TE-5_Questions_from_Industry-_W911RX-17-B-0001 FRK_Laundry _14_Oct_16.pdf
PDF 39 KB Posted
- Attached to
- Laundry Service Fort Riley Kansas
- Solicitation number
- W911RX-17-B-0001
About this file
TE-5 Questions from Industry- W911RX-17-B-0001 FRK Laundry 14 Oct 16
View the file
Other files
Show 40 more
Latest 50 of 68 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions from Industry
Q1- I see that one "Job" pricing is requested how to do you intend on paying the contractor will this just be the same amount each month no matter if the volume is greater or lower?
A1- No, contact is paid on actual work performed.
Q2- Dry Cleaning it says 3 day organizational does that mean that you will send all the dry cleaning at the same time or will it just come in every day?
A2-All cleaning is received on a daily basis.
Q3- The rags are we purchasing the rags and then supplying them or is the government purchasing them and supplying them to their customers on base?
A3- Rags are provided by Fort Riley
Q.4-I had a question regarding the pre-award survey and specifically my past performances for laundry cleaning service, W911RX-17-B-0001. Currently, my company provides service primarily in custodial service but I am interested in this opportunity and I plan on working with a subcontractor for the laundry cleaning service. The subcontractor I plan on working with on only has civilian past performance work and does not have any government contracts.
A.4-In accordance with FAR 15.305 Proposal evaluation. (iv) In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance.
Q.5-My question is due to the limited experience, could I still pursue this opportunity and submit a proposal or if I were to submit a proposal would my proposal be considered non-responsive and not be considered for this award due to not be able to provide 3 past performance references?
A.5-(iii) The evaluation should take into account past performance information regarding predecessor companies, key personnel who have relevant experience, or subcontractors that will perform major or critical aspects of the requirement when such information is relevant to the instant acquisition. Your evaluation would be deemed responsive.