Questions_and_Answers_W911S7-18-B-0014_Asphalt.pdf

PDF 518 KB Posted

Attached to
ASPHALT
Solicitation number
W911S7-18-B-0014
Issued by

About this file

Questions and Answers

View the file

Other files

File Type Posted
Abstract_of_Offers.pdf PDF
Bid_Opening_Sign-In_Sheet.pdf PDF
W911S7-18-B-0014-P0001.pdf PDF
7936_s1.pdf PDF
W911S7-18-B-0014_18_June_18.pdf PDF
Camden_County_Wage_Determination.pdf PDF
Technical_Exhibit_A_FY18.xlsx XLSX spreadsheet
FY_18_Asphalt_SOW_18_June_18.pdf PDF
Pulaski_County_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

W911S7-18-B-0014

Asphalt Requirements, Fort Leonard Wood, MO

1. We have not seen any electronic drawings on the solicitation, will there be any drawings for the bid?

Answer: Yes, per Amendment 00001, See Drawing 7936_s1.

2. This is a Total Small Business Set Aside contract with a size standard of $36.5M correct?

Answer: Yes, Section 10 of the Solicitation states- This acquisition is a Total Small Business Set-Aside. The

NACIS is 237310 with a size standard of $36.5M.

3. Are the quantities that are bid in the contract in anyway guaranteed or are they just an estimate based entirely on funding?

Answer: Quantities on a requirement contract are not guaranteed, Reference FAR 52.216-21 (a)

4. Per the contract clause stating that a contractor wouldn’t be required to fulfill a delivery order of

$500.00 or less, does that mean a delivery order as small as $501.00 would have to be fulfilled?

Answer: FAR 52.216-19 Order Limitations (a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $500.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.

This means that orders for supplies or services that are on this contract but under $500.00, do not obligate the Government to purchase under the contract nor the Contractor obligated to furnish under the contract.

5. Will all excess material that is produced during the Excavation Cleanse item still be required to be hauled off post since the dumps are closed?

Answer: Yes. Refer to Section 01010, Paragraph 14 DISPOSAL OF MATERIALS.

6. Is the contractor financially responsible for all costs for employee training required to work on Fort

Leonard Wood, (OPSEC Training, Anti-Terrorism, I- Watch, Access Passes, etc)?

Answer: Refer to Section 01010, Paragraph 15 ACCESS AND GENERAL PROTECTION/SECURITY POLICY

AND PROCEDURES.

7. Are all traffic control costs as indicated in the solicitation (traffic signage, barricades, flaggers, pilot cars, etc.) incidental?

Answer: Traffic control is required for many work items in the contract but will not be reimbursed as a separate task item.

8. From the wording in the Solicitation “The magnitude of this effort is between $5,000,000.00 and

$10,000,000.00,” is that an estimated quantity based on funding or a guaranteed amount?

Answer: FAR 36.204 Disclosure of the Magnitude of Construction Projects. “Advance notices and solicitations shall state the magnitude of the requirement in terms of physical characteristics and estimated price range. In no event shall the statement of magnitude disclose the Government’s estimate.” The magnitude is NOT a guaranteed amount.

9. Sealed bids + (1) copy must be submitted by the required bid date and time of 2:00 PM on July 18, 2018. Does that mean no electronic bids are allowed?

Answer: No electronic bids are allowed. Per the Solicitation, Section L, L-3 Original bids will not be accepted by facsimile.