SECTION 01 11 00
STATEMENT OF WORK
January 13, 2021
CONSTRUCTION
RFP Final Date: February 25, 2021
1. GENERAL DISCUSSION:
1.1. Project Identification
1.1.1. Project Title: Repair Boilers 6395 & 9134
1.1.2. IJO Number(s): DEJ196069J, DEU205260J
1.1.3. Project Package Number(s): PS 2124
1.2. Description of Work
1.2.1. The contractor shall supply all supervision, labor, equipment, and materials to perform all work in strict accordance with the contract, this statement of work, and identified drawings to repair boilers at 6395 & 9134.
1.3. Area Description
1.3.1. Location
1.3.1.1. Building 6395 is a small (~267 square feet) mechanical utility building that sits behind building 6397 and is located off Garcia Blvd between Magnolia Blvd and Blaine Ave in the Hillside Community.
1.3.1.2. Building 9134 is a barracks building located off Hillside Dr. between Mil Park Ave. and Evergreen Ave.
1.3.2. Known Existing Site Condition
1.3.3. Building 6395 contains two condensing boilers; one serving building 6396 (Hillside CDC) and one serving building 6398 (youth center). The Apex boiler currently in place for building 6396 is to be replaced and is currently not connected to the building’s heating loop. A DPW temporary boiler is in place and will remain in service while the contractor installs the new boiler.
1.3.4. Building 9134 has a failed Aerco MLX-303 modular boiler. A DPW temporary boiler is in place and will remain in service while the contractor installs the new boiler.
1.4. Principal Items To Be Accomplished
1.4.1. The following shall apply to CLINS 0001 & 0003:
1.4.1.1. Contractor shall clean and flush existing heating piping (both loops) using a blend of polymeric and chelating agents that will preferentially remove iron oxides and will assist in softening light calcium deposits prior to installing new boiler and new boiler pump. Follow manufacturer’s directions for use. DPW temp boiler shall remain connected. Follow manufacturer’s instructions for cleaning and length of time. Flush the system until the discharge water is running clear;
contractor shall notify the Government QAR and PM at the beginning and conclusion of the system flush so that the Government may observe the clarity of the water. Attach fittings/blanks as required to perform the flushing. Cleaning agent shall not be flushed through new boiler or new pump. Obtain sewage discharge permit prior to discharge; take a sample of water to be discharged and estimate pH and chlorine PPM for sewage permit. Discharge shall be into the sanitary sewer system unless directed otherwise by DPW personnel (see section 15.3.3). Note:
discharge permits are typically valid for one day at a time. Separate permits may be required depending on the number of discharges required.
1.4.1.2. Contractor shall install new supply and return heating piping and components to/from boiler IAW manufacturer recommendations. Contractor to include at a minimum: boiler pump, secondary low water cut-off (LWCO), boiler isolation valves, temperature gauges and pressure gauges (both supply and return side), balancing valve/circuit setter, check valve, flow switch, and y-strainer.
Pump shall be inline flange type, UL/ETL approved, and sized (gpm) appropriately for the new boiler and existing heating system. Pump shall have isolation valves on each side of pump within 2’ of pump inlet and outlet (see Attachment #1 for additional pump requirements). The secondary external LWCO shall be a mechanical float type with “test and check” on boiler supply with manual reset and be placed slightly higher than internal LWCO. The valve shall have an adjustable built-in vacuum breaker in the upper valve to allow for the rapid evacuation of the water from the float chamber without draining the building pipe drain to floor drain. Install EMCS sensors as required to meet points list/sequence of operations (see respective DDC CLINS). Use dielectric union for dissimilar metals where required. New boiler pump, LWCO, balancing valve, and strainer may not be installed directly above new boiler. Isolation valves on temporary boiler connections shall remain. Contractor shall install dust caps on isolation valves after DPW temporary unit is removed if required.
1.4.1.3. Contractor shall install a condensate neutralizer (CN) on new boiler per manufacturer instructions. CN shall be rated for the system capacity. Pipe to floor drain. Piping shall be properly supported.
1.4.1.4. Contractor shall connect existing natural gas (NG) piping to unit’s gas train inlet as required by manufacturer’s installation instructions to include low point drain, main gas and pilot light regulators, gas vent, and isolation ball valves. Use full size schedule 40 black gas piping conforming to ASME A53/A53M and fittings conforming to ASME B16.3. Paint NG piping if required and label each pipe (supply, vent). Natural gas meter size for gas train inlet pressure and piping shall be verified and sized for the boiler requirements; regulator may be required.
1.4.1.5. All isolation valves shall be full port ball valves with stainless steel trim on pipe 3” and smaller.
Gate valves are acceptable on pipe larger than 3”.
1.4.1.6. Contractor shall perform boiler start up by manufacturer’s representative with DPW present for safety checks in accordance with the manufacturer documentation. Contractor shall give DPW a minimum of 48 hour notice prior to startup.
1.4.1.7. Contractor shall complete boiler inspection and testing via a certified Washington State boiler inspector. Provide certificate as a submittal.
1.4.1.8. Contractor shall water balance boiler loop once new boiler, pump, etc. have been installed and manufacturer startup is complete. Hydronic balance shall be completed prior to requesting PVT, pre-final, or final inspection. Provide balance report as a submittal.
1.4.1.9. Contractor shall insulate new supply/return piping with mineral fiber insulation meeting ASTM C547 or cellular glass insulation meeting ASTM C552. Insulation thickness shall match existing and have a factory applied protective jacket. Corners shall have PVC jacket. Seal the ends of pipe insulation with brush coat of waterproof vapor barrier coating. Sections of insulated piping where support hangers are installed shall have calcium silicate insulation meeting ASTM C533 under the support hangers. Calcium silicate insulation sections shall have a metal guard between insulation jacket and support hanger and insulation section shall be a minimum width of four times the width of the support hanger.
1.4.1.10. Contractor shall install name and directional labeling on each type and size of piping and label all mechanical equipment (boiler, pump, etc.) with durable identification tags. Match naming in new DDC graphics. Name and directional labeling color shall match loop’s existing labeling.
Name and directional labeling shall be installed every 5’ or 270° in bends, whichever is less.
1.4.1.11. Contractor shall install a laminated warranty tag on all new equipment stating contractor’s name, point of contact with phone number, date of install, warranty dates, and Government PM name and email. Attach with zip tie on equipment in noticeable location and complete before Government final inspection.
1.4.2. Base Item CLIN 0001: Repair Boiler, DEJ196069J, BLDG# 6395, Repair
1.4.2.1. Contractor shall remove and dispose of the existing Apex boiler, piping, insulation, fittings, valves, flue, combustion intake, drains, electrical, etc. as required to install new boiler system IAW this SOW and attachments. Close coupled tee and temporary boiler connections are to remain. Remove conductors and conduit back to nearest j-box. Remove gas line as required to install new boiler. All recycled materials and waste shall be documented and submitted to the Government per the DPW CD diversion and disposal reporting instructions. All piping and materials not to be reused for the new boiler shall be removed and disposed of with no abandoned material left on site. The contractor shall allow DPW to remove any demolished materials before disposal; coordinate with Government PM. The entire mechanical room shall be broom cleaned following demolition. Before Government final inspection the floor shall be wet cleaned with cleaning agent and no abandoned materials or trash left on site. Note: existing building pump is on a VFD and is to remain in service with the new system.
1.4.2.2. Contractor shall demo conductors for existing boiler pump disconnect switch. Note: mechanical room has two boilers, each with a boiler pump. Both boiler pump disconnect switches are used to power both pumps from the same circuit. See section 1.4.2.6 for reconfiguration.
1.4.2.3. Contractor shall install a 4” boiler equipment platform on building’s metal floor. Securely anchor new boiler to equipment platform. Equipment platform shall be protected against corrosion, level, and able to support the full weight of the boiler (to include water when filled). Contractor shall provide a submittal showing the strength of the equipment pad is sufficient.
1.4.2.4. Contractor shall install one new 500 MBH input condensing boiler IAW this SOW and manufacturer's instructions with all additional piping, fittings, flue, electrical, etc. required for a complete and usable heating supply system. Maintain clearances around and over equipment and arrange all electrical conduit, piping, exhaust vent, and air intake with clearances for service of all equipment. All additional piping shall be new and drain lines shall be full size copper pipe unless otherwise specified. New piping shall be full size, be rated for the system temperatures and pressures, match the new boiler flow requirements, and match existing piping type (type M copper is not allowed). All fittings (elbows, tees, unions, circuit setters, balancing valves, etc.), shall be brass, bronze, or match existing piping. Copper joints on piping less than 2” in diameter may be soldered; joints above 2” shall be grooved or pressed. Black steel pipe joints shall be threaded for pipe less than 3” pipe diameter; 3” and above may be grooved joints. See section
1.4.2.6 for electrical requirements. See Attachment #1 for boiler specifications.
