W911KB-16-R-0015_RFP_Specs.pdf
PDF 2 MB Posted
- Attached to
- River Revetment Phase III, Unalakleet, Alaska
- Solicitation number
- W911KB-16-R-0015
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W911KB-16-R-0015_AM_6.pdf | ||
| Dwgs-UNK337747A-AM_6-22x34.pdf | ||
| AM_5.pdf | ||
| W911KB-16-R-0015_Amendment__4.pdf | ||
| AM_3_W911KB-16-R-0015.pdf | ||
| W911KB-16-R-0015_Amendment__2.pdf | ||
| 16R0015-0001.pdf | ||
| W911KB-16-D-0015_Dwgs_RFP-11x17.pdf | ||
| W911KB-16-R-0015_RFP_Dwgs.pdf | ||
| W911KB-16-R-0015_RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
US Army Corps of Engineers Alaska District
UNK337747A
(P2 No. 337747)
RFP SPECIFICATIONS
RIVER REVETMENT PHASE III
UNALAKLEET, ALASKA
W911KB-16-R-0015
July 06, 2016
(PAGE INTENTIONALLY LEFT BLANK)
RFP RIVER REVETMENT PHASE III UNK337747A
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 19 40.00 29 SPECIAL ITEMS (CIVIL WORKS)
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)
01 45 04.00 29 CONTRACTOR QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20.01 29 ENVIRONMENTAL PROTECTION
01 57 34.00 29 STORM WATER POLLUTION PREVENTION MEASURES
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 05 - METALS
05 50 14 STRUCTURAL METAL FABRICATIONS
05 50 15 CIVIL WORKS FABRICATIONS
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 09 13.00 29 SURVEYS (CIVIL WORKS)
31 11 00 CLEARING AND GRUBBING
31 41 16 STEEL SHEET PILING
31 62 22 STEEL PIPE PILES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 19 40.00 29
SPECIAL ITEMS (CIVIL WORKS)
PART 1 GENERAL
1.1 SCOPE
1.2 REFERENCES
1.3 SUBMITTALS
1.4 ACCIDENT PREVENTION PLAN
1.4.1 Navigation Safety and Coordination Plan
1.5 FIRE SAFETY
1.6 DISPOSITION OF MATERIALS
1.6.1 Salvageable Material
1.7 TESTS
1.8 WARRANTY OF CONSTRUCTION
1.8.1 Failures
1.9 CAMP FACILITIES
1.10 CONTRACTOR-FURNISHED VEHICLE
1.11 CONTRACTOR FURNISHED BOAT
1.12 OFF-SITE TRANSPORTATION
1.13 FURNISHINGS FOR GOVERNMENT FIELD OFFICE
1.13.1 Radio Communications
1.14 ACCOMMODATIONS FOR GOVERNMENT REPRESENTATIVES
1.15 PARTNERING
1.16 SCHEDULING OF WORK
1.17 COORDINATION OF WORK
1.18 EQUIPMENT
1.19 HAUL ROADS, LOADING RAMPS, AND DOCKS
1.20 BLASTING
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section Table of Contents --
Section 01 19 40.00 29 Page 1
SECTION 01 19 40.00 29
SPECIAL ITEMS (CIVIL WORKS)
PART 1 GENERAL
1.1 SCOPE
Items included in this section cover special features and/or requirements which are not otherwise specified or indicated.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. DEPARTMENT OF DEFENSE (DOD)
DOD Directive 4500.53 Operational Support Airlift (OSA)
Pub. L. 99-661 Commercial Airlift Public Law
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
Government acceptance is required for submittals with a "G" designation.
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G
Equipment Schedule
1.4 ACCIDENT PREVENTION PLAN
The Accident Prevention Plan (APP) requirements listed in this section supplement those for the APP submittal discussed in Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1.
1.4.1 Navigation Safety and Coordination Plan
The Contractor shall submit a Navigation Safety and Coordination Plan as part of the APP. This plan shall include but not be limited to temporary lights at night and/or marker buoys during construction, "Notice to Mariners" and coordination with local officials, and reference to applicable U.S. Coast Guard regulations for construction vessels as well as
Section 01 19 40.00 29 Page 2
SECTION 19, Floating Plant and Marine Activities, of EM 385-1-1.
