Attachment 2 - Painting and Repairs 2026 Task List.xlsx
XLSX spreadsheet 29 KB Posted
- Attached to
- Paint and Repairs IDIQ
- Solicitation number
- W911S7-26-B-A006
About this file
Attachment 2 is a task list for painting and repair services at Fort Leonard Wood and LORA facilities. This document outlines the specific work tasks and deliverables that will be performed under the Paint and Repairs IDIQ contract (W911S7-26-B-A006), a five-year Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside issued by the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis. The task list serves as the primary reference for defining scope and quantities of work to be completed, with payment based solely on actual quantities performed for each task item as directed by the Contracting Officer through individual task orders. The file was amended on August 3, 2026, to clarify task cross-references, add unit abbreviation definitions, and extend the submission deadline to August 18, 2026.
The work encompasses interior and exterior painting and repairs across Fort Leonard Wood and LORA locations, performed in accordance with the Statement of Work and specifications provided in Attachment 1. As an IDIQ contract with a base year plus four option years, work will be issued on a requirements basis with no guaranteed minimum volume. The NAICS code 238320 applies with a $19 million small business size standard. Davis-Bacon Act wage determination MO20260019 governs labor costs, and no site visits are permitted for this solicitation.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Period Painting and Repairs IDIQ - Base Year IGCE
| Task | Task Description | Quantity | U/M | Unit Price | Total |
| 1 | Prepare and Paint miscellaneous surfaces. Use task 15 if texture is required in surface prep. | 40,000 | SQ | $0.00 | |
| 2 | Paint miscellaneous surfaces at other than normal duty hours. | 1500 | SQ | $0.00 | |
| 3 | Provide second coat of paint where one coat fails to adequately cover existing painted wall surface | 2000 | SQ | $0.00 | |
| 4 | Remove incompatible paint | 10 | SQ | $0.00 | |
| 5 | Paint interior surfaces with epoxy paint | 300 | SQ | $0.00 | |
| 6 | Paint exterior doors | 500 | EA | $0.00 | |
| 7 | Prime and paint exterior handrails | 2000 | LF | $0.00 | |
| 8 | Paint Miscellaneous Exterior CMU | 100 | SQ | $0.00 | |
| 9 | Prime & Paint Interior Handrails (Libby NCO Academy Barracks, Typical Bldg 3253) | 1500 | LF | $0.00 | |
| 10 | Prime & Paint Interior Handrails (Rolling Pin Barracks, Typical Bldg 659) | 2000 | LF | $0.00 | |
| 11 | Repair acoustic ceiling textured surface | 1100 | SF | $0.00 | |
| 12 | Replace deteriorated ceiling tile | 14000 | SF | $0.00 | |
| 13 | Replace gypsum board | 10000 | SF | $0.00 | |
| 14 | Tape and finish gypsum board surfaces | 30000 | SF | $0.00 | |
| 15 | Provide textured finish on gypsum board with gypsum plaster/mud (knock-down with trowel) | 20000 | SF | $0.00 | |
| 16 | Remove vinyl/sisal wall covering and prepare surface for paint | 5000 | SF | $0.00 | |
| 17 | Remove vinyl/sisal wall covering and prepare surface for paint at other than normal duty hours (primarily at hospital) | 2500 | SF | $0.00 | |
