21R0002 P00002 Amendment 2.pdf
PDF 407 KB Posted
- Solicitation number
- W911KB21R0002
About this file
This solicitation requests proposals for maintenance dredging services at the Port of Anchorage in Alaska from 2021 through 2023. The scope of work includes surveying, dredging, and disposal of approximately 1.1 million cubic yards of fine-grained shoaled material annually at Anchorage Harbor, with an option to dredge 350,000 cubic yards of sandy material in the Cook Inlet Navigation Channel. The dredging must be performed to keep the Port of Alaska dock face accessible for shipping traffic at all times and allow access to a new petroleum and cement terminal under construction. The solicitation also includes potential periodic maintenance dredging of the Cook Inlet Navigation Channel, which is the marked entrance through Knik Arm Shoal to Anchorage Harbor. Proposals are due in accordance with the instructions in the attached solicitation document. Award is subject to availability of funds.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 21R0002 ANC029 Amendment 3.pdf | ||
| ANC029_SPECS_RFP updated 17 Nov 2020.pdf | ||
| ANC029 Preproposal Conf Nov 10 2020.pptx | PPTX presentation | |
| 21R0002 amendment 5 Nov 2020.pdf | ||
| ANC029_SPECS_RFP.pdf | ||
| ANC029_PLANS_RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911KB21R0002
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Reference Project Title and Location: 2021-2023 Maintenance Dredging, Anchorage, Alaska
a. The above numbered solicitation is hereby amended to update certian sections of the solicitation and provide the Pre-Proposal Conference Minutes. See Summary of Changes for further details on page 2.
b. The date/time for receipt of offers remains unchanged at 8 December 2020 at 2:00 P.M. Alaska Time.
YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THE SF1442.
1. CONTRACT ID CODE PAGE OF PAGES
1 15
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Nov-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB21R0002
X 9B. DATED (SEE ITEM 11)
27-Oct-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Nov-2020
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
PO BOX 6898
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
AMENDMENT #0002
• The following drawings are substituted for the superseded drawings:
NONE
• The following revised documents are substituted for the superseded documents. The identifier “AM#2” appears before and after new and/or revised material and replacement pages are provided, except as noted:
SECTION 00 11 00 Proposal Schedule is replaced in its entirety. Option items for Cook Inlet Navigation Channel Maintenance Dredging are changed from annual options to one option for the contract.
SECTION 00 72 00, FAR 52.211-10 and 52.217-7 are replaced in their entirety. Option items for Cook Inlet Navigation Channel Maintenance Dredging are changed from annual options to one option for the contract.
SECTION 00 73 00.00 29, reissuing pages 6 and 7 for revisions to SCR-
GE116 AND SCR-GE117.
SECTION 31 09 13.00 29 SURVEYS (CIVIL WORKS) is replaced in its entirety. Paragraph 2.1 is revised to clarify hydrographic survey requirements for Cook Inlet Navigation Channel.
• The following documents/drawings are deleted:
• The following documents are added:
• The following revisions are incorporated:
• Other:
PowerPoint presentation from the pre-proposal conference on November 10, 2020 is furnished.
(End of Summary of Changes)
SECTION 00 11 01 - CLIN SCHEDULE
The following have been modified:
PROPOSAL SCHEDULE
AM#2…
Section 00 11 01 – CLIN SCHEDULE
PRICING SCHEDULE
2021-2023 Maintenance Dredging Anchorage, Alaska
BASE ITEMS 2021 DREDGING
Item No.
Description Quantity Unit Unit Price
Amount
Anchorage Harbor Mobilization and Demobilization (2021), Complete
1 JOB $_________ $_________
Anchorage Harbor Maintenance Dredging and Disposal (2021), Complete
0002AA First 800,000 CY 800,000 CY $_________ $_________
0002AB All over 800,000 CY, Complete 300,000 CY $_________ $_________
0003 Anchorage Harbor Dredge Standby (2021), Complete
NTE DAY $_________ $_________
Anchorage Harbor Hydrographic Summer Surveys (2021) - Pre Dredge, Post Dredge and Interim Hydrographic Surveys, Complete
NTE EA $_________ $_________
Anchorage Harbor Hydrographic Winter Surveys 2021/2022, Complete
NTE EA $_________ $_________
TOTAL OF BASE ITEMS (0001 thru 0005) $_________
OPTION ITEMS 2021 MAINTENANCE DREDGING
No.
Description Quantity Unit Unit Price
Amount
0006 Early Season Mobilization (2021), Complete 1 JOB $_________ $_________
0007 Early Season Dredging Days (2021), Complete
NTE DAY $_________ $_________
0008 Early Season Standby (2021), Complete
NTE DAY $_________ $_________
Cook Inlet Navigation Channel Interim Dredging and Disposal (2021), Complete
NTE DAY $_________ $_________
Cook Inlet Navigation Channel Hydrographic Condition Surveys (2021), Complete
NTE EA $_________ $_________
TOTAL OF OPTION ITEMS (0006 thru 0010) $_________
TOTAL OF BASE PLUS OPTIONAL ITEMS (0001 THRU 0010) $_________
OPTION ITEMS 2022 MAINTENANCE DREDGING
No.
