8 September 2022

Project: Fire station Kitchen and Bathroom Remodel

Building Number: 9986

IJO: DBQ180058J, DBQ180098J, DBQ180108J

PM: 2d Lt. Aaron Ault

Site Visit Q + A

1. Will an addition electrical panel/ circuit need to be added?

- Most likely it will not since the scope is a remodel and not an addition, however it can be added as an assumption if deemed necessary by the contractor’s electrical specialists.

2. Will the kitchen layout be required to change as well?

- No, the bathroom layout is only required to change and follow the design layout in attachment 1 of the statement of work.

3. Is a design/ architect contractor required for the bathroom redesign?

- No, the design for the updated bathroom is provided in attachment 1 in the statement of work.

4. Can the contractor’s return be pushed to the 16th from the 9th?

- See Amendment 0003 of the solicitation.

File details come from the government source that posted it. Updated .