Asphalt_Maintenace-Repairs_SOW(draft).pdf
PDF 902 KB Posted
- Attached to
- Asphalt Maintenance/Repairs Federal contract opportunity
- Solicitation number
- W911S2-19-B-8000
About this file
Draft SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CDRLs_D001-D004(draft).pdf | ||
| CDRLs_D013-D016(draft).pdf | ||
| CDRLs_D009-D012(draft).pdf | ||
| CDRLs_D005-D008(draft).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) TECHNICAL SCOPE OF WORK
a) SCOPE: The Contractor shall provide all supervision and furnish all plant, labor, equipment, materials and appliances, and perform all necessary steps and operations to achieve a finished product in connection with the maintenance, repair, and construction of gravel pads, roads, parking lots, asphalt concrete pavement pads, pavement markings; and any work in association with asphalt paving in accordance with the specifications and drawings, and subject to the terms and conditions of the contract from the date of award throughout 30 April 2019.
b) GENERAL: All work shall be done by personnel skilled in the type of work involved. When new work adjoins, connects or abuts existing work or facilities, the existing work or facilities shall be altered as required and the connections made in an approved and professional manner. All existing work or facilities damaged by the contractor’s operations, other than facilities to be removed, shall be repaired or replaced by the Contractor at no cost to the Government. Prior to performance of any work, a pre-performance meeting shall be held at the Installation Contracting Office Fort Drum NY. The Contractor shall have a representative attend who has authority to make decisions for, and sign contractual documents on behalf of the Contractor.
c) LOCATION: The site of the proposed work is located within the Cantonment Area of Fort Drum and Wheeler-Sack Army Airfield, approximately ten miles northeast of Watertown, New York; and in the range areas of Fort Drum, which can be up to 50miles from the cantonment area.
d) PRINCIPAL FEATURES: The work to be performed will include, but is not limited to, the following items in accordance with the Contract documents:
1) GENERAL REQUIREMENTS (See Exhibit A Line Item 001): Cost for this ELIN will be computed based on a percent of the total summed construction ELINs combined and be included for each task order.
The contractor shall provide and implement General Requirements that include, but not limited to: progress schedules, construction progress documentation, submittal procedures, quality control for minor construction including density testing and submitted results, temporary environmental controls, environmental protection, temporary storm water pollution control (such as required Best Management Practices (BMPs)), and construction and demolition waste management.
2) CLEAR & GRUBB See Exhibit A, Line Items 002A, 002B, 002C, 002D, and 002E): Cost for these ELINs will be on a per acre (AC) basis for Light, Medium, and Heavy vegetation clearing and grubbing and for select tree clearing and grubbing on a per each (EA) tree basis.
Acreage shall be computed to the nearest 0.1 acres (i.e., 0.150 acres shall be rounded up to 0.2 acres and 0.149 acres shall be rounded down to 0.1 acres).
All clearing and grubbing operations for work completed under this contract shall be specific to other work ordered under this contractor that is specific to a Task Order and shall not be ordered separately for the sole purpose of site preparation associated with construction activities that will be or are anticipated to be performed by others under a separate contract with the government.
The project site as a whole for purposes of clearing and grubbing shall be as defined below and shall be based on the preponderance of existing vegetation at the site. Where the preponderance of vegetation cannot easily be discerned, the greater level of clearing and grubbing effort shall be used (i.e., if the site cannot be easily cauterized between LIGHT and MEDIUM, the ELIN for MEDIUM shall be used). Clearing and grubbing of trees greater 24” dbh is beyond the scope of this contract.
DRAFT
LIGHT (See Exhibit A, Line Item 002A): Light clearing and grubbing is defined as vegetation, brush, and trees ≤ 6 inches diameter breast height (dbh). Payment will be made on a per acre basis to the nearest 0.1 acres.
MEDIUM (See Exhibit A, Line Item 002B): Medium clearing and grubbing is defined as vegetation, brush, and trees > 6 to ≤ 12 inches dbh and all vegetation defined as LIGHT. Payment will be made on a per acre basis to the nearest 0.1 acres.
HEAVY (See Exhibit A, Line Item 002C): Heavy clearing and grubbing is defined as vegetation, brush, and trees > 12 to ≤ 24 inches dbh and all vegetation defined as LIGHT and MEDIUM. Payment will be made on a per acre basis to the nearest 0.1 acres.
SELECT TREES ≤ 12 Inches dbh (See Exhibit A, Line Item 002D): Select individual tree clearing and grubbing is defined as trees ≤ 12 inches dbh. This ELIN shall only be used for the clearing and grubbing of select trees when specifically stated in the statement of work. This ELIN shall not be used to “supplement” LIGHT, MEDIUM, or HEAVY clearing and grubbing defined sites.
SELECT TREES > 12 Inches to ≤ 24 Inches dbh (See Exhibit A, Line Item 002E): Select individual tree clearing and grubbing is defined as trees > 12 Inches ≤ 24 inches dbh. This ELIN shall only be used for the clearing and grubbing of select trees when specifically stated in the statement of work. This ELIN shall not be used to “supplement” LIGHT, MEDIUM, or HEAVY clearing and grubbing defined sites.
a) Complete Clearing and Grubbing in accordance with the technical requirements of the contract specifications, Fort Drum Requirements, and as defined herein.
b) Clearing of trees and vegetation shall be completed in accordance with Implementing Instruction for Endangered Species Act Consultation Requirements for the Federally- Endangered Indiana Bat and Federally Threatened Northern Long-Eared Bat On Fort Drum Military Installation, June 2015. This implementing requirement may or may not be updated/revised during the performance period of the contract. The contractor shall comply with the latest edition and subsequent updates or revisions during the performance period of this contract. Clearing and Grubbing tress and vegetation shall occur between 16 October and 15 April.
