QA Shades Update 1.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Installation of four Exterior Shading Systems
Solicitation number
W911QY-26-R-SHAD
Issued by

About this file

This is a Questions and Answers document that clarifies requirements for Solicitation W911QY-26-R-SHAD, a Request for Proposals issued by the Department of the Army Materiel Command for the installation of four exterior shading systems at Natick Soldiers Systems Center in Massachusetts. The Q&A addresses structural design specifications, material requirements, submission guidelines, and regulatory compliance. Key clarifications include: posts, foundations, structural supports, and hardware must be designed as permanent structures per IBC/ASCE 7 standards, while fabric shade sails are removable seasonally and do not require engineering for snow loads or year-round exposure; the government will provide removable/tensioning hardware and instructions for seasonal installation and removal by government personnel; engineer drawings are not required in proposal submissions but must be provided during contract performance, though contractors may include a separate line item cost for stamped drawings; the contract is firm fixed-price with no post-award adjustment period for cost reviews; a Massachusetts general contractor's license is required; shading systems must be located minimum 15 feet from buildings, provide at least 10 feet of clearance, and can be configured in multiple pieces; both the Buy America Act and Berry Amendment apply completely to this requirement with applicable DFARS clauses incorporated; fabric should be open-weave with rain protection not prioritized; and separate price and technical proposals must be submitted using the provided "Sail Shade Bid Form."

View the file

Other files

File Type Posted
QA Shades Update 2.xlsx XLSX spreadsheet
Sail Shade Bid Form.xlsx XLSX spreadsheet
QandA Shaders.xlsx XLSX spreadsheet
Install Shaders Combined Synopsis Solicitation.pdf PDF
Sail Shade SOW Attachments 07 22 2026.pdf PDF
SOW Sail Shades 08 03 2026.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionsAnswers
Should the posts, foundations, structural supports, and hardware be designed as permanent structures in accordance with IBC/ASCE 7, while the fabric shade sails are designed to be removed seasonally?Posts, foundations, structural supports, and hardware be designed as permanent structures in accordance with IBC/ASCE 7. -Fabric shade sails are designed to be removed seasonally.
If the fabric is intended to be removed during the winter season, may the design assume that the fabric will be removed prior to snow/ice conditions, or must the installed fabric system also be engineered for applicable snow loads/year-round exposure?The fabric is intended to be removed prior to the winter season, it is not required to be engineered to accept snow loads/year round.
Is the Government expecting the contractor to provide the necessary removable/tensioning hardware and instructions so Government personnel can remove and reinstall the fabric seasonally?The Government is expecting the contractor to provide the necessary removable/tensioning hardware and instructions so Government personnel can remove and reinstall the fabric seasonally.
Are engineer drawings required as part of the bid proposal?No, engineer drawings are not requried to be submitted as part of the proposal. They are required to be submitted during the performance of the contract.
Should the contractor put a line item cost for engineering services based on what stamped drawings would cost?The contractor may include a line item cost for stamped drawings in their proposal.
Is the government willing to amend the solicitation timeline to allow contractors to get drawings from an engineering firm?The government will amend the due date of the solicitation on an as needed basis.
Will the government allow the contractor a few weeks to review subcontractor drawings and check for cost changes after award?No, this contract will be firm fixed price. A firm-fixed-price contract provides for a price that is not subject to any adjustment on the basis of the contractor’s experience in performing the contract.
Can the government publish a list of interested vendors/vendors who attended the site visit?No, the government cannot provide this information.
Is the shading system designed to be broken down seasonally, or to stay on permanently?Designed to be broken down seasonally
Does the Buy America Act and the Berry Amendment apply to this requirement?Yes, both the Buy America Act and the Berry Amendment will apply completely to this requirement. The required DFARS clauses have been incorporated into the solicitation.
Is the fabric open weave?The government requests the fabric be open-weave, rain protection is not a priority.
Does the shading structure need to be in one piece, or multiple pieces? Are gaps allowed?Multiple pieces, must satisfy scope of work requirements for shading, etc
What is the lowest height clearance needed?10 feet
Does the government have site drawings/plans of the proposed construction sites?Contractor will need to contact utility survey company in order to identify utility that may be encountered during construction
Is another states general contracting license valid for this requirement? (Ex: Is a Texas GC license valid in MA)No, a Massachussetts general contractors license is required
How far away from the buildings will these shading systems be? What is the required standoff from the buildings?Shading systems will be at minimum, 15 feet from the building
Do the sites need to be ADA accessible?No, site does not need to be ADA accessible
When does the site need to be open? (Ex: Ready by the start of spring)Refer to period of performance. If winter weather conditions can be expected, do not set up the shades, the government will take care of that once warmer weather is expected.
Do we need to submit separate price and technical proposals?Yes, the government requests that a price proposal be submitted on the provided bid form "Sail Shade Bid Form". A separate technical proposal is requested.
Can the governements budget be provided?No
Questions still being answered
Can the contract POP be extended to 210 days?
Can bidders assume that any fabric colors would be standard basic colors?