Description Quantity Unit Unit Price
Amount
Anchorage Harbor Mobilization and Demobilization (2022), Complete
1 JOB $_________ $_________
Anchorage Harbor
Disposal (2022), Complete
0012AA First 800,000 CY 800,000 CY $_________ $_________
0012AB All over 800,000 CY, Complete 300,000 CY $_________ $_________
0013 Anchorage Harbor Dredge Standby (2022), Complete
NTE DAY $_________ $_________
Anchorage Harbor Hydrographic Summer Surveys (2022) - Pre Dredge, Post Dredge and Interim Hydrographic Surveys, Complete
No.
Description Quantity Unit Unit Price
Amount
Anchorage Harbor Hydrographic Surveys Winter 2022/2023 Winter Surveys, Complete
NTE EA $_________ $_________
0016 Early Season Mobilization (2022), Complete 1 JOB $_________ $_________
0017 Early Season Dredging Days (2022), Complete
NTE DAY $_________ $_________
Early Season Standby (2022), Complete
Channel Interim Dredging and Disposal (2022), Complete
NTE DAY $_________ $_________
Cook Inlet Navigation Channel Hydrographic Condition Surveys (2022), Complete
TOTAL OF OPTION ITEMS (0011 thru 0020) $_________
OPTION ITEMS 2023 MAINTENANCE DREDGING
No.
Description Quantity Unit Unit Price
Amount
Anchorage Harbor Mobilization and Demobilization (2023), Complete
1 JOB $_________ $_________
Anchorage Harbor
Disposal (2023), Complete
0022AA First 800,000 CY 800,000 CY $_________ $_________
0022AB All over 800,000 CY, Complete 300,000 CY $_________ $_________
0023 Anchorage Harbor Dredge Standby (2023), Complete
No.
Description Quantity Unit Unit Price
Amount
Anchorage Harbor Hydrographic Summer Surveys (2023) - Pre Dredge, Post Dredge and Interim Hydrographic Surveys, Complete
NTE EA $_________ $_________
Anchorage Harbor Hydrographic Surveys Winter 2023/2024 Winter Surveys, Complete
NTE EA $_________ $_________
0026 Early Season Mobilization (2023), Complete 1 JOB $_________ $_________
Early Season Dredging Days (2023), Complete
NTE DAY $_________ $_________
0028 Early Season Standby (2023), Complete
Channel Interim Dredging and Disposal (2023), Complete
NTE DAY $_________ $_________
Cook Inlet Navigation Channel Hydrographic Condition Surveys (2023), Complete
TOTAL OF OPTION ITEMS (0021 thru 0030): $_________
OPTION ITEMS COOK INLET NAVIGATION CHANNEL MAINTENANCE DREDGING
Channel Maintenance Dredging and Disposal, Complete
0031AA First 200,000 CY 200,000 CY $_________ $_________
0031AB All Over 200,000 CY 150,000 CY $_________ $_________
Surveys – Weekly and Post- Dredge for Maintenance Dredging
NOTES:
1. NTE = Not to Exceed. Unit pricing for NTE items is not subject to adjustment under FAR 52.211-18, Variation in Estimated Quantities however the quantity may be increased upon approval of the Contracting Officer.
2. ESTIMATED QUANTITIES: The quantities shown in the “QUANTITY” column for all unit priced items measured by the cubic yard (CY) above are estimated quantities. Actual quantities may vary. Reference FAR 52.211-18, Variation in Estimated Quantities and SCR-GE117 Variations in Estimated Quantities – Subdivided Items.
EVALUATION OF OFFERS:
1. AWARD: Award will be made in accordance with Section 00 22 11 –
EVALUATION FACTORS FOR AWARD.
2. EVALUATION OF OPTIONS and TOTAL EVALUATED PRICE: Reference FAR 52.217- 5, the Government will evaluate offers for award purposes by adding the total price of all option items to the total price for the basic requirement.
Evaluation of options will not obligate the Government to exercise the options.
3. EVALUATION OF SUBDIVIDED ITEMS: The Government will evaluate subdivided items in accordance with SCR-GE116 Evaluation of Subdivided Items.
4. INCOMPLETE PROPOSALS: Failure to submit an offer on all items in the schedule will result in an incomplete offer and the offer will be rejected.
Unit or lump sum prices must be shown for each item within the schedule.
5. EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will govern.
6. SPECIAL OFFER CONDITION: If a modification to an offer based on unit prices is submitted which provides for a lump sum adjustment to the total offered price, the application of the lump sum adjustment to each unit price in the proposal schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the proposal schedule.
-- End of Proposal Schedule –
...AM#2
SECTION 00 72 00 - CONTRACT CLAUSES
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within TEN (10) calendar days after the date the Contractor receives notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work as follows:
AM#2…
2021-2023 Maintenance Dredging, Anchorage Harbor, Alaska
FAR 52.211-10
CLIN Number Commence Work Complete Work 0001 – 0004 (Anchorage Harbor) 1 May 2021 (Start Dredging) 31 Oct 2021 (Complete Dredging) 0005 (Hydrographic Surveys Winter 2021/2022) 1 Nov 2021 30 April 2022
0006-0008 (Early Season Anchorage) 1 Apr 2021 (Start Dredging) 30 Apr 2021 (Complete Dredging)
0009 (CINC Interim Dredging) Date of Award 31 Oct 2021
0010 (CINC May Condition Survey) 1 May 2021 15 May 2021 0010 (Additional CINC Condition Survey) During 2021 Season as determined by the Government
0011 – 0014 (Anchorage) 1 May 2022 (Start Dredging) 31 Oct 2022 (Complete Dredging) 0015 (Hydrographic Surveys Winter 2022/2023) 1 Nov 2022 30 Apr 2023
0016-0018 (Early Season Anchorage) 1 Apr 2022 (Start Dredging) 30 Apr 2022 (Complete Dredging)
0019 (CINC Interim Dredging) Date of Award 31 Oct 2022
0020 (CINC May Condition Survey) 1 May 2022 15 May 2022 0020 (Additional CINC Condition Survey) During 2022 Season as determined by the Government
0021 – 0024 (Anchorage) 1 May 2023 (Start Dredging) 31 Oct 2023 (Complete Dredging) 0025 (Hydrographic Surveys Winter 2023/2024) 1 Nov 2023 30 Apr 2024
0026-0028 (Early Season Anchorage) 1 Apr 2023 30 Apr 2023
0029 (CINC Interim Dredging) Date of Award 31 Oct 2023
0030 (CINC May Condition Survey) 1 May 2023 15 May 2023 0030 (Additional CINC Condition Survey) During 2023 Season as determined by the Government
0031-0032 (CINC Maintenance Dredging and Hydrographic Surveys)
15 July of dredge year (Start Dredging)
30 Aug of dredge year (Complete Dredging)
Notes:
1. “Start Dredging” is defined as the first day the dredge digs material and places it in the disposal site. All pre-work requirements will be met, including the pre-dredge survey.
2. “Complete Dredging” is defined as the last day the dredge digs material and places it in the disposal site.
The post-dredge survey occurs within two calendar days afterwards.
…AM#2
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within SEE TABLE BELOW. Delivery of added items shall be in accordance with the dates shown in FAR 52.211-10, unless the parties otherwise agree.
FAR 52.217-7, EXERCISE OF OPTIONS
AM#2…
FAR 52.217-7, EXERCISE OF OPTIONS
2021-2023 Maintenance Dredging, Anchorage Harbor
CLIN Number Award By 0006-0008 (Early Season Anchorage) 15 Feb 2021
0009 (CINC Interim Dredging) 15 Sep 2021
0010 (CINC Condition Surveys) 15 Feb 2021
0011-0015 (Anchorage Maintenance) 15 Feb 2022
0016-0018 (Early Season Anchorage) 15 Feb 2022
0019 (CINC Interim Dredging) 15 Sep 2022
0020 (CINC Condition Surveys) 15 Feb 2022
0021-0025 (Anchorage Maintenance) 15 Feb 2023
0026-0028 (Early Season Anchorage) 15 Feb 2023
0029 (CINC Interim Dredging) 15 Sep 2023
0030 (CINC Condition Surveys) 15 Feb 2023
0031-0032 (CINC Maintenance Dredging and Hydrographic Surveys) No later than 30 Jun 2023
…AM#2
(end clause)
AM#2 2021-2023 MAINTENANCE DREDGING, ANCHORAGE HARBOR ANC029
by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations will apply. For retroactive pricing, the schedule in effect at the time the work was performed will apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer will request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data must be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
1.2.9 SCR-GE115 Basis For Settlement Of Proposals
Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under FAR 49.206-2(b). In evaluating a terminations settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:
(1) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.
(2) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.
(3) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.
(4) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of FAR 31.205-11).
(5) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.
1.2.10 SCR-GE116 Evaluation Of Subdivided Items
Item Nos. AM#2... 0002, 0012, 0022 and 0031 ...AM#2 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its sub-items.
1.2.11 SCR-GE117 Variations In Estimated Quantities, Subdivided Items
This variation in estimated quantities clause is applicable only to Items Nos. AM#2... 0002, 0012, 0022 and 0031 ...AM#2 .
DOCUMENT 00 73 00.00 29 Page 6
(a) Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.
(b) Where the actual quantity of work performed for Items Nos. AM#2...
0002, 0012, 0022 or 0031 ...AM#2 is less than 85% of the quantity of the first sub-item listed under such item, the contractor will be paid at the contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment will be made in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.
(c) If the actual quantity of work performed under Items Nos. AM#2... 0002, 0012, 0022 or 0031 ...AM#2 exceeds 115% or is less than 85% of the total estimated quantity of the sub-item under that item and/or if the quantity of the work performed under the second sub-item or any subsequent sub-item under Items Nos. AM#2... 0002, 0012, 0022 or 0031 ...AM#2 exceeds 115% or is less than 85% of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.
1.3 SAFETY/SITE/SECURITY SCR'S
1.3.1 SCR-SS010 Safety And Health Requirements Manual:
EM 385-1-1 and its changes are available at http://www.usace.army.mil/CESO/Pages/Home.aspx . At the HQ homepage, select Safety and Occupational Health.
The Contractor is responsible for complying with the current edition and all changes posted on the web (see web address above) as of the effective date of this solicitation and must comply with the version in effect on the contract award date. This EM 385-1-1 will remain in effect throughout the life of the contract.
1.3.2 SCR-SS020 Signal Lights:
The Contractor must display signal lights and conduct its operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed; vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-inland (COMDTINST M16672.2) of 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.
1.3.3 SCR-SS030 Communication Security:
All communications with DOD organizations are subject to COMSEC review.