| 18 | Furnish & install corner guards (3" x 3" PVC) | 2000 | LF | $0.00 | |
| 19 | Furnish & install corner guards (3" x 3" stainless steel) | 500 | LF | $0.00 | |
| 20 | Furnish and Install Wall Guards (3" high PVC) | 1000 | LF | $0.00 | |
| 21 | Furnish and Install Wall Guard PVC Corners, Inside and Outside | 60 | EA | $0.00 | |
| 22 | Furnish and Install Wall Guard PVC End Caps | 575 | EA | $0.00 | |
| 23 | Furnish and Install Handrails (5-1/4" PVC) | 1000 | LF | $0.00 | |
| 24 | Furnish and Install Handrail (5-1/4" PVC) Corners, Inside & Outside | 50 | EA | $0.00 | |
| 25 | Furnish and Install Handrail (5-1/4" PVC) Returns, Left and Right | 200 | EA | $0.00 | |
| 26 | Furnish and Install wall Guards (7-3/4" High PVC) | 500 | LF | $0.00 | |
| 27 | Furnish & Install Wall Guard (7-3/4" High PVC) Corners, Inside & Outside | 5 | EA | $0.00 | |
| 28 | Furnish and Install Wall Guard (7-3/4" High PVC) End Caps | 200 | EA | $0.00 | |
| 29 | Replace miscellaneous wood trim | 1000 | LF | $0.00 | |
| 30 | Replace 4" vinyl wall base | 5000 | LF | $0.00 | |
| 31 | Replace 6" vinyl wall base | 100 | LF | $0.00 | |
| 32 | Remove & dispose of lead-based painted casing, sill, trim, base & molding | 120 | LF | $0.00 | |
| 33 | Remove & dispose of lead-based painted exterior door, jamb, trim & threshold | 5 | EA | $0.00 | |
| 34 | Provide R19 Batt Insulation | 1000 | SF | $0.00 | |
| 35 | Paint Exterior Steel Siding | 1000 | SQ | $0.00 | |
| 36 | Paint Exterior Wood Siding | 50 | SQ | $0.00 | |
| 37 | Paint Miscellaneous Trim | 5000 | LF | $0.00 | |
| 38 | Provide & Install Window Blinds (Width 3' to 5') | 2000 | LF | $0.00 | |
| 39 | Provide & Install Window Blinds (Width greater than 5') | 500 | LF | $0.00 | |
| 40 | Pressure Wash Misc. Surfaces (NTE 2 Story) | 1000 | SQ | $0.00 | |
| TOTAL: | $0.00 |
1st Option Period Painting and Repairs IDIQ - Option 1 IGCE
| Task | Task Description | Quantity | U/M | Unit Price | Total |
| 101 | Prepare and Paint miscellaneous surfaces. Use task 15 if texture is required in surface prep. | 40,000 | SQ | $0.00 | |
| 102 | Paint miscellaneous surfaces at other than normal duty hours. | 1500 | SQ | $0.00 | |
| 103 | Provide second coat of paint where one coat fails to adequately cover existing painted wall surface | 2000 | SQ | $0.00 | |
| 104 | Remove incompatible paint | 10 | SQ | $0.00 | |
| 105 | Paint interior surfaces with epoxy paint | 300 | SQ | $0.00 | |
| 106 | Paint exterior doors | 500 | EA | $0.00 | |
| 107 | Prime and paint exterior handrails | 2000 | LF | $0.00 | |
| 108 | Paint Miscellaneous Exterior CMU | 100 | SQ | $0.00 | |
| 109 | Prime & Paint Interior Handrails (Libby NCO Academy Barracks, Typical Bldg 3253) | 1500 | LF | $0.00 | |
| 110 | Prime & Paint Interior Handrails (Rolling Pin Barracks, Typical Bldg 659) | 2000 | LF | $0.00 | |
| 111 | Repair acoustic ceiling textured surface | 1100 | SF | $0.00 | |
| 112 | Replace deteriorated ceiling tile | 14000 | SF | $0.00 | |
| 113 | Replace gypsum board | 10000 | SF | $0.00 | |
| 114 | Tape and finish gypsum board surfaces | 30000 | SF | $0.00 | |
| 115 | Provide textured finish on gypsum board with gypsum plaster/mud (knock-down with trowel) | 20000 | SF | $0.00 | |