1.5 FIRE SAFETY
The Contractor shall obtain a permit from the organization having jurisdiction over the job site for any welding or open flame work.
1.6 DISPOSITION OF MATERIALS
Combustible and noncombustible waste material shall be disposed of off-site.
No burning will be permitted.
1.6.1 Salvageable Material
Salvageable material, if not otherwise indicated, shall become the property of the Contractor. The value of such salvage shall be reflected in the contract price.
1.7 TESTS
The Contractor shall provide testing, except where specifically noted to be performed by the Government, in accordance with SECTION 01 45 04.00 29
CONTRACTOR QUALITY CONTROL.
1.8 WARRANTY OF CONSTRUCTION
a. In addition to any other warranties in this contract, the Contractor warrants, except as provided in subparagraph "i" herein, that the work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
b. This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
c. The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or -controlled real or personal property, when that damage is the result of:
1. the Contractor's failure to conform to contract requirements;
or
2. any defect of equipment, material, workmanship, or design furnished.
d. The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
e. The Contracting Officer will notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
Section 01 19 40.00 29 Page 3
f. If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
g. With respect to all warranties, expressed or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall:
1. Obtain all warranties that would be given in normal commercial practice;
2. Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer;
and
3. Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
h. In the event the Contractor's warranty under subparagraph "b" herein has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
i. Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage which results from any defect in Government-furnished material or design.
j. This warranty shall not limit the Government's rights under the Inspection of Construction clause of this contract with respect to latent defects, gross mistakes, or fraud.
k. Defects in design or manufacture of equipment, specified by the Government on a "brand name and model" basis, shall not be included in this warranty. In this event, the Contractor shall require any subcontractors, manufacturers, or suppliers thereof to execute their warranties, in writing, directly to the Government.
1.8.1 Failures
Upon receipt of notice from the Government of failure of any part of warranted items during the warranty period, the affected part or parts shall be promptly replaced. Such replacement shall include furnishing and installing the necessary new part or parts, making all necessary repairs, restoring the affected item to the operating condition specified in this contract and making all such tests as are necessary to ensure that there are no remaining defects. Such tests shall be performed in the presence of representatives of the Using Agency indicated below. Upon final acceptance of the work or transfer of responsibility to the Government for operation and maintenance of the items covered, whichever is earlier, the Contractor shall be responsible to the Using Agency for the warranty provisions of this contract. A letter stating the applicable warranty provisions shall be furnished to the Contracting Officer in duplicate, in the format and text shown in the sample letter attached to this section.
U.S. Army Engineer District, Alaska
Section 01 19 40.00 29 Page 4
P.O. Box 6898 JBER, Alaska 99506-6898
1.9 CAMP FACILITIES
There are no Government owned camp facilities at the job site for the Contractor's use.
1.10 CONTRACTOR-FURNISHED VEHICLE
The Contractor shall provide and maintain a four-wheel-drive late model Blazer/Explorer-type vehicle at the job site, in good repair and approved by the Contracting Officer, for the use of the Government representatives regularly employed at the job site. The cost of providing the vehicle and fuel, oil, maintenance and repairs shall be borne by the Contractor and included in the contract price. The vehicle shall be in place by start of initial setup work at the job site and maintained through final cleanup.
During any down time, an equal substitute vehicle shall be provided immediately.
1.11 CONTRACTOR FURNISHED BOAT
The Contractor shall provide access for Government personnel to inspect construction work in the water. This will require boat transportation by the Contractor as requested by the Government for up to ten (10), 2 hour inspections for as many as three (3) Government representatives. The cost of providing the boat and fuel, maintenance, and repairs shall be borne by the Contractor and included in the contract price. The boat shall be available by start of initial setup work at the job site and maintained through final cleanup.
