W911KB25RA006-0002 Port of Nome Modification Phase 1A.pdf

PDF 12 MB Posted

Attached to
PORT OF NOME MODIFICATION PHASE 1A, NOME, ALASKA
Solicitation number
W911KB25RA006
Issued by

About this file

This document is a preproposal conference presentation for the Port of Nome Modification Phase 1A project, a U.S. Army Corps of Engineers construction contract in Nome, Alaska. The project involves extending the existing causeway by 1,200 feet, incorporating an 18-ton armor stone embankment with a 30-foot wide road surface, and constructing a 600-foot open-cell sheet pile dock. The estimated contract value ranges from $250-$500 million, with a solicitation (W911KB25RA006) set for advertisement on 28 February 2025 and proposals due on 14 April 2025.

Key project details include a multi-phase port modification plan spanning several years, with Phase 1A focusing on the West Causeway Extension. The project requires complex environmental considerations, including marine mammal protection, water quality management, and essential fish habitat preservation. Environmental coordination involves multiple agencies such as NOAA, NMFS, USFWS, and ADEC, with over 100 environmental and cultural resource stipulations. The project aims to improve maritime infrastructure in the Arctic, providing critical support for 60 regional communities and addressing navigation limitations in the region.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

a. The following drawings are substituted for the superseded documents/sections:

None

b. The following revised documents/sections are substituted for the superseded documents/sections. The identifier “AM#0002” appears before and after new and/or revised materials, except as noted below.

NOTE: Revisions within the following documents do not contain the above referenced identifiers:

- Section 00 00 00 - Procurement and Contracting Requirements

Revised Proposal Due Date

- Section 00 20 00 - Instructions for Procurements

- FAR Clause 52.236-27 (Construction) Alternate 1 has been revised to incorporate a

Second Preproposal Conference

- Section 00 73 46 Revised Wage Determination

c. The following sections are deleted:

NONE

d. The following documents are added:

e. The following revisions are incorporated:

f. Other:

Power Point Slides and attendee List of 1st Preproposal Conference

(End of Summary of Changes)

ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME.

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

Response Due Date revised from 14 Apr 2025 to 28 Apr 2025

Section 00 20 00 - Instructions for Procurements

FAR Clauses Incorporated by Full Text

52.236-27 Site Visit (Construction). (Alternate I) (Feb 1995) Alternate I (Feb 1995)

Alternate I (Feb 1995). If an organized site visit will be conducted, substitute a paragraph substantially the same as the following for paragraph (b) of the basic provision:

(b) An organized site visit has been scheduled for

SECOND PREPROPOSAL CONFERENCE – 2 April 2025 at 2:00PM Alaska Time

(c) Participants will meet at JBER at the Arctic Warrior Event Center, 9387 Kuter Ave JBER, AK99506

For attendees who do not have access to JBER, please call or send an email with your Name (First, Last and MI), Drivers License or Passport #, State, and Date of Birth to tammy.davis@usace.army.mil and michelle.r.mandel@usace.army.mil to obtain a base access.

Provide information for base access no later than 12:00 Alaska Time on 28 April 2025.

For those that do not require a pass for base access, please send the name of attendees who will attend the Second

Preproposal Conference either in person or virtually by close of business on 28 March 2025.

Virtual - Microsoft Teams

Meeting ID: 993 764 301 913

Passcode: ds7Xd2nk

Dial in by phone

+1503-207-9433,,218791405

SECTION 00 73 46

WAGE DETERMINATIONS

"General Decision Number: AK20250001 03/14/2025

Superseded General Decision Number: AK20240001

State: Alaska

Construction Types: Building and Heavy

Counties: Alaska Statewide.

BUILDING AND HEAVY CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 |into on or after January 30, | generally applies to the |2022, or the contract is | contract.

|renewed or extended (e.g., an |. The contractor must pay |option is exercised) on or | all covered workers at |after January 30, 2022: | least $17.75 per hour (or

| | the applicable wage rate | | listed on this wage | | determination, if it is | | higher) for all hours | | spent performing on the | | contract in 2025.

|If the contract was awarded on|. Executive Order 13658 |or between January 1, 2015 and| generally applies to the |January 29, 2022, and the | contract.

|contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least |30, 2022: | $13.30 per hour (or the | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | hours spent performing on | | that contract in 2025.

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2025 1 01/31/2025 2 03/14/2025

ASBE0007-006 02/27/2023

Rates Fringes

Asbestos Workers/Insulator (includes application of all insulating materials protective coverings, coatings and finishings to all types of mechanical systems).........................$ 41.35 16.46

HAZARDOUS MATERIAL HANDLER

(includes preparation, wetting, stripping, removal scrapping, vacuming, bagging, and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 37.38 19.55

BOIL0502-002 01/01/2024

Rates Fringes

BOILERMAKER......................$ 51.08 33.04

BRAK0001-002 07/01/2023

Rates Fringes

Bricklayer, Blocklayer, Stonemason, Marble Mason, Tile Setter, Terrazzo Worker.....$ 42.01 19.20 Tile & Terrazzo Finisher.........$ 35.84 19.20

CARP1281-001 09/01/2024

Rates Fringes

CARPENTER

Including Lather and Drywall Hanging.............$ 48.54 26.32

CARP1281-002 09/01/2024

Rates Fringes

MILLWRIGHT.......................$ 55.42 27.08

CARP2520-003 09/01/2022

Rates Fringes

Diver Stand-by....................$ 47.65 28.32 Tender......................$ 46.65 28.32 Working.....................$ 87.45 28.32 Piledriver Piledriver; Skiff Operator and Rigger..................$ 38.34 26.51 Sheet Stabber...............$ 38.34 26.51 Welder......................$ 43.90 26.51

DEPTH PAY PREMIUM FOR DIVERS BELOW WATER SURFACE:

50-100 feet $1.00 per foot 101 feet and deeper $2.00 per foot

ENCLOSURE PAY PREMIUM WITH NO VERTICAL ASCENT:

5-50 FEET $1.00 PER FOOT/DAY

51-100 FEET $2.00 PER FOOT/DAY

101 FEET AND ABOVE $3.00 PER FOOT/DAY

SATURATION DIVING:

The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.

ELEC1547-004 09/01/2024

Rates Fringes

CABLE SPLICER....................$ 50.94 3%+28.24

ELECTRICIAN......................$ 50.94 3%+28.24

ELEC1547-005 04/01/2024

Line Construction

Rates Fringes

CABLE SPLICER....................$ 70.34 3%+32.54

Linemen (Including Equipment Operators, Technician)...........$ 68.59 3%+32.54 Powderman........................$ 66.59 3%+32.54

TREE TRIMMER.....................$ 41.32 3%+28.10

* ELEV0019-002 01/01/2025

ELEVATOR MECHANIC................$ 71.44 38.435+a+b

FOOTNOTE:

a. Employer contributes 8% of the basic hourly rate for over 5 year's service and 6% of the basic hourly rate for 6 months to 5 years' of service as vacation paid credit.

b. Eight paid holidays:

New Year's Day; Memorial Day; Independence Day;

Labor Day; Veteran's Day; Thanksgiving Day; Friday after Thanksgiving, and Christmas Day

ENGI0302-002 01/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 53.23 29.50

GROUP 1A....................$ 55.33 29.50

GROUP 2.....................$ 52.32 29.50

GROUP 3.....................$ 51.46 29.50

GROUP 4.....................$ 44.06 29.50

TUNNEL WORK

GROUP 1....................$ 58.55 29.50

GROUP 1A...................$ 60.86 29.50

GROUP 2....................$ 57.55 29.50

GROUP 3....................$ 56.60 29.50

GROUP 4....................$ 48.47 29.50

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Roller: Breakdown, Intermediate, and Finish; Back Filler; Barrier Machine (Zipper); Beltcrete with power pack and similar conveyors; Bending Machine;

Boat Coxwains; Bulldozers; Cableways, Highlines and Cablecars; Cleaning Machine; Coating Machine; Concrete Hydro Blaster; Cranes-45 tons and under or 150 foot boom and under (including jib and attachments): (a) Hydralifts or Transporters, all track or truck type,(b) Derricks;

Crushers; Deck Winches-Double Drum; Ditching or Trenching Machine (16 inch or over); Drilling Machines, core, cable, rotary and exploration; Finishing Machine Operator, Concrete Paving, Laser Screed, Sidewalk, Curb and Gutter Machine; Helicopters; Hover Craft, Flex Craft, Loadmaster, Air Cushion, All Terrain Vehicle, Rollagon, Bargecable, Nodwell, and Snow Cat; Hydro Ax: Feller Buncher and similar; Loaders (2 1/2 yards through 5 yards, including all attachments): Forklifts with telescopic boom and swing attachment, Overhead and front end, 2 1/2 yards through 5 yards, Loaders with forks or pipe clamps; Loaders, elevating belt type, Euclid and similar types; Mechanics, Bodyman; Micro Tunneling Machine; Mixers: Mobile type w/hoist combination; Motor Patrol Grader; Mucking Machines:

Mole, Tunnel Drill, Horizontal/Directional Drill Operator, and/or Shield; Operator on Dredges; Piledriver Engineers, L. B. Foster, Puller or similar Paving Breaker; Power Plant, Turbine Operator, 200 k.w. and over (power plants or combination of power units over 300 k.w.); Scrapers-through 40 yards; Service Oiler/Service Engineer; Sidebooms-under 45 tons; Shot Blast Machine; Shovels, Backhoes, Excavators with all attachments, and Gradealls (3 yards and under), Spreaders, Blaw Knox, Cedarapids, Barber Greene, Slurry Machine; Sub-grader (Gurries, Reclaimer, and similar types); Tack tractor; Truck mounted Concrete Pumps, Conveyor, Creter; Water Kote Machine; Unlicensed off road hauler

GROUP 1A: Camera/Tool/Video Operator (Slipline), Cranes-over 45 tons or 150 foot (including jib and attachments): (a) Clamshells and Draglines (over 3 yards),

(b) Tower cranes; Licensed Water/Waste Water Treatment Operator; Loaders over 5 yds.; Certified Welder, Electrical

Mechanic, Camp Maintenance Engineer, Mechanic (over 10,000 hours); Motor Patrol Grader, Dozer, Grade Tractor, Roto-mill/Profiler (finish: when finishing to final grade and/or to hubs, or for asphalt); Power Plants: 1000 k.w.

and over; Quad; Screed; Shovels, Backhoes, Excavators with all attachments (over 3 yards), Sidebooms over 45 tons;

Slip Form Paver, C.M.I. and similar types; Scrapers over yards;

GROUP 2: Boiler-fireman; Cement Hog and Concrete Pump Operator; Conveyors (except as listed in group 1); Hoist on steel erection; Towermobiles and Air Tuggers;

Horizontal/Directional Drill Locator;Licensed Grade Technician; Loaders, (i.e., Elevating Grader and Material Transfer Vehicle); Locomotives: rod and geared engines;

Mixers; Screening, Washing Plant; Sideboom (cradling rock drill regardless of size); Skidder; Trencing Machine under 16 inches; Waste/ Waste Water Treatment Operator.

GROUP 3: ""A"" Frame Trucks, Deck Winches: single power drum;

Bombardier (tack or tow rig); Boring Machine; Brooms-power;

Bump Cutter; Compressor; Farm tractor; Forklift, industrial type; Gin Truck or Winch Truck with poles when used for hoisting; Grade Checker and Stake Hopper; Hoist, Air Tuggers, Elevators; Loaders: (a) Elevating-Athey, Barber Green and similar types (b) Forklifts or Lumber Carrier (on construction job site) (c) Forklifts with Tower (d) Overhead and Front-end, under 2 1/2 yds.

Locomotives:Dinkey (air, steam, gas and electric) Speeders; Mechanics (light duty); Oil, Blower Distribution; Post Hole Diggers, mechanical; Pot Fireman (power agitated); Power Plant, Turbine Operator, under 200 k.w.; Pumps-water; Roller-other than Plantmix; Saws, concrete; Skid Steer with all attachments; Straightening Machine; Tow Tractor

GROUP 4: Rig Oiler/Crane Assistant Engineer;Parts and Equipment Coordinator; Swamper (on trenching machines or shovel type equipment); Spotter; Steam Cleaner; Drill Helper.

FOOTNOTE: Groups 1-4 receive 10% premium while performing tunnel or underground work. Rig Oiler/Crane Assistant Engineer shall be required on cranes over 85 tons or over 100 feet of boom.

IRON0751-003 07/01/2024

Rates Fringes

IRONWORKER

BENDER OPERATOR.............$ 44.99 38.98

BRIDGE, STRUCTURAL,

ORNAMENTAL, REINFORCING

MACHINERY MOVER, RIGGER,

SHEETER, STAGE RIGGER,

BENDER OPERATOR.............$ 44.99 38.98

FENCE, BARRIER INSTALLER....$ 41.49 38.98

GUARDRAIL INSTALLERS........$ 42.49 38.98

GUARDRAIL LAYOUT MAN........$ 42.23 38.98

HELICOPTER, TOWER...........$ 45.99 38.98

LABO0341-001 04/01/2024

Rates Fringes

LABORER (South of the 63rd Parallel & West of Longitude 138 Degrees)

GROUP 1.....................$ 38.25 33.11

GROUP 2.....................$ 39.25 33.11

GROUP 3.....................$ 40.15 33.11

GROUP 3A....................$ 44.28 33.11

GROUP 3B....................$ 50.11 29.06

GROUP 4.....................$ 27.82 33.11

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 42.08 33.11

GROUP 2....................$ 43.18 33.11

GROUP 3....................$ 44.17 33.11

GROUP 3A...................$ 48.71 33.11

GROUP 3B...................$ 55.12 29.06

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders;

Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting;

Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down;

Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down;

Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

LABO0942-001 04/01/2024

Rates Fringes

Laborers: North of the 63rd Parallel & East of Longitude 138 Degrees

GROUP 1.....................$ 38.25 33.11

GROUP 2.....................$ 39.25 33.11

GROUP 3.....................$ 40.15 33.11

GROUP 3A....................$ 44.03 33.11

GROUP 3B....................$ 49.61 29.06

GROUP 4.....................$ 27.82 33.11

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 42.08 33.11

GROUP 2....................$ 43.18 33.11

GROUP 3....................$ 44.17 33.11

GROUP 3A...................$ 48.43 33.11

GROUP 3B...................$ 54.57 29.06

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders;

Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting;

Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down;

Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down;

Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

PAIN1959-001 07/01/2024

NORTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

BRUSH/ROLLER PAINT OR WALL

COVERER.....................$ 40.33 26.17

TAPING, TEXTURING,

STRUCTURAL PAINTING,

SANDBLASTING, POT TENDER,

FINISH METAL, SPRAY,

BUFFER OPERATOR, RADON

MITIGATION, LEAD BASED

PAINT ABATEMENT, HAZARDOUS

MATERIAL HANDLER............$ 40.85 26.17

PAIN1959-002 07/01/2024

SOUTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

General Painter.............$ 35.97 28.52 Industrial Painter..........$ 37.32 28.52 Taper / Paper & Vinyl Hanger......................$ 37.22 28.52

PAIN1959-003 07/01/2024

NORTH OF THE 63RD PARALLEL

Rates Fringes

GLAZIER..........................$ 44.54 29.68

PAIN1959-004 07/01/2023

Rates Fringes

FLOOR LAYER: Carpet.............$ 39.86 15.87

PAIN1959-006 07/01/2024

SOUTH OF THE 63RD PARALLEL

Rates Fringes

GLAZIER..........................$ 45.20 28.32

PLAS0528-006 06/01/2024

PLASTERER

North of the 63rd parallel..$ 52.50 20.67 South of the 63rd parallel..$ 52.50 20.67

PLAS0528-007 04/01/2023

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

North of the 63rd parallel..$ 44.43 22.13 South of the 63rd parallel..$ 44.43 22.13

PLUM0262-002 01/01/2023

East of the 141st Meridian

Rates Fringes

Plumber; Steamfitter.............$ 41.50 27.62

PLUM0367-002 07/01/2021

South of the 63rd Parallel

Rates Fringes

Plumber; Steamfitter.............$ 41.00 27.95

PLUM0375-002 07/01/2024

North of the 63rd Parallel

Plumber; Steamfitter.............$ 51.66 32.90

PLUM0669-002 01/01/2025

Rates Fringes

SPRINKLER FITTER.................$ 56.61 31.39

ROOF0189-006 04/01/2024

Rates Fringes

ROOFER...........................$ 49.62 18.53

SHEE0023-003 07/01/2024

South of the 63rd Parallel

Rates Fringes

SHEET METAL WORKER...............$ 48.75 30.14

SHEE0023-004 07/01/2024

North of the 63rd Parallel

Rates Fringes

SHEET METAL WORKER...............$ 54.00 30.52

* TEAM0959-003 01/01/2025

Rates Fringes

TRUCK DRIVER

GROUP 1.....................$ 51.58 26.43

GROUP 1A....................$ 53.05 26.43

GROUP 2.....................$ 50.12 26.43

GROUP 3.....................$ 49.17 26.43

GROUP 4.....................$ 48.50 26.43

GROUP 5.....................$ 47.62 26.43

GROUP 1: Semi with Double Box Mixer; Dump Trucks (including rockbuggy and trucks with pups) over 40 yards up to and including 60 yards; Deltas, Commanders, Rollogans and similar equipment when pulling sleds, trailers or similar equipment; Boat Coxswain; Lowboys including attached trailers and jeeps, up to and including 12 axles; Ready-mix over 12 yards up to and including 15 yards); Water Wagon (250 Bbls and above); Tireman, Heavy Duty/Fueler

GROUP 1A: Dump Trucks (including Rockbuggy and Trucks with pups) over 60 yards up to and including 100 yards; Jeeps (driver under load)

GROUP 2: Turn-O-Wagon or DW-10 not self-loading; All Deltas, Commanders, Rollogans, and similar equipment; Mechanics;

Dump Trucks (including Rockbuggy and Trucks with pups) over 20 yards up to and including 40 yards; Lowboys including attached trailers and jeeps up to and including 8 axles;

Super vac truck/cacasco truck/heat stress truck; Ready-mix over 7 yards up to and including 12 yards; Partsman;

Stringing Truck

GROUP 3: Dump Trucks (including Rockbuggy and Trucks with pups) over 10 yards up to and including 20 yards; batch trucks 8 yards and up; Oil distributor drivers; Oil Distributor Drivers; Trucks/Jeeps (push or pull); Traffic Control Technician

GROUP 4: Buggymobile; Semi or Truck and trailer;

Dumpster;

Tireman (light duty); Dump Trucks (including Rockbuggy and Truck with pups) up to and including 10 yards; Track Truck Equipment; Grease Truck; Flat Beds, dual rear axle;

Hyster

Operators (handling bulk aggregate); Lumber Carrier;

Water Wagon, semi; Water Truck, dual axle; Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted ""A"" Frame manufactured rating over 5 tons; Bull Lifts and Fork Lifts with Power Boom and Swing attachments, over 5 tons; Front End Loader with Forks; Bus Operator over 30 passengers; All Terrain Vehicles; Boom Truck/Knuckle Truck over 5 tons; Foam Distributor Truck/dual axle; Hydro-seeders, dual axle;

Vacuum Trucks, Truck Vacuum Sweepers; Loadmaster (air and water); Air Cushion or similar type vehicle; Fire Truck/Ambulance Driver; Combination Truck-fuel and grease;

Compactor (when pulled by rubber tired equipment); Rigger (air/water/oilfield); Ready Mix, up to and including 7 yards;

GROUP 5: Gravel Spreader Box Operator on Truck; Flat Beds, single rear axle; Boom Truck/Knuckle Truck up to and including 5 tons; Pickups (Pilot Cars and all light duty vehicles); Water Wagon (Below 250 Bbls); Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted ""A"" Frame, manufactured rating 5 tons and under; Bull Lifts and Fork Lifts (fork lifts with power broom and swing attachments up to and including 5 tons); Buffer Truck; Tack Truck; Farm type Rubber Tired Tractor (when material handling or pulling wagons on a construction project); Foam Distributor, single axle; Hydro-Seeders, single axle; Team Drivers (horses, mules and similar equipment); Fuel Handler (station/bulk attendant); Batch Truck, up to and including 7 yards;

Gear/Supply Truck; Bus Operator, Up to 30 Passengers;

Rigger/Swamper

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the

EO

is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022- 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.

?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted.

ME

refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

1) Has there been an initial decision in the matter? This can be:

a) a survey underlying a wage determination

b) an existing published wage determination

c) an initial WHD letter setting forth a position on a wage determination matter

d) an initial conformance (additional classification and rate) determination

On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:

Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.

Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.)

that the requestor considers relevant to the issue.

3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210.

END OF GENERAL DECISION"

PORT OF NOME MODIFICATION,

NOME, AK

USACE Alaska District

Phase 1A – West Causeway Extension Preproposal Conference

Date: Tuesday, 11 March 2025

Time: 10:00 A.M.

CONTRACTING

CONTRACTING

• W911KB25A006 PORT OF NOME MODIFICATION PHASE 1A – Unrestricted, Fully Designed, FFP Construction Project

• Draft RFP:

https://sam.gov/opp/c88ec9ff2ce34385aca8b6661deee22c/view

• Estimated Magnitude is $250 - $500 Million

• Award will be based on Tradeoff process described in FAR 15.101-1 to determine the proposal which represents the best value to the Government. All evaluation factors, other than price, when combined, are approximately equal to price.

• Evaluation Factors will include Past Performance, Technical Approach, Project Execution/Schedule, Extent Of Participation Of Small Businesses, and Price.

• Proposal due date is 14 April 2025 https://sam.gov/opp/c88ec9ff2ce34385aca8b6661deee22c/view

PROPOSAL PACKAGE

• It shall be the contractor’s responsibility to check the Procurement Integrated Enterprise Environment (PIEE) website for the solicitation and any Amendments and to submit proposals.

• Read Section 00 21 00 Instructions, Conditions and Notices to Offerors

• Acknowledge all Amendments (SF1442)

• Small Business Subcontracting Plan – LG Businesses Upon request by the Contracting Officer for the apparently successful offeror

QUESTIONS

• Submit questions in writing to - Projnet The Bidder Inquiry System and they will be answered in the system and incorporated by amendments as needed - http://www.projnet.org/projnet

• The last day to submit questions will be no later than ten (10) calendar days prior to the proposal due date

• Important: Any remarks, comments, or explanations provided during the conference/site visit shall not change or qualify the terms and conditions of the solicitation or resultant contract. Changes can only be made by formal written amendment(s)

CITY OF NOME

TYPES OF VESSELS PORT OF NOME SERVES

COMMODITY MOVEMENT

TYPES OF VESSELS PORT OF NOME SERVES

SHIP RESUPPLY/CREW CHANGE

9Beyond the Breakwater 2023

10Beyond the Breakwater 2024 Tug/Towing Tanker Passenger/Pleasu rePort Tender Cargo Fishing Military/Law EnforcementResearch Dredging Icebreaker

11CONSTRUCTION ACCESS AND LAYDOWN

• Repair to pre-storm conditions.

• FEMA Funding.

• Awarded FEB 2025.

• Construction Complete NOV 2025.

CAPE NOME JETTY REPAIR

USACE – CIVIL WORKS

KEY STAKEHOLDERS

OVERVIEW OF PORT OF NOME MODIFICATION PROJECT

• First Corps’ construction on Harbor began in 1917.

• Port last upgraded in 2006 to -22 ft MLLW.

• Port Modification authorized for construction in WRDA

2020.

• Provides support to Nome users and regional communities utilizing Section 2006 of WRDA 2007.

• Allows navigation projects in Alaska to be justified based upon:

• Community Viability

• Public Health and Safety

• Access to Subsistence Resources

• Cultural Significance

• Feasibility Report March 2020.

• Design Agreement executed June 2021.

• Project Partnership Agreement executed January

2024.

• Phase 1A advertise date: 28 February 2025.

• Proposals due 14 April 2025.

Deep Water Basin

PROJECT PURPOSE AND OBJECTIVES

• United States only deep-water port in the Arctic.

• Provides a critical link with 60 communities and the rest of Alaska.

• The existing port facilities in the region are overcrowded and have insufficient draft to accommodate larger and deeper drafting vessel traffic.

• The proposed project objective is to improve support for multiple maritime missions: cargo transportation, search and rescue, emergency and oil spill response, natural resource exploration by:

• Reducing draft limitations to allow use by more efficient vessels.

• Increasing dock space to serve more vessels safely and to avoid delays.

• Increasing navigation area to allow for safe and efficient maneuvering of all vessels.

PORT OF NOME MODIFICATION PROGRAM

Phase 1A Phase 3Phase 2Phase 1B

West Causeway Extension 1,200 ft. Causeway 600 ft. Dock

Advertise: FEB 2025 Award: AUG 2025

East Causeway

2.410 ft. Causeway 800 ft. Dock 1,450 ft. Breakwater 130 ft. Causeway Bridge

Advertise: FY30 Award: FY30

Harbor Deepening -28 ft. MLLW Outer Basin -40 ft. MLLW Deepwater Basin

Advertise: MAY 2026 Award: SEP 2026

West Causeway Extension 2,284 ft. Causeway 1,870 ft. Dock

Advertise: FY28 Award FY28

PHASE 1A – WEST CAUSEWAY EXTENSION

Project:

• West Causeway Extension

• 1,200 ft. Causeway

• 600 ft. Dock

• Existing Spur removal

USACE DESIGN CAUSEWAY ARMOR STONE AND

DREDGING (VOLUME 1)

Removal of Spur Breakwater

WEST CAUSEWAY – VOLUME 1

600’ Sheet Pile Dock

1200’ Causeway Extension

Phase 1A (November 2024):

• 18T seaward armor stone, 1.5H:1V

• 13.5T harborside armor north of the dock

• 18T armor south of the dock

• Causeway width expanded to approximately 50 feet to accommodate utility corridor.

• Expanded width continued through nose sections to accommodate future phases. Head section shown below.

HARBOR DESIGN - SECTIONS

ANTICIPATED HAUL ROUTES

STAGING AREAS

PND DESIGN – DOCKS AND MOORINGS (VOLUME 2)

Extend Causeway and Roadway ~1,200’

(Phase 1A) New ~600’ OCSP

Dock Structure (Phase 1A)

Existing East Breakwater to Remain (Phase 1A)

Phase 1A

ADD IN OCSP CROSS SECTION FOR DISCUSSION

ANDREA IS WORKING THIS

Typical Causeway Cross Section at Dock

235’ Wide CausewayHigh Mast Foundation

X-WYE PILE

X-Wye Pile

• Similar to X-Pile

OCSP TEMPORARY SUPPORT

Reference Specification 35 31 16.19

OCSP STABILIZATION

Reference Specification 35 31 16.19

GEOTECH

• Geophysical Survey – Sub-Bottom Profiler and Magnetrometer

• 47 sub-surface objects (likely boulders). Possible areas of dense boulders identified (Fig. 27 of Geophysical Survey Report)

• 16 ferrous objects of interest,

• 1 within breakwater extension (OBJ-13)

• Geotechnical Investigation

• 16 borings

GEOTECHNICAL CONDITIONS

• General Soil Profile Along Breakwater I. Marine Sands II. Reworked Marine Sands and Till III. Glacial Till IV. Marine Sediments V. Glacial Rubble VI. Bedrock

• Medium-Dense Marine Sands ~10-13.5 ft thick

• Anticipate conventional dredging methods

GEOTECHNICAL CONDITIONS

ENVIRONMENTAL

Primary environmental issues affecting Phase IA:

• Harassment of marine mammals (primarily beluga whales and seals) by underwater noise (pile driving, etc.), dredging & fill, project vessel movement.

• Dredged/excavated material placement.

• Water quality (turbidity, spills and discharges).

• Subsistence access.

