ANC029 Preproposal Conf Nov 10 2020.pptx
PPTX presentation 4 MB Posted
- Solicitation number
- W911KB21R0002
About this file
This document outlines a federal solicitation for maintenance dredging services. The U.S. Army Corps of Engineers seeks proposals to dredge approximately 1.1 million cubic yards of material annually from the Port of Anchorage harbor for three years, with optional additional dredging of 350,000 cubic yards annually from the Cook Inlet Navigation Channel. Proposals are due by December 8, 2020, with award anticipated by January 14, 2021. Evaluation will consider offerors' performance capability, experience, past performance, small business participation, and price. The dredging must be conducted to maintain access for shipping traffic at the Port of Anchorage dock face and allow construction of a new petroleum and cement terminal, with surveys provided to monitor shoaling.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 21R0002 ANC029 Amendment 3.pdf | ||
| 21R0002 P00002 Amendment 2.pdf | ||
| ANC029_SPECS_RFP updated 17 Nov 2020.pdf | ||
| 21R0002 amendment 5 Nov 2020.pdf | ||
| ANC029_SPECS_RFP.pdf | ||
| ANC029_PLANS_RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Preproposal Conference 2021-2023 Maintenance Dredging Anchorage, Alaska
W911KB21R0002
November 10, 2020
Building and Preserving Alaska’s Future
US Army Corps of Engineers
BUILDING STRONG®
2021-2023 Maintenance Dredging Anchorage, Alaska Meeting Agenda
Introduction – Christine Dale, Contracting Officer Jeannette Morphew, Contract Specialist
Solicitation Schedule – Christine Dale
Evaluation Factors and Basis of Award – Christine Dale
Project Overview – Donna West, Operations Project Manager
Questions
INTRODUCTION
Roll Call of Participants U.S. Army Corps of Engineers Offerors, Others
Purpose of Meeting This meeting is to brief offerors on the nature of the work and clarify proposal requirements.
The preproposal conference is for informational purposes only. Statements or representations made during the conference are not legally binding. Changes resulting from this conference are official only if issued through an amendment to the solicitation.
INTRODUCTION
Type of Solicitation – Request for Proposals Best Value – Trade Off
Contract Period – Base year + 2 option years
Process for Responding to Questions (Bidder Inquiry) See Section 00 21 00, paragraph 1.5.1
SOLICITATION SCHEDULE
Solicitation Issued: October 27, 2020
Proposals Due: December 8, 2020, 2:00 p.m. (Alaska time) Process for submission of proposals – electronic only
Evaluate Proposals: December 9-31, 2020
Award: on or about January 14, 2021
EVALUATON FACTORS AND BASIS OF AWARD
Section 00 22 11
Factor 1 Performance Capability – Equipment and Survey Plan Factor 2 Experience – Relevant Experience within past 6 years Factor 3 Past Performance – Performance on projects submitted for Experience Factor 4 Extent of Participation of Small Businesses – All offerors. Participation based on total contract dollars (base + all options) Factor 5 Price
Technical Factors, combined, are significantly more important than Price
Total evaluated price for determination of best value is the total of base items and all options items
Small Business Subcontracting Plan required for Large Business Offerors
Anchorage Fairbanks
Juneau
Nome
PROJECT LOCATION
ANCHORAGE HARBOR OVERVIEW
Location: North end of Cook Inlet in south-central Alaska.
Up to 30’ tidal change.
Authorized Project Depth : -35 feet MLLW
Dredge 5’ from dock to 1000’ offshore
Est. Quantity: 1,100,000 cy/year
Dredge Period: May 1 to October 31
Disposal: In-Water 3000’ offshore
Dredge Type: Hopper or Mechanical dredges only
Anchorage Harbor Maintenance Dredging Quantities*
2020 = 935,000 CY
2019 = 1,166,000 CY
2018 = 747,379 CY
2017 = 1,011,548 CY
2016 = 739,012 CY
2015 = 1,206,151 CY
2014 = 1,117,886 CY
2013 = 1,021,088 CY
2012 = 1,067,684 CY
2011 = 944,462 CY
*Quantities do not include early season dredging which is typically 50,000-60,000 CY
Cubic Yards 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 944462 1067684 1021088 1117886 1206151 739012 1011548 747379 1166000 935000
CONTRACT SPECIFICATIONS OF NOTE
01 22 00.00 10 Price and Payment Procedures – Measures of Payment for dredging, surveys and standby
01 57 20.01 29 Environmental Protection – Marine Mammal Mitigation Measures
31 09 13.00 29 Surveys (Civil Works) – Hydrographic Survey Requirements
35 20 23.13 and 35 20 23.23 National Dredge Quality Management Program – Dredge Instrumentation
35 20 24 Maintenance Dredging Cook Inlet Navigation Channel Geotechnical Report included
MEASUREMENT AND PAYMENT
JOB: Full compensation
CY: Estimated quantity. AA items subject to Variations in Estimated Quantities Clauses. Actual quantity may vary.
NTE: Not to exceed unless authorized by Contracting Officer. Quantity may vary. No pricing adjustment under Variations in Estimated Quantities Clauses.
Dredge Limits Project Depth: -35 feet MLLW
Max Pay Line: -39 feet MLLW except -38 feet MLLW for Areas E and F at the dock.
Deeper Dredging (B Areas):
May 1-31 and Sep 15 – Oct 31
Dredge Period: May 1 to Oct 31
Dredging Constraints:
Stop dredging 5 feet from the dock face.
Shoal material is continuously deposited within the project limits throughout the entire dredge season. Historically, shoaling rates of 3,000 to 12,000 cubic yards per day occur within the project area.
Previous dredging indicates the materials above the maximum pay line are recent marine sediment deposits consisting of Sandy Silt, Silt (ML), Silty Clay (CL-ML), Lean Clay (CL), and Silty Sand (SM).
Further information is in Maintenance Dredging Specification 35 20 24.00 29, Section 1.2 Character of Materials, subsection 1.2.1. Anchorage Harbor Maintenance Dredging Character of Materials
Shoal material is continuously deposited within the project limits throughout the entire dredge season. Historically, shoaling rates of 3,000 to 12,000 cubic yards per day occur within the project area.
Previous dredging indicates the materials above the maximum pay line are recent marine sediment deposits consisting of Sandy Silt, Silt (ML), Silty Clay (CL-ML), Lean Clay (CL), and Silty Sand (SM).
Previous dredging efforts indicate the in place relative density of the cohesionless soils range from loose to medium dense and the in place consistency of cohesive soils range from soft to firm. The dredge materials plasticity ranges from nonplastic to medium plasticity. Dredge materials have historically exhibited cohesive behavior which contributes to a reduction in productivity during dredge material disposal. Mechanical means of dislodging the dredged material from dump scows is anticipated and may be required for disposal of dredged material. Dredged materials have exhibited abnormally high shear strengths which also contributed to a reduction in dredging productivity.
Dry densities of dredged material were determined to be between 85 and 105 pounds per cubic foot and the moisture content to be 20 to 25 percent. Local, minor variations and some debris are to be expected, and if encountered shall not be considered materially different within the scope of the DIFFERING SITE CONDITIONS Clause.
Anchorage Harbor Dredge Limits – 2021 Constraints Port of Alaska completing construction of Petroleum and Cement Terminal (PCT) in 2021
Work entails construction of PCT mooring and breasting dolphins
Yellow section of dock and offshore areas will be impacted by construction barges and anchors
POL 2 partially unavailable during first half of 2021 dredge season
PCT unavailable in 2021, maintenance dredging begins 2022
South Float unavailable in 2021, need to work with Port of Alaska or private entity on access
Surveys Summer Surveys – Multibeam
Survey data collection: Mondays & Thursdays
Survey results to Corps/Shippers: 2 days after data collection is complete
Winter Surveys – Singlebeam Up to 18 surveys per season from November to April
Set up winter survey schedule in September
Anchorage Fairbanks
Juneau
Nome
PROJECT LOCATION
Standby Time
Standby Time:
When there is no material above project depth or upon approval of the Contracting Officer.
Standby days should start and end on survey days (Monday or Thursday).
Surveys continue while the dredge is on standby.
Initial NTE amount may be increased by the Contracting Officer
Early Season Dredging (Option) Dredge Area: Area A and sub-areas
Dredge Period: April 1-30
Max Pay Line:
A: -39 feet MLLW B1: -45 feet MLLW B2: -43 feet MLLW B3: -41 feet MLLW E & F: -38 feet MLLW
Dredge Plant: Same as maintenance dredge plant
Method of Payment: Paid per day.
20 dredge days and 10 standby days in contract
Early Season Mobilization: Only costs in addition to annual mobilization
Dredge Day: 12-hour dredging/12 standby
Standby Day: less than 8 hours dredging in 24-hour period
COOK INLET NAVIGATION CHANNEL (OPTION)
Location Cook Inlet Nav. Channel (Option):
Located about 6 miles south of the Anchorage Harbor
(Base) Placement Site Cook Inlet Nav. Channel Placement Site for Anchorage Harbor
COOK INLET NAVIGATION CHANNEL
Dredge and Survey Areas (Option) May 2017 Condition Survey Channel Length = 11,000 feet Channel Width = 1,100 feet Project Depth = - 38 feet Max Payline = - 43 feet
Condition Surveys in May and October
Dredge Period: 15 June - 30 August if needed
Surveys: Once per week while dredging.
Additional option for dredge days if small amount of dredging needed
COOK INLET NAVIGATION CHANNEL (Option) Dredge History
Maintenance Dredge History:
2013:
ESSAYONS removed 2.7 Million CY WESTPORT removed 200,000 CY
2014:
ESSAYONS removed 1.0 Million CY WESTPORT removed 450,000 CY.
No maintenance dredging prior to 2013 or since 2014.