1.12 OFF-SITE TRANSPORTATION
The Contractor shall provide round-trip air transportation between Anchorage, Alaska and the job site for the Government field representative assigned to the project. The assigned representative will normally spend four continuous weeks at the job site and one week back in Anchorage on an alternating basis. The Contractor shall also provide round-trip air transportation for a temporary Government representative between Anchorage and the project site for each of the one week periods. A minimum of two hours overlap shall be allowed on the job site for the regular and temporary representatives to brief each other. A baggage allowance of up to 140 pounds, plus one carry on bag, shall be included on each flight if air transportation is used. If charter aircraft are needed, they shall be DOD Commercial Airlift Review Board approved per Pub. L. 99-661 and DOD Directive 4500.53. If water transportation is used, craft and operator shall comply with all applicable Coast Guard requirements for commercial vessel operations. Dates and times of transportation shall be coordinated with the Contracting Officer.
1.13 FURNISHINGS FOR GOVERNMENT FIELD OFFICE
The living facilities provided for the government representatives may also serve as a Government field office and shall be furnished with one desk, one drawing layout table, three chairs, a four-drawer vertical or two-drawer lateral file cabinet, a portable copier with automatic document feed. The Contractor shall provide a 1 MB DSL multiple connection with a CISCO PIX Box or equivalent connectivity through cable modem to be used by government employees to connect their laptop computers. The Contractor is
Section 01 19 40.00 29 Page 5 encouraged to contact USACE-IT at 1-866-562-2348 for hook up requirements or assistance. The Contractor shall provide sufficient electrical outlets for all equipment. All costs shall be borne by the Contractor and included in the contract price, except that long distance charges incurred by the Government representative will be paid for by the Government upon arrangement with the Contracting Officer.
1.13.1 Radio Communications
The Contractor shall provide and maintain a two-way radio or radios for the Contracting Officer's Representative at the job site throughout the construction duration of on-site activities for communication with job personnel.
1.14 ACCOMMODATIONS FOR GOVERNMENT REPRESENTATIVES
The Contractor shall furnish suitable separate living facilities near the job site to be used as quarters for the Government representatives regularly employed at the job site, and located separately from the Contractor's area. Quarters furnished shall be equivalent in quality to the quarters furnished to the Contractor's supervisory personnel. The facilities shall meet all prescribed safety, sanitation and health requirements. All costs shall be borne by the Contractor and included in the contract price. The facilities shall be subject to the approval of the Contracting Officer and shall meet or exceed the following requirements:
a. One house or modular-type housing unit, with the following:
b. Single rooms for two people, each equipped with dresser, nightstand, full-size bed with clean linen, blankets and pillows; each room to have at least 160 square feet of area.
c. A kitchen equipped with a range (vented hood), garbage disposal, microwave oven, refrigerator with freezer, and cooking and eating utensils.
d. A utility room equipped with clothes washer and dryer.
e. A day room equipped with chairs, couch, and a color television with clear reception of available channels, including cable.
f. A private bathroom for each bedroom, with toilet, wash basin, and shower.
g. Daily maid and janitorial service; weekly linen service.
h. A cable TV with internet access.
The Contractor shall furnish and install utilities, providing connections to service locations. Accommodations shall be in place and connected by start of initial setup work at the job site and maintained through final cleanup. All costs shall be borne by the Contractor and included in the contract price, except that long distance charges incurred by the Government representative will be paid for by the Government upon arrangement with the Contracting Officer.
1.15 PARTNERING
a. The Government intends to encourage the foundation of a cohesive
Section 01 19 40.00 29 Page 6 partnership with the Contractor and its subcontractors. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance, intended to achieve completion within budget, on schedule, and in accordance with plans and specifications.
b. This partnership will be bilateral in makeup, and participation will be totally voluntary. Implementation of this initiative will be a topic of discussion at the Preconstruction Conference. Other recurring or special purpose meetings, as agreed between the Government and the Contractor, will be held as necessary to resolve contentious issues and maintain the partnering spirit.
1.16 SCHEDULING OF WORK
See Section 01 32 01.00 10 PROJECT SCHEDULE
1.17 COORDINATION OF WORK
The Contractor shall be responsible for all coordination with the U.S.
Coast Guard and all concerned State and local interests regarding its activities, and also with any other contractors as specified in the CONTRACT CLAUSES. The Contractor shall keep advised of vessel traffic near the job site and conduct operations so that interference with vessels will not occur. The Contractor shall conduct its work and dispose of its plant and equipment in a manner that will minimize interference with other construction or operations at the job site. The Government does not guarantee unrestricted availability of the site. Upon completion of the work, the Contractor shall promptly remove its plant, including ranges, buoys, piles, and other temporary structures placed by it under the contract, in navigable waters or on shore.
1.18 EQUIPMENT
The following Equipment Schedule shall be completed by the Contractor and submitted within 10 days of receipt of Notice-to-Proceed. The Contractor shall keep equipment on the job sufficient to meet the requirements of the work. The equipment shall be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in the specifications and shall be subject to inspection by the Contracting Officer at all times. The equipment used shall be of a design and have characteristics similar to equipment which has been used successfully for a minimum of 3 years under similar conditions. It shall be the responsibility of the Contractor to prove this equipment has sufficient capacity to accomplish the work in a timely manner without damaging existing facilities or obstructing navigation.
a. Number. For equipment give identifying number or name.
b. Type. Under this heading give general description. Sufficient detailed information shall be furnished to properly delineate the proposed equipment and operation.
c. Capacity. Under this heading, state the estimated capacity of the plant and equipment in cubic yards or tons per day when working materials similar to those anticipated in the work. No reduction in the stated capacity of the plant and equipment employed on the work shall be made except by written permission of the Contracting Officer.
Section 01 19 40.00 29 Page 7
The measure of the "capacity of the plant and equipment" shall be its actual performance on the work.
PLANT AND EQUIPMENT SCHEDULE
(To Be Submitted as Indicated)
Minimum Plant To Be Used Number Type Capacity Manufacturer Age & Condition Location Value
Note: In preparing the above tabulation, the Contractor shall insert the necessary information under the appropriate heading, using a separate line for each major item and additional pages if necessary.
1.19 HAUL ROADS, LOADING RAMPS, AND DOCKS
The use of existing roads for hauling shall be coordinated with Federal, State and Local agencies. It shall be the Contractor's responsibility to acquire all permits and easements for use of existing roads and docks or for construction of new haul roads, loading ramps, and docks. Prior to construction of any haul road or use of existing roads, the Contractor shall submit to the Contracting Officer, for information, a haul road plan demonstrating that the road(s) will meet the safety requirements of EM 385-1-1. Upon completion of the project, the Contractor shall remove all haul roads, loading ramps, and docks it built within the project area, to the satisfaction of the Contracting Officer. Any temporary fill used for these facilities shall be removed and placed in an acceptable disposal area. Any existing access roads shall be left in as good condition as when work started.
1.20 BLASTING
No in-water blasting will be allowed.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
Section 01 19 40.00 29 Page 8
S A M P L E L E T T E R
Contracting Officer Date__________________ Address (as stated in Notice of Award)
SUBJECT: Warranty Provisions, Contract
GENTLEMEN:
This is to acknowledge our responsibility in connection with the warranty provisions of this contract as set forth in the contract specifications.
The following items, equipment or systems furnished or installed under this contract are hereby warranted against defective design, material and workmanship for a period as indicated:
Warranted Item, Identification Warranty Expires at Equipment or System Serial Number, Etc. 11:59 PM Std. Time
Upon receipt of notice from the Government of failure of any part or parts of the warranted item, equipment, or system during the warranty period, the affected part or parts will be replaced promptly with new parts. Such replacement will include furnishing and installing the new part or parts, making all necessary repairs, restoring the item, equipment, or system to the operating condition specified in this contract and making all such tests as are necessary to ensure that there are no remaining defects. Such tests will be performed in the presence of the Representative of the Using Agency indicated below.
We are responsible to ______________________________________ for the warranty provisions of this contract. Correspondence regarding the failure of any of the preceding items, equipment or systems covered by the warranty provisions of this contract should be addressed to:
___________________________________ Telephone Number:
Very truly yours, Signed: ________________________________________ Title: _________________________________________ Organization: __________________________________
-- End of Section --
Section 01 19 40.00 29 Page 9
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.1.1 Base Item 0001: Mobilization and Demobilization
1.1.1.1 Unit of Measure
1.1.2 Base Item 0002: Clearing and Grubbing
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.3 Base Item 0003: Place Modified Diaphragm Piles
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.4 Base Item 0004: Removable Ladders
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.5 Base Item 0005: Fill Cells
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.6 Base Item 0006: Surveys
1.1.6.1 Payment
1.1.6.2 Unit of Measure
1.1.7 Optional Item 0007: Option 1: Bull Rails
1.1.7.1 Payment
1.1.7.2 Unit of Measure
1.1.8 Optional Item 0008: Option 2: Y-Pile and Driven Bollards
1.1.8.1 Payment
1.1.8.2 Unit of Measure
1.1.9 Optional Item 0009: Option 3: Fender Piles
1.1.9.1 Payment
1.1.9.2 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
Section 01 22 00.00 10 Page 1
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the PROPOSAL SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Base Item 0001: Mobilization and Demobilization
Payment will be made for costs associated with mobilization and demobilization, as defined in Special Clause PAYMENT FOR MOBILIZATION AND DEMOBILIZATION. This proposal item also includes all costs associated with project bonding requirements.
1.1.1.1 Unit of Measure
Unit of measure: job.
1.1.2 Base Item 0002: Clearing and Grubbing
1.1.2.1 Payment
Payment will be made for costs associated with operations necessary for all clearing and grubbing operations.
1.1.2.2 Unit of Measure
Unit of measure: job.
1.1.3 Base Item 0003: Place Modified Diaphragm Piles
1.1.3.1 Payment
Payment will be made for costs associated with operations necessary for construction of the: modified diaphragm face sheets, tail walls, termination piles and all associated sheet pile work; and aluminum anodes.
Contract drawings reflect Optional Item 0007: Option 1 (see below).
Without award of Optional Item 0007: Option 1, drive and cut all face sheets as shown and ease all edges and corners at top of sheets.
1.1.3.2 Unit of Measure
Unit of measure: job.
Section 01 22 00.00 10 Page 2
1.1.4 Base Item 0004: Removable Ladders
1.1.4.1 Payment
Payment will be made for costs associated with operations necessary for construction and installation of the removable ladders.
1.1.4.2 Unit of Measure
Unit of measure: job.
1.1.5 Base Item 0005: Fill Cells
1.1.5.1 Payment
Payment will be made for costs associated with operations necessary for filling cells of the modified diaphragm bulkhead with quarry rock, subbase, and aggregate surface course as shown. Work shall include all elements of area grading; completion of the requirements of the settlement monitoring survey; all work associated with demolition and rebuilding the existing rock revetment; and demolition of the exisiting gabions as required.
1.1.5.2 Unit of Measure
Unit of measure: job.
1.1.6 Base Item 0006: Surveys
1.1.6.1 Payment
Payment will be made for costs associated with operations necessary for surveys indicated and shall constitute full compensation for performing the required surveys. Under no circumstance will any payment be made for any survey until all requirements of Section 31 09 13.00 29 SURVEYS (CIVIL WORKS) have been met.
1.1.6.2 Unit of Measure
Unit of measure: job.
1.1.7 Optional Item 0007: Option 1: Bull Rails
1.1.7.1 Payment
Payment will be made for costs associated with operations necessary for construction of bull rails as shown.
1.1.7.2 Unit of Measure
Unit of measure: job.
1.1.8 Optional Item 0008: Option 2: Y-Pile and Driven Bollards
1.1.8.1 Payment
Payment will be made for costs associated with operations necessary for construction of the Y-Pile bollards and driven bollards as shown.
Section 01 22 00.00 10 Page 3
1.1.8.2 Unit of Measure
Unit of measure: job.
1.1.9 Optional Item 0009: Option 3: Fender Piles
1.1.9.1 Payment
Payment will be made for costs associated with operations necessary for construction of the fender piles as shown.
1.1.9.2 Unit of Measure
Unit of measure: job.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Section 01 22 00.00 10 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 10
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
2.1.2.1 Primavera
2.1.2.2 Other Than Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Procurement Activities
3.3.4 Mandatory Tasks
3.3.5 Government Activities
3.3.6 Standard Activity Coding Dictionary
3.3.6.1 Workers Per Day (WRKP)
3.3.6.2 Responsible Party Coding (RESP)
3.3.6.3 Area of Work Coding (AREA)
3.3.6.4 Modification Number (MODF)
3.3.6.5 Bid Item Coding (BIDI)
3.3.6.6 Phase of Work Coding (PHAS)
3.3.6.7 Category of Work Coding (CATW)
3.3.6.8 Feature of Work Coding (FOW)
3.3.7 Contract Milestones and Constraints
3.3.7.1 Project Start Date Milestone and Constraint
3.3.7.2 End Project Finish Milestone and Constraint
3.3.7.3 Interim Completion Dates and Constraints
3.3.7.3.1 Start Phase
3.3.7.3.2 End Phase
3.3.8 Calendars
3.3.9 Open Ended Logic
3.3.10 Default Progress Data Disallowed
3.3.11 Out-of-Sequence Progress
3.3.12 Added and Deleted Activities
Section 01 32 01.00 10 Page 1
3.3.13 Original Durations
3.3.14 Leads, Lags, and Start to Finish Relationships
3.3.15 Retained Logic
3.3.16 Percent Complete
3.3.17 Remaining Duration
3.3.18 Cost Loading of Closeout Activities
3.3.18.1 As-Built Drawings
3.3.18.2 O & M Manuals
3.3.19 Anticipated Adverse Weather
3.3.20 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD/DVDs
3.5.2 Narrative Report
3.5.3 Schedule Reports
3.5.3.1 Activity Report
3.5.3.2 Logic Report
3.5.3.3 Total Float Report
3.5.3.4 Earnings Report by CLIN
3.5.3.5 Schedule Log
3.5.4 Network Diagram
3.5.4.1 Continuous Flow
3.5.4.2 Project Milestone Dates
3.5.4.3 Critical Path
3.5.4.4 Banding
3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS
Section 01 32 01.00 10 Page 2
SECTION 01 32 01.00 10
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "L" designation; submittals not having a "G" or "L" designation are for information only. Submittals with an "L" shall be submitted through serial letter to the government. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G Preliminary Project Schedule; L Initial Project Schedule; L Periodic Schedule Update; L
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this
Section 01 32 01.00 10 Page 3 specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
Section 01 32 01.00 10 Page 4
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features require design completion
c. Long procurement activities
d. Submission and approval of as-built drawings.
e. Contractor's pre-final inspection.
f. Correction of punch list from Contractor's pre-final inspection.
g. Government's pre-final inspection.
h. Correction of punch list from Government's pre-final inspection.
Section 01 32 01.00 10 Page 5
i. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. All Activity Codes shall be developed and assigned to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day shall be the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the
Section 01 32 01.00 10 Page 6 activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, Section 01 32 01.00 10 Page 7 fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 04.00 29 CONTRACTOR QUALITY CONTROL. An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule shall be a finish milestone titled "End Project."
The project schedule must be constrained to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. The start milestone shall be called "Start Phase X" where "X" refers to the phase of work.
3.3.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the
Section 01 32 01.00 10 Page 8 finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. The assignment of the non-work days should be over a seven-day week since weather records are compiled on seven-day weeks, which will cause some of the weather related non-work days to fall on weekends.
3.3.9 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" must have no predecessor logic, and the last activity -"End Project" must have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.10 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.11 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.12 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
Section 01 32 01.00 10 Page 9
3.3.13 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.14 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.3.15 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
3.3.16 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.3.17 Remaining Duration
Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
3.3.18 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.18.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.
3.3.18.2 O & M Manuals
Cost load the "Submission and approval of O & M manuals" activity not less
Section 01 32 01.00 10 Page 10 than $20,000. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.
3.3.19 Anticipated Adverse Weather
Paragraph applicable to contracts with clause entitled TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Reflect the number of anticipated adverse weather delays allocated to a weather sensitive activity in the activity's calendar.
3.3.20 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4.1 Preliminary Project Schedule Submission
Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Activity code any activities that are summary in nature after the first 90 calendar days with Bid Item (CLIN) code (BIDI), Responsibility
Section 01 32 01.00 10 Page 11
Code (RESP) and Feature of Work code (FOW).
3.4.2 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval within 42 calendar days after notice to…