About this file
This is a Solicitation, Offer, and Award form (Standard Form 1442) for a construction project at Watervliet Arsenal in New York.
The solicitation seeks design, materials, installation, workmanship, fabrication, assembly, erection, inspection, quality control, and testing of a new structural steel flooring system to support manufacturing equipment in Building 35. The footprint requiring replacement is approximately 280 square feet (28 feet long by 10 feet wide), with the existing flooring to be removed and replaced with a new metal flooring system capable of supporting equipment weighing up to 18,000 pounds. The work is classified as construction (NAICS 238310) with Product Service Code R699. The contract is firm fixed price with a period of performance of 90 calendar days from receipt of Notice to Proceed, with an expected performance window from 18 May 2026 to 31 August 2026. Performance and payment bonds equal to 100 percent of the original contract price are required only if the contract price exceeds $150,000. The solicitation is a sealed bid (IFB) with offers due by 02:30 PM local time on 07 May 2026, and a mandatory site visit is scheduled for 28 April 2026 at 2:00 p.m. at Watervliet Arsenal. All work must comply with applicable codes including International Building Code, AISC standards, AWS welding standards, and ASTM specifications. Contractor personnel working on-site must sign a non-disclosure agreement regarding Watervliet Arsenal cannon production technology. The contractor must obtain confined space certification for all personnel and submit certifications daily. A 24-hour advance notice is required for gate access, and Real ID-compliant identification is mandatory. All materials must be domestic per Buy American requirements, and wage determination NY2 (latest revision) applies to the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 138132A0625_US ARMY_LA-1050 OVEN_D071725_APPROVAL LAYOUT_REV A.pdf | ||
| a6514b90-7a7f-4507-aa18-ccad6d7a6360.jpg | JPG image | |
| IMG_0488.jpeg | JPEG file | |
| IMG_0482.jpeg | JPEG file | |
| IMG_0493.jpeg | JPEG file | |
| IMG_0484.jpeg | JPEG file | |
| IMG_0490.jpeg | JPEG file | |
| IMG_0489.jpeg | JPEG file | |
| IMG_0485.jpeg | JPEG file | |
| RFI RESPONSES.docx | DOCX document | |
| IMG_0487.jpeg | JPEG file | |
| IMG_0486.jpeg | JPEG file | |
| IMG_0483.jpeg | JPEG file | |
| IMG_0494.jpeg | JPEG file | |
| IMG_0495.jpeg | JPEG file | |
| IMG_0491.jpeg | JPEG file | |
| Minor Heat Treat Floor Service SOW.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section A - Solicitation/Contract Form
MINOR HEAT TREAT FLOORING SYSTEMInstrument Name:
Product Service Code : R699
SITE VISIT
DATE: Tuesday, 28 April 2026 @ 2:00 p.m.
LOCATION: 1 Buffington St. Watervliet, NY 12189 (Watervliet Arsenal)
FOR ACCESS INTO THE FRONT GATE PLEASE CONTACT Maria DeCrescenzo, (518)266- 4641, maria.d.decrescenzo.civ@army.mil WITH NAME(S) AND COMPANY REPRESENTED AT
LEAST A MINIMUM OF 24 HOURS IN ADVANCE OF SITE VISIT.
MEETING POINT IS THE FRONT GATE PARKING AREA JUST INSIDE THE MAIN ENTRANCE.
PLEASE PLAN TO ARRIVE AT LEAST 15 MINUTES EARLY TO ALLOW TIME GETTING
THROUGH THE GATE PROCESSING THROUGH THE VISITOR'S CENTER.
POINT OF CONTACT IS: Maria DeCrescenzo or James Cantamessa @ (518) 266-4025
THIS IS THE ONLY SITE VISIT, ALTERNATE DATES AND/OR TIMES WILL NOT BE GRANTED!
A REAL ID-COMPLIANT DRIVER'S LICENSE OR SUPPLEMENTAL IDENTIFICATION
(PASSPORT, TWIC, ETC.) IS REQUIRED FOR ACCESS ONTO POST. ACCESS WILL BE
DENIED FOR ALL WHO DO NOT PRESENT A REAL ID.
