A01_-_PWS.docx
DOCX document 161 KB Posted
- Attached to
- Renovation Services for SEDD Front Office
- Solicitation number
- W911QX-16-T-0058
About this file
Amended PWS 05/05/2016
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_Questions_and_Answers.docx | DOCX document | |
| A07_Site_Visit_Information.docx | DOCX document | |
| A01_DD1423.doc | DOC document | |
| A07_Wage_Determinations.docx | DOCX document | |
| A01_PWS.docx | DOCX document | |
| A07_-_Solicitation.pdf | ||
| A01_-_Draft_PWS.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS) Front Office Renovation, Bld. 207 U.S. Army Adelphi Laboratory Center (ALC) C.1 Background: The primary mission of United States Army Garrison, ALC is to provide valuable support services and infrastructure to enable scientific research, development, and well-being of the workforce. ALC serves the Soldier and collaborates with Army science and research by providing excellent lab facilities and support services.
C.1.1 Place of Performance: The work to be performed under this contract will be performed in Building 207 at Adelphi Laboratory Center (ALC), 2800 Powder Mill Road, Adelphi, Maryland 20783.
C.1.2 Security Requirements: All contractors working at the Adelphi Laboratory Center (ALC), who do not possess a Common Access Card (CAC), or another approved Federal identification card, must be vetted using the National Crime Information Center (NCIC) Interstate ID Index (III), which is the Army minimum baseline background check for entrance onto Army installations. Contrators shall submit a completed Form 191 to the Contracting Officer Representative for each person requiring access to the facility.
C.2 Objective: The Contractor shall complete office renovations as described in Section C.3 and Figure 1 of this PWS, to include minor demolition, electrical, carpeting, painting, and partition wall assembly. During the performance of this contract, the Contractor will be responsible for providing all personnel, equipment, supplies, transportation, tools, materials, supervision, and other items and non-personal services necessary to complete the office renovations.
C.3 Requirements:
C.3.1 Demolition: The Contractor shall complete the work listed below to prepare for the installation of the new modular wall system, as shown in Figure 2. The Contractor shall be responsible for moving furniture and boxes in office areas designated for carpet and/or painting.
· The Contractor shall remove and dispose of approximately 250 square feet (SF) of existing wall paper and/or textured paint.
· The Contractor shall remove and dispose of approximately 6000 SF of carpet tile and approximately 1250 linear feet (LF) of cove base.
· The Contractor shall be responsible for the removal of all debris from the Adelphi Laboratory Center facilities and shall produce their own dumpster. An area outside of the loading dock will be set aside for one (1) Contractor-provided dumpster.
C.3.2 Relocation: The Contractor shall complete the work listed below to prepare for the installation of the new modular wall system, as shown in Figures 1 and 2.
· The Contractor shall remove and relocate of twenty-two (22) existing sections of suspended ceiling tiles (for removal and relocation of light fixtures, HVAC diffusers, and fire sprinkler heads).
· The Contractor shall remove and relocate eleven (11) existing light fixtures to accommodate the new modular wall system.
· The Contractor shall remove and relocate six (6) existing electrical junction boxes installed in raised flooring.
· The Contractor shall remove and relocate twelve (12) existing raised floor panels.
C.3.3 Construction: The Contractor shall complete the work listed below accordance with Figures 1 and 2:
C.3.3.1 Modular Wall System: The Contractor shall provide and install approximately 83.5 lineal feet (LF) and three (3) doors, in accordance with Figure 1, using Transwall ZWall modular wall system, or equivalent materials. The Contractor shall ensure the modular wall system includes the following:
· Clerestory windows, split finish wood and textile panels on the cooridor side of the panel, and solid textile on the interior side of the panel. The Contractor shall include a markerboard at 48” high on the interior of the panel.
· The Contractor shall ensure clerestory panels, door frames, and all trim are metallic powder coated in color.