c) Clearing shall consist of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Trees, stumps, roots, brush, and other vegetation in areas to be cleared shall be cut off flush with or below the original ground surface, except such trees and vegetation as may be indicated or directed to be left standing.
i) Trees designated to be left standing within the cleared areas shall be trimmed of dead branches 1-1/2 inches or more in diameter and shall be trimmed of all branches the heights 12-feet above ground surface or as indicated or directed.
ii) Limbs and branches to be trimmed shall be neatly cut close to the bole of the tree or main branches. Cuts more than 1-1/2 inches in diameter shall be painted with an approved tree-wound paint.
d) Grubbing: Shall consist of the removal and disposal of stumps, roots larger than 3 inches in diameter, and matted roots from the designated grubbing areas.
i) Material to be grubbed, together with logs and other organic or metallic debris not suitable for backfill purposes, shall be removed to a depth of not less than 18 inches below the original surface level of the ground in areas indicated to be grubbed and in areas indicated as construction areas under this contract, such as areas for buildings, and areas to be paved.
ii) Depressions made by grubbing shall be filled with suitable material and compacted to make the surface conform to the original adjacent surface of the ground.
e) The contractor shall coordinate through PW Engineering’s Project Manager the environmental review of the tree clearing limits with Fort Drum’s Forest Management Program and Fish & Wildlife Management Program.
f) Requests for environmental review shall be submitted to PW Engineering’s Project Manager a minimum of five (5) business days prior to scheduled tree clearing operations.
g) No tree cutting, clearing of vegetation, or grubbing operations will be permitted prior to Government approval of the clearing limits.
h) Once the final footprint has been established on the ground, and clearing limit drawing files have be provided, Fort Drum’s Forest Management Program will make a determination of timber value as either un-merchantable or merchantable.
i) Merchantable timber will be marked with red paint by the Forest Management Program inspector.
j) Timber determined to be un-merchantable due to size, species, or amount shall be the contractor’s responsibility to dispose off from the installation and an appropriately permitted facility timber determined to have value to the government shall be handled in one of the three options:
Option 1: The contractor shall fell, limb, haul, and pile all valued timber in an area designated by the PW Environmental Forestry Management Program (this is typical of small project foot prints and low quantities of trees). Government retains ownership of the timber with value. For this option, the contractor shall comply with the following:
Option 2: Timber rights for the timber to be removed on this project are required to be purchased from the U.S. Government prior to removal. The contractor will execute a local sale contract will with the Fort Drum Forest Management Program and the fair market value (as determined by the Forest Management Program based on historical Fort Drum stumpage values). The contractor shall deposit into the Army Forestry Account a dollar amount equal to the fair mark value of the timber.
Option 3: Timber rights for the timber to be removed on this project are required to be purchased from the U.S. Government prior to removal. The contractor will execute a local sale contract will with the Fort Drum Forest Management Program and the fair market value (as determined by the Forest Management Program based on historical Fort Drum stumpage values). The contractor shall deposit into the Army Forestry Account a dollar amount equal to the fair mark value of the timber.
k) Where the Forest Management Program will harvest the timber thru a commercial timber sale the contractor will coordinate work with the Forest Management Program.
Coordination of work will define timelines and deliverables for each.
l) Where construction scoping is developed prior to the final footprint and final value assessment timber rights for timber to be removed on this project are required to be purchased from the U.S. Government prior to removal; or timber will need to left onsite.
m) In cases of removal, a local sales contract will be conducted with the Fort Drum Forest Management Program and the fair mark value (as determined by the Forest Management Program based on historic stumpage values) will be deposited by the contractor into the Army Forest Management Account. Trees marked with a painted red stripe are the property of the U.S. Government. These trees shall be handled in the following manner by the contractor.
i) Trees must be fell and all limbs removed from the trunk;
ii) Trees shall be cut starting from the base (as close to the ground as possible). The entire main stem shall be kept in on piece, to a top diameter of 8 inches; and
All stem shall be piled in a manner and area designated by Fort Drum Forest Management Program.
3) SELECT DEMOLITION (See Exhibit A Line Items 003): The cost for this ELIN shall be based on the total CY volume calculated existing in place. ELIN is presented in CY to be removed.
Excavate, remove and dispose of existing surface and subsurface debris/material down to Base Course/Sub-grade material. Complete selective demolition of reinforced, non-reinforced concrete pavement, asphalt pavements or other materials (headwalls, stairs, pipe, etc.) in accordance with the technical requirements of the contract specifications and as defined herein.
a) Work to include but not be limited to demolition of all concrete and asphalt pavements or other materials as specified.
b) Demolition of pavements shall be completed using industry standard practices, such as the double saw cut method, which protects adjacent pavement that is to remain from damage.
c) Work shall include all saw cutting, demolition, removal, and disposal of removed construction debris.
4) EXCAVATION (See Exhibit A, Line Item 004): The cost for this ELIN shall be based on the total CY volume calculated existing in place.
Excavate, remove and dispose of existing surface and subsurface materials (such as grass, topsoil, sand, gravel, and rocks). Excavation work shall be completed in accordance with the technical requirements of the contract specifications.
a) Work shall include stripping of existing top soil, bulk excavation to subgrade, fine grading, compaction and testing of subgrade materials, stockpiling, and disposal of waste soils.
b) Soils excavated onsite that meet the classification requirements for Select Granular Fill may be stock piled onsite and reused for construction.
c) Waste soils not meeting the classification for Select Granular Fill or soils that meet the classification for Select Granular Fill that are not reused shall be disposed of off from government property.
Topsoil stripped from the site that meets the technical requirements for TOPSOIL may be stockpiled onsite and reused for site restoration. Topsoil stripped from site that does not meet the technical specifications for TOPSPOIL shall not be reused and disposed of off from government property.