DOCUMENT 00 73 00.00 29 Page 7
SECTION TABLE OF CONTENTS
DIVISION 31 - EARTHWORK
SECTION 31 09 13.00 29
SURVEYS (CIVIL WORKS)
PART 1 GENERAL
1.1 SCOPE
1.2 REFERENCES
1.3 SUBMITTALS
1.4 SERIAL LETTERS
1.5 SURVEY PLAN AND EQUIPMENT
1.6 CERTIFICATION
1.7 GOVERNMENT-FURNISHED DATA
PART 2 PRODUCTS
2.1 SURVEYS
2.2 SURVEY DATA
2.2.1 SURVEY CONTROL TABLE
2.2.2 SURVEY POINT FILES
2.2.3 SURVEY DRAWINGS
2.2.4 QUANTITY COMPUTATIONS
2.2.5 FIELD PHOTOS
2.2.6 QUALITY CONTROL
2.3 ORGANIZATION FOR ELECTRONIC SURVEY DATA
2.4 PRELIMINARY AND FINAL SURVEY DELIVERABLES
PART 3 EXECUTION
3.1 EXISTING MONUMENTS
3.2 ACCURACY
3.3 ATTACHMENT
ATTACHMENTS:
Attachment A - DREDGE COMPUTATION METHOD
-- End of Section Table of Contents --
SECTION 31 09 13.00 29 Page 1
SECTION 31 09 13.00 29
SURVEYS (CIVIL WORKS)
PART 1 GENERAL
1.1 SCOPE
Items included in this section cover topographic and/or hydrographic survey requirements as specified herein or indicated on the drawings.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-1003 (Nov 2013) Engineering and Design - Hydrographic Surveying
EM 1110-1-1005 (Jan 2007) Engineering and Design - Control and Topographic Surveying
EM 1110-1-1003 (Feb 2011) Engineering and Design - Navstar Global Positioning System Surveying
EM 385-1-1 (2014) Safety and Health Requirements Manual
POA-EC-G-GE-1 (Apr 2020) USACE Alaska District Minimum Survey Standards, Edition 2
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Survey Plan; G
1.4 SERIAL LETTERS
Serial letters must be used to transmit the following to the Contracting Officer's Representative (COR):
1. Notification of intent to perform a pre-dredge or post-dredge survey.
2. Final deliverables of the pre-dredge survey(s), interim condition survey(s), and post-dredge survey(s). See the paragraph 2.4 PRELIMINARY AND FINAL SURVEY DELIVERABLES in this section for details.
SECTION 31 09 13.00 29 Page 2
3. Proposed winter survey schedule. See paragraph 2.1 SURVEYS in this section for details.
1.5 SURVEY PLAN AND EQUIPMENT
The Contractor must provide a survey plan to the Contracting Officer's Representative (COR) describing the following, as a minimum:
A. Survey Procedures - provide a written description of survey procedures that shows the independent surveyor must provide surveys meeting all requirements of EM 1110-1-1005 for control/topographic surveying, EM 1110-1-1003 for Global Positioning Systems, EM 1110-2-1003 for hydrographic surveying, and POA-EC-G-GE-1 for USACE Alaska District Minimum Survey Standards.
B. Survey Equipment - provide the name, model, year of manufacture, and electronic frequencies of all the horizontal positioning, recording/depth-finding, and tidal equipment to be used. Provide the manufacturer's stated positional accuracy and capability for all the equipment to be used.
C. Survey Control Plan - a horizontal and vertical control plan must be submitted. The plan must include procedures for local vertical control to be verified through two published primary NOAA tidal benchmarks. Horizontal primary control being constrained and the local control to be verified in the field will be documented in a control diagram within the plan. See the paragraph 3.1 EXISTING MONUMENTS for further information.
D. Survey Quality Assurance/Quality Control (QA/QC) Plan - describe how the independent, licensed surveyor(s) will provide the QA/QC of their survey(s) in accordance with EM 1110-1-1005 , EM 1110-2-1003 , EM 1110-1-1003 , and POA-EC-G-GE-1.
E. Survey Vessel - provide documentation that the survey vessel to be used is safe and suitable for operation in the waters in which the work is to be performed in accordance with EM 385-1-1 . Document experience and qualifications for all personnel that will be used for operation of the survey vessel as well as the position and recording/depth finding equipment.
F. Survey Team - provide the independent hydrographic/topographic survey firm name, qualifications and experience, and demonstrate how the surveyor meets the minimum requirements stated in this specification. Names and resumes for all survey field personnel, and their responsibility to the independent hydrographic/topographic surveyor, must be included.
G. Survey Support Team - the Contractor must list any other personnel not directly employed by the hydrographic/topographic surveyor that will be performing surveying for this contract. Provide qualifications, experience, and describe their responsibility to the Contractor and the independent hydrographic/topographic surveyor.
1.6 CERTIFICATION
The Contractor must provide an independent surveyor that is a Professional Land Surveyor (PLS) with a license valid in the State of Alaska to be in responsible charge of all topographic and control surveys. The Contractor
SECTION 31 09 13.00 29 Page 3 must also provide an independent Certified Hydrographer from the American Congress for Surveying and Mapping (ACSM) or the Hydrographic Society of America (THSOA) to oversee all hydrographic surveys. At least one member of the field survey crew conducting the control survey and subsequent hydrographic and topographic field work must document at least three years of experience in surveying civil works projects (e.g. navigation channels, ports, small boat harbors, beach nourishment projects, erosion control features, etc.) similar to this contract.
1.7 GOVERNMENT-FURNISHED DATA
The COR will provide the Contractor with an AutoCAD Civil 3D file (2013 Drawing .dwg format) meeting the referenced version of TR-12-6. The file will contain a template capable of producing survey drawings, as described in 2.2.3 SURVEY DRAWINGS, complete with area map, borders, title block, and other miscellaneous information. The file will also provide design surfaces to compute volumes removed. An Excel spreadsheet of the survey control will also be provided to the Contractor. The Contractor will verify all Government-furnished data and notify the COR of any information found in error. The Contractor will be responsible for obtaining the software and computer systems necessary to produce the survey data described in this section.
PART 2 PRODUCTS
2.1 SURVEYS
The Contractor must provide surveys through use of an independent hydrographic/topographic survey firm as specified in this section, the contract drawings, and in accordance with the publications listed in 1.2 References. The hydrographic/topographic survey firm will complete all field work and produce the survey deliverables. The Contractor's independent hydrographic/topographic surveyor must perform the following surveys in this contract:
A. Pre-dredge surveys B. Interim condition surveys C. Post-dredge surveys
All summer surveys must be multibeam. The summer survey period is between May 1 and October 31 of the base and each option year, if awarded.
Multibeam surveys will be collected with sufficient overlap of data to obtain full bottom coverage of the entire survey limits.
All winter surveys must be singlebeam. The winter survey period is between November 1 and April 30 of the base and each option year, if awarded.
Singlebeam surveys will cover the entire survey limits. Hydrographic cross sections must be collected every 500 feet and perpendicular to the project baseline. Point spacing must not exceed 25 feet along the cross sections and all breaks in grade must be located. Transects must be collected every 100 feet perpendicular to the cross sections. For all transects, point spacing must not exceed 25 feet and all breaks in grade must be located.
In the area within 250 feet of the project baseline, survey data must be collected on a 50 foot grid. If sea ice conditions prevent the above requirements from being met, notify the COR immediately for instructions on how to proceed.
Coordination with the port operations manager, the COR, and any vessels operating within the survey limits will be required by the Contractor and
SECTION 31 09 13.00 29 Page 4 their independent hydrographic/topographic surveyor.
A. Pre-dredge/Condition survey(s). Pre-dredge surveys of the entire Anchorage Harbor survey limits and condition surveys of Cook Inlet Navigation Channel survey limits, as shown on the contract drawings, will be conducted as follows, if awarded:
1. Anchorage Harbor pre-dredge survey for maintenance dredging performed no more than 10 calendar days prior to the scheduled start of dredging. AM#2... A Cook Inlet Navigation Channel condition survey performed in May of each year. An additional Cook Inlet Navigation Channel condition survey performed as determined by the Government. The additional Cook Inlet Navigation Channel condition survey may be a post dredge survey if Cook Inlet Navigation Channel interim dredging is awarded or an additional condition survey at any time during the applicable contract year. ...AM#2
2. Performed by the Contractor's independent hydrographic/topographic surveyor.
3. Preceded by the Contractor notifying the COR in writing, by use of a serial letter, of their intent to perform each survey at least 7 calendar days in advance of survey activities.
4. Since this is a multi-year contract, a pre-dredge survey for Anchorage Harbor must be conducted before the start of each maintenance season.
5. The Anchorage Harbor pre-dredge survey must also include the POA Shoal survey limits identified on the drawings.
6. The preliminary survey deliverable must be submitted to the COR within 3 calendar days after completion of the survey field work.
7. The Government will have 7 calendar days to review and comment on the preliminary survey deliverable.
8. The preliminary deliverable of a pre-dredge survey will be accepted by the COR in writing, by email, before the start of any dredging activities. The contractor will not start maintenance dredging work without written acceptance of the pre-dredge survey by the Government.
9. The Contractor will have 5 calendar days from receipt of COR comments to finalize the survey and submit the final survey deliverable.
B. Interim condition survey(s). Interim condition surveys must be performed and submitted to the COR (1) to verify that the project is being dredged as defined in the contract plans and specifications and
(2) as the basis for pay estimates. Interim condition surveys will be conducted as follows:
1. The estimated number of interim condition surveys is 54 summer surveys and 20 winter surveys per year for Anchorage Harbor and AM#2... 9 interim maintenance dredging surveys per year for Cook Inlet Navigation Channel if the Cook Inlet Navigation Channel
SECTION 31 09 13.00 29 Page 5 maintenance dredging is awarded. . ...AM#2
2. Performed by the Contractor's independent hydrographic/topographic surveyor.
3. Anchorage Harbor summer interim surveys will be performed on Mondays and Thursdays of each week following the pre-dredge survey and ending on October 31 of the base and option years.
4. Anchorage Harbor winter surveys will usually be performed between Wednesday and Friday and generally occur 1 week before the lowest set of tides for each month and once per week starting in February. A winter survey schedule will be proposed by the Contractor in a serial letter by September 15 of the base year and option years (if awarded). The Contractor and Contracting Officer's Representative will meet and agree on the final survey schedule by October 15 of the base and option years.
5. AM#2... Cook Inlet Navigation Channel maintenance dredging surveys will be performed once per week during maintenance dredging of Cook Inlet Navigation Channel maintenance dredging (if awarded) ...AM#2
6. Anchorage Harbor summer and winter interim condition surveys must cover the full extent of the Anchorage Harbor survey limits indicated on the drawings. Survey of the POA Shoal survey limits is not required for the interim condition surveys.
8. Summer maintenance dredging volumes removed will be computed using the "DREDGE COMPUTATION METHOD shown in Attachment A.
9. The preliminary survey deliverable must be submitted to the COR within 2 calendar days of survey completion.
10. The Government will have 5 calendar days to review and comment on the preliminary survey deliverable.
11. The Contractor will have 5 calendar days from receipt of COR comments to finalize the survey and submit the final survey deliverable.
C. Post-dredge survey(s). Post-dredge surveys of the entire Anchorage Harbor survey limits and the Cook Inlet Navigation Channel survey limits (if dredging is awarded), as shown on the contract drawings, will be conducted as follows:
1. Performed no more than 2 calendar days after the completion of dredging.
2. Performed by the Contractor's independent hydrographic/topographic surveyor.
3. Preceded by the Contractor notifying the COR in writing, by use of a serial letter, of their intent to perform a post-dredge survey at least 7 calendar days in advance of survey activities.
4. Since this is a multi-year contract, a post-dredge survey for Anchorage Harbor must be conducted at the end of each maintenance dredging season.
SECTION 31 09 13.00 29 Page 6
5. The Anchorage Harbor post-dredge survey must also include the Anchorage Shoal survey limits identified on the drawings.
6. The preliminary survey deliverable will be submitted to the COR within 3 calendar days after the completion of the survey field work.
7. The Government will have 5 calendar days to review and comment on the preliminary survey deliverable.
8. The Contractor will have 5 calendar days from receipt of COR comments to finalize the survey and submit the final survey deliverable.
Prior to the Contractor demobilizing from any project site, post-dredge survey(s) to determine if required contract requirements have been attained over the entire project area must be performed by the Contractor's independent hydrographic/topographic surveyor within the time limits stated above.
Availability of Materials: All field notes, sketches, computations, and work products made by the Contractor and their independent hydrographic/topographic surveyor in establishing the above surveys must be available at all times during the progress of the work and for ready examination by the Contracting Officer or their designated representative.
2.2 SURVEY DATA
The Contractor's independent hydrographic/topographic surveyor must provide the following data using the most recently published horizontal and vertical datums specified in the contract. Notify the COR in writing if any project control or datums provided in the contract are found in error or out of date. The COR will provide the Contractor with written direction on how to proceed in such cases. All data will be collected under suitable conditions, which is defined as when the environmental conditions in the survey area do not prevent data acquisition or create questionable data. Data acquired under these conditions may be subject to rejection by the COR. Coordinate with the COR when unsuitable conditions occur during an originally scheduled survey.
2.2.1 SURVEY CONTROL TABLE
Provide all field verified survey control monuments as digital data in US Survey Feet reduced to the nearest one-hundredth (0.01) foot. Survey control must be provided in PNEZD format and submitted in comma-separated values (.csv) file extensions. A survey control spreadsheet will be provided to the Contractor as described in 1.7 GOVERNMENT-FURNISHED DATA.
Document in writing any deviations in position or elevation for survey control, which have been accepted by the COR, and provide the corrected survey control spreadsheet.
2.2.2 SURVEY POINT FILES
Provide all hydrographic depth soundings and topographic shots (if applicable) as digital data in US Survey Feet reduced to the nearest one-tenth (0.1) foot referenced to mean lower low water (MLLW). Point files must be submitted in ENZ format and submitted with ".xyz" file extensions:
SECTION 31 09 13.00 29 Page 7
A. All multi-beam hydrographic soundings must be sorted into 3, 6, 12, 24 and 30 foot cell size, shoal biased and mean value (on cell-center), with z-values in elevation mode (points below the 0.0 foot MLLW elevation include a minus sign and points above the 0.0 foot MLLW elevation have no sign). Additionally, provide two eHydro point files. One using the 3 foot cell size with a mean value (on cell-center) sort and the other using the 30 foot cell size with shoal biased (on cell-center) sort. Both eHydro point files must contain metadata and use the naming convention outlined in POA-EC-G-GE-1.
B. All single-beam hydrographic soundings collected in the field must be provided with z-values in elevation mode (points below the 0.0 foot MLLW elevation include a minus sign and points above the 0.0 foot MLLW elevation have no sign). Additionally, provide two eHydro point files. One using the 3 foot cell size with a mean value (on cell-center) sort and the other using the 30 foot cell size with shoal biased (on cell-center) sort. Both eHydro point files must contain metadata and use the naming convention outlined in POA-EC-G-GE-1.
C. All topographic shots collected in the field must be provided with z-values in elevation mode (points below the 0.0 foot MLLW elevation include a minus sign and points above the 0.0 foot MLLW elevation have no sign).
For each point file, provide a metadata file meeting the FGDC metadata formatting. Refer to Hypack's "Simplified Metadata" for content.
2.2.3 SURVEY DRAWINGS
All survey depth soundings and topographic shots (if applicable) will be recorded and legibly plotted in planimetric view across the entire survey limits, as shown on the contract drawings, using the layout(s) provided in the AutoCAD file described in 1.7 GOVERNMENT-FURNISHED DATA. For dredging areas, shoal-biased soundings must be used and care shall be taken to show the highest soundings, that is, those with the least depth on the survey drawings. The soundings and topographic shots (if applicable) plotted on the survey drawings must be in depth mode (points below the 0.0 foot MLLW elevation have no sign and points above the 0.0 foot MLLW elevation have a positive sign). Include a 3D color relief plot of the survey depth soundings and topographic shots (if applicable) in a separate layout within the survey drawings using the shoal biased point file(s). For dredging projects, the 3D color relief legend must use warm colors (red, orange, yellow, etc.) for elevations above the project depth and cool colors (green, blue, indigo, violet, etc.) for elevations below the project depth.
2.2.4 QUANTITY COMPUTATIONS
All quantity computations must be performed by the Contractor's independent hydrographic/topographic surveyor using the sorted, edited, tide corrected point files as described in 2.2.2 SURVEY POINT FILES.
Quantity computations for this contract will use the 3 foot sort, mean biased point file (on cell-center) of the hydrographic/topographic data collected within the survey limits. The AutoCAD Civil 3D file described in
1.7 GOVERNMENT-FURNISHED DATA will be capable of computing quantities using design surfaces based on the project limits specified in the contract. Quantity computations must be reported in cubic yards in an Excel spreadsheet or other tabular format as approved by the COR. All
SECTION 31 09 13.00 29 Page 8 quantity computations must include notes stating the point file(s) and surface build characteristics used. Any edits or surface build properties for the point files and design surfaces made by the independent hydrographic/topographic surveyor must be preserved in the AutoCAD file submitted for Government review and comment. Any external, Land XML files generated or used to calculate quantities must also be submitted for Government review and comment.
All quantity computations must use the composite method.
1. For each survey provide a running total of the quantity of available and removed material to project depth (PD), between PD and required depth (RD), between RD and the maximum payline (MP). For the post-dredge survey(s) and each interim condition survey, provide the over-dredge (OD) volume representing the quantity removed beyond the applicable tolerance of the MP defined in the contract.
2. For each survey, compute the cut and fill to project depth (PD), between PD and required depth (RD), and between RD and the maximum payline (MP). Report the quantity for each dredge area as well as the total for the project. Report the quantities for the current and previous survey.
Calculate and report the survey to survey difference in cut and fill quantity for each dredge area as well as the total for the project.
3. Compute the over-dredge (OD) quantity by comparing the difference of fill quantity to the maximum payline (MP) for each survey. Report the over-dredge (OD) quantity between successive surveys as well as the total for the project.
4. For Anchorage Harbor maintenance dredging quantity computations only, shoaling is computed by taking the maximum payline (MP) quantity available on the previous survey and subtracting the maximum payline (MP) quantity available on the current survey. That quantity is then subtracted from the difference in raw quantity removed by the dredge for that interval.
This number is the total shoaled amount. The total shoaled amount is multiplied by the ratio of the area covered by the dredge over the area designated for dredging at each interval. The contour for the maximum payline (MP) depth is used to define the outer limit for the designated dredge area. A sample computation is shown in Attachment A.
2.2.5 FIELD PHOTOS
Provide field photos for each survey. Document any weather conditions, obstructions, vessels, or other conditions which may have impacted full data collection within the survey limits.
All field photos must contain a geotag in the properties to document the geospatial location that the photo was taken and be saved in a logical and identifiable format (.jpg extensions).
2.2.6 QUALITY CONTROL
Submit all QA/QC reports and field notes with each preliminary and final survey deliverable. Perform all QA/QC in accordance with EM 1110-1-1005 , EM 1110-2-1003 , EM 1110-1-1003 , and the POA-EC-G-GE-1 . Deviations from the Contractor's submitted and approved survey plan must be submitted to the COR for additional review and approval before conducting survey field work.
The Certified Hydrographer's bathymetric data format must provide complete
SECTION 31 09 13.00 29 Page 9 traceability for all positions, soundings, and corrections including sensor offsets, biases, dynamic attitude, sound speed, position, sensor position, date and time, vertical datum reducers, and sounding data from acquisition through post processing. Data quality and edit flags must be traceable.
Provide documentary evidence that all calibration, performance tests, and quality control were performed in accordance with the submitted and approved survey plan. This will include a written log (or equivalent digital record) of sensor offset and alignment measurements, patch test calibration results, sound velocity measurements, bar checks, squat calibrations, tide/stage observations, performance test results, etc., pertaining to the survey. Also include associated control monument quality control (peg test, level closures, etc.).
2.3 ORGANIZATION FOR ELECTRONIC SURVEY DATA
Survey data for each preliminary and final deliverable must be organized in individual folders labeled MM_DD_YYYY Type of Survey. The MM_DD_YYYY component must be the final date of field data collection for each survey.
