Q and A for Site Visit.pdf
PDF 161 KB Posted
- Attached to
- Ag Outlease Fort Riley, KS
- Solicitation number
- W911RX-24-Q-0017
About this file
This document appears to be a question and answer (Q&A) session related to a site visit for Federal Contract Opportunity W911RX-24-Q-0017, titled "Ag Outlease Fort Riley, KS". The key details are as follows:
The contract requires the contractor to plan, program, coordinate, estimate, and schedule work to maintain agricultural conservation structures (terraces and waterways), agricultural outlease access roads, and provide renovation services at Fort Riley, KS. The Q&A session addressed questions about maps depicting the road locations, the contractor's responsibility for clearing brush on both sides of water brakes, and how the contractor will bill for inspections. Specifically, the contractor will be responsible for clearing brush on both sides of the water brakes, and will bill for inspections under CLIN 1 of the contract. The Q&A also referenced several attached documents, including maps that may have minor changes to the locations of the terraces and road surfaces.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Visit Notes W911RX-24-Q-0017
Information: There will be a mini- PWS provided with each task order stating how far the brush should be off the road. Roads will be billed off CLIN 3. The roads are gravel and must be crowned 16 ft wide.
Question 1: Are there Maps that reflect the roads?
Answer 1: In Attachment 1: All maps may have minor changes to the locations of the terraces due to repairs and revisions since the data was updated.
Attachment 5a: The road surfaces (gravel verses natural surface) may have changed since the maps were created for the project. There should be three tariffs and there are only two in area one.
Attachment 5b: The road surfaces are correct; no changes have been made since the map was created for the contract.
Question 2: Is the contractor responsible to clear the brush for both sides of the water brake both up and down hill?
Answer 2: Yes, the contractor will be responsible to clear the brush for both sides of the water brake.
Question 3: How will the contractor bill for inspections?
Answer 3: the Contractor will bill off CLIN 1 for all inspections.