5) GEOSYNTHETICS (See Exhibit A, Line Item 005a and 005b): The cost for these ELINs shall be based on the total SY calculated in place.
(See Exhibit A, Line Item 005a): Provide and install geotextile soil stabilization fabric in accordance with the manufactures installation instructions and recommendations. Install geotextile soil stabilization fabric on an appropriately prepared subgrade. Geotextile soil stabilization fabric shall meet NYSDOT Standard Specification Geosynthetics, 737.0106 Combination Monofilament/Fibrillated Yarn – Woven (C‐W), Class 1 Strength (<50% elongation).
(See Exhibit A, Line Item 005b): Provide and install geogrids in accordance with the manufactures installation instructions and recommendations. Geogrids shall meet NYSDOT Standard Specification 737-07 Geogrids for the intended application.
6) SELECT GRANULAR FILL (See Exhibit A, Line Item 006): The cost for this ELIN shall be based on the total CY calculated in place.
Supply, place, grade, and compact new Select Granular Fill (by CY). Select granular fill material for general backfill will consist of materials classified as GW, GP, SW, or SP by ASTM D2487. Select granular fill for use under pavements shall meet NYSDOT Standard Specification 733-1101 – Select Granular Fill (Typical). Select granular fill shall be installed in 12-inch lifts as to the thickness specified and compacted to 95% of the laboratory maximum density in accordance with ASTM D1557.
7) AGGREGATE SUBBASE COURSE (See Exhibit A, Line Item 007). The quantity ordered and payment shall be based on the total CY calculated in place.
Supply, place, roll and compact new crushed stone aggregate base course. Provide and install subbase material in accordance with the technical requirements of the contract specifications and as specified herein. Grade & compact existing subgrade course.
a) Subgrade shall be constructed to line, grade, and cross section and compacted to a depth of 6-inches in accordance with ASTM D1557 to a minimum of 95% of the laboratory maximum density prior to placement of the subbase material.
b) Pavement Subbase material shall:
i) Be NYDOT Type 2 stone (NYDOT Item 304.12).
ii) Be placed in 6-inch lifts compacted to 95% of the laboratory maximum density in accordance with ASTM D1557.
iii) Extend a minimum of 6-inches beyond the edge of the paving surface (i.e., outside edge of lowest pavement course).
iv) Be constructed to line, grade and cross section prior to placement of paving course.
c) Each subbase course shall have a compacted thickness of not less than 6 inches.
d) Correct surface deviations in the top lift in excess of 3/8 inch by loosening, adding or removing material, reshaping, watering, and compacting.
8) HOT MIX ASPHALT (HMA) PAVING (See Exhibit A, Line Item 008a, 008b, 008c, and 008d). The quantity ordered and payment shall be based on the total SY calculated in place.
(See Exhibit A, Line Item 008a): Provide and install 1.5-inch thick 9.5 F2 Top Course HMA, 70 Series Compaction (NYSDOT Item 402.097202). Price shall include application of tack coat to the contact surface of the underlying HMA.
(See Exhibit A, Line Item 008b): Provide and install 2.5-inch thick 19 F9 Binder Course HMA, 70 Series Compaction (NYSDOT Item 402.197902). Price shall include application of tack coat to the contact surface of the underlying HMA.
(See Exhibit A, Line Item 008c): Provide and install 3-inch thick 37.5 F9 Base Course HMA, 70 Series Compaction (NYSDOT Item 402.377902).
(See Exhibit A, Line Item 008d): Provide and install 6-inch thick 37.5 F9 Base Course HMA, 70 Series Compaction (NYSDOT Item 402.377902). Base Course HMA shall be installed in two (2) three inch lifts. Price shall include application of tack coat to the contact surface of the first HMA base course.
HMA pavement shall be provide and installed in accordance with NYSDOT Standard Specifications for Type F2 conditions. Apply tack coat on the contact surfaces between all HMA pavement lifts in accordance with NYSDOT Standard Specification Section 407, Tack Coat, prior to placing HMA mixture regardless of time period between lifts. Tack coat application rates shall be in accordance with NYSDOT Standard Specification Table 407-1.
Tack coat shall be NYSDOT Item 407.0102 Diluted Tack Coat. Paving over a tack coat should not commence until the emulsion has broken (goes from brown to black) or is tacky when touched. Compact the HMA pavement sufficiently using the NYSDOT 70 Series Compaction Method for routine paving. Where project work is not sufficient to establish Pavement Target Density (PTD) prior to routine paving, achieve pavement densities in a range of 92% to 97%, expressed as a percentage of the mixture’s maximum theoretical density (MMTD). Where work is sufficient to establish PTD prior to routing paving, establish the PTD in accordance with NYSDOT Standard Specification for 70 Series Compaction Method. Begin routine paving immediately after the PTD has been established. Compact the pavement sufficiently to achieve the PTD value at each test location. The minimum acceptable density reading will be 96% or maximum of 103% of the PTD in a single test location and 98% of the PTD calculated as a moving average of the last 10 test locations as determined by a density gauge. Use a nuclear gauge to monitor pavement density. Note, the calculated PTD should be between 92% and 97% of the mixtures MMTD when considering a typical offset for the gauge being used. The MMTD shall be provided to the government which can be obtained from the HMA producer.
9) PAVEMENT MARKINGS (See Exhibit A, Line Item 009a through 009m).