Environmental agency coordination documents:

• MMPA Incidental Harassment Authorization (IHA) – NOAA Marine Mammal Monitoring and Mitigation Plan (4MP) Plan of Cooperation (POC)

• ESA Biological Opinion – NMFS

• ESA Informal Consultation LOC – USFWS

• Essential Fish Habitat Consultation Letter – NMFS Habitat

• National Historic Preservation Act LOC – SHPO

• CWA Section 401 Certificate – ADEC

Over 100 project environmental and cultural resource stipulations; see USACE “Compilation of Environmental Mitigatory Measures”

Marine Mammal Monitoring & Mitigation Plan (4MP) - Establishes:

o Authorized take numbers o Mitigation zones

• Shutdown zones

• Harassment zones

• Assumed take zones o Observer roles and responsibilities

• Number and placement of PSOs depends on activity o Monitoring & mitigatory procedures

• Baseline monitoring o Data collection and reporting requirements

The IHA contains special monitoring requirements that are NOT included in the 4MP

Includes:

o Passive acoustic monitoring (PAM)

• For recording MM vocalizations and pile driving sound energy verification

• Acoustic Monitoring Plan to be approved by

NMFS 30 days prior to pile driving o Aerial overflights to assist in estimating species presence in far field during fender pile installation

Dredged Material Placement

Initial 6.5-acre on-shore site for up to 60K cy (if needed) Proposed 241-acre near shore beach nourishment site

Essential Fish Habitat o “To the extent practicable, the existing fish passages in the causeway and breakwater will be kept passable through removal of accumulated sediment as necessary”, especially during new rubblemound construction.

o “Rock for new rubblemound construction will be free of contaminants and invasive species. To the extent practicable, rock material removed from the existing rubblemound structures in the course of construction will be reused at the project site.”

o Reserve boulders and large cobbles from Phase 1 dredging and stockpile for future hard bottom habitat enhancement o “Reasonable precautions and controls must be used to prevent incidental and accidental discharge of petroleum products or other hazardous substances…” o “During construction, spill response equipment and supplies… shall be available and used immediately to contain and cleanup… pollutant spills. Any spill amount must be reported…” o “All dredging shall be conducted so as to minimize the amount of dredge material and suspended sediments that enter the Norton Sound. Appropriate Best Management Practices (BMPs) will be employed...”

o Etc.

Water Quality (CWA Sec 401 WQ Certification)

CLOSE OUT

Temporary End Protection Plan :

1.5 TEMPORARY END PROTECTION PLAN (TEP)

Section lays out the requirement for protecting incomplete sections of causeway and sheetpile for delay of 30 calendar days, seasonal shutdown or for any other reason. This will be contractor design and constructed.

CAMP Facilities:

1.12 CAMP FACILITIES

There are no Government owned camp facilities at the job site for the Contractor's use.

1.12.1 Required Workforce Camp

Provide temporary housing for non-resident contractor and subcontractor employees. Utilization of housing existing prior to the contract award date is prohibited. Upon completion of the project, remove temporary housing established for the contract. Any temporary fill used for these facilities shall be removed and placed in accordance with local, state, and federal regulations.

Questions:

Michelle.R.Mandel@usace.army.mil Tammy.Davis@usace.army.mil

CLOSE OUT

REF.

SPECIFICATIONS

• CAMP FACILITIES

• TEP

• 01 19 40.00 29 mailto:Michelle.R.Mandel@usace.army.mil mailto:Tammy.Davis@usace.army.mil

1st Preproposal Attendance Roster -

Blake Sylvie – Dutra Group

Kento Tanase – Glosten

Brent Deener – Manson Construction

Mike Coolige – St Fabrication

Sherman Leifer – Ram Industrial

PoNM_Phase 1A_PreProposalConference_20250311.pdf
Port of nome modification, nome, ak
Contracting
Contracting
Proposal package
QUESTIONS
City of Nome
Types of vessels port of nome Serves
Types of vessels port of nome Serves
Slide Number 9
Slide Number 10
Construction access and laydown
Cape Nome Jetty repair
USACE – Civil works
Key stakeholders
Overview of Port of Nome Modification Project
Project Purpose and Objectives
Port of Nome Modification Program
Phase 1A – West causeway extension
Usace design causeway armor stone and dredging (volume 1)
West Causeway – Volume 1
Slide Number 21
Anticipated haul routeS
Staging AREAS
Pnd Design – docks and moorings (volume 2)
Slide Number 25
Add in OCSP cross section for discussion�Andrea is working this
X-Wye Pile
OCSP Temporary Support
OCSP Stabilization
geotech
GeotechNICAL CONDITIONS
GeotechNICAL CONDITIONS
Environmental
Environmental
Environmental
Environmental
ENVIRONMENTAL
Close Out
Close out