A01_-_Questions_and_Answers.xlsx
XLSX spreadsheet 13 KB Posted
- Solicitation number
- W911QX-16-T-0019
About this file
Questions and Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A01_-_Instruction_Manual-_ABB_Power_Center.pdf | ||
| A01_-_January_Adelphi_Transformer_Report.pdf | ||
| A01_-_3000_kVa_Substation_Information_Package.pptx | PPTX presentation | |
| A01_-__Revised_PWS.doc | DOC document | |
| A02_-_ACC-APG_Adelphi_Local_Clauses_Full-Text_Attachment_(for_Combo_Synopsis-Solicitation).docx | DOCX document | |
| A02_-_Wage_Determinations.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SOLICITATION W911QX-16-T-0019 | |
| Question | Answer |
| 1a. Will the Army consider the removal of the transformer and repair at a contractors facility? | |
| 1b. The Government will consider the removal of all units for repair at a contractor's facility. The removal, repair, service and return to service of the transformer and high voltage switch cabinet shall be the responsibility of the contractor. |
| 2a. Please provide pictures of the transformer that needs repair. | 2b. Please see attachment titled "3000 kVa Substation Information Package". The transformer was deemed good upon follow up testing. |
| 3a. Even if we attend the site visit, we can only estimate the cost of repairs or make assumptions, how will bids be compared. | |
| 3b. Please see attachment titled "Evaluation Criteria". | |
| 4a. Please provide the test reports that have been performed after damage. | 4b. Please see attachment titled "3000 kVa Substation Information Package". |
| 5a. What is the year of manufacture? Need a picture of the Nameplate? | 5b. Please see attachment titled "3000 kVa Substation Information Package". |
| 6a. Can you provide copy of original as-built ABB drawings for substation? | 6b. Manual provided, reference "Instruction Manual ABB Power Center" |
| 7a. Can you provide copy of 3MVA transformer test reports, including oil test report? | 7b. Please attachment titled "3000 kVa Substation Information Package". |
| 8a. Advise if HV Cable is to be replaced on the incoming and two outing circuits, lengths as well as type, size, etc. (would think this being 20 years old you should replace all cables) | 8b. HV Input Cable length from manhole to gear is ~ 85'. We only want to replace the 13.8 kV main feed cable for this effort. See updated PWS |
| 9a. The 500KVA transformer, would you like this tested? | 9b. No |
| 10a. Will testing be in accordance with NETA? | 10b. NETA/NICET testing standards. See updated PWS |
| 11a. Does the Pad mount transformer need to be tested? | 11b. No, That is the 500 kVA transformer referenced above in 9a/b |
| 12a. Does the Cable feeding the pad mount transformer need to be replaced? | 12b. No |
| 13a. If removal of equipment is necessary, who is responsible for disposal and is there any stipulations to disposal of government property? | 13b. Removal of any failed equipment and debris shall be the responsibility of the Contractor. There are no stipulations on the anticipated removal of any equipment/debris related to this repair effort. |
| 14a. What size cable and cable specs is required from the man hole to new gear? | 14b. See updated PWS |
| 15a. Please confirm the lifting capacity of the on-site crane and fork lift. | 15b. Sm. Forklift - 5400lbs. Lg. Forklift - 12,500 lbs. Crane - 30,000 lbs. |
| 16a. Please confirm the on-site crane and fork lift will be available for contractor’s use and the operator will be provided. | 16b. We will provide the operator |
| 17a. Please provide a specification and size for the 5 KV load side cables. | 17b. They won't be replaced or tested |
| 18a. Please confirm the existing oil filled transformer does not contain PCB’s. | 18b. No PCBs present. See oil test report |
| 19a. If the existing equipment is replaced with new is the contractor responsible for removal from the site? | 19b. Removal of any failed equipment and debris shall be the responsibility of the Contractor. There are no stipulations on the anticipated removal of any equipment/debris related to this repair effort |
File details come from the government source that posted it. Updated .