| 116 | Remove vinyl/sisal wall covering and prepare surface for paint | 5000 | SF | $0.00 | |
| 117 | Remove vinyl/sisal wall covering and prepare surface for paint at other than normal duty hours (primarily at hospital) | 2500 | SF | $0.00 | |
| 118 | Furnish & install corner guards (3" x 3" PVC) | 2000 | LF | $0.00 | |
| 119 | Furnish & install corner guards (3" x 3" stainless steel) | 500 | LF | $0.00 | |
| 120 | Furnish and Install Wall Guards (3" high PVC) | 1000 | LF | $0.00 | |
| 121 | Furnish and Install Wall Guard PVC Corners, Inside and Outside | 60 | EA | $0.00 | |
| 122 | Furnish and Install Wall Guard PVC End Caps | 575 | EA | $0.00 | |
| 123 | Furnish and Install Handrails (5-1/4" PVC) | 1000 | LF | $0.00 | |
| 124 | Furnish and Install Handrail (5-1/4" PVC) Corners, Inside & Outside | 50 | EA | $0.00 | |
| 125 | Furnish and Install Handrail (5-1/4" PVC) Returns, Left and Right | 200 | EA | $0.00 | |
| 126 | Furnish and Install wall Guards (7-3/4" High PVC) | 500 | LF | $0.00 | |
| 127 | Furnish & Install Wall Guard (7-3/4" High PVC) Corners, Inside & Outside | 5 | EA | $0.00 | |
| 128 | Furnish and Install Wall Guard (7-3/4" High PVC) End Caps | 200 | EA | $0.00 | |
| 129 | Replace miscellaneous wood trim | 1000 | LF | $0.00 | |
| 130 | Replace 4" vinyl wall base | 5000 | LF | $0.00 | |
| 131 | Replace 6" vinyl wall base | 100 | LF | $0.00 | |
| 132 | Remove & dispose of lead-based painted casing, sill, trim, base & molding | 120 | LF | $0.00 | |
| 133 | Remove & dispose of lead-based painted exterior door, jamb, trim & threshold | 5 | EA | $0.00 | |
| 134 | Provide R19 Batt Insulation | 1000 | SF | $0.00 | |
| 135 | Paint Exterior Steel Siding | 1000 | SQ | $0.00 | |
| 136 | Paint Exterior Wood Siding | 50 | SQ | $0.00 | |
| 137 | Paint Miscellaneous Trim | 5000 | LF | $0.00 | |
| 138 | Provide & Install Window Blinds (Width 3' to 5') | 2000 | LF | $0.00 | |
| 139 | Provide & Install Window Blinds (Width greater than 5') | 500 | LF | $0.00 | |
| 140 | Pressure Wash Misc. Surfaces (NTE 2 Story) | 1000 | SQ | $0.00 | |
| TOTAL: | $0.00 |
2nd Option Period Painting and Repairs IDIQ - Option 2 IGCE
| Task | Task Description | Quantity | U/M | Unit Price | Total |
| 201 | Prepare and Paint miscellaneous surfaces. Use task 15 if texture is required in surface prep. | 40,000 | SQ | $0.00 | |
| 202 | Paint miscellaneous surfaces at other than normal duty hours. | 1500 | SQ | $0.00 | |
| 203 | Provide second coat of paint where one coat fails to adequately cover existing painted wall surface | 2000 | SQ | $0.00 | |
| 204 | Remove incompatible paint | 10 | SQ | $0.00 | |
| 205 | Paint interior surfaces with epoxy paint | 300 | SQ | $0.00 | |
| 206 | Paint exterior doors | 500 | EA | $0.00 | |
| 207 | Prime and paint exterior handrails | 2000 | LF | $0.00 | |
| 208 | Paint Miscellaneous Exterior CMU | 100 | SQ | $0.00 | |
| 209 | Prime & Paint Interior Handrails (Libby NCO Academy Barracks, Typical Bldg 3253) | 1500 | LF | $0.00 | |
| 210 | Prime & Paint Interior Handrails (Rolling Pin Barracks, Typical Bldg 659) | 2000 | LF | $0.00 | |
| 211 | Repair acoustic ceiling textured surface | 1100 | SF | $0.00 | |
