EWCP Industry Day Slides.pdf
PDF 4 MB Posted
- Attached to
- Industry Day - Information Session on the Emergency Water Conveyance Prototype (EWCP), Juneau, Alaska
- Solicitation number
- W911KB26RWP02_INDUSTRY
About this file
This document is an Industry Day presentation for the U.S. Army Corps of Engineers (USACE) Emergency Water Conveyance Prototype (EWCP) project located in Juneau, Alaska, held on 21 August 2026. The project aims to develop a concept, design, and construct a prototype system to protect the Mendenhall Valley from glacier lake outburst floods (GLOFs) originating from Suicide Basin. The primary objective is to prevent water levels in the Suicide Basin Glacier Dammed Lake from rising above 1,100 feet (NAVD88) and to continuously manage peak discharge rates of approximately 1,000 cubic feet per second to protect downstream communities.
The acquisition will be conducted as an Other Transaction (OT) Agreement for a prototype project utilizing a Progressive Design-Build (PDB) delivery method under the authority of 33 U.S.C. § 2313. The acquisition timeline includes: white papers due 4 September 2026; pitch presentations 28-30 September 2026; post-selection Phase 1 proposal due 21 October 2026; OT Phase 1 services negotiation 29-30 October 2026; revised Phase 1 proposal due 4 November 2026 at 2:00 PM; and OT Agreement award on 11 December 2026. Questions must be submitted through the ProjNet Suite Bidder Inquiry System (Solicitation Number W911KB-27-9-A001, Bidder Inquiry Key CXJ4M5-6EBBZZ) by 28 August 2026 at 2:00 PM AKDT. The project is led by USACE Alaska District with oversight from Pacific Ocean Division and USACE Headquarters.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EWCP Industry Day Registration.pdf | ||
| EWCP Sign-In Sheets.pdf | ||
| EWCP Industry Day.mp4 | MP4 file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. ARMY CORPS OF ENGINEERS
Emergency Water Conveyance Prototype (EWCP) Juneau, Alaska
Industry Day 21 August 2026
Agenda
• Welcome & Introductions
• Problem Statement
• Objective
• Technical Background
• Acquisition Approach
• Questions
Welcome
We are honored to gather here on Lingít Aaní, in Dzántik'i Héeni, and the unceded territory of the Áakʼw Ḵwáan. We acknowledge that Lingít Peoples have been stewards of these lands and waters since time immemorial.
Introductions Pacific Ocean Division
• Jose Sanchez – Engineering & Business Director
USACE HQ
• Dr. Georgette Hlepas – Principle Geotechnical Engineer Alaska District
• James Sauceda – Chief, Engineering Division
• Curtis Lee – Project Manager
• Mike Records – Technical Lead
• Michelle Nelsen – Agreements Officer
• Jennifer Gosh – Agreements Specialist
Problem Statement
Develop a concept, design, and construct a new Emergency Water Conveyance Prototype (EWCP) to protect the Mendenhall Valley from the severe and escalating flood hazard from glacier lake outburst floods (GLOFs) originating from Suicide Basin.
Objective Prevent water levels in the Suicide Basin Glacier Dammed Lake (GDL) from reaching an elevation sufficient to produce an impactful GLOF event.
• Prevent water levels in the Suicide Basin GDL from rising above an elevation of 1,100 feet (NAVD88) .
• Continuously manage peak discharge rates of approximately 1,000 cubic feet per second (CFS) to protect downstream communities.
Technical Background:
Glacier Lake Outburst Floods (GLOFs)
Technical Background:
Glacier Dammed Lakes (GDLs)
Example #1: Snow GDL
Example #2: Lake No Lake GDL Suicide Basin GDL
Technical Background: Location Overview
Regional Overview
Mendenhall Gl.
Mendenhall Lake
Mendenhall Valley
Suicide Glacier
Suicide Basin
Mendenhall Valley Suicide Basin
Nugget Cr.
Bullard Mtn.
Bullard Mountain
Mendenhall Lake
Nugget Creek
Technical Background: Flood Routing
Ice Dam
Technical Background: Video Tour
Acquisition Approach
• Other Transaction (OT) Agreement for a Prototype Project
• Progressive Design-Build (PDB) Delivery Method
• Authority for Award: 33 U.S.C. § 2313
Anticipated Acquisition Timeline
• Step 1: White Papers Due: 4 September 2026
• Step 2: Pitch Presentations: 28-30 September 2026
• Post-Selection Phase 1 Proposal Due: 21 October 2026
• Negotiate OT (Phase1) Services: Tentative: 29-30 October 2026
• Revised Phase 1 Proposal Due: 4 November 2026, 2:00 PM
• Award OT Agreement: 11 December 2026
Questions
• Submit questions to ProjNet Suite Bidder Inquiry System at https://www.projnet.org/projnet.
• Solicitation Number: W911KB-27-9-A001
• Bidder Inquiry Key: CXJ4M5-6EBBZZ
• Questions Due: 28 August 2026, 2:00 PM AKDT https://www.projnet.org/projnet
| U.S. Army Corps of Engineers |
| Agenda |
| Welcome |
| Introductions |
| Problem Statement |
| Objective |
| Technical Background: �Glacier Lake Outburst Floods (GLOFs) |
| Technical Background: �Glacier Dammed Lakes (GDLs) |
| Technical Background: Location Overview |
| Technical Background: Flood Routing |
| Technical Background: Video Tour |
| Acquisition Approach |
| Slide Number 13 |
| Anticipated Acquisition Timeline |
| Questions |