Pavement markings shall be installed in accordance with NYSDOT Standard Specification Section 640 – Reflectorized Pavement Marking Paints, the Manual for Uniform Traffic Control Devices (latest Edition), and the NYSDOT Supplement. When pavement markings are applied under traffic, the contractor shall provide all necessary maintenance and protection of traffic to protect the work operations and to protect the painted pavement markings until thoroughly dry and serviceable. Reflective glass beads shall conform to NYSDOT Standard Specification 727- 05 Glass Beads for Reflectorized Pavement Paints. The painted pavement markings shall be uniformly applied to the pavement surface at the minimum specified wet film thickness of 20-mills. Immediately following paint application, reflective glass beads shall be uniformly applied to the wet paint film at the rate of 6 lb/gal of paint. The applied pavement markings shall have clean-cut edges and true and smooth alignment.
(See Exhibit A, Line Item 009a): White Paint Reflectorized Pavement Stripes – 20 mils (NYSDOT Item 640.20). The quantity ordered and payment shall be feet along the centerline of the pavement stripe and shall be based on one 4-inch wide stripe. Stripes shall include Normal Lane Line, Normal Edge Line, Normal Broken Lane Line, Norma Dotted Lane Line, and Normal Dotted Extension Line.
(See Exhibit A, Line Item 009b): Yellow Paint Reflectorized Pavement Stripes – 20 mils (NYSDOT Item 640.21). The quantity ordered and payment shall be in feet along the centerline of the pavement stripe and shall be based on two 4-inch wide stripe. Stripes shall include Partial Barrier Line (PBL) and Full Barrier Line (FBL).
(See Exhibit A, Line Item 009c): White Paint Reflectorized Pavement Letter – 20 mils (NYSDOT Item 640.22). The quantity ordered and payment shall be based per letter basis. For example, the word “ONLY” will be measured as 4 units.
(See Exhibit A, Line Item 009d): White Paint Reflectorized Pavement Symbols – 20 mils (NYSDOT Item 640.23). The quantity ordered and payment shall be based per symbol basis.
Double and triple headed arrows will each be measured as single unit (i.e., there is no difference in measurement between a single, double, or triple headed arrow).
(See Exhibit A, Line Item 009e): White Paint Reflectorized Pavement Type L Cross Walk – 20 mils (Ladder Bar). The quantity ordered and payment shall be based on the total linear footage of 1-foot wide strips necessary to complete the entire crossing. Example: Type L Cross Walk requires 36 1-foot wide by 8-foot long ladder bars, the total contract length is 288 feet).
(See Exhibit A, Line Item 009f): White Paint Reflectorized Pavement Stop Line – Type B (SL-B) – 20 mils. The quantity ordered and payment shall be based linear foot basis measure along the centerline of the stop line.
(See Exhibit A, Line Item 009g): White or Yellow Paint Reflectorized Pavement Hatch Lines
- Type A (HL-A) – 20 mils. The quantity ordered and payment shall be based on the total linear footage of 8-inch wide hatch lines as measured along the centerline of each hatch.
(See Exhibit A, Line Item 009h): White or Yellow Paint Reflectorized Pavement Hatch Lines
- Type B (HL-B) – 20 mils. The quantity ordered and payment shall be based on the total linear footage of 12-inch wide hatch lines as measured along the centerline of each hatch.
(See Exhibit A, Line Item 009i): White or Yellow Paint Reflectorized Pavement Hatch Lines
- Type C (HL-C) – 20 mils. The quantity ordered and payment shall be based on the total linear footage of 24-inch wide hatch lines as measured along the centerline of each hatch.
(See Exhibit A, Line Item 009j): White Paint Reflectorized Pavement Railroad Grade Crossing – 20 mils. The quantity ordered and payment shall be based on each complete crossing. A complete crossing shall include the 24-inch wide clearance line, two 24-inch crossbars, two “R” letters, and the “X” symbol.
(See Exhibit A, Line Item 009k): White Paint Reflectorized Pavement Parking Stall – 20 mils.
The quantity ordered and payment shall be based on the total linear footage of 4-inch wide pavement striping.
(See Exhibit A, Line Item 009l): White Paint Reflectorized Pavement Parking – Handicap Symbol – 20 mils. The quantity ordered and payment shall be on a per symbol basis. The 4-inch wide handicap parking stall striping is ordered under Item 009k.
(See Exhibit A, Line Item 009m): White Paint Reflectorized Pavement Oversize Handicap Parking Stall Hatch Lines – Handicap Symbol – 20 mils. The quantity ordered and payment shall be for each oversized handicap parking stall. The 4-inch wide handicap parking stall striping is ordered under Item 009k.
10) COLD MILLING (See Exhibit A, Line Item 010). The quantity ordered and payment shall be based on the total SY of milled area to depth of 1.5 inches. This work shall consist of the milling, shaping, and removal of portions of the existing paved surface and subsequent cleaning utilizing equipment and procedures in accordance with NYSDOT Standard Specification Section 490 – Cold Milling. Areas not accessible to the milling machine, such as around and/or adjacent to inlets, manholes, and curbs may be removed by a small milling machine, handwork, or other industry standard method. All milled material, including that removed by other means, shall be immediately removed from the milled surfaces and adjacent surfaces. Surfaces shall be cleaned of all fines and dust prior to opening to traffic. The Contractor shall conduct operations in such a manner that dust is controlled and is not objectionable. Milled and adjacent surfaces shall be cleaned again, prior to the placement of tack coats, or pavement courses if traffic has been allowed on the milled surface and/or if more than 48 hours have elapsed since the initial cleaning.
11) CULVERTS (See Exhibit A, Line Item 011a through 011q). The quantity ordered and payment shall be based on the per linear foot basis of the specified pipe material and diameter.
Provide and install culverts in accordance with NYSDOT Standard Specification Section 603
– Culverts and Storm Drains. Work shall include all piping materials, excavation, pipe bedding, backfill, compaction, and grading for a complete installation.
(See Exhibit A, Line Item 011a): Smooth Interior corrugated Polyethylene Culvert and Storm Drain Pipe – 18-inch diameter (NYSDOT Item 603.9818).
(See Exhibit A, Line Item 011b): Corrugated Aluminum End Sections Pipe (NYSDOT Item 603.5424). This end section is for Item 011a.
(See Exhibit A, Line Item 011c): Smooth Interior corrugated Polyethylene Culver and Storm Drain Pipe – 24-inch diameter (NYSDOT Item 603.9824)
(See Exhibit A, Line Item 011d): Corrugated Aluminum End Sections Pipe (NYSDOT Item 603.5430). This end section is for Item 011c.
(See Exhibit A, Line Item 011e): Smooth Interior corrugated Polyethylene Culver and Storm Drain Pipe – 30-inch diameter (NYSDOT Item 603.9830)
(See Exhibit A, Line Item 011f): Corrugated Aluminum End Sections Pipe (NYSDOT Item 603.5436). This end section is for Item 011e.
See Exhibit A, Line Item 011g): Smooth Interior corrugated Polyethylene Culver and Storm Drain Pipe – 36-inch diameter (NYSDOT Item 603.9836)
(See Exhibit A, Line Item 011h): Corrugated Aluminum End Sections Pipe (NYSDOT Item 603.5442). This end section is for Item 011g.
(See Exhibit A, Line Item 011i): Reinforced Concrete Pipe Class III – 18-inch diameter (NYSDOT Item 603.6018)
(See Exhibit A, Line Item 011j): Reinforced Concrete Pipe End Sections (NYSDOT Item 603.7318). This end section is for Item 011i.
(See Exhibit A, Line Item 011k): Reinforced Concrete Pipe Class III – 24-inch diameter (NYSDOT Item 603.6024)
(See Exhibit A, Line Item 011l): Reinforced Concrete Pipe End Sections (NYSDOT Item 603.7324). This end section is for Item 011k.
(See Exhibit A, Line Item 011m): Reinforced Concrete Pipe Class III – 30-inch diameter (NYSDOT Item 603.6030)
(See Exhibit A, Line Item 011n): Reinforced Concrete Pipe End Sections (NYSDOT Item 603.7330). This end section is for Item 011m.
(See Exhibit A, Line Item 011p): Reinforced Concrete Pipe Class III – 36-inch diameter (NYSDOT Item 603.6036)
(See Exhibit A, Line Item 011q): Reinforced Concrete Pipe End Sections (NYSDOT Item 603.7336). This end section is for Item 011p.
12) AIRFIELD ASPHALT PAVEMENT CRACK SEALING (See Exhibit A, Line Item 012):
The quantity ordered and payment will be on a linear foot basis. Clean, prepare and fill existing cracks in asphalt concrete surface and existing cracks in the joint between existing asphalt concrete shoulder and existing concrete runway/taxiway on Wheeler Sack Army Airfield as per specifications of UNIFIED FACILITIES CRITERIA UFC 3-250-08FA; STANDARD
PRACTICE FOR SEALING JOINTS AND CRACKS IN RIGID AND FLEXIBLE
PAVEMENTS; ARMY TM 5-822-11, AIR FORCE AFP 88-6, Chap. 7. Joint sealant to be used shall be equal or better to General Services Administration Federal Specifications (SS-S- 1401C or SS-S-1614A, as applicable) or as per ASTM Specifications ASTM D6690 or ASTM D7116 as applicable). (Reference Exhibit Line Items A032, B032, and C032)
SS-S-1401C Sealant, Joint, Non-Jet-Fuel-Resistant, Hot-Applied, for Portland Cement and Asphalt Concrete Pavements
SS-S-1614A Sealants, Joint, Jet-Fuel-Resistant, Hot-Applied, for Portland Cement and Tar Concrete Pavements
13) CLEANING, SEALING, AND FILLING JOINTS AND CRACKS (NON AIRFIELD
ASPHALT PAVEMENT (See Exhibit A, Line Item 013): The quantity ordered will be on a SY basis of existing pavement and/or shoulder surfaces repaired. Work shall be completed in accordance with NYSDOT Standard Specification 633-02 Cleaning, Sealing and/or Filling Joints and Cracks; except as modified herein. Joints and cracks less than 1/8-inch are not required to be cleaned or sealed. Seal joints and cracks in existing pavement from 1/8 to 1-inch wide with an asphalt filler.
14) RAISE/LOWER EXISTING UTILITY STRUCTURES TO FINAL GRADE (See
Exhibit A, Line Items 0014): The quantity ordered and payment shall be based on the per unit basis. Work shall include the raising and lowering of utility manholes covers/frames, handhold pull box frames/covers, valve boxes, and like structures to match final grades.
Replacement of broken or severely damaged structures is not the contractor’s responsibility.
It is the contractor’s responsibility to notify the contracting officer of any structures that are not specifically identified in the task order requirement that will affect construction. Failure of the contractor to notify the Contracting Officer will be at the contractor’s risk. Failure to notify the Contracting Officer may result in the Contracting Officer requiring the contractor to raise or lower structures at no additional cost to the government.
15) SITE RESTORATION (See Exhibit A, Line Items 0015A, 0015B): The quantity ordered and payment shall be based on the number of square yard (SY) basis of surface area restored.
Complete site restoration in accordance with the technical requirements of the contract specifications and as defined herein.
a) TOPSOIL AND HYDROSEED (See Exhibits A Line Items 010A): Cost of this ELIN will be based on a per square yard (SY) basis of the restored area.
i) Topsoil shall contain from 5 to 10% organic matter as determined by the Organic Carbon, 6A Chemical Analysis Method described in DOA SSIR 42. Maximum particle size, ¾ inch with maximum 3% retained on ¼-screen.
ii) The pH shall be tested in accordance with ASTM D 4972. Other components shall conform to the following limits:
Silt 25 – 50% Clay 10 – 30% Sand 20 – 35% pH 5.5 – 7.0 Soluble Salts 900 ppm (maximum)
iii) Provide and install 4 inches of topsoil to meet required finish grade.
iv) After areas have been brought to finish grade, incorporate fertilizer, pH adjusters, and soil conditioners into soil a minimum depth of 4-inches by disking, harrowing, tilling or other method approved by the contracting officer.
v) Remove debris and stones larger than ¾ inch in any dimension remaining on the surface after finish grading.
vi) Correct irregularities in finish surfaces to eliminate depressions.
vii) Protect finished topsoil areas from damage by vehicle and pedestrian traffic.
viii) Apply fertilizer, pH adjusters, and soil conditioners at rates determined by laboratory soil analysis of the soils at the job site and in accordance with the manufacturer’s recommended application rates.
ix) On areas to receive topsoil, prepare the compacted subgrade soil to a 2-inch depth for bonding of topsoil with subsoil.
x) Spread topsoil evenly to a thickness of 4 inches and grade to the elevations and slopes required.
xi) Do not spread topsoil when frozen or excessively wet or dry.
xii) Provide State-approved seed of the latest season’s crop delivered in original sealed packages, bearing producer’s guaranteed analysis for percentages of mixture, purity, germination, weed seed content, and inert materials.
xiii) Wet, moldy, or otherwise damaged seed shall be rejected.
xiv) Planting dates/Seasons are classified into three categories: Season 1 (Spring) Season
2 (Fall), Temporary (Summer) and defined as follows:
Seed Planting: Planting Dates Season 1 (Spring): 15 April to 15 June Season 2 (Fall): 15 August to 1 October Temporary (Summer): 16 June to 14 August
Planting Season Type Percent (by weight) Season 1 and Season 2 As specified As specified Temporary Perennial Ryegrass 100
Temporary seeding must later be replaced by Season 1 or Season 2 plantings for a permanent stand of grass. The same requirements of turf establishment for Season 1 and Season 2 apply to temporary seeding.
xv) Seed mixtures can vary on a case-by-case basis, depending on project site conditions, soil test results, and agronomy. Only State-certified seed of the latest season’s crop, provided in original sealed packages bearing the producer’s guaranteed analysis for percentages of mixture, purity, germination, hard seed, weed seed content, and inert material will be accepted. Seed will conform to AMS-01. Weed seed will not exceed 1% by weight of total mixture. Wet, moldy, or otherwise damaged seed will be rejected. The percentage of pure live seed of each kind in each container or bad seed delivered will be computed by multiplying the percent germination by the percent purity and dividing by 100. The percentage of pure live seed of each kind multiplied by the new weight of the container or bag will indicate the number of pounds of pure live seed of each kind in the container or bag.
Contractor shall provide seed with mixture weight and purity as follows:
Type I – General Lawn Use
Botanical Name Common Name Variety % Mix by Weight
% Pure Live Seed
Poa pratensis Kentucky Bluegrass Baron or Equal 40 68
Festuca rubra L.
Ssp. Commutate Gaud. Chewing Fescue
Jamestown II or equal 25 78
Festuca rubra Creeping Red Fescue Jasper or equal 20 78
Lolium perenne Perennial Ryegrass
Manhattan II or equal 15 88
Type 2 – Low-Growing and Hardy Seed Mix (WSAAF Only) at 110 lbs/acre
Botanical Name Common Name Variety
% Mix by Weight
% Pure Live Seed
Poa compressa Canada Bluegrass 18 80
Festuca rubra L.
Panicum virgatum L.
Creeping Red Fescue
Spring: Cave-in-the-rock Switchgrass Fall: Jasper 23 78
Festuca ovina Sheeps Fescue Azur 23 78 Festuca ovina Var ‘Duriusculila’ Hard Fescue Reliant 23 78 Lotus cornicultatus L. Birds Trefoil Empire 9 85 Agrotis gigantean Roth Redtop 4 83
Provide high magnesium lime application at the rate of 2 tons per acre to push the soil pH to
7.0 neutral territories for turf establishment and stabilize the aluminum toxicity of existing surface soils. Most soils have tested in the high 4s to the low 6s on Fort Drum (source: PW Environmental). Provide a fertilizer application rate of 600 pounds per acre of 10-10-10 (N-P- K).
Most WSAAF soils have tested poorly with very low to no organic content. Provide organic soil boosters by application of liquid cow or horse manure slurry.
Type 3 – Seed Mix for Ranges
Botanical Name Common Name Variety
% Mix by Weight
% Pure Live Seed
Poa compressa Canada Bluegrass 18 80
Festuca rubra L.
Panicum virgatum L.
Creeping Red Fescue
Spring: Cave-in-the-rock Switchgrass Fall: Jasper 23 78
Festuca ovina Sheeps Fescue Azur 23 78 Festuca ovina Var ‘Duriusculila’ Hard Fescue Reliant 23 78 Lotus cornicultatus L. Birds Trefoil Empire 9 85 Agrotis gigantean Roth Redtop 4 83
Seed Purity: Contractor shall provide seed with the following purity
Botanical Name Common Name
Min % Pure Seed
Min. % Germination And Hard Seed
Max % Weed Seed
Festuca Rubra Creeping Red Fescue 98 90 2
Lotium Perene Perennial Ryegrass 88 90 12 Trufolium Repens White Clover 88 90 12
Immediately before seeding, restore soil to proper grade. Do not see when ground is muddy, frozen, snow covered, or in an unsatisfactory condition for seeding. Apply seed within 24-hours after seedbed preparation.
Seeding method shall be by hydro seeding. Fiber shall be added at 1,000 pounds, dry weight, per acre. Seed shall be mixed to ensure broadcasting at the rate of 2.25 pounds per 1000 square feet. When hydraulically sprayed on the ground, material shall form a blotter like cover impregnated uniformly with grass seed. Spread with one application with no second application of mulch.
Start watering areas seeded as required by temperature and wind conditions. Apply water at a rate sufficient to insure thorough wetting of soil to a depth of 2 inches without runoff. During the germination process, seed is to be kept actively growing and not allowed to dry out.
b) Gravel (See Exhibit A Line Items 010B): The existing gravel areas shall be excavated a minimum of 5 feet beyond the outermost edge of the affected/damaged area to a depth of 12 inches. Subgrade soil shall be compacted to 95% modified proctor to a depth of 6 inches. Contractor shall install 12 inches of NYSDOT Type 2 stone (NYSDOT Item 304.12) in two (2) 6-inch lifts compacted to 95% modified proctor.
e) SPECIFICATIONS: The contractor shall comply with the technical requirements of the Unified Facility
Guide Specifications (UFGS) listed here-in as well as Technical requirements specified in the Statement of Work (SOW). Where conflicts exist between the UFGS and this SOW, the contract SOW shall prevail. All work completed under this contract to be completed in accordance with the technical and quality requirements of the applicable UFGS. UFGS are updated quarterly in February, May, August and November. UFGS may be obtained at the following: http://wbdg.org/ccb/browse_cat.php?c=3
Specification Title 01 45 00.10.20 Quality Control for Minor Construction 01 57 20.00 10 Environmental Protection 01 57 23 Temporary Storm Water Pollution Control 01 74 19 Construction and Demolition Waste Management 31 00 00 Earthwork 31 11 00 Clearing and Grubbing 32 12 16 Hot Mix Asphalt (HMA) for Roads 32 92 19 Seeding 33 40 00 Storm Drainage Utilities NYSDOT NYDOT Standard Specifications
f) SUBMITTALS: Submittals shall be provided as specified herein and as required by the submittal register and Contract Data Requirement List (CDRL). Failure to furnish submittals could result in a work stoppage and in addition, materials furnished and/or installed not meeting the specifications may be rejected by the KO or the duly appointed representative. The Contractor shall submit to the Government for review the following construction submittals at the specified frequency:
Submittal Frequency Select Granular Fill Aggregate Base Course Geosynthetics
- Soil Stabilization Fabric
- Geogrids
Hot Mix Asphalt Materials
- Base Course
- Binder Course
- Top Course
- Tack Coat
- MMTD
Topsoil Seed Mix
Annually or within 10-days of a change of Material or Supplier
Compaction Test Results Asphalt Density Testing Results
5-days after Field test
g) CONSTRUCTION APPROVAL SUBMITTALS: To implement the requirements in clause 52.236-5, entitled "Material and Workmanship", the Contractor shall submit ENG Form 4025-R, “Transmittal of Shop Drawings, Equipment Data, Material Samples, or Manufacturer's Certifications” to the KO or designated Government representative. Unless otherwise specified all data submittals shall be submitted electronically (three hard copies upon request). Work associated with the items being submitted will not begin until approval is received from Public Works. The forms will be furnished to the Contractor by the Government.
h) MAINATENANCE AND PROTECTION OF TRAFFIC: The contractor is responsible to providing and implementing maintenance and protection of traffic (MPT). Maintenance and protection of the traffic shall be in accordance with the Manual for Uniform Traffic Control Devices (latest edition), the NYSDOT MUTD Supplement and NYSDOT standards.
i) FINAL INSPECTION: Upon the completion of each TO the Contractor shall notify the Contracting Officer and PW via email ten working days in advance of the request to schedule a final inspection (Exhibit D, Data Item #0010). Prior to a request for final inspection, the Contractor's Quality control (QC) representative shall conduct his own inspection and ensure all deficiencies are corrected. The Contractor’s QC representative will provide a copy of his QC inspection report to the Government’s inspector with a copy of the status of deficiency correction. The Government reserves the right to approve or disapprove the request for a final inspection based on project deficiency items.
Mission and Installation Contracting Command (MICC), PW, the customer, and other personnel as necessary (e.g., Fire Department, Safety, NEC, MEDDAC, Physical Security, and Environmental personnel) will jointly conduct the final inspection with the Contractor. The Contractor shall correct any noted discrepancies/punch list items discovered at the final inspection prior to the TO completion date listed on the TOR and final acceptance by the Government. The Government shall not ask for a correction or rework of an item if the work was not required by the SOW or a regulation or requirement incorporated within the TO or contract. The Contracting Officer or his authorized representative may schedule more than one final inspection if determined necessary. Prior to the final inspection date, the Contractor shall submit the final record drawings, as built drawings, DD Form 1354 documents, warranty information to the COR for review and approval (Exhibit D, Data Item #0009).
2) PROTECTION AND RESTORATION OF WORK AREA: During work operations, the Contractor shall protect all designated existing work sites and grounds with the proper barricades (including barricades with flashing safety lights at night where appropriate), signs, flagging and/or other acceptable safety control/protective devices. All existing work sites, structures or facilities to include access roads, vegetation, and utilities, disturbed or damaged by the Contractor’s operations, other than those designated to be demolished, shall be repaired, replaced, and/or restored by the Contractor at no additional cost to the Government. The work shall be performed in an approved workmanlike manner and shall be acceptable to the Contracting Officer.
3) CLARIFICATION OF WORK: Before submitting bids, it shall be the responsibility of each bidder to visit the site of work, survey the existing conditions and verify all portions of the work to be done. During the solicitation process, the Government will schedule a site visit for all interested bidders; date and time to be announced. The Contractor shall arrange his work to prevent inconveniences or stoppage to operations, and will appraise itself of working conditions and any inefficiency expected to be encountered during the Contract work. Failure of the bidder to inspect the site of work prior to preparing his bid shall in no way relieve it of the responsibility to perform all of the work required.