| 212 | Replace deteriorated ceiling tile | 14000 | SF | $0.00 | |
| 213 | Replace gypsum board | 10000 | SF | $0.00 | |
| 214 | Tape and finish gypsum board surfaces | 30000 | SF | $0.00 | |
| 215 | Provide textured finish on gypsum board with gypsum plaster/mud (knock-down with trowel) | 20000 | SF | $0.00 | |
| 216 | Remove vinyl/sisal wall covering and prepare surface for paint | 5000 | SF | $0.00 | |
| 217 | Remove vinyl/sisal wall covering and prepare surface for paint at other than normal duty hours (primarily at hospital) | 2500 | SF | $0.00 | |
| 218 | Furnish & install corner guards (3" x 3" PVC) | 2000 | LF | $0.00 | |
| 219 | Furnish & install corner guards (3" x 3" stainless steel) | 500 | LF | $0.00 | |
| 220 | Furnish and Install Wall Guards (3" high PVC) | 1000 | LF | $0.00 | |
| 221 | Furnish and Install Wall Guard PVC Corners, Inside and Outside | 60 | EA | $0.00 | |
| 222 | Furnish and Install Wall Guard PVC End Caps | 575 | EA | $0.00 | |
| 223 | Furnish and Install Handrails (5-1/4" PVC) | 1000 | LF | $0.00 | |
| 224 | Furnish and Install Handrail (5-1/4" PVC) Corners, Inside & Outside | 50 | EA | $0.00 | |
| 225 | Furnish and Install Handrail (5-1/4" PVC) Returns, Left and Right | 200 | EA | $0.00 | |
| 226 | Furnish and Install wall Guards (7-3/4" High PVC) | 500 | LF | $0.00 | |
| 227 | Furnish & Install Wall Guard (7-3/4" High PVC) Corners, Inside & Outside | 5 | EA | $0.00 | |
| 228 | Furnish and Install Wall Guard (7-3/4" High PVC) End Caps | 200 | EA | $0.00 | |
| 229 | Replace miscellaneous wood trim | 1000 | LF | $0.00 | |
| 230 | Replace 4" vinyl wall base | 5000 | LF | $0.00 | |
| 231 | Replace 6" vinyl wall base | 100 | LF | $0.00 | |
| 232 | Remove & dispose of lead-based painted casing, sill, trim, base & molding | 120 | LF | $0.00 | |
| 233 | Remove & dispose of lead-based painted exterior door, jamb, trim & threshold | 5 | EA | $0.00 | |
| 234 | Provide R19 Batt Insulation | 1000 | SF | $0.00 | |
| 235 | Paint Exterior Steel Siding | 1000 | SQ | $0.00 | |
| 236 | Paint Exterior Wood Siding | 50 | SQ | $0.00 | |
| 237 | Paint Miscellaneous Trim | 5000 | LF | $0.00 | |
| 238 | Provide & Install Window Blinds (Width 3' to 5') | 2000 | LF | $0.00 | |
| 239 | Provide & Install Window Blinds (Width greater than 5') | 500 | LF | $0.00 | |
| 240 | Pressure Wash Misc. Surfaces (NTE 2 Story) | 1000 | SQ | $0.00 | |
| TOTAL: | $0.00 |
3rd Option Period Painting and Repairs IDIQ - Option 3 IGCE
| Task | Task Description | Quantity | U/M | Unit Price | Total |
| 301 | Prepare and Paint miscellaneous surfaces. Use task 15 if texture is required in surface prep. | 40,000 | SQ | $0.00 | |
| 302 | Paint miscellaneous surfaces at other than normal duty hours. | 1500 | SQ | $0.00 | |
| 303 | Provide second coat of paint where one coat fails to adequately cover existing painted wall surface | 2000 | SQ | $0.00 | |
| 304 | Remove incompatible paint | 10 | SQ | $0.00 | |
| 305 | Paint interior surfaces with epoxy paint | 300 | SQ | $0.00 | |
| 306 | Paint exterior doors | 500 | EA | $0.00 | |
| 307 | Prime and paint exterior handrails | 2000 | LF | $0.00 | |
| 308 | Paint Miscellaneous Exterior CMU | 100 | SQ | $0.00 | |
| 309 | Prime & Paint Interior Handrails (Libby NCO Academy Barracks, Typical Bldg 3253) | 1500 | LF | $0.00 | |
| 310 | Prime & Paint Interior Handrails (Rolling Pin Barracks, Typical Bldg 659) | 2000 | LF | $0.00 | |
| 311 | Repair acoustic ceiling textured surface | 1100 | SF | $0.00 | |
| 312 | Replace deteriorated ceiling tile | 14000 | SF | $0.00 | |
| 313 | Replace gypsum board | 10000 | SF | $0.00 | |
| 314 | Tape and finish gypsum board surfaces | 30000 | SF | $0.00 | |
| 315 | Provide textured finish on gypsum board with gypsum plaster/mud (knock-down with trowel) | 20000 | SF | $0.00 | |
| 316 | Remove vinyl/sisal wall covering and prepare surface for paint | 5000 | SF | $0.00 | |
| 317 | Remove vinyl/sisal wall covering and prepare surface for paint at other than normal duty hours (primarily at hospital) | 2500 | SF | $0.00 | |
| 318 | Furnish & install corner guards (3" x 3" PVC) | 2000 | LF | $0.00 | |
| 319 | Furnish & install corner guards (3" x 3" stainless steel) | 500 | LF | $0.00 | |
| 320 | Furnish and Install Wall Guards (3" high PVC) | 1000 | LF | $0.00 | |
| 321 | Furnish and Install Wall Guard PVC Corners, Inside and Outside | 60 | EA | $0.00 | |
| 322 | Furnish and Install Wall Guard PVC End Caps | 575 | EA | $0.00 | |
| 323 | Furnish and Install Handrails (5-1/4" PVC) | 1000 | LF | $0.00 | |
| 324 | Furnish and Install Handrail (5-1/4" PVC) Corners, Inside & Outside | 50 | EA | $0.00 | |
| 325 | Furnish and Install Handrail (5-1/4" PVC) Returns, Left and Right | 200 | EA | $0.00 | |
| 326 | Furnish and Install wall Guards (7-3/4" High PVC) | 500 | LF | $0.00 | |
| 327 | Furnish & Install Wall Guard (7-3/4" High PVC) Corners, Inside & Outside | 5 | EA | $0.00 | |
| 328 | Furnish and Install Wall Guard (7-3/4" High PVC) End Caps | 200 | EA | $0.00 | |
| 329 | Replace miscellaneous wood trim | 1000 | LF | $0.00 | |
| 330 | Replace 4" vinyl wall base | 5000 | LF | $0.00 | |
| 331 | Replace 6" vinyl wall base | 100 | LF | $0.00 | |
| 332 | Remove & dispose of lead-based painted casing, sill, trim, base & molding | 120 | LF | $0.00 | |
| 333 | Remove & dispose of lead-based painted exterior door, jamb, trim & threshold | 5 | EA | $0.00 | |
| 334 | Provide R19 Batt Insulation | 1000 | SF | $0.00 | |
| 335 | Paint Exterior Steel Siding | 1000 | SQ | $0.00 | |
| 336 | Paint Exterior Wood Siding | 50 | SQ | $0.00 | |
| 337 | Paint Miscellaneous Trim | 5000 | LF | $0.00 | |
| 338 | Provide & Install Window Blinds (Width 3' to 5') | 2000 | LF | $0.00 | |
| 339 | Provide & Install Window Blinds (Width greater than 5') | 500 | LF | $0.00 | |
| 340 | Pressure Wash Misc. Surfaces (NTE 2 Story) | 1000 | SQ | $0.00 | |
| TOTAL: | $0.00 |
4th Option Period Painting and Repairs IDIQ - Option 4 IGCE
| Task | Task Description | Quantity | U/M | Unit Price | Total |
| 401 | Prepare and Paint miscellaneous surfaces. Use task 15 if texture is required in surface prep. | 40,000 | SQ | $0.00 | |
| 402 | Paint miscellaneous surfaces at other than normal duty hours. | 1500 | SQ | $0.00 | |
| 403 | Provide second coat of paint where one coat fails to adequately cover existing painted wall surface | 2000 | SQ | $0.00 | |