(Additional Info)
SAFETY GLASSES ARE REQUIRED. SAFETY SHOES AND ANY OTHER APPROPRIATE
PERSONAL PROTECTIVE ITEMS ARE ALSO RECOMMENDED.
LOCAL NARRATIVES
A. NOTICE OF WATERVLIET ARSENAL INFORMATION/REQUIREMENTS
(a) IMPORTANT DELIVERY/QUALITY REQUIREMENTS:
W911PT26QA066
(1) ALL OFFERORS MUST CAREFULLY REVIEW THE DELIVERY REQUIREMENT IN THE
REQUEST FOR QUOTE OR SOLICITATION. WHEN SUBMITTING AN OFFER/BID, PLEASE
ENSURE THAT YOU CAN MEET THE DELIVERY SCHEDULE.
(2) ON TIME DELIVERY IS VERY CRITICAL. THEREFORE, YOU MUST ADHERE TO THE
DELIVERY REQUIREMENTS INDICATED IN ANY RESULTANT AWARD. FAILURE TO
COMPLY WITH THE CONTRACTUAL DELIVERY SCHEDULE, MAY RESULT IN TERMINATION
OF THE ORDER OR REQUIRE CONSIDERATION IF THE GOVERNMENT ELECTS TO
EXTEND DELIVERY. (NOTE: Non-availability of raw materials, subcontractor issues, scheduling conflicts, should be considered at the time you are submitting your offer/bid. They are not acceptable excuses for failing to meet the delivery after award).
(3) PROVIDING QUALITY PRODUCTS THAT CONFORM TO THE CONTRACT ARE JUST AS
IMPORTANT AS MEETING THE REQUIRED DELIVERY. DELIVERY OF NONCONFORMING
PRODUCTS RESULTS IN DELIVERY DELAYS AND INCREASED COSTS TO THE ARSENAL.
(4) PAST PERFORMANCE FOR QUALITY AND DELIVERY MAY BE A MAJOR
CONSIDERATION IN MAKING DETERMINATIONS FOR FUTURE CONTRACT AWARDS.
NOTICE: Throughout this document we may use the terms "we" and "you", the term "we" means the government of the United States of America, and the term "you" means the contractor.
(b) WATERVLIET ARSENAL INFORMATION FOR CONTRACTORS:
"Watervliet Arsenal Information for Contractors" document is incorporated by reference in all solicitations and contracts. The full text version of the instructions is available at Internet address:
http://www.wva.army.mil/Documents/Contracting/WAIC.pdf Upon request, the contracting officer will make its full text available."
POC - CONTRACT SPECIALIST/BUYER: Maria Decrescenzo
TELEPHONE NUMBER: 518-266-4641
E-MAIL ADDRESS: maria.d.decrescenzo.civ@army.mil
Please provide the following information for your company.
VENDOR NAME: __________________
VENDOR POC: __________________
POC PHONE: __________________
E-MAIL ADDRESS (see note below): __________________
UNIQUE ENITITY ID: __________________
CAGE CODE (if known): __________________
TAX ID NUMBER: __________________
NOTE: Your e-mail address is required so that in the event you receive the resultant award, we can e-mail it to you. If we experience difficulties with e-mail, it will be data faxed.
(c) POSTERS:
(1) Contracts for Material, Supplies, Articles and Equipment Exceeding $15,000/Service Contract Labor Standards. Orders subject to these Acts require contractors to post WH Publication 1313, "Employee Rights on Government Contracts".
(2) Construction Orders. Orders for construction require contractors to post WH Publication 1321, "Employee Rights under the Davis Bacon" and the Office of Federal Contract Compliance poster on "Equal Employment Opportunity is the Law."
(3) These posters can be accessed electronically at http://www.dol.gov.
(4) Hard copies of the posters will be made available upon request to the contracting officer.
(d) PAYMENTS:
Any vendor that receives an award (except those paid by credit card or accommodation check) can view invoice payments made by DFAS at https://piee.eb.mil/ using the "my invoice" system.
You will be required to register in order to view payments. Payment information is maintained for 120 days from invoice payment. Vendors can find out when invoices have been paid by Electronic Funds Transfer (EFT), etc. This website can save valuable time and frustration over billing questions and it is a free service.
(e) RELEASE OF INFORMATION:
The contractor shall not release or authorize release of DoD specifications; acceptance test results; information involving critical military technology; or any other information in which the DoD maintains proprietary rights, or is otherwise confidential or classified. This restriction includes any endorsement by the Department of Army of a contractor. Release of information under the circumstances referenced above requires the prior written approval of the Contracting Officer responsible for this contract. It is the contractor's responsibility to be familiar with, and comply with the requirements of Chapter 5, page 22, paragraph 5-48, of AR 360-1 may be found at http://www.
usapa.army.mil/pdffiles/r360_1.pdf.
*** END OF NARRATIVE ***
*** END OF NARRATIVE ***
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price
Amount
0001 RIGGING AND FABRICATION Contractor to provide all labor, material, arts and equipment required to provide the design, materials, installation, workmanship, fabrication, assembly, erection, inspection, quality control, and testing of a new structural steel flooring system required to support manufacturing equipment in Building 35 at the Watervliet Arsenal. Wage Determination General Decision Number:
NY2, latest revision applies and is incorporated. Magnitude of this Project is between $25,000 and $100,000 Period of Performance is 90 Calendar Days from receipt of Notice to Proceed. 100% Payment and Performance Bonds (only if quote is over $150k) are required Technical POC is James Cantamessa Claimant Program Code: C2 Pricing Arrangement: Firm Fixed Price
1 Lot
Section C - Description/Specifications/Statement of Work
C._1_ Submission of Recordable Injuries and Illness Cases (Dec 2012) (ACC-Warren (WVA))
Watervliet Arsenal is pursuing OSHA Voluntary Protection Program (VPP) recognition. The VPP impacts all contractors whose employees cumulatively work more than 1000 hours per quarter within a calendar year at Watervliet Arsenal (herein referred to as "applicable contractors"). It is the contractor's responsibility to ensure its employees and managers are in full compliance with OSHA requirements and have a general understanding of VPP. Detailed information on VPP is available on the OSHA website at http://www.osha.gov/dcsp/vpp/index.html . All contractors, whether regularly involved in routine site operations or engaged in temporary projects such as construction or repair, must follow the safety and health rules of Watervliet Arsenal.
Applicable contractors are required to annually submit to Watervliet Arsenal, ATTN: TAWV-XO-S /Safety Office, Bldg. 10, 1 Buffington Street, Watervliet, NY 12189-4000 or email: usarmy.
watervliet.tacom.list.watesafety@mail.mil the following documents (covering the previous calendar year quarters) by 15 January:
- Total Case Incidence Rate (TCIR)
- the number of recordable injuries and illness cases per 100 full-time employees that a site has experienced in a given time frame.
- Days Away, Restricted, and/or Transfer Case Incident Rate (DART)
- Number of recordable injuries and illness cases per 100 full-time employees resulting in days away from work, restricted work activity, and/or job transfer that a site has experienced in a given time frame.
- OSHA Form 300A
Applicable contractors may submit the above immediately following the completion of a quarter, if desired.
*** END OF NARRATIVE ***
Requirements RIGGING AND FABRICATION - to provide the design, materials, installation, workmanship, fabrication, assembly, erection, inspection, quality control, and testing of a new structural steel flooring system required to support manufacturing equipment in Building 35 at the Watervliet Arsenal.
CLIN only - Requisition Document Number (MILSTRIP, DLMS, FEDSTRIP) : W16H1F526100KB Product Service Code : R699 North American Industry Classification System (NAICS) : 238310 Bill to Party: W16H1F
Section E - Inspection and Acceptance
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.246-12 Inspection of Construction. 1996-08
Overall Contract Inspection/Acceptance Locations
0001 Inspection and Acceptance Location
Both Destination Instructions: Inspection and acceptance terms per SOW.
DoDAAC: W911PT CountryCode: USA
W6QK ACC WVA
ACC WATERVLIET ARSENAL, 1 BUFFINGTON ST
WATERVLIET, NY 12189-4050
UNITED STATES
James Cantamessa
Section F - Deliveries or Performance
0001 Delivery Schedule From date of lead time event to completion of performance 90 Calendar Days
Date of Notice to Proceed Receipt 1 LotQuantity
Address and POC Place of Performance DoDAAC: W911PT CountryCode: USA
W6QK ACC WVA
ACC WATERVLIET ARSENAL, 1 BUFFINGTON ST WATERVLIET, NY 12189-4050
UNITED STATES
Period of Performance From 18 May 2026 To 31 Aug 2026
Section G - Contract Administration Data
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.
2018-12
252.236-7000 Modification Proposals--Price Breakdown.
1991-12
DFARS Clauses Incorporated by Full Text
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.232-7006 Wide Area WorkFlow Payment Instructions.
2023-01
WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)
(a) As used in this clause- Definitions.
"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.
"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.
"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) The WAWF system provides the method to electronically process Electronic invoicing.
vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) To access WAWF, the Contractor shall- WAWF access.
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) The Contractor should follow the training instructions of the WAWF WAWF training.
Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/
(e) Document submissions may be via web WAWF methods of document submission.
entry, Electronic Data Interchange, or File Transfer Protocol.
(f) The Contractor shall use the following information when WAWF payment instructions.
submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) The Contractor shall submit payment requests using the following Document type.
document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items-
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
N/A
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
CONSTRUCTION INVOICE
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial financing, submit a commercial financing request.
(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]
(3) The Contractor shall use the information in the Routing Data Document routing.
Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC
HQ0303
Issue By DoDAAC
W911PT
Admin DoDAAC N/A
Inspect By DoDAAC N/A
Ship To Code N/A
Ship From Code N/A
Mark For Code N/A
Service Approver (DoDAAC) N/A
Service Acceptor (DoDAAC)
W911PT
Accept at Other DoDAAC N/A
LPO DoDAAC N/A
DCAA Auditor DoDAAC N/A
Other DoDAAC(s) N/A
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) The Contractor shall ensure a receiving report meets the Receiving report.
requirements of DFARS Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
N/A
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
Section H - Special Contract Requirements
H._1_ SERVICES/CONSTRUCTION REQUIREMENTS
(a) SCHEDULE UNIT OF MEASURE NOTE: When "LOT" is stated as a unit of measure it is the equivalent to "JOB".
(b) WORK PERFORMED ON-SITE AT WATERVLIET ARSENAL:
The contractor agrees that each employee working at Watervliet Arsenal will sign the "Contractor Personnel Agreement on Non-Disclosure of Watervliet Arsenal Technology below. Signatures must be received by the Contract Administrator before work may begin and any resultant delay won't be considered an excusable delay to contract performance as defined in the contract clause "Default". Additional copies of this Non-Disclosure Statement can be found on the Internet at http://www.wva.army.mil/Documents/Contracting/nondis.pdf
(d) CONTRACTOR PERSONNEL AGREEMENT ON NON-DISCLOSURE OF WATERVLIET
ARSENAL TECHNOLOGY
(1) The Undersigned, as an employee of (Name of Firm) agrees to the following terms and conditions.
(2) Any knowledge gained, as a result of my being permitted on Watervliet Arsenal's premises, concerning cannon production technology (as defined below) or other technology on any defense item being manufactured or developed at Watervliet Arsenal, will not be released outside of (Name of firm) and/or the United States of America (this prohibition includes, but is not limited to, the company's domestic and foreign subsidiaries, affiliates, etc.), nor will such technology be used to manufacture or assist another in the manufacture of cannon (as described below) or other defense items being manufactured or developed at Watervliet Arsenal, without the written prior approval of Watervliet Arsenal.
(3) Definitions:
(a) CANNON: is defined as any and all components/parts of a complete assembly consisting of a tube, breech mechanism, tube attachments, muzzle appendages, firing mechanisms, and all integral components. It may also be a component of a weapons system of 40mm Bore or over such as tank guns, towed and self-propelled howitzers, naval guns, mortars and recoilless guns.
(b) CANNON PRODUCTION TECHNOLOGY: is defined as the technical data package and manufacturing technology.
(1) TECHNICAL DATA PACKAGE: cannon engineering drawings, specifications and standards.
(2) MANUFACTURING TECHNOLOGY: technical knowledge, documentation, assistance and equipment and machines used and/or useful in the manufacturing of cannon.
(c) TECHNICAL KNOWLEDGE: the know how collected, trade secrets, production experience and special skills necessary for the production of cannon and the technical information and inventions necessary for the manufacture of cannon and relating to the manufacture of cannon.
(d) TECHNICAL DOCUMENTATION: manufacturing technical data comprised of drawings, specifications, schemes, composition, descriptions, methods of calculations, instructions and other information necessary for the manufacture of cannon.
(e) TECHNICAL ASSISTANCE: all assistance required to make practical and economical use of the technology required to manufacture cannon, such as delivery of documentation, training of personnel, instructions, consultations and acquainting of specialists with the most economical method of using this technology in the manufacture of cannon.
(f) EQUIPMENT AND MACHINES: production machines, machine accessories, apparatuses, spare parts and tooling used for cannon manufacture.
TYPED OR PRINTED NAME SIGNATURE DATE
TYPED OR PRINTED NAME SIGNATURE DATE
TYPED OR PRINTED NAME SIGNATURE DATE
(e) JOB SITE AVAILABILITY:
The work site will be available for performance during normal business hours: Monday through Thursday Business Hours: 7:00 a.m. EST to 3:00 p.m. EST
Friday Business Hours: Every other Friday from 7:00a.m. EST to 2:00 p.m. EST
Fridays will be staggered with every other Friday being a closed business day.
The first Friday of 2026 to be closed is January 09, 2026.
Based on the above, service contractors should call contract/purchase order administrator in advance if service is scheduled for a Friday to determine if the Arsenal will be open for business.
When a federal holiday is normally observed on Friday, the Arsenal may be closed on the preceding Thursday. In this case, contact the contract/purchase order administrator in advance if scheduling service to determine if the Arsenal will be open for business. Work at other than the above hours won't be allowed unless the contractor makes an application at least 48 hours in advance and gets written contracting officer approval. No guarantee is made that the job site will be made available other than as stated above.
(f) CONTROL OF FOREIGN VISITORS TO WATERVLIET ARSENAL:
Offerors are advised that any employee or representative of their company who is not a U.S.
citizen, (or is representing a foreign company) and is a U.S. citizen), planning on visiting the Watervliet Arsenal for the purpose of attending: bid conferences, bid openings, site visits, engineering services, or any other visit related to this solicitation will be escorted at all times by an arsenal representative while on the installation grounds. Therefore, offerors must notify the Contracting Officer in advance (a minimum of two [2] weeks) of any proposed visit by a non-U.S.
citizen or U.S. citizen representing a foreign firm, to assure proper clearance for entry into the arsenal. Failure to comply, or disclose a foreign national visitor, may subject the Contractor to the penalties set forth in 18 U.S.C.A. Section 1001, Chapter 14.
Due to manpower constraints, Watervliet Arsenal is often unable to provide escort services during contract performance. Therefore, if the resulting contract requires performance on Watervliet Arsenal property, employees, individuals or subcontractors representing the successful offeror who are not U.S. citizens may not, depending on staffing levels and the availability of escorts, be allowed access to the Arsenal for purpose of contract performance. Be further advised that the inability of the Arsenal to provide escorts resulting in denial of access to Watervliet Arsenal of the aforementioned personnel will not be considered an excusable delay to contract performance as defined in the contract clause "Default" contained in the contract. Therefore, offerors should consider the above contingencies during offer preparation.
