B.08.03 PFAS Soil Washing Amendment 0003.pdf
PDF 758 KB Posted
- Solicitation number
- W911KB22R0030
About this file
This solicitation requests proposals for the treatment and disposal of approximately 130,000 cubic yards of per- and polyfluoroalkyl substances (PFAS) contaminated soil at Eielson Air Force Base in Alaska. Soil treatment shall utilize soil washing on site to separate soil fractions and ensure sand and gravel components meet target cleanup levels for PFAS under Alaska regulations. Post-treatment sampling is required to verify compliance. Treated soil will be placed on base at an approved location. Offerors must submit proposals through the Procurement Integrated Enterprise Environment system by 2:00 PM AKST on August 12, 2022. This acquisition is a competitive total small business set-aside. The contract is subject to availability of funds, and the project may be cancelled or revised at any time prior to award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.08.03 PFAS Soil Treatment Amendment 0004.pdf | ||
| Bidder Inquiry Report.pdf | ||
| EAL_Template_MAY_22.xlsx | XLSX spreadsheet | |
| Soil Washing_Sum2022_V32-3_P151.pdf | ||
| F-0249 Eielson PFAS TS Report_FINAL_May-2019.pdf | ||
| B.08.03 PFAS Soil Washing Amendment 0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911KB22R0030
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
PFAS Soil Washing Treatment, Eielson Air Force Base, Alaska
a. The purpose of this Amendment is to include changes in Section C, Section L and Section M as w ell as other items stated on the Summary of Changes.
b. The proposal due date HAS changed. Please submit your proposal by 2:00 PM AKST on 12 August 2022 in PIEE Solicitation in accordance w ith Section L, paragraph 1.8, Proposal Submittals.
POC for this amendment is Angela Padua, angela.padua@usace.army.mil
1. CONTRACT ID CODE PAGE OF PAGES
1 75
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Jul-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB22R0030
X 9B. DATED (SEE ITEM 11)
06-Jul-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Jul-2022
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
2204 TALLEY AVENUE
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
a. The following drawings are substituted for the superseded documents/sections:
NONE
b. The following drawings are added:
c. The following revised documents/sections are substituted for the superseded documents/sections: The identifier “AM#0003” appears before and after new and/or revised materials as noted below
SECTION C
--Revised Schedule paragraph.
--Revised Authority and Points of Contact paragraph
SECTION L
--Revised Proposal Submittal language
--Included paragraph 1.4.1.6. for offerors site visit
--Included paragraph 1.11 Notes
SECTION M
--Revised Factor 1: Technical Approach – Evaluation and Basis of Award paragraph
--Revised Factor 2: Key Personnel – Evaluation and Basis of Award paragraph
--Revised Factor 3: Past Performance (Confidence Assessment) – Proposal Submittal paragraph
--Revised Factor 3: Past Performance (Confidence Assessment) – Evaluation and Basis of Award paragraph
--Revised Factor 4: Price Proposal paragraph
--Revised Evaluation of Offerors and Basis of Award
d. The following sections are deleted:
Section C
--Removed Contractor Manpower Reporting paragraph
--Removed Proposal Submittal language and moved it to Section L
Section L
--Removed Contract Estimated Magnitude
--Removed Buy American Act for Construction Materials
e. The following documents are added:
--Attachment 1 Offeror Experience – Prime Contractor
--Attachment 2 Past Performance Questionnaire (PPQ)
--Attachment 3 Key Personnel Resume
--EAL_Template_MAY_22.xlsx
--Bidder Inquiry
--F-0249 Eielson PFAS TS Report_FINAL_May-2019.pdf
--Soil Washing_Sum2022_V32-2_P151.pdf
f. Other:
(End of Summary of Changes)
SECTION B - SUPPLIES OR SERVICES AND PRICES
PWS BID SCHEDULE
PROPOSAL SCHEDULE
Item Estimated Unit
No. Description Quantity Unit Price Amount
0001. Project Management 1 Job $________ $________ and Work Plan
0002. Treatment of Soil 1 Job $________ $________
Stockpiles from EIE405
0003. Treatment of Soil 1 Job $________ $________
Stockpiles from EIE384
0004. Treatment of Soil 1 Job $________ $________
Stockpiles from EIE386
Base Total: $____________________
0005. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE376
0006. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE365
0007. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE378
0008. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE382
0009. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE420
0010. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE377
0011. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE379
0012. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE385
0013 OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE388
0014. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE389
0015. OPTIONAL Treatment of Soil 1 Job $________ $________
Stockpiles from EIE393
0016. OPTIONAL EE/CA and AM 1 Job $________ $_________
0017. OPTIONAL Treatment of 50 Job $________ $________
Additional 1000CY
0018. OPTIONAL Additional Soil 40 Job $________ $________
Washing Pass per 1000 CY
0019. OPTIONAL Disposal of Fines 50 Job $________ $________ per 1000 ton
0020. INCENTIVES 10% of Reduction 1 Each $________ $________ in Disposal Costs
Option Total: $____________________
Base + Option Total: $____________________
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
PERFORMANCE WORK STATEMENT
RFP Notes: Subject to Availability of Funds. Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.
Treatment and Disposal of PFAS Contaminated Soil Stockpiles
Multiple Projects
Eielson Air Force Base, Alaska
Performance Work Statement
1 July 2022
Revision AM#0001 12 July 2022
Revision AM#0003 28 July 2022
GENERAL
The objective of this performance work statement (PWS) is to treat and dispose of poly-and perfluoroalkyl substances (PFAS) contaminated soil that is currently stockpiled at Eielson Air Force Base (EAFB), Alaska. The work shall be conducted in compliance with 18 Alaska Administrative Code (AAC) 75 Oil and Other Hazardous
Substances Pollution Control and all other applicable federal, state, and local regulations. The Contractor shall be responsible for identifying and complying with the applicable federal, state, and local regulations that will affect this contract.
The Contractor shall be responsible for fully executing this PWS under a Performance-Based Acquisition (PBA).
This shall be accomplished by conducting required environmental services for which the United States Air Force
(USAF) is statutorily responsible. The Contractor shall address all environmental, scheduling, and regulatory issues, and assume contractual liability and responsibility for the achievement of the performance objectives for contaminated soil treatment or disposal.
The Contractor shall, in accordance with the terms and conditions more particularly set forth below, furnish all labor, management, facilities, supplies, equipment, transportation, and material (other than those to be furnished by the Government as hereinafter provided), and do all things necessary for, or incidental to, performance of the work as set forth below. The Contractor shall furnish to the Government plans, reports, and other data together with supporting material developed during the period of performance. During the progression of the work, the Contractor shall provide adequate professional supervision and quality control to assure the accuracy, quality, completeness, and progress of the work. Work will be conducted with coordination with: United States Army Corps of Engineers
(USACE), USAF, Air Force Civil Engineering Center (AFCEC), Alaska Department of Environmental
Conservation (ADEC), United States Environmental Protection Agency (USEPA), and other stakeholders, as required. All work shall be performed in accordance with the guidance documents listed in Section 0.
BACKGROUND
EAFB occupies approximately 19,700 acres in the Tanana Valley Flood Plain of interior Alaska. The property includes 3,650 improved acres along with forest, ponds, and wetlands. Over 3,000 people work at the installation, and it is home to over 3,200 active-duty personnel and their families. The 354th Fighter Wing (Wing) is the host unit at EAFB and is assigned to the 11th Air Force. The 11th Air Force falls under the Pacific Air Force (PACAF), headquartered at Joint Base Elmendorf-Richardson (JBER), Alaska. The Wing supports operations, maintenance, mission support, and medical group functions and is host to ten tenant units. Stakeholders include residents of
EAFB; the towns of Salcha, Moose Creek, and North Pole; state and federal natural resource agencies; USEPA; and
ADEC.
In 2016, the USAF announced that it would locate two squadrons of F35A fighter planes at Eielson Air Force Base in interior Alaska. The bed down of these planes required the construction of numerous facilities and infrastructure over the past 4 years, with each project involving varying amounts of soil excavation to support building foundations, site grading, and utility installation. Most of the new facilities are in an area of the installation with known environmental impacts from PFAS, including perfluorooctane sulfonate (PFOS) and perfluorooctanoic acid
(PFOA). To avoid delay to the construction projects, the USAF developed an approach for the on-base management and stockpiling of potentially impacted soils. This approach was approved through the 2018 F-35 Programmatic
Quality Assurance Program Plan (QAPP) Work Plan (USAF 2018). Additional documents associated with EAFB can be found on the administrative record webpage: https://ar.afcec-cloud.af.mil/.
Soils from fourteen (14) construction projects have been placed in stockpiles at the long-term storage area (Landfill
#3 or the adjacent contingency areas) on EAFB. Soil from thirteen (13) construction projects are included in this solicitation. Soil volumes are approximate, all soils associated with an awarded project shall be treated/disposed regardless of actual quantities. The stockpile survey data are included in a comprehensive characterization report
(AFCEC 2021) provided as Government Furnished Information (GFI).
Table 1: Soil Stockpile Volume by Construction Project
Project name
Air Force
MILCON
Project
Number
USACE
ID
PFAS and/or
PFAS/POL
Contaminated
Soil (CY)
Uncontaminated
Soil (CY)
Total
Volume
(CY)
Flight Simulator FTQW163011 EIE365 6,244 0 6,244
Hangar and Propulsion
Dispatch
FTQW170106 EIE376 4,606 0 4,606
ADAL FTD Facility1 FTQW170100 EIE377 715 0 715
FY17 F-35 Aircraft Weather
Shelters (Sqd 1)
FTQW170112 EIE378 37,448 555 38,003
Hangar/Squad Ops/AMU1 FTQW170114 EIE379 423 0 423
FY17 F-35A Weather Shelter
(Sqd 2)
FTQW183001 EIE382 47,710 1,844 49,554
FY18 F-35A AGE Facility/
Fillstand
FTQW180103 EIE384 10,360 0 10,360
OSS/ Weapons/ Intel Fac1 FTQW180102 EIE385 318 0 318
FY18 F-35A Consolidated
Munitions Admin
FTQW180107 EIE386 5,764 0 5,764
R-11 Fuel Truck Shelter1 FTQW180105 EIE388 963 0 963
FY18 F-35A Satellite Dining
Facility1
FTQW180106 EIE389 514 0 514
FY18 F-35A Extended
Utiliduct to South Loop
FTQW180111 EIE405 4,384 0 4,384
Repair Alpha through Delta
Row Aprons Phase II
FTQW190501 EIE420 10,841 1,132 11,972
Total 130,290 3,531 133,820
Stockpile volumes in Cubic Yards (CY)
Note 1: Projects were included in 2021 Soil Disposal contract and volumes are estimated.
Representative soil samples were collected from each stockpile for chemical analysis and physical property evaluation in accordance with the 2018 F-35 Programmatic QAPP and/or the 2020 Project-Specific Work Plan and
Uniform Federal Policy (UFP) QAPP for F-35 Soil Stockpiles Characterization Sampling (AFCEC 2020). The results are summarized in a comprehensive characterization report (AFCEC 2021). The soil concentrations exceed the 18 AAC 75.341 Table B1 Migration to Groundwater (MTGW) cleanup levels for PFOS, PFOA, and other contaminants (primarily polycyclic aromatic hydrocarbons (PAHs) and pesticide in soil stockpile EIE 405-3. The contractor shall segregate each stockpile based on the results of the characterization report, ensuring segregation of contaminated from uncontaminated soil, and propose an appropriate strategy to address each category of soil.
Uncontaminated and treated soil can be placed on the installation at a pre-approved location (assume within 7 miles of stockpile location).
Table 2: Target Cleanup Levels for Stockpiled Soil
Category Regulatory Criteria
PFOS/PFOA and/or PFOS/PFOA/OTHER
Contaminated Soil
18 AAC 75.341 Table B1 (MTGW) for PFOS, PFOA, and other contaminants
Soil Below ADEC Clean Up Levels 18 AAC 75.341 Tables B1 and B2 (MTGW)
PERFORMANCE OBJECTIVES AND STANDARDS
The USACE Alaska District is requesting environmental services as described in this PWS. The Contractor shall be required to furnish all labor, materials, and equipment necessary to meet the performance objectives and standards identified in Table 3 below. Unless noted otherwise, indicated delivery deadlines are assumed to be calendar days.
Table 3: Performance Requirements Summary
Performance Objective Performance Measure
TASK 1: Project Management and Work Plan
Pre-Draft Work Plan UFP-QAPP, Soil Treatment
Plan (STP), Waste Management Plan (WMP), Accident Prevention Plan (APP), etc.) within 75 calendar days of Task Order award
Draft Work Plan within 15 calendar days of resolving USACE and USAF comments
Final Work Plan within 15 calendar days of resolving regulatory comments on the draft
Meetings Scheduled as indicated and needed
Draft and Final Meeting agenda/notes submitted on time
Pre-Draft: Submitted on time and sufficient detail/quality to allow USACE and UAF review.
Draft: USACE and USAF approval through Contracting
Officers Representative (COR).
AM#0001…
Draft-Final: Regulatory Approval.
Final: USAF, USACE, and Regulatory Approval.
…AM#0001
TASK 2-15 and 17: Treatment of Stockpiles
Treatment/disposal of PFAS and/or PFAS/other contaminated soil (volume specified in Table 1)
Segregate from contaminated soil, and transport and place uncontaminated and treated soil on the installation (volume specified in Table 1)
Site restoration
Pre-Draft Closure Report within 30 days of receipt of final analytical results and disposal certificates
Draft Closure Report within 15 calendar days of resolving USACE and USAF comments
Draft-Final Report within 15 calendar days of resolving regulatory comments on the draft
Final Report within 7 calendar days of receiving regulatory concurrence on the Draft Final.
Treatment: Completion of closure reporting including confirmation laboratory results collected in accordance with the approved QAPP and documented in closure report demonstrating achievement of the most stringent 18 AAC 75 cleanup levels for PFAS and other contaminants.
Disposal: Completion of closure report with documentation of receipt of weight tickets from the final disposal location.
All uncontaminated and treated soil placed at location indicated by installation, graded to match surrounding area, and hydroseeded.
All stockpile liners, covers, and other material disposed. Site restoration complete.
Pre-Draft Report: Submitted on time and sufficient detail/quality to allow USACE and USAF review.
Draft Report: USACE and USAF approval through COR.
Draft-Final Report: Regulatory Approval.
Final Report: USAF, USACE, and Regulatory Approval.
TASK 16: Engineering Evaluation Cost
Assessment (EE/CA) and Action Memorandum
(AM)
Pre-Draft: Submitted on time and sufficient detail/quality to allow USACE and UAF review.
Draft: USACE and USAF approval through COR.
Final: Regulatory Approval and completion of public coordination.
USACE approval through the COR.
TASK 18: Additional Soil Washing Pass
Treatment of PFAS and/or PFAS/POL contaminated soil (per 1,000 cubic yards (CY))
Treatment: Completion of closure reporting including confirmation laboratory results collected in accordance with the approved QAPP and documented in closure report demonstrating achievement of the most stringent 18 AAC 75 cleanup levels for PFAS and other contaminants.
TASK 19: Disposal of Fines
Dispose of PFAS and/or PFAS/POL contaminated soil (per 1,000 tons)
Disposal: Completion of closure report with documentation of receipt of weight tickets from the final disposal location.
INCENTIVES
Reduction in quantity of “Fines” requiring disposal
Documentation of reduction in “Fines”. Compare anticipated quantify vs actual including additional treatment under
Optional Task 18.
Multiple milestones and/or deliverables may be listed for each performance objective. Payments will be based on successful completion of the milestones. Final decisions regarding the adequacy of milestone and deliverable completion resides with the COR, with appropriate acceptance and approval of necessary documentation by USAF.
TASKS
The tasks included in this PWS are described in this section and listed in Table 4 below. Optional tasks may be awarded individually or a group depending on funding availability.
Table 4: Tasks by Number
Task No. Task Name
Task 1 Project Management and Work Plan
Task 2 Treatment of Stockpiles from EIE405
Task 3 Treatment of Stockpiles from EIE384
Task 4 Treatment of Stockpiles from EIE386
OPTIONAL Task 5 Treatment of Stockpiles from EIE376
OPTIONAL Task 6 Treatment of Stockpiles from EIE365
OPTIONAL Task 7 Treatment of Stockpiles from EIE378
OPTIONAL Task 8 Treatment of Stockpiles from EIE382
OPTIONAL Task 9 Treatment of Stockpiles from EIE420
OPTIONAL Task 10 Treatment of Stockpiles from EIE377
OPTIONAL Task 11 Treatment of Stockpiles from EIE379
OPTIONAL Task 12 Treatment of Stockpiles from EIE385
OPTIONAL Task 13 Treatment of Stockpiles from EIE388
OPTIONAL Task 14 Treatment of Stockpiles from EIE389
OPTIONAL Task 15 Treatment of Stockpiles from EIE393
OPTIONAL Task 16 EE/CA and Action Memorandum
OPTIONAL Task 17 Treatment of Additional per 1,000 CY (award up to 50 times)
OPTIONAL Task 18 Additional SW Pass per 1,000 CY (award up to 40 times)
OPTIONAL Task 19 Disposal of Fines per 1,000 tons (award up to 50 times)
INCENTIVES 10% of Disposal of Fines per 1000 ton
GENERAL REQUIREMENTS FOR SOIL TREATMENT OR DISPOSAL
Soils must be treated and disposed in accordance with applicable federal, state, and local regulations as well as
USAF and USACE policies and procedures and the most current version of the National Defense Authorization Act
(NDAA). Nothing in this contract shall exempt the Contractor from Federal, State, or local laws or regulations unless a specific exemption has been acquired.
Soil stockpile maintenance and monitoring is currently being conducted under a separate contract. The contractor shall coordinate with this contractor on the turnover of soil stockpiles for treatment. The Contractor will take possession of stockpiles under awarded Contract Line Item Numbers (CLINS) at the end of this contract (30 June
2023) until final disposition of the soil. Stockpiles shall be maintained in accordance with the EAFB Stockpile
Standard Operating Procedure (included as GFI). The Contractor shall ensure that all treated material is appropriately stockpiled pending confirmation of achieving target cleanup levels (TCLs).
The Contractor shall treat soil stockpiles from F-35 construction projects using Soil Washing (SW). Ultimately the contractor shall be responsible for ensuring the entire awarded volume of soil is treated to meet the TCLs or disposed at an approved facility. The Contractor shall independently verify the stockpile volume and percent “fines” to verify the results provided in the GFI are accurate. Verification methodology and results would be subject to
USACE review and concurrence.
The primary performance objective is to conduct treatment using SW to separate the soil fractions and reduce PFAS concentrations in the sand and gravel fraction (based on Stockpile Characterization Report, Brice 2021) below
TCLs. It is anticipated that a single pass will be sufficient to separate the sand and gravel soil fractions and reduce
PFAS levels below TCLs. However, the contractor is ultimately responsible for determining actual number of passes required to achieve the performance objective.
The secondary performance objective is to reduce the percentage of the “fines” (silt and clay fraction) that ultimately requires disposal at an approved facility. The Contractor shall determine if an additional pass of the “fines” through the SW system can further reduce PFAS concentrations in this soil fraction to achieve TCLs. If the Contractor is unable to reduce PFAS levels in the fines below the TCL, following additional passes and SW system optimization, the Contractor shall utilize one of the following disposal options:
Disposal at a USEPA approved RCRA Subtitle C or D landfill that has a leachate collection system or
Disposal at a USEPA approved Class I Underground Injection Control (UIC) facility.
The Contractor shall receive a performance incentive for reducing the portion of the fines that ultimately require disposal. Reductions may be achieved through additional passes through the SW system and/or treatment optimization efforts. The Stockpile Characterization Report (AFCEC 2021) includes soil gradation results and identifies the percent fines for each stockpile. Once the contractor has demonstrated that the soil and gravel fraction meet TCLs the Contractor shall determine if additional pass of the “fines” through the SW system can reduce PFAS levels below TCLs. An incremental optional task is included for additional pass of the fines through the SW system.
If the Contractor can demonstrate that a second pass of the fines would be cost effective to reduce the PFAS levels below TCLs, the Government will negotiate incentives with the contractor based on potential savings of treatment over disposal cost. If the Contractor is unable to demonstrate that additional treatment can effectively reduce the quantity of soil requiring disposal it is anticipated they will abandon attempts at additional treatment and dispose of the fines.
Treated soil shall be sampled to confirm the adequacy of the treatment process. The contractor shall utilize ISM sampling with a maximum decision unit size of 500 CY, calculate the 95% UCL using the 2020 Interstate
Technology & Regulatory Council (ITRC) requirements, and compare sampling results to the most stringent ADEC soil cleanup level for the analytes that exceeded within the Decision Unit (DU) prior to treatment.
The Contractor shall prepare a Closure Report to document the treatment and disposal of stockpiles. The Closure report should include laboratory results, 95% UCL calculations, waste manifests, disposal certificates, documentation of placement of clean soil, etc. The purpose of the Closure Report is to document how and where all associated wastes have been treated and/or disposed. The Closure Report for multiple projects may be combined if tasks are awarded or completed concurrently.
The Contractor shall conduct site restoration by removing and disposing of all stockpile liners, covers, sandbags, and other associated materials. Berms and sumps shall be graded to match the surrounding area. The area should be graded to drain such that the water will not pool or cause erosion. The existing cap on Landfill No. 3 shall not be disturbed or excavated.
The contractor shall place treated and uncontaminated soil at a pre-approved location on the installation. The contractor shall grade the material to maintain the natural contour of the land and apply hydroseed (using a seed mix appropriate for the area). AM#0001…For proposal purposes the Contractor shall assume maximum fill thickness of 10 feet….AM#0001
A laydown yard will be made available on EAFB for Contractors use to place equipment, perform treatment of soils, and/or placement of office trailers. Approximately ½ acre of laydown yard located east of Building 4371 will be available, however, the Contractor shall not restrict access to the Asbestos Landfill, the fenced Storage Yard, or the
Contaminated Media Holding Cells Facility. Electrical power will be available for Contractors use on a for purchase basis. Current utility rates will be included as GFI with this solicitation. The Contractor shall make all electrical connections to an existing power pole and/or transformer-mounted pad located near Building 4371. The Contractor may request additional laydown yard space; however, the Government cannot guarantee space will be available.
Water from Building 4371 and/or Mullins Pit may be available upon Contractor’s request for dust suppression and other uses.
Task 1: Project Management and Work plan
The Contractor shall provide overall project management for the duration of this contract, including the development, implementation, and maintenance of project schedules, events, and resources; periodic project meetings; and monthly reports describing progress towards achieving project objectives. The Contractor shall include incremental project management and meeting costs in the optional tasks to account for extensions of the contract completion date (CCD).
The Contractor shall develop a Work Plan (WP) that addresses all technical and regulatory aspects of the project.
Management activities shall include but are not limited to:
Timely and appropriate responses to inquiries from the USACE Contracting Officer (KO), Contracting Officer
Representative (COR), and Project Manager (PM) regarding aspects of the project. All USACE project delivery team inquiries will be communicated to the Contractor through the PM or COR, and all contractor correspondence shall be directed to the PM and COR.
Management and control of all project performance including subcontracted services.
Project Schedule
The Contractor shall submit a detailed schedule within ten (10) days of award of this contract showing the periods in which work will be performed and milestone dates to complete the scoped tasks. The project schedule shall be provided in Gantt chart format and shall include dates for starting and completing critical features of the work. The
Contractor will review the applicable submittal dates and propose a deliverable schedule that allows the government sufficient time to review and coordinate in time to meet all required regulatory agency submittal dates. The
Contractor shall update and resubmit the schedule when changes to the schedule are realized, and with each monthly status report submission.
Meetings
The Contractor shall arrange, prepare for, and participate in the following meetings:
Kick off meeting with the USACE PM and COR, and EAFB Remedial Project Manager (RPM) (assume one 4-hour meeting). The kickoff meeting will be held within 10 days of contract award. The meeting shall be conducted by teleconference.
Attend EAFB RPM meetings. The Contractor PM and one other Contractor personnel shall attend RPM meetings approximately every other month during each task order. Assume 1-hour meetings held via teleconference.
Conduct monthly status meetings with USACE personnel to discuss monthly status report (MSR), progress and other issues. Assume 1-hour meetings held via teleconference.
As required, the Contractor shall participate in and/or facilitate project coordination, comment resolution, status updates, and/or public outreach meetings with the Eielson RPM, USACE, ADEC, and USEPA and other stakeholders. For proposal purposes assume quarterly (4 per year) 4-hour long meetings, and that 50% of meetings will be held in Fairbanks with the remainder occurring via virtual teleconference.
Presentation materials shall be prepared for these meetings. Materials shall be provided for Government review 5 days prior to each meeting. Draft meeting minutes shall be prepared by the Contractor and provided to the USACE
PM and USAF RPM within seven (7) days of the conclusion of each meeting. Final meeting minutes will be submitted five (5) days after comment receipt.
There may be occasions when subsequent meetings may be called by either party to re-confirm mutual understandings and/or address contract deficiencies that may require corrective actions. If applicable, the Contractor shall attend meetings to discuss technical or regulatory issues and project progress and status. If applicable, the
Contractor shall assist with the review, interpretation, and application of new statutory and regulatory requirements.
The Contractor shall make recommendations for USAF integration, as required.
The Contractor shall keep a record of each meeting, phone conversation, and written correspondence (including email) affecting decisions relating to the performance of this contract task order. A summary of all meeting minutes, phone conversations, and written correspondence from the previous month shall be submitted with the MSRs.
Monthly Status Reports
The Contractor shall prepare MSRs consisting of a summary of work that was completed the previous month, work currently underway, work planned for future month(s), current project schedule, communications from USACE and
USAF, monthly exposure hours, cost variances, and other pertinent project information are required. Exposure hours shall be reported on the Work-Related Injuries/Illness and Exposure form in accordance with Engineering Manual
(EM) 385-1-1 section 01.D.05c. Each status report shall state whether current work is on schedule. If the work is not on schedule, the Contractor shall state what actions are anticipated to get back on schedule. MSRs shall be submitted via email to the USACE PM and COR no later than the 10th day of the calendar month following the month covered by the report.
Prepare Work Plan
The Contractor shall prepare a Work Plan that meets the UFP-QAPP format. The plan must describe the treatment and disposal method.
Planning documents shall be issued in pre-draft draft, draft-final and final versions according to the submittal requirements and project schedule set out in AM#0001….Sections 5.7 and 5.8 …AM#0001 of this PWS. No work at the site shall be performed until the Planning Documents are accepted by USACE and USAF.
UFP-QAPPs
The UFP-QAPP shall be developed following the format specified in the Intergovernmental Data Quality Task
Force (IDQTF) documents and shall include descriptions of tasks to be performed, including information that would previously been included in a Field Sampling Plan (FSP) and a Quality Assurance Project Plan (QAPP). The UFP-
QAPP shall be developed in accordance with the Department of Defense (DoD) Quality Systems Manual (QSM) version 5.4 (or the most recent version), and the UFP for QAPPs as developed by the IDQTF and as described by the three consensus documents: UFP-QAPP Manual, UFP-QAPP Workbook, and UFP-QAPP Compendium.
The UFP-QAPP shall identify sampling and analysis requirements for stockpile post liner and post treatment confirmation sampling. As part of the development of the UFP-QAPP, PFAS sampling much follow stringent sampling protocol and the requirements in AM#0001… section 5.6… AM#0001.The UFP-QAPP shall contain sufficient information for field personnel to understand sampling and field measurement requirements. Relevant worksheets shall be populated to provide a comprehensive description of all onsite activities and provide necessary supporting information, including sample locations, sampling procedures, summaries of analyses to be performed, protocols for instrument and equipment operation and use, shipment of samples for offsite analyses, data documentation, and reporting requirements. In accordance with the USACE Manual for electronic Deliverables
(MED), a detailed Sample Summary Sheet shall be included. The Contractor shall provide a description of how the summary sheet will be used in the field to ensure proper QA/QC samples will be collected in the field. See Section 0 for specific PFAS sampling and analysis requirements.
Relevant worksheets shall be populated such that there is sufficient information for field and laboratory personnel to understand the requirements for sample handling, quality control, analytical methods, data review/validation, and data reporting. Appropriate Detection Limits (DLs), Limits of Detection (LOD), Limits of Quantitation (LOQs), and recovery control limits shall be specified, and rationale provided. Recovery control limits shall be consistent with the most current version of the DoD QSM. The UFP-QAPP shall also detail how the Contractor intends to meet the data quality objectives and to ensure the accuracy, precision, representativeness, completeness, defensibility, and comparability of the data. The UFP-QAPP shall address all levels of the investigation with enough detail to become an audit guide for field and laboratory work. The UFP-QAPP shall also include the laboratory’s DoD Environmental
Laboratory Accreditation Program (ELAP) and ADEC Laboratory approvals, to include extraction, method, and analyte lists (not just the certificate itself).
Waste Management Plan
The Contractor shall prepare a plan detailing the way wastes will be managed both onsite and offsite. As appropriate and as applicable, this plan shall include any soil or wastewater generated, pumped, or collected as part of any field activities. The plan shall propose facilities to be used for treatment, storage, and/or disposal; shall identify whether transfer facilities are to be used; and how the wastes will be tracked to ultimate disposal in accordance with all federal, state, and local laws to include the off-site rule as necessary.
The Contractor shall prepare properly completed manifests for the transportation and disposal of hazardous and/or contaminated soil and provide them to the Eielson Hazardous Waste Facility. An USAF representative will review and sign the manifests. The COR will indicate which Government personnel will sign manifests as generator. The
Contractor shall allow the Government seven calendar days for review and signature of the manifests. The
Contractor shall also prepare a properly completed ADEC approval to transport contaminated soil or ground water for treatment when applicable.
Soil Treatment Plan
The Contractor shall prepare a detailed Soil Treatment Plan. The Soil Treatment Plan (STP) shall: identify the treatment process, include detailed schematics of treatment systems, identify any soil additives, evaluate air quality concerns (plans to contain fugitive emissions and dust from soil handling), and identify permits and regulatory approvals required. The STP shall include a detailed scheduled that addresses the soil treatment processing rate and duration of treatment. The Contractor shall address post treatment sampling and analysis in the UFP-QAPP.
APP/SSHPs
The Contractor shall develop and implement a written Accident Prevention Plan (APP) in accordance with guidelines specified in EM 385-1-1. The APP shall include a Site Safety and Health Plan (SSHP) written in accordance with 29 Code of Federal Regulations (CFR) 1910.120 and 29 CFR 1926.65 as an attachment. The
APP/SSHP shall cover all work scoped under this task order. This document shall be submitted as draft and final versions to USACE; the Government does not “approve” the APP/SSHP, but it is required for the Government’s records.
Task 2: Treatment of Stockpiles from EIE405
The Contractor shall treat soil stockpiles from EIE405. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3. Stockpile
EIE405-3 (approximately 1,452 CY) contains pesticide that may require out of state disposal under Optional Task
19. The Contractor shall evaluate characterization data to recommend appropriate disposition of this stockpile.
Task 3: Treatment of Stockpiles from EIE384
The Contractor shall treat soil stockpiles from EIE384. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
Task 4: Treatment of Stockpiles from EIE386
The Contractor shall treat soil stockpiles from EIE386. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 5: Treatment of Stockpiles from EIE376
The Contractor shall treat soil stockpiles from EIE376. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 6: Treatment of Stockpiles from EIE365
The Contractor shall treat soil stockpiles from EIE365. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 7: Treatment of Stockpiles from EIE378
The Contractor shall treat soil stockpiles from EIE378. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 8: Treatment of Stockpiles from EIE382
The Contractor shall treat soil stockpiles from EIE382. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 9: Treatment of Stockpiles from EIE420
The Contractor shall treat soil stockpiles from EIE420. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 10: Treatment of Stockpiles from EIE377
The Contractor shall treat soil stockpiles from EIE377. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 11: Treatment of Stockpiles from EIE379
The Contractor shall treat soil stockpiles from EIE379. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 12: Treatment of Stockpiles from EIE385
The Contractor shall treat soil stockpiles from EIE385. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 13: Treatment of Stockpiles from EIE388
The Contractor shall treat soil stockpiles from EIE388. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 14: Treatment of Stockpiles from EIE389
The Contractor shall treat soil stockpiles from EIE389. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 15: Treatment of Stockpiles from EIE393
The Contractor shall treat soil stockpiles from EIE393. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3.
OPTIONAL Task 16: EE/CA and Action Memorandum
The Contractor shall prepare a Non-Time Critical Response Action (NTCRA) Engineering Evaluation/Cost
Assessment (EE/CA) and an Action Memorandum (AM) in accordance with EPA “Guidance on Conducting
NTCRA under CERCLA” (EPA 1993). The Contractor shall prepare pre-draft, draft, draft-final and final versions of the EE/CA in accordance with the submittal requirements and project schedule set out in AM#0001… Sections
5.70 and 5.8 …AM#0001 of this PWS. The EE/CA shall contain:
Executive Summary
Introduction
Site Characterization Summary, Identification of removal action objectives, Identification and analysis of Removal Action Alternatives (RAA), Comparative analysis of RAA’s, and
Recommended Removal Action Alternative.
The final version of the EE/CA will be made available to the public.
The Contractor shall publish a notice of availability and brief description of the EE/CA in a major local newspaper.
The Contractor will publish a public notice for a 30-day public comment period. The USACE and AF will review and approve the public notice prior to publishing. The Contractor will collect comments, both written and oral, and prepare written responses for USACE and AF review and approval.
The Contractor shall prepare draft and final versions of the AM for submittal to the USACE and USAF for review and comment. The final version of the AM will be signed by the USAF.
OPTIONAL Task 17: Treatment of Additional 1000 CY
The Contractor shall treat approximately 1,000 CY of PFAS contaminated soil from other construction projects. The
Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3. This task may be awarded up to fifty (50) times. AM#0001… For proposal purposes the Contractor shall assume that any additional soil will be hauled to a location adjacent to area of the existing soil stockpiles (landfill #3 and vicinity) and stockpiled pending treatment…AM#0001.
OPTIONAL Task 18: Additional SW Pass
The Contractor shall treat approximately 1,000 CY of fines with a supplemental soil washing pass. The Contractor shall comply with General Requirements for soil treatment and disposal (Section 4.1) and achieve the performance requirements identified in Table 3. This task may be awarded up to forty (40) times.
OPTIONAL Task 19: Disposal of Fines
The Contractor shall dispose of approximately 1,000 tons of PFAS contaminated fines or other soil. The Contractor shall utilize one of the following disposal options:
Disposal at a USEPA approved RCRA Subtitle C or D landfill that has a leachate collection system or
Disposal at a USEPA approved Class I Underground Injection Control (UIC) facility.
The Contractor shall ensure that soil moisture in the fines is below 20% by weight prior to transport. The Contractor shall comply with General Requirements for soil disposal (Section 4.1) and achieve the performance requirements identified in Table 3. This task may be awarded up to fifty (50) times.
INCENTIVES
The Contractor shall receive a performance incentive for reducing the portion of the fines that ultimately require disposal. Maximum incentives will be received if the Contractor can treat the entire soil volume without requiring use of Optional Task 18. If the Contractor can demonstrate that a second pass of the fines would be cost effective to reduce the PFAS levels below TCLs the Government will negotiate incentives with the contractor based on potential savings of treatment over disposal cost. If the Contractor is unable to demonstrate that additional treatment can effectively reduce the quantity of soil requiring disposal it is anticipated they will abandon attempts at additional treatment and dispose of the fines. The Contractor shall demonstrate their ability to reduce disposal at their cost and prior to award of Task 18 or issuance of any incentives.
Table 5 - Incentives
Percent Reduction in Fines Requiring Disposal Incentive Percentage
25% 2.5% of disposal costs
50% 5% of disposal costs
75% 7.5% of disposal costs
100% 10% of disposal costs
For example: Project EIE 384 includes 10,360 CY of PFAS contaminated Soil. Assume the following: disposal is
$500/ton, additional treatment is $150/CY, soil density is 1.4 tons/cy, and 24% fines. Approximately 2,500 CY of this soil is “fines”. If the Contractor can treat entire soil volume and reduce the amount of fines requiring disposal by 100%, they would receive an incentive bonus based on 10% of the disposal cost for the 2,500CY (2500cy X 1.4 tons/CY X $500/ton X 0.1) for a total of $175,000. If the Contractor can treat the fines with a second pass and successfully reduce the amount of fines requiring disposal by 100% they would receive an incentive bonus based on
10% of the disposal cost minus the additional treatment cost for the 2,500CY ({[2500cy X 1.4 tons/CY X $500/ton]-
[2,500CY X $150/CY]} X 0.1) for a total of $157,500.
TECHNICAL REQUIREMENTS AND STANDARDS
The Contractor shall be responsible for complying with the technical requirements and standards discussed below.
General Requirements
All work shall be performed in accordance with all applicable federal, state, and local regulations as well as USAF and USACE policies and procedures. The Contractor shall be responsible for identifying the applicable federal, state, and local regulations that will affect this contract.
Permits
The Contractor shall obtain all permits as required by state and local regulatory agencies and USAF policies and procedures. Work shall comply with applicable federal, state, and local regulatory requirements, as well as USACE and USAF requirements.
Base Access, Training, and Other Installation Requirements
The Contractor shall conduct work in compliance with the installation access protocols and training requirements.
Required Base access, training, and other installation requirements are discussed below.
Base Access
The USACE PM will provide the Contractor the Installation access forms. The USAF will sponsor key members of the project team. The Contractor shall not contact the Installation directly for access.
Support personnel shall be able to pass security screening to allow access to Government controlled facilities. The
Contractor shall comply with EAFB access policy and Coronavirus disease Guidance
(https://www.eielson.af.mil/coronavirus/).
Work Site Coordination https://www.eielson.af.mil/coronavirus/
The Contractor shall coordinate work site activities to ensure the protection of human health and the environment;
the prevention of damage to property, utilities, materials, supplies, and equipment; and the avoidance of work interruptions. The Contractor shall provide physical security to the work area with security equipment and personnel, as needed.
The Contractor shall conduct work in compliance with the installation environmental policy, in accordance with installation’s Environmental Management System, and respective to the installation’s significant aspects and environmental action plans (EAPs). The Contractor shall comply with Occupational Safety and Health
Administration (OSHA) safety and health regulations and local safety office requirements. The Contractor is required to provide the KO copies of any OSHA Report(s) submitted during the duration of this TO.
A dig permit is required prior to performing any type of ground disturbing work, to include blading, excavation, or boring; no ground disturbing site work conducted under this contract is allowed without approved plans and having an approved dig permit. The contractor shall follow any applicable Land Use Controls for sites where work is conducted on EAFB.
Contractor Quality Control
The Contractor shall ensure that appropriate internal quality control practices are employed throughout the performance of this contract. The Contractor’s quality control practices shall be internal, meaning that the
Contractor shall not use the USACE technical review and comment procedure as a substitute for the appropriate internal quality checks and corrections. The objectives of the Contractor’s quality control practices shall be to ensure that submittals are complete, internally consistent, technically accurate, in compliance with accepted industry practices, and generally free from copy errors such as misspellings, grammatical errors, formatting problems, etc.
Additional objectives of the Contractor’s quality control practices shall be to ensure that all procedures, including but not limited to chemical data review, field practices, and oversight of subcontractors’ work, are checked for completeness, consistency, technical accuracy, compliance with accepted industry practices, and general absence of errors throughout the performance of the procedure. The goal of the Contractor’s quality control practices shall be to identify and correct problems before they are carried forward in the project, and to ensure that submittals meet professional standards of quality.