The Type of Survey will be based on the list in 2.1 SURVEYS required for this contract. The survey products listed in 2.2 SURVEY DATA must be provided in the appropriate sub-folders using the naming convention that follows:
MM_DD_YYYY Type of Survey
001_PRELIM DELIVERABLE or 002_FINAL DELIVERABLE
510_CAD FILES
511 XML
512_ETRANSMIT ZIP
513_PDF
514_DWG
520_REPORT
530_SPREAD SHEETS
540_PHOTOS
541_SITE PHOTOS
542_CONTROL PHOTOS
543_U-SMART PHOTOS
544_AERIAL PHOTOS
545_NAVIGATION AIDS
546_LAND SURVEY PHOTOS
547_HYDRO SURVEY PHOTOS
550_SURVEY FIELD NOTES
560_USMART FORMS
570_LAND SURVEYS
571_POINT FILES
572_CONTROL SURVEYS
574_RAW DATA
580_HYDRO SURVEYS
581_POINT FILES
SECTION 31 09 13.00 29 Page 10
582_VOLUMETRIC FILES
583_PROJECT DATA
584_RAW DATA
585_PROCESSED DATA
586_EHYDRO POINT FILES
The Contractor must use the POA-EC-G-GE-1 as guidance for the appropriate files to save in each folder and sub-folder described above. Coordinate with the COR with any questions on this format.
2.4 PRELIMINARY AND FINAL SURVEY DELIVERABLES
Each survey described in 2.1 SURVEYS must be submitted as a preliminary and a final deliverable and contain all components described in 2.2 SURVEY DATA, except that quantity computations are not required for winter surveys.
The preliminary survey deliverable must be posted to the Contractor maintained ftp site followed by e-mail notification to the COR that the survey data is ready for review and comment. The COR will review each preliminary survey deliverable which will either be:
1. Rejected Without Further Review. The preliminary survey deliverable is incomplete as a result of not providing all the data required in 2.2 SURVEY DATA and/or not fulfilling the minimum requirements described in this section. The COR will notify the Contractor of this status for the preliminary survey deliverable. The Contractor must address the issue(s), upload the data to the Contractor maintained ftp site, and again notify the COR by e-mail that the survey data is ready for review and comment.
2. Disapproved With Comments. The preliminary survey deliverable has substantial deficiencies, which may include but not be limited to, issues with the data required in 2.2 SURVEY DATA and/or not conforming to the requirements described in 3.2 ACCURACY. The preliminary survey deliverable must address the comments provided by the COR, be re-submitted to the Contractor maintained ftp site within five (5) calendar days, have modified or corrected files use the term REV# in the naming convention where # is the amount of times the file has been modified or corrected to date, and again notify the COR by e-mail that the survey data is ready for additional review and comment.
3. Accepted With Comments. The preliminary survey deliverable substantially meets the requirements of the contract. Comments may be provided on minor deficiencies that must be corrected in the final survey deliverable; the preliminary survey deliverable does not need to be re-submitted to the Contractor maintained ftp site again. The COR will issue a drawing number to the Contractor along with any comments by e-mail. The Contractor must revise the accepted preliminary survey deliverable, in accordance with the comments and drawing number issued by the COR, and submit the final survey deliverable.
Final survey deliverables must be a complete record of the survey; data from the preliminary survey deliverable that was not revised must be included again in the final survey deliverable. Final survey drawings described in 2.2.3 SURVEY DRAWINGS must be saved in AutoCAD Civil 3D 2013 Drawing .dwg and PDF formats and include the PLS stamp, signature, and date for the surveyor in responsible charge of all topographic and control survey components. Projects that include hydrographic surveying must also include the signature of the Certified Hydrographer within the AutoCAD
SECTION 31 09 13.00 29 Page 11
Civil 3D 2013 Drawing .dwg and PDF. The Contractor must provide all components described in 2.2 SURVEY DATA for the final survey deliverable.
The final survey deliverable must be posted to the Contractor maintained ftp site and a serial letter will be used to notify the COR that the final survey deliverable is complete and available for download. The COR will review the final survey deliverable to ensure all comments have been addressed. The Contractor will be required to re-submit any final deliverable which is incomplete at no additional cost to the Government.
PART 3 EXECUTION
3.1 EXISTING MONUMENTS
As part of the Pre-dredge/Pre-construction survey(s), verify by GPS or conventional survey methods the horizontal position, and condition of existing primary and local control monuments mentioned or shown on the drawings. Primary and local vertical control must be verified through a minimum of two published, primary NOAA tidal benchmarks using differential leveling. Request approval from the COR to correct any deviances in position or elevation prior to making any modifications to the data described in 2.2.1 SURVEY CONTROL TABLE. The COR must be provided any subsequent corrected data of any of the control monuments, which will be provided for Government review and comment in the preliminary survey deliverable.
3.2 ACCURACY
Each survey described in 2.1 SURVEYS must conform to requirements as specified in EM 1110-1-1005 , EM 1110-2-1003 , EM 1110-1-1003 , and POA-EC-G-GE-1. Specifically, the following accuracies must be obtained:
A. Horizontal Control Point Closure Standard must be Second Order Class II referenced to Alaska State Plane based on NAD83 in US Survey Feet.
B. Distance closure error, after azimuth adjustment, must not exceed 1 part in 20,000 parts.
C. Traverse adjustment must be by the Compass Rule Method.
D. Static GPS adjustment must be performed using Least Squares.
E. Vertical control must be referenced to mean lower low water (MLLW = 0.0 feet) based on the 1983-2001 tidal epoch, holding current published NOAA/CO-OP values.
F. Levels must meet USACE Third Order for primary and local monuments at the project site.
3.3…