(h) CONTRACTOR IDENTIFICATION:
Contractor employees shall identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. In addition, contractor personnel shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence, and when working in situations where their actions could be construed as official government acts.
*** END OF NARRATIVE ***
*** END OF NARRATIVE ***
Section I - Contract Clauses
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.
2017-01
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Deviation 2026-O0038)
2026-02
52.204-13 System for Award Management- Maintenance. (Deviation 2026- O0038)
2026-02
52.204-19 Incorporation by Reference of Representations and Certifications.
2014-12
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Deviation 2026- O0038)
2026-02
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.
(Deviation 2026-O0038)
2026-02
52.219-6 Notice of Total Small Business Set-Aside. (Deviation 2026- O0038)
2026-02
52.222-3 Convict Labor. (Deviation 2026- O0038)
2026-02
52.222-6 Construction Wage Rate Requirements. (Deviation 2026- O0038)
2026-02
52.222-7 Withholding of Funds. (Deviation 2026-O0038)
2026-02
52.222-8 Payrolls and Basic Records.
(Deviation 2026-O0038)
2026-02
52.222-9 Apprentices and Trainees.
(Deviation 2026-O0038)
2026-02
52.222-10 Compliance with Copeland Act Requirements. (Deviation 2026- O0038)
2026-02
52.222-11 Subcontracts (Labor Standards).
(Deviation 2026-O0038)
2026-02
52.222-12 Contract Termination-Debarment. 2014-05
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.
2014-05
52.222-14 Disputes Concerning Labor Standards. (Deviation 2026- O0038)
2026-02
52.222-15 Certification of Eligibility. 2014-05
52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation 2026- O0038)
2026-02
52.222-50 Combating Trafficking in Persons. (Deviation 2026-O0038)
2026-02
52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation 2026-O0038)
2026-02
52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation 2026- O0038)
2026-02
52.223-5 Pollution Prevention and Right-to- Know Information.
2024-05
52.223-23 Sustainable Products. (Deviation 2026-O0038)
2026-02
52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.
2024-05
52.228-2 Additional Bond Security. 1997-10
52.228-5 Insurance-Work on a Government Installation.
1997-01
52.228-11 Individual Surety-Pledge of Assets.
2021-02
52.228-12 Prospective Subcontractor Requests for Bonds.
2022-12
52.228-14 Irrevocable Letter of Credit. 2014-11
52.232-8 Discounts for Prompt Payment. 2002-02
52.232-33 Payment by Electronic Funds Transfer-System for Award Management.
2018-10
52.232-39 Unenforceability of Unauthorized Obligations.
2013-06
52.232-40 Providing Accelerated Payments to Small Business Subcontractors.
2023-03
52.233-3 Protest after Award. (Deviation 2026-O0038)
2026-02
52.233-4 Applicable Law for Breach of Contract Claim. (Deviation 2026- O0038)
2026-02
52.236-5 Material and Workmanship.
(Deviation 2026-O0038)
2026-02
52.236-7 Permits and Responsibilities.
(Deviation 2026-O0038)
2026-02
52.240-91 Security Prohibitions and Exclusions. (Deviation 2026- O0038)
2026-02
52.242-14 Suspension of Work. 1984-04
52.243-5 Changes and Changed Conditions. (Deviation 2026- O0038)
2026-02
52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation 2026-O0038)
2026-02
52.246-21 Warranty of Construction. 1994-03
52.249-4 Termination for Convenience of the Government (Services) (Short Form).
1984-04
DFARS Clauses Incorporated by Reference
Date
Alternate Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials.
2011-09
252.203-7002 Requirement to Inform Employees of Whistleblower Rights.
2022-12
252.204-7003 Control of Government Personnel Work Product.
1992-04
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.
2024-05
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.
2023-01
252.204-7022 Expediting Contract Closeout. 2021-05
252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials.
2014-09
252.225-7048 Export-Controlled Items. 2013-06
252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.
2023-01
252.225-7060 Prohibition on Certain 2023-06
Procurements from the Xinjiang Uyghur Autonomous Region.
252.225-7972 Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems. (DEVIATION 2024-O0014)
2024-08 Deviation 2024- O0014
2024-08
252.232-7010 Levies on Contract Payments. 2006-12
252.240-7997 NIST SP 800-171 DoD Assessment Requirements.
(DEVIATION 2026-O0025)
2026-02 Deviation 2026- O0025
2026-02
252.243-7001 Pricing of Contract Modifications. 1991-12
252.244-7999 Subcontracts for Commercial Products or Commercial Services. (DEVIATION 2026- O0015)
2026-02 Deviation 2026- O0015
2026-01
252.247-7023 Transportation of Supplies by Sea.
2024-10
FAR Clauses Incorporated by Full Text
Date
Alternate Deviation
Variation Effective Date
52.219-28 Postaward Small Business Program Rerepresentation.
(Deviation 2026-O0038)
2026-02
Postaward Small Business Program Rerepresentation (Feb 2026) (Deviation 2026-O0038)
(a) . As used in this clause-Definitions
Long-term contract means a contract of more than five years in duration, including options.
However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern-
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
(2) , as used in this definition, means business concerns, one of whom directly or Affiliates indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts-
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document /support--table-size-standards.
(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-
(1) Was set aside for small business and has a value above the simplified acquisition threshold;
(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or
(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
(1) The Contractor represents that it is, is not a small business concern under NAICS Code assigned to contract number.238290 ____
(2) [Complete only if the Contractor represented itself as a small business concern in paragraph .] The Contractor represents that it is, is not, a small disadvantaged (g)(1) of this clause business concern as defined in .13 CFR 124.1001
(3) . The Women-owned small business (WOSB) joint venture eligible under the WOSB Program Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique entity ____ identifier of each party to the joint venture: __.]
(4) . The Economically disadvantaged women-owned small business (EDWOSB) joint venture Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique entity ____ identifier of each party to the joint venture: __ .]
(5) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under the . The Contractor represents that it is, is not an SDVOSB joint venture eligible SDVOSB Program under the SDVOSB Program that complies with the requirements of 13 CFR 128.402. [ The ____ Contractor shall enter the name and unique entity identifier of each party to the joint venture:
(6) [ HUBZone joint venture eligible under the HUBZone Program. Complete only if the offeror is ] The offeror represents, as part of its offer, that It is, is not a HUBZone small business concern.
a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c).
[ The Contractor shall enter the name and unique entity identifier of each party to the joint ____ venture: .] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [ Contractor to sign and date and insert ____ authorized signer's name and title.]
(End of clause)
52.225-9 Buy American-Construction Materials. (Deviation 2026- O0038)
2026-02
Buy American-Construction Materials (Feb 2026) (Deviation 2026-O0038)
(a) . As used in this clause-Definitions
Commercially available off-the-shelf (COTS) item-
(1) Means any item of supply (including construction material) that is-
(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.
However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means-
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if-
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States.
Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
None
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical .components
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A) of this clause.(1)
(3) The procedures in paragraph (b)(3)(i)(A) of this clause will no longer apply as of January (2) 1, 2030.
(B) .For domestic construction material that is a critical item or contains critical components
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3) (i)(B) of this clause.(1)
(3) The procedures in paragraph (b)(3)(i)(B) of this clause will no longer apply as of January (2) 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)
(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.
(d) . To permit evaluation of requests under paragraph (c) of this clause based on Data unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity Price (dollars)*
Item 1:
Foreign construction material.
Domestic construction material.
Item 2:
Foreign construction material.
Domestic construction material.
[* Include all delivery costs to the construction site and any applicable duty (whether or not a ].duty-free entry certificate is issued)
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of ]response; if oral, attach summary.
[ ]Include other applicable supporting information.
(End of clause)
52.228-15 Performance and Payment Bonds-Construction (Deviation 2020-O0016)
2020-06 Deviation 2020- O0016
2020-04
PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (APR 2020) (DEVIATION 2020-
O0016)
(a) Definitions. As used in this clause-
Original contract…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .