoice and within 45 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.
1.17 iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity Antiterrorism Officer. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR.
This training shall be completed within 30 calendar days of contract award or prior to submission of final invoice and within 30 calendar days of new employees commencing performance with the results reported to the COR no later than 45 calendar days after contract award.
1.18 Access and general protection/security policy and procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy.
In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
1.18.1 Contractors requiring Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05. The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a Department of Defense (DoD) facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.
1.18.2 For contractors that are not eligible for CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.19 The contractor employees must be adequately trained in the handling and disposal of hazardous waste, in particular, lead paint and asbestos. Hazardous materials must be handled and disposed of appropriately by the contractor. Disposal is at contractor’s expense. The contractor must comply with all local, state, and federal environmental laws, regulations, and policies prior to final approval of work completed. National Environmental Policy Act (NEPA) documents must be completed prior to award of the contract or notice to proceed.
2. GENERAL POST AWARD:
2.1 Where any conflict occurs between the requirements of federal, state, and local laws, codes, ordinances, rules and regulations, the most stringent shall govern.
2.2 The Contractor shall, at all times, keep the premises free from accumulation of waste material and rubbish caused by his work, or his subcontractors. At the completion of work, the Contractor shall thoroughly clean the work site. All debris, rubbish, and waste material shall be removed from the property at the Contractor’s expense and disposed of in an official disposal site.
2.3 The Contractor shall make no changes or deviate from the approved design of this project without written permission from the KO. In the case where a change is required, the Contractor will notify the COR of the requirement and shall not proceed with the change until such time as a modification to the contract is issued by the KO.
2.4 Prior to ordering any materials, the Contractor shall submit to the COR for approval submittals on all new items being installed on this project. Submittal may be shop drawings, diagrams, catalog cut-sheets, samples, and any other related material.
2.5 The Contractor shall submit a written construction schedule of work for this project to the KO and COR prior to the start of the project.
2.6 The Contractor shall be responsible for the conditions of the job site, including safety of all persons, and property during performance of the work. Safety shall conform to all applicable Federal, State, local laws, codes and regulations established by the City of Grand Prairie, County of Dallas and State of Texas Division of Safety.
2.7 All work shall be in compliance with the current applicable federal, state and city codes.
2.8 All work shall be completed within 30 days upon receipt of Notice To Proceed (NTP). The contractor shall have 15 days for submittals and procurement and 15 days for completion of work.
3. SUBMITTALS:
Prior to ordering any materials, the Contractor shall submit to the COR for approval submittals for all new items being installed. Submittals may be cut sheets, samples, spec sheet, so long as it is clear and easily readable. Submittals must be e-mailed, faxed or sent directly to the office of the COR using Engineer Form 4025-R, dated March 2012, as the coversheet.
4. SITE WORK:
4.1 SUMMARY:
4.1.1 The Contractor shall initially investigate the Erosion problems in order to solve the erosion issues at the Building Sites outlined below and to correct these problems by repairing the erosion issues at these particular site locations.
4.1.2 The Contractor is responsible for furnishing all labor, materials and equipment to repair the Land Erosion problems on the site areas at Building 8000 (Dinning Hall) and Building 301 (Administration Bldg.).
4.1.3 The Contractor shall locate the affected problem area and complete all work as outlined for this project per the attached drawings, pictures and this SOW. Any deviation from the stipulations of this plan of work concerning parts, changes, addition, etc. should be immediately brought to the attention and discussed with the COR.
4.2 REPAIRING BLDG 8000 SITE:
4.2.1 The Contractor shall locate the affected problem areas at the curb side from the attached drawings and pictures by locating the hole that was caused by the erosion that runs beneath the street. (See sheets 1&2 of drawings) also refer to the Pictures that are attached.
4.2.2 The Contractor shall inject a Flowable fill (Concrete Mixture) or a Polyurethane material by a method called Foam jacking directly into the hole that was caused by the erosion. The particular method chosen should be discussed with the COR/AFOS before start of work.
4.2.3 The Contractor may alternatively install a sand based grout material using a process called Mud Jacking. The void area from the hole should be completely filled until it reaches the bottom surface of the street as well as closes the perimeters of the entire hole.
4.2.4 The Contractor shall fill the Gap on the top surface of the road that divides the edge of the curb from the edge of the road itself with a Polymer-Modified Sealant or a similar type of material. (Please refer to Sheet 1 & 2 of drawings and attached pictures for a detailed view of this area.
4.2.5 After properly Repairing the eroded affected area, the Contractor shall then landscape the surrounding areas by using a Synthetic Erosion Control material, Top soil as needed and then resurfacing the entire area with new grass to match the existing grass. The COR/AFOS will determined just how much of this area should be re-grassed and the area determined where to end based on the Contractor best reliable recommendation.
4.3 REPAIRING BLDG 301 SITE:
4.3.1 The Contractor shall locate the two (2) affected problem areas at the edge of the parking lot area by reviewing the attached drawings and pictures that specifically detail’s those areas that were caused by erosion. (See sheet 3 of drawings along with attached Pictures)
4.3.2 The Contractor shall inject a Flowable fill (Concrete Mixture) or a Polyurethane material by a method called Foam jacking directly into the hole that was caused by the erosion. The particular method chosen should be discussed with the COR/AFOS before start of work. The affected areas here are not as bad as the ones on the site of Bldg. 8000 therefore the Contractor may Chose just to use Grout or Soil to fill the void areas. The decision should be made between the COR/AFOS.
4.3.3 The Contractor may alternatively install a sand based grout material using a process called Mud Jacking. The void area from the hole should be completely filled until it covers the entire area of the both Holes.
4.3.4 The Contractor shall Seal all of the cracked areas on the surface of the parking area with a matching Sealant mixture. This mixture should match the areas of the surface and all cracks should be resealed with this area being closed off to let dry.
4.3.5 After properly Repairing the eroded affected area, the Contractor shall then landscape the surrounding area by using a Synthetic Erosion Control material, Top soil as needed and then resurfacing the entire area with new grass to match the existing grass. The COR/AFOS should make the determination on what and how much of the area should be treated based on the Contractors best reliable recommendation.
5. WARRANTY:
5.1 All work specified in this contract shall have a warranty of a minimum period of one full calendar year for parts and labor from the customer’s acceptance date. At the final acceptance walk-through, the Contractor shall provide to the COR a signed warranty letter.
6. QUALITY CONTROL AND INSPECTIONS:
6.1 All work shall be inspected by the contractor’s quality control person and final inspection shall be performed by the COR prior to final payment.
6.2 Contractor shall maintain a clean, clear, and safe working environment at all times.
6.3 Only qualified personnel familiar with the proper construction techniques shall be used.
6.4 All site coordination shall be accomplished through the 63d Readiness Division Gary Davis.
7. POINTS OF CONTACT:
AFOS:
COR: