PRS Dugway SRM School Age Services Bldg 5111
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Requirement Summary (PRS)
Dugway SRM School Age Services Building 5111
Statements Standards/AQLs Incentive/Remedy
2.1.4 Contractor shall
obtain all permits required to do the work.
a) Obtain all required permits.
AQL: 100% compliance.
Work will not be allowed to proceed without documentation of required permits. Claim for delay will not be allowed for lack of obtaining a required permit. Affects CPARS rating.
2.1.14 Contractor to
perform TAB and commissioning of new system after work is completed to be in compliance with Federal Energy Management Program Standards.
a) Specified work is performed.
AQL: 100% compliance.
Reconstruction and/or correction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.1.15 Contractor shall
install Anti-Terrorist Force Protection switch IAW UFC 4- 010-01 Appendix B-
4.3. The emergency
air distribution shutoff switch shall stop all fans and close all outside air dampers mounted next to the new thermostats.
a) System functions as specified.
AQL: 100% compliance.
Reconstruction and/or correction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.1.17 Contractor shall
install smoke detectors in the return ductwork interfaced with the new unit’s microprocessor connecting to the DPG Fire Departments existing system.
This includes
a) Specified items are installed and function with the existing fire alarm system.
AQL: 100% compliance.
Reconstruction and/or correction without extension of period of performance or additional compensation.
Affects CPARS rating.
testing and verify the existing fire alarm system for each unit to verify operation per the manufactures instructions.
2.1.18 Requirement for
new unit interface device to be compatible with the existing Fire Alarm Control Panel (FACP).
a) System functions with the existing fire alarm control panel.
AQL: 100% compliance.
Reconstruction and/or correction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.1.19 Require NICET
Level III Fire Alarm Technician or equal to supervise installation.
a) Qualifications as specified.
AQL: 100% compliance.
Affects CPARS rating.
2.1.20 The Contractor shall
coordinate with Dugway Proving Ground Fire Department to test and verify interface with the existing Fire Alarm (FA) System. During testing, if any devices are not found working correctly, then report it to the Fire Chief, COR and/or
DPW.
a) Smoke detectors interface functions as specified.
AQL: 100% compliance.
Reconstruction and/or correction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.1.21 Develop and update
the existing fire alarm control schematic and include the update in as-built drawings.
a) Fire alarm control schematic included in record drawings.
Delay to final payment until correct record drawings are received.
Affects CPARS rating.
2.1.22 Conduct FA Test
per NFPA 72 for the new devices and all initiating devices connected to the new units.
a) Fire alarm test complies with specified standard.
AQL: 100% compliance.
Reconstruction and/or correction without extension of period of performance or additional compensation.
2.2.3.1 Remove existing a) Perform specified work. Correction without debris and mark the exact locations for the (2) horizontal flow curb units and penetration for the conduit lines and the electrical disconnect switches. See Detail on M-601.
AQL: 100% compliance. extension of period of performance or
2.2.3.2 Verify and mark the
thru holes for all the horizontal penetrations for all new ductwork.
Supply galvanized wall sleeves with fire dampers and seal the openings.
a) Perform specified work.
AQL: 100% compliance.
b) Provide specified items.
AQL: 100% compliance.
Correction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.2.4.1 Contractor to
provide a new power supply and control wiring to the
(2) new packaged rooftop HVAC units.
Provide additional conduit and conductors as required – See drawing E101.
Remove existing utility pole currently serving pole mounted XFMR's and provide new pole mounted utility service as per details on drawing E-102. Provide a new utility pole to feed new 300KVA, 12.7KVA primary, 120/208V secondary, 3 phase, 4 wire utility XFMR.
Transformer secondary shall feed new 800A with 800A main circuit breaker 'MCB',
a) Provide specified electrical components/systems.
AQL: 100% compliance.
Resubmittal and/or reconstruction without extension of period of performance or
120/208V, 3 phase, 4 wires NEMA 3R Main Distribution panel 'MDP'.
Provide new panel with required breakers to power panelboards previously fed from demolished utility pole. Refer to note (#4) on drawing E- 102 for further information.