1.4.2.5. Contractor shall install new flue vent and combustion air intake per National Fuel Gas Code / NFPA 54 ANSI Z223.1 and boiler manufacturer instructions; existing roof penetration shall be utilized and be correctly sealed (waterproof and fire stop). Contractor shall modify roof penetration as required for new vent and intake sizes. The vent shall be sloped minimum ¼”/ft.
toward boiler flue gas condensate collection point. The intake shall be sloped minimum ¼”/ft toward the boiler. Support vent and intake at intervals no less than 4’ apart. Contractor shall follow manufacturer guidelines for type and size of vent pipe strap and follow guidelines for thermal expansion and movement of vent pipe. Install rain caps, screens, guy wires, etc. as required. The vent pipe material shall be CPVC or stainless steel and be procured from a supplier approved by the boiler manufacturer. The intake piping shall be PVC meeting ASTM D1784 and shall be suitable for the temperature at the boiler combustion air intake connection point. PVC shall be sealed and pressure tight. Vent and intake shall be full size diameter for the new boiler.
Vent and intake piping schedule/thickness shall be IAW manufacturer. Contractor shall maintain clearances between roof, vent, and intake IAW manufacture recommendations. Do not exceed maximum equivalent lengths.
1.4.2.6. Contractor shall install new electrical conductors, conduit, and circuit breakers as required powering all equipment. Conductors and circuit breakers that are removed as part of demo may not be reused. Set screw connectors shall not be used on conduit. Contractor shall install new circuit breaker and conductors for new boiler pump’s disconnect switch; powering new pump with its own (existing) disconnect switch. Circuit breaker shall be UL listed and have a minimum short-circuit current rating equal to or greater than the short-circuit current rating of the panelboard in which the circuit breaker will be mounted. Series rated circuit breakers and plug-in circuit breakers are not allowed. Existing circuit breaker and conductors powering existing boiler pump (Mod Con boiler) are to remain. Any flexible conduit runs used shall be limited to 3’ maximum in length per component and shall be properly supported. Cable ties/zip ties are not permitted for conduit support. Contractor shall update panel schedules and switch/j-box labeling that is altered during construction. Contractor shall connect new boiler to existing emergency stop switch (ESS). ESS connection shall be hardwired.
1.4.2.7. Contractor shall perform heating water testing by a 3rd party qualified water treatment contractor and develop a water treatment plan. Add chemicals per the treatment plan. Provide testing results, treatment plan, and chemicals added as a submittal to the Government and place in O&M. Clean all heating coil strainers (entire building/both loops) after system startup by manufacturer representative but prior to chemical addition and final inspection. Contractor shall notify DPW QAR a minimum of 24 hours prior to cleaning strainers so that DPW QAR may observe. Note:
6396 is occupied from 0600-1800 M-F and is generally not accessible to contractor personnel.
Cleaning of the strainers shall be conducted during a weekend. Coordinate building access with Government PM/QAR.
1.4.2.8. Contractor shall install O&M’s in a clear plastic container near boiler properly labeled “BLDG 6395 O&M’s. Note: Apex boiler in BLDG 6395 provides heating to BLDG 6396.” Contractor shall supply DPW PM with an electronic copy of new O&M’s (boiler, pump, etc.) on a CD as a submittal.
1.4.3. Base Item CLIN 0002: DDC Controls, DEJ196069J, BLDG# 6395, Repair
1.4.3.1. Contractor shall set boiler controls per manufacturer’s requirements using boiler control capabilities for enable/disable, water temperature set points using outdoor reset schedule, and boiler pump control. For outside air reset, program the boiler for operation between 32°F-68°F outside air (OSA) temp to secondary loop temperature of 150°F-100°F (adjustable). See Attachment #2 for additional sequence of operations and point list requirements.
1.4.3.2. Contractor shall update the building’s existing EMCS as required; add a network communication protocol card for monitoring enable/disable boilers, changing boiler temperature set points, and other points as required to meet the sequence of operations and points in Attachment #2. Update EMCS graphics to new boiler. Note: JACE license may require updating based on boiler protocol.
Contractor shall install new components/controls as required (sensors, actuators, thermostats, CT’s, panels, controllers, etc.). New controllers shall be Tridium compatible.
1.4.3.3. Contractor shall conduct a modified Performance Verification Test (PVT) on boiler with DPW BMS system manager. Provide a PVT checklist submittal before scheduling PVT. Contractor shall follow JBLM DDC specification 23 09 23 (Attachment #2) to include a 14 day notice when requesting PVT.
