Performance Requirement Summary (PRS)
Repair Chapel Wiring
Statements Standards/AQLs Incentive/Remedy
3.1 Chapel a) As described in
sections 3.1.1 to 3.1.15.7 AQL: 100% Compliance.
3.1.1 In the utility room provide a new
70 amp, double pole breaker in panel 6-A to replace existing 60 amp breaker to power new distribution panel to be placed in the chapel.
3.1.2 Use existing number 6 AWG
wiring from panelboard 6-A, see drawing E-101, to new distribution panelboard to be mounted on north wall of the chapel.
3.1.3 Provide new 70 amp, 12-space, 120/208-volt, 1 phase, 60 Hz panelboard, with main breaker and cover, to replace existing panelboard on north wall.
3.1.4 Remove and save paneling in
Chapel as needed. Run new conduit and replace visible conduit behind existing furred out wall so as to remain hidden from view. At the completion of the project, replace paneling and return wall to original condition.
3.1.5 Remove carpeting, see AD-101
for details, to allow saw cutting of concrete floor.
3.1.6 Saw-cut two trenches, see AD-
101 for details (12” W x12” D), in floor to provide power from new panelboard to new floor outlets and for installing conduit to run communication cable from audio control area to east utility tunnel.
3.1.7 Run 1" PVC conduit from new
panelboard through saw-cut trench to a 2 (two) gang electrical floor box.
3.1.7.1 Provide separate circuits to each
duplex receptacle.
3.1.7.2 Provide a brass plate cover for
the receptacle box and place box so that the cover is flat and level with the floor after carpet is installed so as to prevent any tripping hazard.
3.1.8 Provide a 12”x12" PVC junction
box to be mounted in the floor for communication.
3.1.8.1 Mount box at the junction point of
the two trenches to allow for the 2-1/2" conduit installed in both trenches to be connected to the box.
3.1.8.2 Provide a 14”x14" brass cover
for the box and place box so that the cover is flat and level with the floor after carpet is installed so as to prevent a tripping hazard.
Modify cover to allow for penetration of multiple communication points from the control center to other parts of the chapel.
3.1.9 From the 12”x12" PVC box
provide 2-1/2" to be placed in the north-south trench to the north wall, see E-101 for details, to provide a connection path for communication cabling for multiple equipment. Also provide 2-1/2" PVC to be placed in the east-west trench as a connection path for existing multi-wire communication cable to be run from the control area through the conduit into the access tunnel, along the access tunnel south to be fed through an access point by the altar area to existing equipment.
3.1.10 Provide means of connection for
communication from audio control to altar.
3.1.11 Provide means of communication
from control table to north mounted projector.
3.1.12 Provide new conduit from new
distribution center to provide power to the south overhead projector, sound system, and south projection screen.
Remove old wiring consisting of SO cable and extension cords.
Provide new grounded receptacles and new grounded cord/plug sets to connect equipment to newly supplied power.
3.1.13 Provide new conduit for
automatic shade operators on windows, run behind the wall and rewire to timers internally.
Remove existing SO cord connectors.
3.1.14 Upon completion of conduit and
box installation, backfill the trenches with sand, compacted to a level of the bottom of existing concrete. Provide rebar doweled into existing concrete to provide support for new concrete and fill and level new concrete in trenches to existing floor. See A- 101 for details.
a) Compacted fill sand.
AQL: 100 % compliance.
3.1.14.1 Provide adequate load bearing
capacity.
a) Load capacity of 1500
PSF.
3.1.14.2 Concrete shall be ready-mix
concrete conforming to ASTM C150, Type IIA.
3.1.14.3 The maximum nominal size
coarse aggregate is 3/4 inch, in accordance with ACI MCP SET Part 3.
a) ACI MCP SET Part 3.
3.1.14.4 The air content shall be between
4.5 and 7.5 percent with slump between 2 and 5 inches.
3.1.14.5 The maximum water cement
ratio is 0.50.
3.1.14.6 Calcium Chloride shall not be
used.
3.1.14.7 The concrete mix design, including Accelerating Admixture, shall be submitted for Government review.
3.1.14.8 Finishing concrete shall be in
conformance with the following requirements:
3.1.14.8.1 In compliance with ACI 318.
3.1.14.8.2 Remove all fins and loose
materials, and surface defects including filling of tie holes.
Repair all honeycomb areas and other defects. Remove all unsound concrete from areas to be repaired.
3.1.14.8.3 Concrete shall be flush and even
with existing floor level.
3.1.14.9 Curing and Protection of
concrete shall be in conformance with the following requirements:
3.1.14.9.1 Provide curing compound
conforming to ASTM C 309.
a) ASTM C 309.
3.1.14.9.2 Ensure concrete is protected
from Hot and/or Cold weather per ACI 318.
a) ACI 318.
3.1.14.10 Before placing concrete, verify
that all conduit and embedded items are firmly and securely fastened in place. Provide conduit and embedded items free of oil and other foreign matter, such as loose coatings of rust, paint and scale. Embedding of wood in concrete is permitted only when specifically authorized or directed.
3.1.14.11 Contractor will send a mix design
for Government approval.
Provide three (3) cylinders for strength tests. Test concrete for compressive strength at 7 and 28 days for each design mix.
Concrete test specimens shall conform to ASTM C 31. Perform Compressive strength testing conforming to ASTM C 39. Test a minimum of one cylinder on day seven and one on day 28 and maintain the last cylinder as a reserve.
a) ACI 318 5.6.1.3
3.1.14.12 Upon testing the concrete the
following procedures shall be adhered to:
3.1.14.12.1 Ensure that the concrete is
properly consolidated, finished, protected, and cured.
3.1.14.12.2 Report the results of all tests and
inspections conducted at the project site. Submit test and inspection reports within 3 days of conducting the inspection or receiving the test results.
a) ACI 318.
3.1.15 Provide new carpeting to replace
existing throughout the chapel area.
a) As described in sections 3.1.15.1 to 3.1.15.7 AQL: Meet or exceed.
3.1.15.1 The type of carpet shall be
broadloom with a cut and loop pile type.
3.1.15.2 The gauge or pitch shall have a
minimum of 1/12” in accordance with ASTM D5793.
a) ASTM D5793.
AQL: 100% compliance.
3.1.15.3 The minimum stitches or
rows/wire shall be 47 per every 10 square centimeters.
3.1.15.4 The surface pile weight shall
have a minimum of 28.5 ounces per square yard. This does not include weight of backings.
Determine weight IAW ASTM D5848.
a) ASTM D5848.
AQL: 100% Compliance.
3.1.15.5 The carpet shall be solution
dyed.
3.1.15.6 The backing material shall be
unibond plus.
3.1.15.7 Provide static control to
permanently regulate static buildup to less than 3.5 kV when tested at 20 percent relative humidity and 21 degrees C IAW
AATCC 134.
a) AATCC 134.
3.1.15.8 Carpet Installation to be within
CRI104 installation standards.
a) CRI104 AQL: 100% Compliance
3.1.15.9 Retain existing doorway
thresholds at all doorways affected by new carpeting. Re-install existing thresholds after installation of new carpeting.
3.1.15.10 Provide new base moldings in all
areas receiving new carpet. Base moldings style to match existing in adjacent areas.
3.1.15.11 Floor preparation for carpet shall
be IAW the following:
3.1.15.11.1 Preparation: do not install carpet
on surfaces that are unsuitable and/or prevent proper installation. Carpet installation will be over a carpet cushion that meets minimum density of 22 lbs per cubic foot (recycled pad must meet this criterion). Prepare floor surface IAW carpet manufacturer requirements. Repair holes, cracks, depressions, or rough areas using material recommended by the cushion or adhesive manufacture. Level off surface, free floor of any foreign materials and sweep clean.
Before beginning work, test subfloor with glue and cushion to determine "open time" and bond.
3.1.15.11.2 Concrete primer: use concrete
primer IAW requirements of the carpet cushion manufacturer and/or adhesive selected.
3.1.15.11.3 Deliver carpet system materials
to the site in the manufacturer's original wrappings and packages clearly labeled with the manufacturer's name, brand name, size, dye lot number, and related information.
3.1.15.11.4 Provide extra carpeting material
from same dye lot consisting of 10% of the total square footage of installed carpet for future maintenance.
3.1.15.11.5 Furnish first quality carpet, free
of visual blemished, streaks, poorly dyed areas, fuzzing of pile yarn, spots or stains, and other physical and manufacturing defects.
3.1.15.11.6 Provide the CRI indoor air quality
(IAQ) label.
3.1.15.11.7 Carpet type bearing the label will
indicate that carpet has been tested and meets the criteria of the CRI Green Label
a) CRI Green Label requirements for the IAQ Test Criteria.
3.1.15.11.8 Perform all work by installers
who are international certified floor covering installer association (CFI) certified or manufacturer-approved installers.
3.1.15.11.9 Conduct installation IAW the
manufacturer's printed instructions. Where manufacturer does not provide instructions, installation shall be IAW CRI 104.
a) Instructions or CRI
Statements Standards/AQLs Incentive/Remedy
3.2 Meeting Rooms a) As described in
sections 3.2.1 to 3.2.7
3.2.1 Remove all existing wire mold.
3.2.2 Provide new round conduit IAW the
NEC to replace any existing wire mold which carries 120/208 volt power wiring.
3.2.3 Provide new wire mold for all
communication wiring. All cable shall be hidden through the use of raceways, elbows, couplings and tees. Provide to the government three
(3) samples of products to be used for approval prior to installation.
3.2.4 Remove all existing wiring for outlet
receptacles and wiring to lights.
Provide new wiring, IAW the NEC, and replace all receptacles with 20 amp grounded receptacles. Provide new GFCI (Ground Fault Circuit Interrupter) receptacles IAW the NEC.
3.2.5 Paint all existing conduit to match
existing wall color.
3.2.6 In the nursery provide tamper
resistance 20 Amp receptacles.
Statements Standards/AQLs Incentive/Remedy
3.3 Fire Protection a) As stated in
3.3.1 Have a certified fire engineer, IAW
UFC 3-600-01, design a:
3.3.1.1 In the kitchen provide a new
UL300A residential fire suppression system over the stove IAW NFPA 96 (current edition) listed that will:
3.3.1.1.1 Provide a shunt trip that upon a
high temperature incident will isolate input power to the stove and hood.
3.3.1.1.2 Provide an alarm output to a fire
control panel that will auto dial dispatch.
3.3.1.1.3 Provide a dry/wet chemical
extinguishing agent that is initiated by a high temperature (grease fire) as designated by current code and/or UFC 3-600-01 and a certified fire engineer.
3.3.1.2 Provide a new fire control panel by
the west entrance.
3.3.1.3 Provide pull switches at each
entrance.
3.3.1.4 Provide strobes and audible
alarms.
3.3.1.5 Provide all interconnections and
coordinate with the Network Enterprise Center (NEC) to complete auto dialer. Run all connections in prior approved wire mold.