2.2.4.3 Provide new
conductors, conduit and circuit protection for new HVAC units.
a) Provide specified electrical components/systems.
AQL: 100% compliance.
Reconstruction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.2.4.4.a The Contractor shall be responsible to supply, route and tie-in the gas supply lines in the building to each propane fired heating roof top unit. This includes the existing domestic hot water unit as part of this project.
a) Provide propane supply to indicated items/systems.
AQL: 100% compliance.
Reconstruction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.2.4.4.b The Contractor shall coordinate the design with DPG to verify the gas pressure and flow requirements to each unit including verifying the calculations, documentation, drawings, and any other tie-ins into to the existing supply line and obtain their approval of the installation if required.
a) Provide propane pressure calculations.
AQL: 100% compliance.
Correction to piping sizes without extension of period of performance or
2.2.4.4.d Ensure that all piping, ductwork, valve supports, and hangers comply with area seismic requirements.
Piping and ductwork shall be insulated where appropriate and include ID tags, labels, thermometers, gages, isolation valves, etc. if required by the Client Agency.
a) Seismic supports/hangers comply with local requirements.
AQL: 100% compliance.
b) Insulation provided as specified.
AQL: 100% compliance.
Resubmittal and/or reconstruction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.2.4.5 Sound and vibration
control shall be in accordance with
UFC 3-410-01,
Heating, Ventilating, and Air Conditioning Systems.
a) Specified items/systems comply with the specified criteria.
AQL: 100% compliance.
Reconstruction and/ or correction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.2.4.5.a Route (3/4 inch) condensate lines with a minimum slope of (1/8 inch) to the closest roof drain and install a condensate pump with electrical power if necessary.
a) Condensate lines as specified.
AQL: 100% compliance.
Reconstruction and/ or correction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.2.4.5.c Contractor to evaluate adequacy of existing structural members, design and provide retrofits and/or reinforcements per the drawings and configurations of the new HVAC system.
Review and approve the gravity and seismic loads (uniform or concentrated loads) to ensure not to exceed the
a) Provide the specified analysis, if necessary.
allowable load limits set by current code requirements.
Contractor to design and provide supports or reinforcement if necessary.
2.2.4.6 All items shall be
evaluated and installed in accordance with the requirements of ASCE 7 (latest edition), UFC 1- 200-01 and International Building Code.
a) Installation complies with the specified criteria.
AQL: 100% compliance.
Reconstruction and/ or correction without extension of period of performance or additional compensation.
Affects CPARS rating.
2.2.4.7 Structural
evaluation shall be reviewed by a licensed Professional Engineer registered to practice in the state of Utah to determine the roof loading for both rooftop units.
a) Analysis performed by person with the specified qualifications.
AQL: 100% compliance.
Resubmittal of analysis without extension of period of performance or additional compensation.
Affects CPARS rating.
2.2.4.11 Contractor shall
provide training and O&M Manuals.
a) Provide the specified items.
AQL: 100% compliance.
Delay of final payment until specified items are complete. Affects
CPARS rating.
6.1.1 Task specific:
Quality Control Plan, Hazard Analysis and Safety/Health Plan.
Construction Schedule (PDF)
a) Provide the specified items.
AQL: 100% compliance.
Delay of construction until specified items are provided without extension of period of performance or additional compensation.
Affects CPARS rating.
6.1.2 Operations and
maintenance manuals, 4 sets, shall be submitted after completion of work and include
a) Provide the specified items.
AQL: 100% compliance.
Delay of final payment until specified items are complete. Affects
CPARS rating.
manufacturer’s data and warranty.
6.1.3 As-built drawings a) Provide the specified items.
AQL: 100% compliance.
Delay of final payment until specified items are complete. Affects
CPARS rating.
6.1.4 Completed DD
Form 1354
a) Provide the specified items.
AQL: 100% compliance.
Delay of final payment until specified items are complete. Affects
CPARS rating.
6.1.5 Structural
modifications to existing curbs and calculations for installation of new HVAC units.
a) Provide the specified items.
File details come from the government source that posted it. Updated .