1.4.4. Base Item CLIN 0003: Repair Boiler, DEU205260J, BLDG# 9134, Repair
1.4.4.1. Contractor shall remove and dispose of the existing Aerco boiler, boiler pump, expansion tank, piping, insulation, fittings, valves, flue, combustion intake, drains, electrical, etc. as required to install new boiler system IAW this SOW and attachments. Close coupled tee and temporary boiler connections are to remain. Remove conductors and conduit back to nearest j-box. Remove gas line as required to install new boiler. All recycled materials and waste shall be documented and submitted to the Government per the DPW CD diversion and disposal reporting instructions.
All piping and materials not to be reused for the new boiler shall be removed and disposed of with no abandoned material left on site. The contractor shall allow DPW to remove any demolished materials before disposal; coordinate with Government PM. The entire mechanical room shall be broom cleaned following demolition. Before Government final inspection the floor shall be wet cleaned with cleaning agent and no abandoned materials or trash left on site.
1.4.4.2. Contractor shall add to the existing cast-in-place concrete equipment pads as required for new equipment. Pads shall be larger than equipment with chamfered edges; chamfer shall be a minimum of 1”. Equipment pads shall be reinforced with rebar such that the new equipment pads can properly support the new equipment. Maintain 3” clearance around all edges of equipment pads. Match height of existing pad. Do not cover/block floor drains. Equipment shall be securely anchored to the pads. Contractor shall provide the Government with a submittal showing that the new equipment pads meet the requirements of ACI 301.
1.4.4.3. Contractor shall install new ASME rated pre-charged full-acceptance bladder expansion tank with new isolation valve and pressure gauge. Tank shall be supplied with a heavy duty butyl replaceable bladder. Tank shall be properly secured/mounted. See Attachment #1 for additional requirements.
1.4.4.4. Contractor shall install one new 285 MBH input condensing boiler IAW this SOW and manufacturer's instructions with all additional piping, fittings, flue, electrical, etc. required for a complete and usable heating supply system. Maintain clearances around and over equipment and arrange all electrical conduit, piping, exhaust vent, and air intake with clearances for service of all equipment. All additional piping shall be new and drain lines shall be full size copper pipe unless otherwise specified. New piping shall be rated for the system temperatures and pressures, match the new boiler flow requirements, and match existing piping type (type M copper is not allowed).
New boiler loop piping shall match existing piping diameter; install fittings on new boiler as required. All fittings (elbows, tees, unions, circuit setters, balancing valves, etc.), shall be brass, bronze, or match existing piping. Copper joints on piping less than 2” in diameter may be soldered; joints above 2” shall be grooved or pressed. Black steel pipe joints shall be threaded for pipe less than 3” pipe diameter; 3” and above may be grooved joints. See section 1.4.4.6 for electrical requirements. See Attachment #1 for boiler specifications.
1.4.4.5. Contractor shall install new flue vent and combustion air intake per National Fuel Gas Code / NFPA 54 ANSI Z223.1 and boiler manufacturer instructions; existing wall penetrations shall be utilized and be correctly sealed (waterproof and fire stop). Contractor shall modify wall penetrations as required for new vent and intake. The vent and intake piping shall be sloped minimum ¼”/ft. toward the boiler where possible. Horizontal portions of the venting system shall be supported to prevent sagging and may not have any low sections that could trap condensate.
Support vent and intake at intervals no less than 5’ apart. The boiler shall not support the weight of the vent or intake. Install rain caps, screens, guy wires, etc. as required. The vent pipe material shall be CPVC and be procured from a supplier approved by the boiler manufacturer. The intake piping shall be PVC and shall be suitable for the temperature at the boiler combustion air intake connection point. Vent and intake piping shall be sealed and pressure tight per manufacturer specifications, be full size diameter for the new boiler, and meet ANSI/ASTM D1738/F441. Vent and intake piping schedule/thickness shall be IAW manufacturer. Contractor shall maintain clearances between wall, vent, and intake IAW manufacture recommendations. Do not exceed maximum equivalent lengths.
1.4.4.6. Contractor shall install new electrical conductors, conduit, and circuit breakers as required powering all equipment. Conductors and circuit breakers that are removed as part of demo may not be reused. Set screw connectors shall not be used on conduit. Contractor shall connect new boiler pump to existing disconnect toggle switch. New circuit breakers shall be UL listed and have a minimum short-circuit current rating equal to or greater than the short-circuit current rating of the panelboard in which the circuit breaker will be mounted. Series rated circuit breakers and plug-in circuit breakers are not allowed. Any flexible conduit runs used shall be limited to 3’ maximum in length per component and shall be properly supported. Cable ties/zip ties are not permitted for conduit support. Contractor shall update panel schedules and switch/j-box labeling that is altered during construction. Contractor shall connect new boiler to existing emergency stop switch (ESS). ESS connection shall be hardwired.