· Door hardware for the modular wall system that includes a sliding track, rollers, guide, and 6” pull loops. The Contractor shall ensure that the door frames include a transom window, prepped for sliding track and guide. The Contractor shall ensure the doors are 1.75” solid wood veneer and prepped for the sliding track and guide.
· Glass that is ¼” tempered with factory glazing.
C.3.3.2 Heating, Ventilation, and Air Conditioning (HVAC): The Contractor shall provide and install one (1) HVAC supply grill and associated duct work.
C.3.3.3 Carpeting: The Contractor shall provide and install approximately 1200 SF of carpet tile border by Shaw Adorn or equivalent. The Contractor shall provide and install approximately 4800 SF of carpet field tile, Shaw 1395 Focus, or equivalent. The carpet must accommodate a raised floor system.
C.3.3.4 Wall Base: The Contractor shall provide and install approximately 1250 LF of Armstrong wall base, R4824 Cocoa, or equivalent.
C.3.3.5 Painting: The Contractor shall provide and install one (1) coat of primer and two (2) finish coats of paint in the approximate amounts as follows: 200 SF of Sherwin Williams, color French Roast or equivalent, 800 SF of Sherwin Williams, color Windy Blue or equivalent, and 10,000 SF of Sherwin Williams, color Morning Sun or equivalent. The Contractor shall paint the door jams and window frames to match the French Roast color.
C.3.3.6 Fire Sprinklers: The Contractor shall provide and install three (3) new sprinkler heads. The Contractor shall ensure the sprinkler heads function with the existing fire sprinkler and system. The Contractor shall test the sprinker heads in accordance with National Fire Protection Accosiation (NFPA) 25, with the assistance of the Directorate of Public Works (DPW).
C.4 Deliverables:
C.4.1.1 Material Cut Sheets and Samples: The Contractor shall propose and submit a manufacturer’s cut sheet for new lighting and modular walls systems. The Contractor shall also propose and submit a sample of each new type of finish material to be installed, including panel textile, paint, carpet, and cove base. Material submittals shall be provided to the COR within two (2) weeks after contract award. The COR will respond with comments to the Contractor within one (1) week of receipt of the submission. The Contractor shall submit the final submittal for approval within one (1) week of receipt of the COR comments. The final submittals shall be approved by the COR before work begins.
C.4.1.2 Schedule of Work: The Contractor shall provide a schedule of work that incorporates all defined tasks noted in section C.3. A draft copy of this schedule shall be provided to the COR within one (1) week after the material submittals are approved. The COR will return the schedule, with input/comments, to the Contractor within one (1) week of receipt of the submission. The Contractor shall submit the final schedule, for approval, within one (1) week of receipt of the plan with COR comments. The final schedule of work shall be approved by the COR before work begins.
C.4.1.3 Accident Prevention Plan: The Contractor shall develop an accident prevention plan in accordance with EM 385-1-1, Appendix A, and provide a draft copy to the COR within one (1) week after the material submittals are approved. The accident prevention plan will be reviewed by the COR for completeness and compliance with OSHA and EM 385-1-1. The COR will return the accident prevention plan, with input/comments, to the Contractor within one (1) week of receipt of the submission. The Contractor shall submit the final accident prevention plan, for approval, within one (1) week of receipt of the plan with COR comments. The final accident prevention plan shall be approved by the COR before work begins.
C.5 Applicable Publications:
The requirements and standards contained in the following publications and regulations shall be followed for all work to be accomplished under this PWS:
· Code of Federal Regulations (29 CFR 1910)
· EM385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual 2008 edition
· Federal Acquisition Regulations (FAR) clause 52
· NFPA 70E, Standard for Electrical Safety in the Workplace 2015 edition
· NFPA 70, National Electrical Code 2014 edition
· Unified Facilities Guide Specifications (UFGS) 013529 (formerly 01525)
FIGURE 1
Modular Wall Layout
FIGURE 2
Contracting Officer:
image3.emf image1.png image2.emf