Geotechnical Site Information
Geotechnical Data Report, Cook Inlet Navigation Channel Dredging, September 2014
(Provided as an attachment in Specification 35 20 24.00 29 Maintenance Dredging)
All drawings, figures, and photographs presented is this presentation are from the solicitation. No new information is being presented.
The subsurface exploration for this project was conducted from 10 September to 5 October 2007. A total of 48 test borings were drilled, ranging in depth from 34 to 42 feet below mudline.
From July to September 2008, a trial dredging program was conducted in virgin areas (no previous dredging) where future dredging is planned for the Anchorage Harbor Deepening project.
Reference Maintenance Dredging Specification 35 20 24.00 29 Section 1.2 Character of Materials 1.2.2 Cook Inlet Navigation Channel
Previous maintenance dredging indicates the materials above the maximum pay line consist of poorly graded sand (SP). Gravel, cobble, and boulder sized particles were also encountered throughout the length and width of the channel below the approximate elevation of -38 feet MLLW.
The quantity of gravel, cobble, and boulder sized particles encountered during previous maintenance dredging was estimated to be five percent or less by volume.
Cook Inlet Navigation Channel Character of Materials
Shoal material is continuously deposited within the project limits throughout the entire dredge season. Historically, shoaling rates of 3,000 to 12,000 cubic yards per day occur within the project area.
Previous dredging indicates the materials above the maximum pay line are recent marine sediment deposits consisting of Sandy Silt, Silt (ML), Silty Clay (CL-ML), Lean Clay (CL), and Silty Sand (SM).
Previous dredging efforts indicate the in place relative density of the cohesionless soils range from loose to medium dense and the in place consistency of cohesive soils range from soft to firm. The dredge materials plasticity ranges from nonplastic to medium plasticity. Dredge materials have historically exhibited cohesive behavior which contributes to a reduction in productivity during dredge material disposal. Mechanical means of dislodging the dredged material from dump scows is anticipated and may be required for disposal of dredged material. Dredged materials have exhibited abnormally high shear strengths which also contributed to a reduction in dredging productivity.
Dry densities of dredged material were determined to be between 85 and 105 pounds per cubic foot and the moisture content to be 20 to 25 percent. Local, minor variations and some debris are to be expected, and if encountered shall not be considered materially different within the scope of the DIFFERING SITE CONDITIONS Clause.
Maintenance Dredging
Reference: Geotechnical Data Report Cook Inlet Navigation Channel Dredging September 2014
Previous maintenance dredging indicates the materials above the maximum pay line consist of poorly graded sand (SP). Gravel, cobble, and boulder sized particles were also encountered throughout the length and width of the channel below the approximate elevation of -38 feet MLLW. The quantity of gravel, cobble, and boulder sized particles encountered during previous maintenance dredging was estimated to be five percent or less by volume. Previous dredging efforts indicate the in place relative density of the cohesionless soils range from loose to medium dense and measured total unit weights varied from 105 to 118 pounds per cubic foot.
Maintenance Dredging
Previous maintenance dredging indicates the materials above the maximum pay line consist of poorly graded sand (SP). Gravel, cobble, and boulder sized particles were also encountered throughout the length and width of the channel below the approximate elevation of -38 feet MLLW. The quantity of gravel, cobble, and boulder sized particles encountered during previous maintenance dredging was estimated to be five percent or less by volume. Previous dredging efforts indicate the in place relative density of the cohesionless soils range from loose to medium dense and measured total unit weights varied from 105 to 118 pounds per cubic foot.
Maintenance Dredging
Previous maintenance dredging indicates the materials above the maximum pay line consist of poorly graded sand (SP). Gravel, cobble, and boulder sized particles were also encountered throughout the length and width of the channel below the approximate elevation of -38 feet MLLW. The quantity of gravel, cobble, and boulder sized particles encountered during previous maintenance dredging was estimated to be five percent or less by volume. Previous dredging efforts indicate the in place relative density of the cohesionless soils range from loose to medium dense and measured total unit weights varied from 105 to 118 pounds per cubic foot.
Questions?
Contact Info:
Jeannette Morphew, Contacting Specialist – (907) 753-5594 Jeannette.L.Morphew@usace.army.mil
Christine Dale, Contracting Officer - (907) 753-5618 Christine.A.Dale@usace.army.mil image10.jpeg image11.emf image12.JPG
Microsoft_Excel_Worksheet.xlsx Sheet1
Anchorage Maintenance Dredge Quantities
Year Cubic Yards
2007 1,766,357
2008 1,338,281
2009 702,366
2010 619,506
2011 944,462
2012 1,067,684
2013 1,021,088
2014 1,117,886
2015 1,206,151
2016 739,012
2017 1,011,548
2018 747,379
2019 1,166,000
2020 935,000
&Z&F
Cubic Yards 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 1766357 1338281 702366 619506 944462 1067684 1021088 1117886 1206151 739012 1011548 747379
Sheet2
Sheet3 image13.JPG image14.JPG image15.jpg image16.png image17.JPG image18.JPG image19.jpeg image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpeg image1.png image2.png image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.png image8.png image9.png