4) DISPOSITION OF MATERIALS: All materials which are not reused shall be classified as unsalvageable material. Unsalvageable material shall be identified as non-recoverable or recyclable and segregated on site. Non-recoverable material shall be removed from the site by the Contractor and disposed of off-post at a permitted facility in accordance with local, state and federal laws and regulations. Recoverable materials shall be diverted from disposal through recycling or re-use in accordance with federal and state law and regulation. Weights in pounds or tons for disposal and recycle shall be forwarded to the Public Works, Environmental Division at the completion of work. In case of a conflict among these laws and regulations, the most stringent law or regulation shall apply.
5) SCHEDULE OF OPERATIONS: The Contractor shall submit a schedule of proposed operations to the
Contracting Officer for approval. Such schedule shall be subject to change so that the Contractor's work does not conflict with or otherwise disrupt normal operations of the Government.
6) NORMAL WORKING HOURS: Normal working hours are 0730 to 1600 hours Monday through Friday excluding holidays. All work shall be performed during these hours unless otherwise approved by the Contracting Officer. The Contractor may be required to reimburse the Government for the cost of inspecting work performed outside of normal working hours.
7) CLEAN-UP: The Contractor shall clean up and containerize all debris and discarded materials resulting from his operations at the end of each workday. The Contractor shall ensure that debris collection containers are closed and secured at the end of each workday. The Contractor shall institute measures for the daily prevention of blow-away litter and debris from the worksite. Open burning of scrap or unsalvageable material is forbidden.
8) PROJECT ACCESS: The Contractor shall maintain access to the job site at all times under all normal seasonal weather conditions, at no additional cost to the Government.
9) INSTALLATION ACCESS, CONTROL AND SECURITY:
a. Installation Access and Identification of Contractor’s Employees – Entry to the installation requires the following: Rapid Gate identification for everyone in the vehicle, current vehicle registration, proof of insurance, and valid driver's license for the vehicle driver. The Government will not be responsible for damages due to delay/stoppages caused by failure to comply. The Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this Contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.
b. The Contractor shall provide a list of names and dates of birth of all employees that will be working on this Contract to include subcontractors. The Contractor shall provide these names to Chief, Physical Security no later than 30 business days of receiving the Contract.
c. RAPIDGate Program - Each employee who requires access to Fort Drum to perform work under any Contract, at any tier, must obtain a RAPIDGate identification credential to obtain access to Fort Drum. A RAPIDGate identification credential will only be issued to an employee, at any tier, if the employee requires access to Fort Drum more than twice per week or when the Contract spans more than 30 days. Vendors, Contractors, and sub-contractors are responsible for all costs associated with their enrollment in RAPIDGate. Contractor employees, at any tier, who require access to Fort Drum twice per week or less often will be required to sign in daily. A RAPIDGate identification credential will only be issued to a Contractor’s employees if the Contractor participates in the RAPIDGate Program. The RAPIDGate Program is a mandatory program.
d. The Contractor shall provide information as required by the RAPIDGate Program Contractor (RPC) to enable the Contractor to conduct a criminal history background check (CHBC) on Contractor employees who are to have access to Fort Drum. The Contractor is responsible for paying the RPC the Contractor’s company registration fee and the fee per employee for conducting the CHBC and issuing the RAPIDGate identification credential. If the CHBC is not adverse, a RAPIDGate identification credential will be sent to the Fort Drum Physical Security Division by the RPC where the Contractor’s employee will present the required I-9 documents to be vetted and will then be issued the RAPIDGate identification credential. If the CHBC is adverse, the RPC is prohibited from issuing a RAPIDGate identification credential to the Fort Drum Physical Security Division. If a RAPIDGate identification credential is denied for any reason, the Contractor’s employee may request adjudication or a waiver from the installation. If a Contractor’s employee is denied a RAPIDGate identification credential for any reason, the employee will not be allowed access until the case is adjudicated or a waiver is requested and approved. There is an appeals process through RAPIDGate to the Directorate of Emergency Services. Final determination to allow entry and the issuance of a RAPIDGate credential rest with the Garrison Commander or his designee, the Director, Emergency Services.
e. If an employee no longer needs the RAPIDGate identification credential for any reason (e.g. quits their job or no longer performs under the Contract), the Contractor is required to collect the RAPIDGate identification credential from the employee and surrender it to the Fort Drum Physical Security Division within four (4) calendar days of such change. If the RAPIDGate identification credential cannot be returned within the required time frame for any reason, the Contractor shall immediately notify the RPC and Physical Security Division verbally, followed up in writing the next work day. Email notification is authorized. An employee’s inability to obtain entrance to a Government installation because they do not have the required identification badge or visitor’s pass shall not excuse timely performance of the requirements of this Contract. RAPIDGate identification credentials are currently issued at the Fort Drum Physical Security Division located in the Fort Drum MP Station. The Government may change the location at which RAPIDGate identification credential are issued or returned, with or without advance notice to the Contractor. Any such changes shall not be a basis for adjusting the Contract price under any clause of this Contract.
f. RAPIDGate identification credential will not be reproduced or copied by the Contractor, its subcontractors, or their employees. If an employee’s RAPIDGate identification credential is lost, stolen, or reproduced, the Contractor shall verbally report the loss, theft, or reproduction to both the RPC and the Fort Drum Physical Security Division on the day such loss, theft, or reproduction is discovered, followed by a written report of the circumstances to both the RPC and Fort Drum Physical Security Division within two (2) calendar days.
g. Each…
This is the start of the file's text. The full file is on GovTribe.