1.4.4.7. Contractor shall perform heating water testing by a 3rd party qualified water treatment contractor and develop a water treatment plan. Add chemicals per the treatment plan. Provide testing results, treatment plan, and chemicals added as a submittal to the Government and place in O&M. Clean all heating system strainers after system startup by manufacturer representative but prior to chemical addition and final inspection (strainers: boiler loop, pump strainers, air separator, etc.).
Contractor shall notify DPW QAR a minimum of 24 hours prior to cleaning strainers so that DPW QAR may observe.
1.4.4.8. Contractor shall install O&M’s in a clear plastic container near boiler properly labeled “BLDG 9134 O&M’s.” Contractor shall supply DPW PM with an electronic copy of new O&M’s (boiler, pump, etc.) on a CD as a submittal.
1.4.5. Base Item CLIN 0004: DDC Controls, DEU205260J, BLDG# 9134, Repair
1.4.5.1. Contractor shall set boiler controls per manufacturer’s requirements using boiler control capabilities for enable/disable, water temperature set points using outdoor reset schedule, and boiler pump control. For outside air reset, program the boiler for operation between 0°F-68°F outside air (OSA) temp to secondary loop temperature of 160°F-110°F (adjustable). See Attachment #2 for additional sequence of operations and point list requirements.
1.4.5.2. Contractor shall update the building’s existing EMCS as required; add a network communication protocol card for monitoring enable/disable boilers, changing boiler temperature set points, and other points as required to meet the sequence of operations and points in Attachment #2. Update EMCS graphics to new boiler. Note: JACE license may require updating based on boiler protocol.
Contractor shall install new components/controls as required (sensors, actuators, thermostats, CT’s, panels, controllers, etc.). New controllers shall be Tridium compatible.
1.4.5.3. Contractor shall conduct a modified Performance Verification Test (PVT) on boiler with DPW BMS system manager. Provide a PVT checklist submittal before scheduling PVT. Contractor shall follow JBLM DDC specification 23 09 23 (Attachment #2) to include a 14 day notice when requesting PVT.
2. PERFORMANCE AND SCHEDULING:
2.1. Performance Period Requirements
2.1.1. The Contractor is required to commence work under this Contract within ten (10) calendar days after the date of issuance of the Notice to Proceed (NTP) for the Base Item(s), prosecute the work diligently, and complete all work on all Base Item(s) no later than 180 calendar days after the date of issuance of the Notice to Proceed for the Base Item(s). The time stated for completion includes final cleanup of the premises and submission of all required close-out documentation.
2.1.2. Blank copies of Government forms required by this SOW will be provided to the Contractor within 14 calendar days of award issuance. Examples of these forms include: daily reports, ENG Form 4025-R, HJB 229, etc.
2.2. Award of Options
2.2.1. N/A
2.3. Construction Phasing Requirements
2.3.1. Contractor shall coordinate all shut downs/outages with DPW.
2.3.2. The DPW temporary boilers shall remain in operation during the boiler replacement for 6395 & 9134. The contractor shall inform and coordinate with DPW O&M when the new equipment is installed and the temporary unit can be removed. Cut over times shall not exceed 4 hours. The contractor shall give DPW O&M, QAR, and PM the proper when notice when requesting cut over time.
2.4. Perform other work necessary
2.4.1. The contractor shall be responsible for providing a complete and useable product/system and shall be responsible for accomplishing all tasks incidental to the completion of the project requirements. Requirements for a complete and useable product which are not explicitly called out in the SOW but are reasonably discernable via any other method than destructive testing shall be considered a requirement of the project/contract.
3. SUBMITTAL PROCEDURES:
3.1. Project Submittal Requirements: All submittals shall be submitted electronically (emailed) to the government Project Manager (PM) in Adobe Acrobat .pdf format. An ENG Form 4025 shall accompany each submittal. These forms will be furnished to the Contractor by the PM. The submittal file name shall be in the format “Contract # – submittal #, submittal name” for example;
“0020-001 RTU”. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Drawings if required by the SOW shall be in ACAD format and a second electronic copy in PDF format. The Government reserves the right to request submittals not listed in this SOW; any submittals not listed in this SOW but requested by the Government shall become a requirement of the project. Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Contractor shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified.
3.1.1. The Government reserves the right to require the contractor to resubmit any item found not to comply with the contract. This does not relieve the contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the KO from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the contractor of the requirements to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
3.1.2. Government Approval. Government approval is required for critical materials, deviations, equipment whose compatibility with the entire system must be checked, safety requirements, and other items as designated by the KO. Government approval is required for any deviations from the solicitation or accepted proposal and other items as designated by the KO. These deviations must contain proper documentation stating why this deviation is necessary and why it is beneficial to the government.
3.1.3. Information Only. Submittals not requiring Government approval will be for information only. The approving authority will not provide approval of information only submittals but shall provide acknowledgement of receipt.
3.1.4. Variations. Variations from contract requirements require Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government and/or overall project. Discussion with KO or their representative (DPW PM, MICC CS, etc.)
prior to submission will help ensure functional and quality requirements are met and minimize rejections and resubmittals. Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may result in the Government requiring rejection and removal of such work at no additional cost to the Government. When proposing a variation, deliver written request to the KO, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation. Check the column "variation" of ENG Form 4025 for submittals that include proposed variations requested by the contractor. Set forth in writing the reason for any variations and annotate such variations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.
3.1.5. Approval. When approving authority is KO or the designated representative, the Government will:
Note date on which submittal was received. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents. Identify returned submittals with one of the actions defined in paragraph entitled "Review Notations" and with markings appropriate for action indicated. Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. The transmittal form (4025-R) showing approval of the submittal will be retained by the KO and one copy of the transmittal form will be returned to the contractor electronically. The KO's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory.
Approval or acceptance will not relieve the contractor of the responsibility for any error that may exist, as the contractor is responsible for the satisfactory construction of all work. After submittals have been approved or accepted by the KO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
3.1.6. Disapproval. Contractor shall make corrections required by the KO. If the contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, notice as required under the clause entitled, "Changes" is to be given to the KO.
Failure to point out deviations may result in the Government requiring rejection and removal of such work at the contractor's expense. If changes to submittals are necessary, the contractor shall make such revisions and submission of the submittals in accordance with the procedures above within 7 calendar days. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
3.1.7. Duration for submittal review: The Government shall have up to 14 calendar days to review each submittal starting when the Government receives the electronic submission. Longer review times may be required on a case-by-case basis.
3.2. Project Schedule:
3.2.1. Prepare for approval a Project Schedule, as specified herein, pursuant to the contract clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the contractor proposes to perform the work and dates on which the contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including construction sequences, is required. The scheduling of construction is the responsibility of the contractor. Contractor management personnel shall actively participate in its development.
Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.
3.2.1.1. Approved Project Schedule. Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded.
The schedule will provide the basis for all progress payments. If the contractor fails to submit any schedule within the time prescribed, the Contracting Officer (KO) may withhold approval of progress payments until the contractor submits the required schedule.
3.2.1.2. Default Terms. Failure of the contractor to comply with the requirements of the contract shall be grounds for a determination, by the KO, that the contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the KO may terminate the contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2.2. BASIS FOR PAYMENT AND COST LOADING: Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each invoice payment.
Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the KO to evaluate contractor percentage complete for the purposes of payment.
Failure of the contractor to provide all required information will result in the disapproval of the preliminary, initial, and subsequent schedule updates. In the event schedule revisions are directed by the KO and those revisions have not been included in subsequent revisions or updates, the KO may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the KO. The aggregate value of all activities coded to a contract line item number (CLIN) shall equal the value of the CLIN on the Project Schedule. The Government will withhold 5% of the project amount for submission and acceptance of any and all closeout documents as specified in each project and this shall be shown on the project schedule.
3.2.3. PROJECT SCHEDULE DETAILED REQUIREMENTS: The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the contractor to meet the requirements of this specification will result in the disapproval of the schedule.
3.2.3.1. Critical Path Method. Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).
3.2.3.2. Level of Detail Required. Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the KO, will result in its disapproval. The KO will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
a. Activity Durations. Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Procurement activities are defined herein.
b. Permit Activities. Include permit activities, when required, with the necessary conferences and follow-up actions and dates. Include the permitting schedule in the Project Schedule, showing the sequence of events involved in carrying out the project permit tasks within the specific contract period. This shall be at a detailed level of scheduling sufficient to identify all major permitting tasks, including those that control the flow of work.
c. Procurement Activities. Tasks related to the procurement of long lead materials or equipment shall be included as separate activities in the project schedule. Long lead materials and equipment are those materials that have a procurement cycle of over 30 days. Examples of procurement process activities include, but are not limited to: submittals, approvals, procurement, delivery, start-up, and testing.
d. Mandatory Tasks. The following tasks (as required) must be included and properly scheduled:
1. Submission of closeout submittals, equipment commissioning, controls testing plan submission, controls testing, performance verification testing, other systems testing, Contractor’s internal project inspection, correction of punchlist from the Contractor’s pre-final inspection, final inspection.
2. Government Activities. Show Government and other agency activities that could impact progress. These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3. Contract Line Item Number (CLIN) Coding. Code all activities to the CLIN on the CLIN Schedule to which the activity belongs. An activity shall not contain more than one CLIN code. CLIN code all activities, even when an activity is not cost loaded (to include preconstruction and post construction activities).
3.2.4. Scheduled Project Completion and Activity Calendars. The schedule interval shall extend from Notice to Proceed (NTP) date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7-day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. Assign the Category of Work Code - Weather Sensitive Installation to those activities that are weather sensitive. Original durations must account for anticipated normal adverse weather. The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the contractor intends to perform work during those periods.
3.2.4.1. Project Start Date. The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called “NTP”.
3.2.4.2. Project Completion Date. Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "Project Completion”.
3.2.5. PROJECT SCHEDULE SUBMISSIONS: The contractor shall provide the submissions as described below:
3.2.5.1. Project Schedule Submission. Submit the Project Schedule for approval within 7 calendar days after NTP. The schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. The Project Schedule shall be at a reasonable level of detail as determined by the KO. This requirement is in addition to any required schedules or submittals submitted in response to a Request for Proposal (RFP).
3.2.5.2. Project Schedule Updates. At the request of the KO, the contractor shall provide and submit an updated Project Schedule. These submissions will enable the KO to assess the contractor's progress. If the contractor fails or refuses to furnish the information and Project Schedule data, which in the judgment of the KO or authorized representative is necessary for verifying the contractor's progress, the contractor shall be deemed not to have provided an estimate upon which progress payment may be made.
3.2.6. REQUESTS FOR TIME EXTENSIONS: In the event the contractor believes they are entitled to an extension of the contract performance period, completion date, or any interim milestone date, furnish the following for a determination by the KO: justification, project schedule data, and supporting evidence (Ex: daily reports showing delays) as the KO may deem necessary.
Submission of proof of excusable delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is a condition precedent to any approvals by the Government. In response to each RFP issued by the Government, the contractor shall submit a schedule impact analysis demonstrating whether or not the change contemplated by the Government impacts the critical path.
3.2.6.1. Justification of Delay. The Project Schedule shall clearly display that the contractor has used, in full, all the float time available for the work involved with this request. The KO's determination as to the number of allowable days of contract extension shall be based upon the Project Schedule updates in effect for the time period in question, and other factual information. Actual delays that are found to be caused by the contractor's own actions, which result in a calculated schedule delay, will not be a cause for an extension to the performance period, completion date, or any interim milestone date.
3.2.6.2. Unexcused Delays. Unexcused delays will result in a disapproval of any time extension request and the Contractor will be required to complete the work within the original period of performance. If the Contractor cannot complete the work within the original period of performance, the Contractor will be required to provide consideration to the Government in order to receive a time extension. Consideration will be established on a case by case basis but examples include but are not limited to extended warranty period, upgraded materials, etc.
3.3. Accident Prevention Plan:
3.3.1. Use a qualified person to prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". Specific requirements for some of the APP elements are described below. The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the contractor's overall safety and health program. Include any portions of the contractor's overall safety and health program referenced in the APP in the applicable APP element and made site specific. The Government considers the prime contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing its subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP shall be signed by the person and firm (senior person) preparing the APP, the contractor, the on-site superintendent, the designated site safety and health officer and any designated CSP and/or CIH.
3.3.2. Submit the APP to the Government personnel within 14 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP.
3.3.3. Once accepted by the KO or their representative, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the KO, until the matter has been rectified.
3.3.4. Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the KO, or their representative, project superintendent, SSHO, and quality control manager. Should any hazard become evident, stop work in the area, secure the area, and develop a plan to remove the hazard. Notify the KO within 24 hours of discovery. Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public (as defined by ASSE/SAFE A10.34,) and the environment.
3.3.5. Copies of the accepted plan will be maintained at the KO's office and at the job site. Continuously review and amend the APP, as necessary, throughout the life of the contract. Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered.
4. PROJECT REQUIRED SUBMITTALS:
4.1.1. Pre-Construction Submittals:
4.1.1.1. Quality Control Plan – Plan shall list contractor POC’s with phone numbers and list any subcontractor’s used with POC’s and phone numbers.
4.1.1.2. Accident Prevention Plan with AHA’s
4.1.1.3. Environmental Protection Plan
4.1.1.4. Hazardous materials list with safety data sheet for each material (see section 16.6). HJB Form
225 may be required.