| 404 | Remove incompatible paint | 10 | SQ | $0.00 | |
| 405 | Paint interior surfaces with epoxy paint | 300 | SQ | $0.00 | |
| 406 | Paint exterior doors | 500 | EA | $0.00 | |
| 407 | Prime and paint exterior handrails | 2000 | LF | $0.00 | |
| 408 | Paint Miscellaneous Exterior CMU | 100 | SQ | $0.00 | |
| 409 | Prime & Paint Interior Handrails (Libby NCO Academy Barracks, Typical Bldg 3253) | 1500 | LF | $0.00 | |
| 410 | Prime & Paint Interior Handrails (Rolling Pin Barracks, Typical Bldg 659) | 2000 | LF | $0.00 | |
| 411 | Repair acoustic ceiling textured surface | 1100 | SF | $0.00 | |
| 412 | Replace deteriorated ceiling tile | 14000 | SF | $0.00 | |
| 413 | Replace gypsum board | 10000 | SF | $0.00 | |
| 414 | Tape and finish gypsum board surfaces | 30000 | SF | $0.00 | |
| 415 | Provide textured finish on gypsum board with gypsum plaster/mud (knock-down with trowel) | 20000 | SF | $0.00 | |
| 416 | Remove vinyl/sisal wall covering and prepare surface for paint | 5000 | SF | $0.00 | |
| 417 | Remove vinyl/sisal wall covering and prepare surface for paint at other than normal duty hours (primarily at hospital) | 2500 | SF | $0.00 | |
| 418 | Furnish & install corner guards (3" x 3" PVC) | 2000 | LF | $0.00 | |
| 419 | Furnish & install corner guards (3" x 3" stainless steel) | 500 | LF | $0.00 | |
| 420 | Furnish and Install Wall Guards (3" high PVC) | 1000 | LF | $0.00 | |
| 421 | Furnish and Install Wall Guard PVC Corners, Inside and Outside | 60 | EA | $0.00 | |
| 422 | Furnish and Install Wall Guard PVC End Caps | 575 | EA | $0.00 | |
| 423 | Furnish and Install Handrails (5-1/4" PVC) | 1000 | LF | $0.00 | |
| 424 | Furnish and Install Handrail (5-1/4" PVC) Corners, Inside & Outside | 50 | EA | $0.00 | |
| 425 | Furnish and Install Handrail (5-1/4" PVC) Returns, Left and Right | 200 | EA | $0.00 | |
| 426 | Furnish and Install wall Guards (7-3/4" High PVC) | 500 | LF | $0.00 | |
| 427 | Furnish & Install Wall Guard (7-3/4" High PVC) Corners, Inside & Outside | 5 | EA | $0.00 | |
| 428 | Furnish and Install Wall Guard (7-3/4" High PVC) End Caps | 200 | EA | $0.00 | |
| 429 | Replace miscellaneous wood trim | 1000 | LF | $0.00 | |
| 430 | Replace 4" vinyl wall base | 5000 | LF | $0.00 | |
| 431 | Replace 6" vinyl wall base | 100 | LF | $0.00 | |
| 432 | Remove & dispose of lead-based painted casing, sill, trim, base & molding | 120 | LF | $0.00 | |
| 433 | Remove & dispose of lead-based painted exterior door, jamb, trim & threshold | 5 | EA | $0.00 | |
| 434 | Provide R19 Batt Insulation | 1000 | SF | $0.00 | |
| 435 | Paint Exterior Steel Siding | 1000 | SQ | $0.00 | |
| 436 | Paint Exterior Wood Siding | 50 | SQ | $0.00 | |
| 437 | Paint Miscellaneous Trim | 5000 | LF | $0.00 | |
| 438 | Provide & Install Window Blinds (Width 3' to 5') | 2000 | LF | $0.00 | |
| 439 | Provide & Install Window Blinds (Width greater than 5') | 500 | LF | $0.00 | |
| 440 | Pressure Wash Misc. Surfaces (NTE 2 Story) | 1000 | SQ | $0.00 | |
| TOTAL: | $0.00 | ||||
| GRAND TOTAL (BASE YEAR PLUS 4 OPTION YEARS): | $0.00 | ||||
| SQ | Square (100 square feet) | ||||
| SF | Square Feet | ||||
| LF | Linear Feet | ||||
| EA | Each |