A01_-__Revised_PWS.doc
DOC document 94 KB Posted
- Solicitation number
- W911QX-16-T-0019
About this file
Revised PWS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A01_-_Instruction_Manual-_ABB_Power_Center.pdf | ||
| A01_-_January_Adelphi_Transformer_Report.pdf | ||
| A01_-_3000_kVa_Substation_Information_Package.pptx | PPTX presentation | |
| A01_-_Questions_and_Answers.xlsx | XLSX spreadsheet | |
| A02_-_ACC-APG_Adelphi_Local_Clauses_Full-Text_Attachment_(for_Combo_Synopsis-Solicitation).docx | DOCX document | |
| A02_-_Wage_Determinations.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS) 13.8-4160 Transformer-Disconnect Repair Adelphi, MD Army Research Laboratory – Sensors and Electron Devices Directorate
C.1 BACKGROUND:
This PWS outlines the repair of an existing concrete pad mounted, 60 Hertz (Hz), 13,800 Volts Alternating Current (VAC) to 4160 VAC Delta-Wye, 3000 Kilo Volt Amp (kVA), ASEA Brown Boveri (ABB) unit substation that is used at the Power Electronics facility in building 500 at the Army Research Laboratory, Adelphi Laboratory Center (ALC), Adelphi MD 20783. The 13,800 VAC VersaSwitch on the high side of the transformer was severely damaged due to an animal induced flash over event across two (2) of the three (3) phases. The event damaged multiple fiberglass interphase barriers, busbar assemblies, 18 kilovolt (kV) surge arrestors, A155C2D0R0-125E fuses, porcelain standoff insulators and cables in the VersaSwitch Cabinet. The three (3) phase, type Restricted Substance List (RSL), oil insulated unit substation transformer’s primary to secondary windings was tested and deemed to meet industry standards and does not require repair. The Medium-Voltage Vacuum Power Circuit breaker contained in the 4160 VAC cabinet was inspected and found to be exposed to rodent activity and will therefore require testing and a maintenance action to ensure proper operation. The existing service in the manhole is a wye splice from the 500 thousands circular mils kcmil, 15 kV, Ethylene Propylene Rubber (EPR), 133% insulation level, single conductor service (feeder 1-7) with a 3/0 copper ground wire. The existing tap is terminated in live end caps. The Period of Performance (PoP) for this requirement is anticipated to be three (3) months after contract award and two (2) option years.
C.2 OBJECTIVE:
The Contractor shall provide all certified trained labor, documentation, tools, and equipment to return the functionality of the 13,800 VAC to 4,160 VAC unit substation to its original state of operation.
C.3 REQUIREMENT:
C.3.1 The Contractor shall send all repair personnel to building 500 at the US Army Research Laboratory (ARL), ALC located at 2800 Powder Mill Rd. Adelphi, MD 20783, to perform on-site inspection and repair of the damaged unit substation following International Electrical Testing Association (NETA) and/or National Institute for Certification in Engineering Technologies (NICET) testing standards.
C.3.2 The Contractor shall provide all parts, labor, and materials necessary to replace or repair the damaged unit substation 13,800 VAC, fused-disconnect, VersaSwitch returning it to its original state of operation.
C.3.2.1 The Contractor shall install all panels and guards properly to prevent future animal encroachment into the enclosure.
C.3.2.2 The Contractor shall only use replacement parts that function in a manner consistent with the Original Equipment Manufacturer (OEM) parts if OEM parts are not available.
C.3.2.3 The Contractor shall replace the high voltage cables between the VersaSwitch and the 3000 kVA transformer.
C.3.2.4 The lightning arrestors shall be 12 kV intermediate class.
C.3.3 The Contractor shall inspect, test and complete a standard maintenance action on the Medium-Voltage, 4,160 VAC, Vacuum Power, Circuit breaker.
C.3.3.1 The Contractor shall ensure all panels and guards are properly installed to prevent future animal encroachment into the enclosure.
C.3.3.2 The Contractor shall inspect, test and complete a standard maintenance action of the control power transformer and the potential transformer(s) on the 4160 volt sections of the unit substation.
C.3.4 The Contractor shall replace all cables having a total length of 85 feet (each), which tie into the primary 13,800 VAC feeder located in the building 500 power feed man-hole located between Floral drive and the building 500 power substation.
C.3.4.1 The Contractor shall replace the pull/junction box between the manhole and the VersaSwich with a box capable of providing for the adequate bend radius of the 13,800 VAC cable.
C.3.4.2 The Contractor shall use Number One (1) American Wire Gauge (AWG) copper, One (1) Conductor (1/C), Type MV-105, 15kV, 220 mils EPR insulation power cable for underground duct bank installation.
C.3.4.3 The Contractor shall provide catalog cuts for approval of all proposed materials to be installed in the manhole for the transition between the 500 kcmil feeder and the One (1) AWG tap to the new/repaired 15 kV disconnect switch.
C.3.4.4 The Contractor shall provide qualifications of all medium voltage cable splicers to DPW for approval before any cable splicing work is performed.
C.3.5 The Contractor shall remove all failed equipment and debris from the ALC installation.
C.3.6 The Contractor shall ensure all replaced or repaired equipment powers up to a functional state of operation.
C.3.7 The Contractor shall be present when primary power is restored to the substation to ensure satisfactory operation.
C.4 WARRANTY
The Contractor shall unconditionally warrant the repairs made in C.3.1 through C.3.8 above for:
Parts - One (1) year after repair.
Labor - One (1) year after repair.
C.5 DELIVERABLES/DOCUMENTATION:
C.5.1 The Contractor shall provide a final report of all the repairs no later than four (4) weeks after work completion. The Contractor shall ensure that the report includes a list of all the items replaced and repaired on the 13,800 kVAC to 4,160 VAC unit substation with their respective part or inventory numbers. The Contractor shall submit the report via electronic transmission to the Government. The Government will provide specific transmission instructions to the Contractor no later than two (2) weeks after contract award.
C.6 TRAVEL:
To the maximum extent possible, the Contractor will provide electronic media over existing secure high bandwidth or other secure communications links rather than by Contractor travel. When travel between the Contractor’s facility, ARL, and various Continental United States (CONUS) locations are required; the Contractor shall ensure that all travel is performed in accordance with the Joint Travel Regulations (JTR). The Contractor shall request approval for travel from the Contracting Officer Representative (COR) in writing two (2) weeks prior to scheduling the travel arrangements. The COR will provide approval in writing no later than (NLT) one (1) week after receipt of travel request.
C.7 CONFORMANCE TO CODES AND STANDARDS:
The Contractor shall ensure all electrical work conforms to requirements of the National Electrical Code - 2014.
C.8 HOURS OF OPERATION:
C.8.1 The Contractor personnel shall work Monday through Friday, eight (8)-hour days covering core work hours of 0900-1500 excluding Federal holidays unless otherwise directed by the COR during the inspection and installation phase of the contract.
C.8.2 The Contractor personnel shall work eight (8)-hour days Saturday through Sunday covering core work hours of 0900-1500 excluding Federal holidays unless otherwise directed by the COR during the tie-in and testing phase of the contract.
C.9 SAFETY:
The Contractor personnel shall follow all safe work practices as dictated by the National Fire Protection Association (NFPA)-70E 2015 and all applicable Occupational Safety & Health Administration (OSHA) standards. All contract electricians and electrician helpers shall submit the most recent copy of their NFPA 70E training certificate of completion. The Contractor shall conduct a pre-work meeting with the ARL safety office to ensure that the Contractor has an approved work plan. The Contractor shall provide health and safety plans of company personnel and Contractors to the ARL safety office.
C.10 ANTI-TERRORISM/OPERATIONAL SECURITY (AT/OPSEC):
C.10.1 Contractor employees and all associated sub-contractor employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by the COR as Government Furnished Information (GFI) at contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable) such as wearing of ID Badges etc. The Contractor shall also provide all information locally required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by the COR based on Department of Defense (DOD), Headquarters, Department of the Army (HQDA), and/or local policy. In addition to the changes otherwise authorized by the changes clause of the contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the COR may require changes in Contractor security matters or processes. During FPCON Charlie and Delta and other required postures such a Lockdown, Shelter In Place (SIP) or Evacuation, Contractor employees will resume work as soon as possible after the FPCON has been lowered or the posture returned to normal operations. This pertains to real situations and exercises.
C.10.2 Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
C.11 OPTION YEARS
C.11.1 CLIN 0002 – OPTION YEAR ONE (1)
The Contractor shall perform two (2) maintenance inspections during the year at six (6) month intervals. The Contractor shall maintain and repair any outstanding issues found during the inspections and keep the unit substation operating at OEM specifications.
C.11.2 CLIN 0003 – OPTION YEAR TWO (2)
The Contractor shall perform two (2) maintenance inspections during the year at six (6) month intervals. The Contractor shall maintain and repair any outstanding issues found during the inspections and keep the unit substation operating at OEM specifications.
C.12 DISTRIBUTION
C.12.1 The Contractor shall distribute this PWS in accordance with the following distribution statement:
Distribution Statement A: 1. Approved for public release; distribution is unlimited.
File details come from the government source that posted it. Updated .