4.1.1.5. Construction/Project Schedule
4.1.1.6. Training and Completion Letters (AT/FP, OPSEC, iWATCH, E-Verify)
4.1.1.7. Submittal Register (ENG Form 4288-R)
4.1.2. Construction Submittals:
4.1.2.1. Manufacturer’s equipment specification sheets. All applicable items such as model numbers, sizes, and accessories shall be indicated using arrows or highlight.
4.1.2.2. Applicable materials meeting specifications of SOW.
4.1.2.3. Closeout Submittals:
4.1.2.4. Operation and Maintenance (O&M) manual to include:
a. Contractor’s Warranty Letter
b. Equipment operations and maintenance manual
c. Startup and test reports
d. Checklists
4.1.2.5. One printed Operation and Maintenance (O&M) manual in 3-ring binder
4.1.2.6. The Contractor shall provide a letter of non-retention for all contract documents, plans, drawings, and specifications after the destruction of all copies that are not required by the contractor to meet legal requirements.
4.1.2.7. HJB Form 953
4.1.2.8. 1354(s)
4.1.2.9. As-Built Drawings
5. DRAWINGS , SPECIFICATIONS & CODES:
5.1. Drawings
5.1.1. The drawings outlined below are attached:
Drawing Number
Sheet Number
Title Rev Number
Date
Attachment #1 – Equipment Specs Attachment #2 – DDC Seq, Points, Regs Attachment #3 – As-Builts Attachment #4 – Pictures
5.1.2. Dimensions and utility locations are approximate and must be verified in the field.
5.2. Specifications
5.2.1. JBLM DDC Specification 23 09 23
5.3. Codes
5.3.1. The Contractor shall comply with all pertinent Local, State, and Federal building life/health/safety codes as listed.
5.3.1.1. Applicable Unified Facilities Criteria (UFC)
5.3.1.2. UFC 1-200-01: General Building Requirements http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01
5.3.1.3. UFC 1-200-02: High Performance and Sustainable Building Requirements https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-02
5.3.1.4. ASA IE&E SDD policy
https://www.wbdg.org/FFC/ARMYCOE/POLICY/Army_SDD_Policy_Update_2017.pdf
5.3.1.5. UFC 1-201-01 Non-Permanent DOD Facilities in Support of Military Operations
5.3.1.6. EM 385-1-1
(http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx)
5.3.1.7. National Electrical Code, NFPA 70
5.3.1.8. National Plumbing Code
5.3.1.9. National Fire Protection Association (NFPA) Codes
5.3.1.10. Telecommunication Industry Association/Electrical Industry Association Wiring Standards
(Building Telecommunication Wiring Standards)
5.3.1.11. Army Installation Information Infrastructure Architecture Policy (I3A)
5.3.1.12. JBLM Design Standard specifications (http://www.lewis-mcchord.army.mil/designstandards/)
5.3.1.13. JBLM 420-1 (2020)
5.3.1.14. JBLM Master Plan, which includes Architectural Appearance Standards
5.3.1.15. PWE-707, Standard Operating Procedure for Construction and Demolition (C&D) Waste
Planning and Reporting (Available through government Project Manager)
5.3.1.16. National Pollutant Discharge Elimination System (NPDES) small Municipal Separate Storm
Sewer Systems (MS4) Permit No. WAS-026638. Use guidance documents found at https://home.army.mil/lewis-mcchord/index.php/my-Joint-Base-Lewis-Mcchord/all-services/public_works-environmental_division/stormwater
6. SAFETY:
6.1 In addition to the detailed requirements included in the provisions of this contract, comply with USACE EM 385-1-1, and all Federal, state, and local, laws, ordinances, criteria, rules, and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
6.2 Activity Hazard Analysis (AHA):
6.2.1 The AHA format shall be in accordance with USACE EM 385-1-1. Submit the AHA for review at least 14 calendar days prior to the start of a project; an accepted AHA is required to start onsite work. Format subsequent AHA’s as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.
6.2.2 The AHA list will be reviewed periodically (at least monthly) and updated as necessary when procedures, scheduling, or hazards change.
6.2.3 Develop the activity hazard analyses using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA. The AHA will be developed by the contractor, supplier, or subcontractor and provided to the prime contractor for submittal to the KO or their representative.
6.3 HOT WORK: Required
6.3.1 Obtain a permit prior to performing hot work (welding, cutting, etc.) or operating other flame-producing/spark producing devices. The JBLM Fire Prevention Branch provides a training for Contractors so that they may self-issue hot work permits. CONTRACTORS ARE REQUIRED TO MEET ALL CRITERIA BEFORE BEING ABLE TO SELF ISSUE A PERMIT. The contractor will provide at least two (2) twenty (20) pound 4A:20 BC rated extinguishers for normal hot work.